Вы находитесь на странице: 1из 7

SECTION 01700

PROJECT CLOSE-OUT REQUIREMENTS

1. PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Project Closeout: Term used to describe certain collective project requirements,


indicating completion of Work that are to be fulfilled near end of Contract time in
preparation for final acceptance and occupancy of Work by Owner, as well as
final payment to the Contractor and normal termination of Contract.

B. Time of Closeout: Directly related to "Substantial Completion"; therefore, the time


of closeout may be a single time for individual elements of the work that have
been certified as substantially complete at different dates. This time variation, if
any, shall be applicable to the other provisions of this Section.

1.02 PREREQUISITES TO SUBSTANTIAL COMPLETION

A. General: Complete the following before requesting the Handover Committee


inspection for certification of substantial completion, either for the entire work or
for portions of the Work.

1. In progress payment request that coincides with, or is the first request


following date of substantial completion is claimed, show either 100%
completion for portion of work claimed as "substantially complete", or list
incomplete items, the value of incomplete work, and reasons for Work
being incomplete.

2. Include supporting documentation for completion as indicated in these


contract documents.

B. Submit a statement showing an accounting of changes to the Contract Sum.

C. Submit specific warranties, workmanship/maintenance bonds, maintenance


agreements, final certifications and similar documents.

D. Obtain and submit releases enabling the Owner's full, unrestricted use of the
Work and access to services and utilities. Where required, include occupancy
permits, operating certificates and similar releases.

E. Submit record drawings, maintenance manuals, final project photographs,


damage or settlement survey, property survey, and similar final record
information.

F. Deliver tools, spare parts, extra stock of materials and similar physical items to
the Owner.
G. Make final change-over of locks and transmit keys to Owner. Advise Owner's
personnel of change-over in security provisions.

H. Complete start-up testing of systems, and instruction of the Owner's operating


and maintenance personnel. Discontinue or change over and remove temporary
facilities and services from the project site, along with construction tools and
facilities, mock-ups, and similar elements.

I. Complete final cleaning-up requirements, including touch-up painting of marred


surfaces.

J. Touch-up and otherwise repair and restore marred exposed finishes.

K. Inspection Procedures: Upon receipt of Contractor's request for inspection,


Handover Committee will either proceed with inspection or advice Contractor of
unfilled prerequisites.

1. Following initial inspection, Handover Committee will either prepare


Certificate of Substantial Completion, or will advise Contractor of work
which must be performed before certificate will be issued. Handover
Committee will repeat inspection when requested and when assured that
work has been substantially completed.

2. Results of the completed inspection will form the initial "Punch List" for final
acceptance.

1.03 PREREQUISITES TO FINAL ACCEPTANCE

A. General: Complete the following before requesting the Engineer final inspection
for certification of final acceptance, and final payment as required by the General
Conditions. List known exceptions, if any, in the request.

1. Submit the final payment request with final releases and supporting
documentation not previously submitted and accepted. Include certificates
of insurance for products and completed operations where required.

2. Submit an updated final statement, accounting for final additional changes


to the Contract Sum.

3. Submit a certified copy of the Engineer final Punch List of itemized work to
be completed or corrected, stating that each item has been completed or
otherwise resolved for acceptance and has been endorsed/dated by the
Engineer.

4. Submit final meter readings for utilities, a measured record of stored fuel,
and similar data either as of the date of substantial completion, or else
when the Owner took possession of and responsibility for corresponding
elements of the work.

5. Submit Certificate of Payment, Zakat and Income.


B. Re-inspection Procedure: The Engineer shall re-inspect the Work upon receipt of
the Contractor's notice that the Work, including Punch List items resulting from
earlier inspections, has been completed, except for these items whose
completion has been delayed because of circumstances that are acceptable to
the Engineer.

1. Upon completion of re-inspection, the Engineer will either prepare a


certificate of completion of the Maintenance Period or will advice the
Contractor of work that is incomplete or of obligations that have not been
fulfilled, but are required for final acceptance.

2. If necessary, the re-inspection procedure will be repeated.

1.04 RECORD DOCUMENT SUBMITTALS

A. As-Built Drawings: Contractor shall prepare As-Built drawings from the record
drawings. Information shall be presented in the following form:

1. Electronic Files: As-Built drawings files shall be submitted to the Engineer.


Drawings shall be prepared using latest AutoCAD version (*.DWG
Format).

2. Reproducible Copies (Transparencies or Sepias): All As-Built drawings and


other Contract documents.

Copies of the As-Built drawings shall be submitted in accordance with SECTION


01300 - SUBMITTALS for approval.

B. Specifications: Complete mark-up of Technical Specifications shall be submitted


to the Engineer before initial acceptance.

C. Record Product Data: During the progress of the work maintain one copy of
each product data submittal, and mark up significant variations as approved by
the Engineer in the actual work in comparison with the submitted information.

Include both variations from the manufacturer's instructions and


recommendations for installation. Give particular attention to concealed
products and portions of the work which cannot otherwise be readily discerned
at a later date by direct observation. Note related change orders and mark-up of
record drawings and specifications. Upon completion of mark-up, submit
complete set to the Engineer for record.

D. Record Sample Submittal: Immediately prior to the time(s) of initial completion,


the Engineer will meet with Contractor at site, and will determine which of the
submitted samples maintained by the Contractor during the progress of the work
are to be submitted to the Engineer for record purposes.

E. Miscellaneous Record Submittals: Immediately prior to time(s) of initial


completion,

complete miscellaneous records and place in good order, properly identified and
bound or filled, ready for continued use and reference. Submit to the Engineer
for record.

