Вы находитесь на странице: 1из 3

Antiquated Structural Systems Series

Part 9b – Open Web Steel Joists


By D. Matthew Stuart, P.E., S.E., F. ASCE, SECB
CONCENTRATED LOAD

For this series of articles, “antiquated” has been defined as TYP. L2x2x¼ REQ’D
IF LOAD DOES NOT OCCUR
meaning outmoded or discarded for reasons of age. In reality, AT JOIST PANEL POINT OR
however, most of the systems that have been discussed are no > 6” AND EXCEEDS 150# ®

E
longer in use simply because they have been replaced by more
innovative or more economical methods of construction.
This article, however, deals with a method of construction

R
that is still very much in use today. Nevertheless, the historic,
original construction practices described here may still be
encountered in existing structures. Therefore, the primary

U
JOIST
purpose of this series of articles will be fulfilled, which is to
compile and disseminate a resource of information to t enable
igofh existing

T
structural engineers to share their knowledge y r
opbut are capable
structural systems that may no longer be inCuse HANGER ROD
of being adapted or reanalyzed for safe reuse in the marketplace

C
of today and the future. Figure 1: Typical concentrated load on joist detail.

TYPICAL CONCENTRATED LOAD

e
U
Evaluation and Modification ONjoist
to obtain results from a standard ASTM JOIST DETAIL
is capable of safely supporting the im-

n
of Existing Joists tension coupon test, a determination as to posed loads. However, if the maximum

i
R
The author would first like to thank whether the joist is 36 ksi (J- Series) or 50 moment is greater than one foot from the

z
the Steel Joist Institute (SJI) for providing ksi (H-Series) can be made. midspan point, the capacity of the joist

T
much of the material that was used in the If no drawings are available, it is still pos- may not be sufficient even if the applied
development of this article. The evaluation
and strengthening of existing open web

g a
sible to establish the approximate capacity
of the member by field measuring the
moment is less than the specified capacity.
This situation can occur for two reasons.

S
steel joists and Joist Girders is often required chord and web member sizes, as well as First, the moment capacity envelope of
as a result of equipment upgrades or new

a
the overall configuration of the joist. This the joist may actually be less in regions
Engineer’s Notebook

installations and adaptive reuse or change information can then be used to analyze of the span that are not within one foot

m
in use of a facility. The SJI provides an the structure as a simple truss. Critical of the midspan point. Second, a shift in
excellent resource for the evaluation and assumptions that must be made with this the moment envelope from that normally
modification of existing joists and Joist approach include the yield strength of the associated with a uniformly loaded simple
Girders in Technical Digest No. #12. members and whether the existing panel span (and the prerequisite shear envelope)
The first step in the process of evaluating point welds are capable of developing the may result in stress reversals in the web
an existing joist is to determine the capacity full capacity of the connected component members (i.e., from tension to compres-
of the member. Ideally, the best method members. An alternate method includes sion) for which the original member was
for doing this is through original construc- filling out the Joist Investigation Form not designed or manufactured. A similar,
tion or shop drawings, which allow the located on the SJI website. SJI has indi- although typically more advantageous, con-
identity of the joist to be established. cated considerable success in identifying dition also can occur with J- or H-Series
Similarly, it is also sometimes possible to the series and designation for many older joists because of variations in the uniform
identify the joist by means of fabrication joists with this resource. shear capacity of these members.
tags left attached to the joists in the field. The next step in the evaluation process When the existing joists do not have
However, if tags can be found, more often is to determine all of the existing loads sufficient capacity to support the new
than not the tag only identifies the shop on the joist system. The existing and new loads, one of three methods can be used to
piece mark number rather than the actual loading criteria are then used to establish rectify the condition: load redistribution,
aids for the structural engineer’s toolbox

