Early Management
PILLAR REFERENCE GUIDE
Version 3
November 2016
Page 1 of 39 | STRICTLY CONFIDENTIAL – FOR INTERNAL USE ONLY
EARLY MANAGEMENT (EM)
PILLAR REFERENCE GUIDE
TABLE OF CONTENTS
Table of contents ......................................................................................................................................... 3
Document control ........................................................................................................................................ 4
Introduction .................................................................................................................................................. 5
Target audience.......................................................................................................................................................... 5
Objective .................................................................................................................................................................... 5
The document is... ...................................................................................................................................................... 5
The document is not... ................................................................................................................................................ 5
Document map ............................................................................................................................................. 6
Pillar definition ............................................................................................................................................. 7
What is a Pillar?.......................................................................................................................................................... 7
Pillar mission .............................................................................................................................................................. 7
Pillar objectives........................................................................................................................................................... 8
Pillar role .................................................................................................................................................................... 8
Pillar Implementation Strategy ................................................................................................................... 9
Starting EM Pillar ........................................................................................................................................................ 9
EM Implementation CYCLE ...................................................................................................................................... 10
Expected Contribution to TPM Maturity Phases ....................................................................................................... 13
Interactions with the other Pillars .............................................................................................................................. 14
Pillar methodology .................................................................................................................................... 16
Description................................................................................................................................................................ 16
EM Systems ............................................................................................................................................................. 16
Synchronization of Activities ..................................................................................................................................... 17
Interactions between EM Cycle and Projects ........................................................................................................... 17
Expected Results – Measures .................................................................................................................................. 19
Waste Prevention....................................................................................................................................... 21
Description................................................................................................................................................................ 21
Activities ................................................................................................................................................................... 21
Deliverables .............................................................................................................................................................. 25
Standards & Feedback .............................................................................................................................. 26
Description................................................................................................................................................................ 26
Activities ................................................................................................................................................................... 26
Deliverables .............................................................................................................................................................. 31
Project Management Foundations ........................................................................................................... 32
Description................................................................................................................................................................ 32
Activities ................................................................................................................................................................... 32
Deliverables .............................................................................................................................................................. 35
Operations & Start-up Management ........................................................................................................ 36
Description................................................................................................................................................................ 36
Activities ................................................................................................................................................................... 36
Deliverables .............................................................................................................................................................. 39
DOCUMENT CONTROL
Changes made
Date of update Updated by Status of
(Section numbers and Version #
(dd/mm/yyyy) (Author name) document
description)
02.09.2013 Jose Ferrato EM Pillar Reference Guide 1.0 Superseded
01.09.2015 Jose Ferrato EM Pillar Reference Guide 2.0 Superseded
Complete revision of the
24.11.2016 Robert Le Dortz 3.0 Released
document
INTRODUCTION
DOCUMENT MAP
This document is part of the TPM Knowledge Center. The link below gives you access to this
Knowledge Center and other TPM related documents (Implementation Strategy, Governance,
Pillar Reference Guides and Support Material).
PILLAR DEFINITION
WHAT IS A PILLAR?
Early Management aims to build and sustain
What it is capability for industrialisation excellence,
The EM Pillar is a team of people who have enhancing cooperation between R&D,
expertise in, and disseminate, Early Operations and Project Teams in a
Management methodologies. consumer-driven war to eliminate waste from
initial new design to full-scale production.
A “Pillar leader or member” is usually a role,
not a position. Refer to the NCE Operating
Framework for details.
What it does…
It builds people competency on the EM
methodology through training, coaching and
assessments.
PILLAR MISSION
Our mission is to enable our people to deliver
Manufacturing Excellence through
industrialisation projects. This means launch
new equipment, processes and products with
a sustainable Vertical Start-Up, so that
business objectives are reached at the right
time and at the right cost.
STARTING EM PILLAR
At Market Level At Factory Level
The launch of EM Pillar at Market level is For launching the Pillar in factories, it is
aligned with the TPM implementation Plan of necessary to have a Market EM Pillar
the market. As soon as the first factory of launched. Factory EM Pillar will be launched
market gets ready for progressing to Phase as part of the TPM Phase 1 implementation,
1, the pillar should be launched and its as illustrated in the image below. For
members trained to better support the factories where important Industrialisation
achievement of Manufacturing Excellence projects are forecasted, it is also
through industrialisation. recommended to launch the EM pillar as
early as possible in order to start building
capability in the teams.
EM IMPLEMENTATION CYCLE
Description needed for the market and factories to deliver
Early Management Pillar works in a cycle of Operational Excellence.
continuous improvement that helps to Once the Market and selected Factories have
consistently develop internal capability for met the conditions to launch the pillar they
preventing waste in each industrialisation need to set the cycle and perform it at least
project selected in the OMP. By leveraging once a year and every time there is a
this cycle we keep ensuring that every effort significant change in the OMP or in the
we put on Industrialisation delivers the short projects portfolio, such as changes in
term business results and also sets the long priorities, new business requirements, major
term industrial capabilities and competencies organisational changes, etc
Lead Participate
Market NCE Champion
Chief Engineer Market TPM Manager
Market Level
I&R Manager FI Market Pillar Leader
EM Pillar Leader
Factory EM Pillar Leader
Factory TPM Coordinator
Factory Level Factory manager
FI Pillar representative
Factory Executive Committee
At project level, from a practical point of view, part of their scope, as well as they plan and
these interactions are triggered as part of the receive the necessary support during the
project team’s activities during the project project execution.