1.05 OPERATING AND MAINTENANCE INSTRUCTIONS

A. Arrange for each Installation of work requiring continuing maintenance or


operation to meet with the operating personnel at the project site to provide
basic instructions needed for proper operation and maintenance of the entire
work. Review maintenance manuals, record documentation, tools, spare parts
and materials, lubricants, fuels, identification system, control sequences,
hazards, cleaning and similar procedures and facilities. For operation
equipment, demonstrate start-up, shut-down, emergency operations, noise and
vibration adjustments, safety, economy/ efficiency adjustments, and similar
operations. Review maintenance and operations in relation with applicable
guarantees, warranties, agreements to maintain, bonds, and similar continuing
commitments.

B. Contractor shall submit 2 sets of Operation and Maintenance data prior to final
inspection, size A-4 and/or A-3 text pages as applicable, bound in expandable
binders with durable covers.

C. Contractor shall prepare binder covers with printed title - OPERATION AND
MAINTENANCE INSTRUCTIONS, title of project, and subject matter of binder
when multiple binders are required.

D. Language for Operation and Maintenance Manuals: Manuals shall be prepared


in Arabic and English. Where manufacturer's Arabic literature shall not be
available, Contractor shall be responsible for providing the Arabic translated
manuals.

E. Binder contents shall be internally subdivided with permanent page dividers;


logically organized as described below, with tab titling clearly printed under
reinforced laminated plastic tabs.

F. Binder Contents: Contractor shall prepare a Table of Contents for each volume,
with each Product or system description identified.

G. Binder - Part 1: Directory, listing names, addresses, and telephone numbers of


Architect/Engineer, the Engineer, Contractor, subcontractors, and major
equipment suppliers.

H. Binder - Part 2: Operation instruction and maintenance manuals, arranged by


system and subdivided by Specification section.

For each category, identify names, addresses, and telephone numbers of


subcontractors and suppliers. Identify the following:

1. List of equipment.

2. Significant design criteria including performance data, dimensions,


weights, and capacities.

3. Parts list for each component.

4. Installation instructions.

5. Operating instructions.

6. Maintenance manuals and instructions for equipment and systems


including service manuals and wiring diagrams.

7. Maintenance instructions for finishes, including recommended cleaning


methods and materials and special precautions identifying detrimental
agents.

I. Binder - Part 3: Project documents and certificates, including the following:

1. Shop drawings and product data.

2. Air and water balance reports.

3. Potable water system disinfection reports.

4. Elevator and dumbwaiter test reports and certifications.

5. Other certificates as specified.

6. Photocopies of warranties, guaranties, and bonds.

J. Contractor shall submit one copy of the completed binder volumes in the final
form 30 days prior to final inspection at substantial completion. This copy will be
returned after final inspection, with the Engineer comments. Revise content of
documents as required prior to final submittal.

K. Within 10 days after final inspection, Contractor shall submit 2 copies of the final
revised binder volumes to the Engineer for hand-over to Owner.

1.06 FINAL CLEANING

A. Special cleaning for specific units of work is specified in the various technical
specifications.

B. Provide final cleaning of the work at the time indicated, consisting of cleaning
each surface or unit of work to the normal "clean" condition expected for a first
class building cleaning and maintenance program. Comply with manufacturer's
instructions for cleaning operations.

C. Except as otherwise indicated or requested by the Owner, remove temporary


protective devices and facilities which were installed during the course of the
work to protect previously completed work during the remainder of the
construction period.

D. Comply with the safety standards and governing regulations for cleaning
operations. Do not burn waste materials at the site, nor bury debris or excess
materials on the property, nor discharge volatile or other harmful or dangerous
materials into drainage system. Remove waste materials from the site and
dispose of in lawful manner.

1.07 WARRANTIES AND BONDS

A. Submit written warranties to the Engineer prior to the date certified for
Substantial Completion. If the Engineer certificate of Substantial Completion
designates a commencement date for warranties other than the date of
Substantial Completion for the Work, or a designated portion of the Work, submit
written warranties upon request of the Engineer.

When a special warranty is required to be executed by the Contractor, or the


Contractor and a subcontractor, supplier or manufacturer, prepare a written
document that contains appropriate terms and identification, ready for execution
by the required parties. Submit a draft to the Owner through the Engineer for
approval prior to final execution.

Refer to individual sections of Division 2 through 16 each specific content


requirements, and particular requirements for submittal of special warranties.

B. Form warranties and bonds in heavy-duty, commercial quality, durable 3-ring


vinyl covered loose-leaf binders, thickness as necessary to accommodate
contents, and sized to receive A-4 paper.

1.08 CONTINUING INSPECTIONS

A. Where required by special guarantees, warranties, agreements to maintain,


workmanship bonds and similar continuing commitments, comply with requests
to participate in inspections at the end of each time period of such continuing
commitments.

1.09 DELIVERY TURNOVER INVENTORY REQUIREMENTS

A. Upon product delivery, the Contractor shall:

1. Conduct tests and operational checks to ensure serviceability of property


to be transferred.

2. Verify cleanliness and overall condition as acceptable.

3. Ensure that manufacturer's operations and maintenance manuals are


available for transfer.

4. Ensure that keys to rolling stock, buildings and equipment are ready for
turnover to the Owner.
2. PART 2 - PRODUCTS

(Not used)

1. PART 3 - EXECUTION

(Not Used)

END OF SECTION

Вам также может понравиться