joist designation. the shear and moment envelope of the adding new joists or beams, or reinforcing
In some instances, it may only be possible individual joist, for comparison with the the existing joists. Load redistribution
to establish the type or series of the allowable shear and moment envelope involves the installation of a sufficiently
joist through the available documenta- based on either the historical data provided stiff member perpendicular to the span
tion. In this situation, it is possible to by SJI or an independent analysis of the of the joist as required to distribute the
assume conservatively that the capacity member as a simple truss. In the former applied load to enough adjacent joists such
of the existing joist is no more than the case, unless the joists were fabricated with that no one joist is overstressed as a result
lightest joist in the corresponding series a uniform shear and moment capacity over of the new loading. Adding new joists or
for the given depth. In addition, if it is the entire span length (i.e., KCS joists), beams typically involves the installation of
not clear whether a J- or H-Series joist is then it is also necessary to evaluate the lo- an additional framing member parallel to
involved, the J-Series joist should always cation of the maximum imposed moment. the joist span, such that all or most of the
be conservatively assumed because of its Typically, if the maximum moment is new applied load is supported by the new
lower load-carrying capacity. However, if within one foot of the midspan point framing. New self-supporting beams can
a definitive distinction is required, and it is and the maximum applied moment is also be installed perpendicular to the joist
possible to secure a material sample in order less than the joist moment capacity, the span, as required to reduce the original

STRUCTURE magazine 18 November 2009


span length of the member. Another alternative joists by means of loose end bearing assem- load-carrying capacity of the joists. However,
consists of new independent, self-supporting blies. In this scenario, the joists are first erected it is still necessary to analyze the existing
beam and column frames that avoid the on a diagonal to allow the top chord to be joists to ensure that no load reversals have
imposition of any new loads on the existing lifted above the bearing elevation. The joist occurred in tension-only web members, and
joist framing system. Reinforcing involves the is then rotated into an orthogonal position, with that the actual applied moment falls within
installation of supplemental material to the the lower portion of the bearing assembly then the remaining existing moment capacity en-
original joist as required to increase the load- dropped and welded into place. Typically, in velope of the joist. As with load redistribution
carrying capacity of the member. this situation, a shallower bearing seat is also pro- solutions, both of the above new framing
® ap-
The key to the successful use of load redis- vided for ease of installation and then shimmed proaches may be difficult to install.

E
tribution is the installation of a structural once the new joist is in its proper position. New framing that involves the installation
member that can adequately and predictably When new beams or other similar mem- of independent, stand-alone beam and column

R
distribute the applied load to enough adjacent bers are added perpendicular to the joist span, frames is intended to provide direct support
joists to justify the safe support of the load. A the new framing serves to reduce the span of of the new loads such that there is no impact
method of calculating the relative stiffness of a the existing members, thereby increasing the on the existing joist framing. This type of new

U
distribution member is available in the reference
material noted in the online version of this
h t
yrig

T
article. In general, if the spacing of the joists is
less than approximately 78% of the calculated Cop
relative stiffness of the distribution member

C
and the joists, and the length of the distribu-
tion member is less than the inverse of the
calculated relative stiffness, then the distri-

e
U
bution member may be considered as rigid

n
enough to calculate the static load reactions to

i
R
the affected joists.

z
For load redistribution solutions, it is the
author’s preference to use trussed distribution

T a
members, rather than individual beams, to
ensure adequate transfer of the applied load.

g
S
Trussed means continuous members located

a
perpendicular to both the bottom and top
chords of the existing joists in conjunction

m
with diagonal web members connected to the
continuous members at the intersection of the
joist chords. The resulting configuration looks
like a truss and provides greater stiffness than
an individual beam connected to either the
bottom or top joist chords alone. The author
also recommends that no more than five joists
be engaged by any one redistribution member.
In addition, the use of pipes for the continu-
ous redistribution truss chord members can
be advantageous, as this type of section fits
neatly through the V-shaped panel point
openings created at the intersection of the
existing chords and web members. However,
load redistribution solutions may be difficult
to install, depending on accessibility and the
presence of existing MEP systems, ceilings or
other appurtenances.
As indicated above, adding new joists or
beams to an existing system can also be used
to accommodate new loads on an existing
joist structure. When new members are added
parallel to the existing joists, the new framing
can be used either to reduce the tributary area
of the existing joists or to provide direct sup-
port of the new loads such that there is no
impact on the existing joists. Methods used
to install new parallel framing often involve
manufacturing, shipping and erecting the new
members using field splices. However, it is pos-
Figure 2.
sible to install new full-length manufactured

