Академический Документы
Профессиональный Документы
Культура Документы
1. PART 1 - GENERAL
D. Obtain and submit releases enabling the Owner's full, unrestricted use of the
Work and access to services and utilities. Where required, include occupancy
permits, operating certificates and similar releases.
F. Deliver tools, spare parts, extra stock of materials and similar physical items to
the Owner.
G. Make final change-over of locks and transmit keys to Owner. Advise Owner's
personnel of change-over in security provisions.
2. Results of the completed inspection will form the initial "Punch List" for final
acceptance.
A. General: Complete the following before requesting the Engineer final inspection
for certification of final acceptance, and final payment as required by the General
Conditions. List known exceptions, if any, in the request.
1. Submit the final payment request with final releases and supporting
documentation not previously submitted and accepted. Include certificates
of insurance for products and completed operations where required.
3. Submit a certified copy of the Engineer final Punch List of itemized work to
be completed or corrected, stating that each item has been completed or
otherwise resolved for acceptance and has been endorsed/dated by the
Engineer.
4. Submit final meter readings for utilities, a measured record of stored fuel,
and similar data either as of the date of substantial completion, or else
when the Owner took possession of and responsibility for corresponding
elements of the work.
A. As-Built Drawings: Contractor shall prepare As-Built drawings from the record
drawings. Information shall be presented in the following form:
C. Record Product Data: During the progress of the work maintain one copy of
each product data submittal, and mark up significant variations as approved by
the Engineer in the actual work in comparison with the submitted information.
complete miscellaneous records and place in good order, properly identified and
bound or filled, ready for continued use and reference. Submit to the Engineer
for record.
B. Contractor shall submit 2 sets of Operation and Maintenance data prior to final
inspection, size A-4 and/or A-3 text pages as applicable, bound in expandable
binders with durable covers.
C. Contractor shall prepare binder covers with printed title - OPERATION AND
MAINTENANCE INSTRUCTIONS, title of project, and subject matter of binder
when multiple binders are required.
F. Binder Contents: Contractor shall prepare a Table of Contents for each volume,
with each Product or system description identified.
1. List of equipment.
4. Installation instructions.
5. Operating instructions.
J. Contractor shall submit one copy of the completed binder volumes in the final
form 30 days prior to final inspection at substantial completion. This copy will be
returned after final inspection, with the Engineer comments. Revise content of
documents as required prior to final submittal.
K. Within 10 days after final inspection, Contractor shall submit 2 copies of the final
revised binder volumes to the Engineer for hand-over to Owner.
A. Special cleaning for specific units of work is specified in the various technical
specifications.
B. Provide final cleaning of the work at the time indicated, consisting of cleaning
each surface or unit of work to the normal "clean" condition expected for a first
class building cleaning and maintenance program. Comply with manufacturer's
instructions for cleaning operations.
D. Comply with the safety standards and governing regulations for cleaning
operations. Do not burn waste materials at the site, nor bury debris or excess
materials on the property, nor discharge volatile or other harmful or dangerous
materials into drainage system. Remove waste materials from the site and
dispose of in lawful manner.
A. Submit written warranties to the Engineer prior to the date certified for
Substantial Completion. If the Engineer certificate of Substantial Completion
designates a commencement date for warranties other than the date of
Substantial Completion for the Work, or a designated portion of the Work, submit
written warranties upon request of the Engineer.
4. Ensure that keys to rolling stock, buildings and equipment are ready for
turnover to the Owner.
2. PART 2 - PRODUCTS
(Not used)
1. PART 3 - EXECUTION
(Not Used)
END OF SECTION