POWER GRID CORPORATION OF INDIA LIMITED DOC NO.

MR/CF/SA/04/R-2 DATED: 01/08/07


CORPORATE OPERATION SERVICES SUB STATION :
BAY NO :
PRE-COMMISSIONING OF SURGE ARRESTER EQUIPMENT IDENTIFICATION NO :
COMMISSIONING FORMATS DATE OF TESTING :

I REGION :

II DATE OF III DATE OF


ERECTION : ENERGISATION :

IV DETAILS OF EQUIPMENT :

LOA NO :

MAKE :

TYPE :

SL NO. : R - PHASE : Y - PHASE : B - PHASE :

YEAR OF
MANUFACTURE :

FEEDER NAME :

V RATING :

VOLTAGE RATING :

VI DETAILS : CHECKLIST / TESTING

SL. DESCRIPTION STATUS REMARK


NO YES NO RECORD DEFICIENCIES, IF ANY

1 EQUIPMENT IS FREE FROM DIRT / DUST


FOREIGN MATERIALS ETC.

2 EQUIPMENT IS FREE FROM ALL VISIBLE


DEFECTS ON PHYSICAL INSPECTION

3 SUPPORT STRUCTURES & SURGE COUNTER


HAS BEEN PROVIDED WITH DOUBLE EARTH

4 ALL NUTS AND BOLTS ARE TIGHTENED


CORRECTLY AS PER SPECIFIED TORQUE

5 EQUPIMENT ERECTION IS COMPLETE IN


ALL RESPECT
(ATTACH REMAINING ACTIVITIES,IF ANY)

6 PERMANENT LA LAVELLING AND


IDENTIFICATION IS DONE

1 OF 3 SURGE ARRESTOR
POWER GRID CORPORATION OF INDIA LIMITED DOC NO. MR/CF/SA/04/R-2 DATED: 01/08/07
CORPORATE OPERATION SERVICES SUB STATION :
BAY NO :
PRE-COMMISSIONING OF SURGE ARRESTER EQUIPMENT IDENTIFICATION NO :
COMMISSIONING FORMATS DATE OF TESTING :

SL. DESCRIPTION STATUS REMARK


NO YES NO RECORD DEFICIENCIES, IF ANY
7 LEVELLING AND ALIGNMENT OF STRUCTURE
AND BASE FRAME IS CHECKED

8 ALL INSULATORS & SURGE COUNTER ARE


FREE FROM ANY PHYSICAL DEFECTS

9 TIGHTNESS OF NUTS BOLTS OF TERMINAL


CONNECTORS ARE CHECKED

10 ERECTION COMPLETION CERTIFICATE ALONG


WITH LIST OF OUTSTANDING ACTIVITIES
REVIEWED

11 CHECK ONE END OF SURGE COUNTER IS


CONNECTED TO THE BOTTOM OF LA STACK AND
ONE END OF SURGE COUNTER HAS BEEN EARTHED

12 THE DIRECTION OF THE EXHAUST VENT PORTS


AWAY FROM THE PROTECTED EQUIPMENT AND
OTHER ARRESTER POLES

13 CREARANCE FROM THE ARRESTER TO EARTHED


OBJECTS AND FROM THE ARRESTER POLE TO
ANOTHER ARRESTER POLE MAINTAINED AS PER
OUTLINE DRAWING AND ALL ERECTION HAS BEEN
DONE AS PER DRAWING ISSUED BY ENGG. DEPT.

VII INSULATION RESISTANCE MEASUREMENT : ( USING 5KV MEGGER)

SL. NO BETWEEN PHASE MIN VALUE > 1000 M OHMS


R-PHASE Y-PHASE B-PHASE
1 1ST STACK & EARTH MOHM
2 2ND STACK & EARTH MOHM
3 3RD STACK & EARTH MOHM
4 4TH STACK & EARTH MOHM
5 5TH STACK & EARTH MOHM
6 6TH STACK & EARTH MOHM

VIII SURGE COUNTER READING

SL. NO READING PHASE


R-PHASE Y-PHASE B-PHASE
1 COUNTER READING

2 OF 3 SURGE ARRESTOR
POWER GRID CORPORATION OF INDIA LIMITED DOC NO. MR/CF/SA/04/R-2 DATED: 01/08/07
CORPORATE OPERATION SERVICES SUB STATION :
BAY NO :
PRE-COMMISSIONING OF SURGE ARRESTER EQUIPMENT IDENTIFICATION NO :
COMMISSIONING FORMATS DATE OF TESTING :

IX CAPACITANCE & TAN DELTA MEASUREMENT

STACK CAPACITANCE TAN DELTA REMARKS


TOP
MIDDLE 1
MIDDLE 2
BOTTOM

X CHECKING OF HEALTHINESS OF SURGE MONITOR :


REFER MANUFACTURER'S CATALOGUE FOR DETAIL CHECKING OF SURGE MONITOR

XI THIRD HARMONIC RESISTIVE CURRENT MEASUREMENT

PH TOTAL 3RD HARMONIC RESISTIVE CURRENT (I3 REMARKS


CURRENT R) in µ A
R
Y
B

THE VALUE OF THIRD HARMONIC CURRENT AFTER COMPENSATION SHALL BE LESS THAN 30 µA. IN
CASE OF DISCREPANCY, TEST RESULTS TO BE FORWARDED TO CC/OS.

XII FINAL DOCUMENTATION REVIEW

A FINAL DOCUMENT OF PRE-COMMISSIONING CHECKS


REVIEWED AND APPROVED YES NO

B DOCUMENTS REGARDING SPARES, EQUIPMENT, O & M


MANNUALS ETC AVAILABLE AT SITE FOR O & M
PURPOSE YES NO

C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"


ARE AVAILABLE AT SITE YES NO

SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :


NAME : NAME : NAME : NAME :
DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION :
ORGANISATION : ORGANISATION :
( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C)( POWERGRID COMM TEAM )

3 OF 3 SURGE ARRESTOR