STRUCTURE magazine 19 November 2009


framing can involve beams located either be- version of this article will assist in increasing
neath or above the impacted existing framing the likelihood that the capacity of a joist can be D. Matthew Stuart, P.E., S.E., F. ASCE,
and supported by new columns and founda- determined using the historical data that is SECB is licensed in 20 states. Matt
tions, or beams that frame between existing available from SJI. currently works as a Senior Project Manager
columns. This type of solution can also in- Typically, the investigation of an exist- at the main office of CMX located in New
volve new beam frames supported from posts ing joist results in the need to modify the Jersey, and also serves as Adjunct Professor
located directly above existing beams or col- structural system to provide for the support for the Masters of Structural Engineering
umns. The above solutions are typically more of new imposed loads. At this juncture, the ®
Program at Lehigh University, Bethlehem,
adaptable to the presence of existing MEP sys- engineer must then determine if he or she

E
PA. Mr. Stuart may be contacted at
tems, ceilings or other appurtenances. is more comfortable with assuming the re- mstuart@CMXEngineering.com.
Procedures for reinforcing joists are expertly sponsibility and liability for modifying a pre-

R
described in SJI Technical Digest No. #12 and engineered product or employing a possibly
involve two basic approaches: 1) ignore the less risky option, such as load redistribution
strength of the existing member and simply or adding new joist or beam framing. To assist

U
design the new reinforcement to carry all of structural engineers with the evaluation and
the applied load, or 2) make use of the strength modification process, the author has included a
t
righ (Figure 2, page 19) that

T
of the existing member when designing the copy of a flowchart
p y
reinforcing. Both of the recommended ap- Co as result of numerous proj-
was developed
proaches typically involve significantly more ects that involved existing joists.▪

C
labor costs than material costs because of the
expense associated with field welding.
The author prefers to avoid the use of field

e
U
reinforcement for the following reasons. A References

n
manufactured open web steel joist is basically

i
80 Years of Open Web Steel Joist Construction

R
a pre-engineered product; however, when an A Compilation of Specifications and Load Tables Since 1928

z
engineer involved with the modification of Steel Joist Institute
an existing joist specifies new field installed

T a
Myrtle Beach, South Carolina
reinforcement, that same engineer assumes the 2009
responsibility for the overall adequacy of the

g
S
joist. This liability extends to not only the Catalog of Standard Specifications, Load Tables and Weight Tables for Steel Joists and Joist

a
reinforcing modifications but also, inherently, Girders
to any pre-existing, unknown conditions 42nd Edition

m
or deficiencies in the joist. In addition, field Steel Joist Institute
welding associated with the installation of Myrtle Beach, South Carolina
reinforcement also poses concerns for the design 2007
engineer. Problems associated with field welding Technical Digest No. #12
are discussed in Technical Digest No. #12 and Evaluation and Modification of Open Web Steel Joists and Joist Girders
include temporary localized loss of the mate- Steel Joist Institute
rial strength of the existing steel due to heat Myrtle Beach, South Carolina
generated by the weld, induced eccentricities, 2007
inadequate load path mechanisms, and lack of
access, particularly at the top chord. Designing with Steel Joists, Joist Girders and Steel Deck
The only exceptions that the author makes James Fisher, Michael West, Julius Van de Pas
include the installation of supplemental web Nucor Corporation
members as needed to transfer concentrated 1991 (Second Edition – 2002)
loads greater than 150 pounds on chords that Miscellaneous Steel Joist and Joist Girder Specifications and Load Tables
are located greater than 6 inches from a panel SJI Archives
point to the closest adjacent panel point (Fig- Steel Joist Institute, Technology, Engineering, and Education Center
ure 1, page 18), and reinforcement designed Myrtle Beach, South Carolina
by the original manufacturer’s engineer. The first Joist Investigation Form
exception is the author’s rule of thumb and is www.steeljoist.org/investigation
not formally endorsed by SJI, because it is not Steel Joist Institute
applicable in all cases; for example, it may be Myrtle Beach, South Carolina
fine for a 30K12, but not for a 10K1.
The analysis of existing open web steel joists
can be a challenging undertaking and often
involves a considerable amount of detective
work. Unfortunately, there is typically little
or no documentation available concerning
the capacity of a specific existing joist under
investigation. However, it is hoped that the ref-
erence information provided in the online

STRUCTURE magazine 20 November 2009

Вам также может понравиться