preparation and execution. This will ensure
project teams consider other Pillar’s inputs as
PILLAR METHODOLOGY
DESCRIPTION
In our journey toward Manufacturing Start-Up will be delivered if and only if the
Excellence it is critical that for every activities of each of these systems are
industrialisation project and each time we performed in a synchronized way. This
introduce a new technology or product to a requires good cooperation between all key
factory a clear focus is made on designing stakeholders, specifically Operations,
“waste out”. For that purpose, all project Categories and R&D. Deep involvement and
related activity have been classified into 4 strong collaboration of key equipment
main systems that are described below. It suppliers may also be required.
must be highlighted that sustainable Vertical
EM SYSTEMS
The 4 different systems and their purpose are Project Management Foundations
described below:
Provide the disciplined way for the teams to
Waste Prevention steer and deliver projects, including the
Ensure clear identification and understanding sequencing of activities
of losses and provide ways to prevent them.
Operations & Start-up Management
Standards and Feedback Ensuring the Operational preparation and
Ensure adherence to Standards and enable Start-Up execution required to enable
continuous learning from projects and current Vertical Start-up.
manufacturing operations
SYNCHRONIZATION OF ACTIVITIES
Project’s activities required are sequenced planning, scheduling and controlling, and
through a Multi-Functional Project Workflow, thereby avoiding the waste of time, money,
a stage gate process defined to conduct any and resources. All the required activities are
industrialization projects within Nestlé. It grouped in the Task Completion Checklist.
covers all the key tasks in a project’s At each step and for each activity, the
execution, as well as the milestones and expected Deliverables are clearly defined
gates required to monitor and control the and available for the Project Teams.
project. For more information about Project Workflow
It reflects internal and external best practices please refer to the EM Knowledge Center.
in project management and provide structure
to project management, standardization in
Expected
Type Measure Frequency Why do we need this measure?
result
At the end of This is the final measure of project success
PPI Vertical Start-up Yes
the Project (see details in the next section)
Vertical Start-Up
Definition
EM aims for flawless introduction of new …has been delivered and validated
products and equipment, impacting all 5 for Manufacturing Excellence
dimensions of Manufacturing Excellence. …is free of problems and with
This means launch new equipment, minimum waste
processes and products with a sustainable …has been delivered On time, Right
Vertical Start-Up, which is defined as follows. First time
…had capabilities built from a defect
It is a measure of Project Success that shows free design to deliver a defect free
that the new production system: operation
Measure
A line achieves sustained AI ≥ 80% in less Technically Acceptance Time Line
than 100 days after commissioning Agreed for selected SKU’s
completion. It applies for both new and
modified lines. In Full Ramp-Up Elements:
The key contributors for achieving this are: Ramp up Plan Agreed based on
Success Criteria validated by Steering
On Time Elements: Committee on MS2 / Go to Industrialize
Commissioning completion on time: No Gate.
gaps on installation, on functionality, Volume for Product Launch Gate by
Safety or food safety. Confirmed with SKU
Steering committee at Gate Go to Asset Intensity Target Sustained for 3+
Qualification Meeting (MS6). weeks
WASTE PREVENTION
DESCRIPTION
Why / purpose
As described the primarily objective of EM preventive actions taken as part of new
Pillar is to enable our Project Teams to projects, to avoid same issues to reoccur.
deliver a loss-free manufacturing solution. The continuously application of this process,
It is understood that the Product Cost may be project after project, will contribute to build a
affected by different kind of losses, as ‘loss-free by design’ mindset, and to achieve
illustrated in the image below: Manufacturing Excellence with every project.
Waste Prevention System groups the
different activities that will enable the Project
Teams to remove waste by design.
ACTIVITIES
Understand Losses
Set Target
Prevent losses
types of problems/losses with varying levels eliminate the root cause of losses, in the
of complexity. design. Verification that activities results will
meet forecasted targets can be ensured
Single Minute Exchange of Die (SMED): during Design Reviews as described in the
enables optimization of planned stoppages, Project Management Foundations system.
with direct impact on Asset Intensity. Additionally to this, it is also important to
confirm that the actions taken are delivering
Failure Mode and Effect Analysis (FMEA): the expected results in later stages. This will
is a technique used to identify, prioritize and be done during:
eliminate potential failures within a system, in
order to implement countermeasures to Factory Acceptance Test (FAT): is the
prevent failures. opportunity to perform safety tests, static
tests, dry tests without product, and
Value Stream Engineering Design (VSED): performance tests with product in a new
provides a systematic approach to optimize piece of equipment under near production
basic plant designs, ensuring the most long conditions at the manufacturer’s facility prior
term value, optimizing process flows, line it is delivered to the factory.
layout. The FAT is a contractual requirement that
prevents shipping a machine that does not
Breakdown Analysis (BDA): is a process to meet the requirements specified in the
understand root cause of machine contract with the supplier.
breakdowns and identify countermeasures to
prevent them to happen again in the future.
For more details, refer to PM Reference Induced Failure Test: to confirm the
Guide. capability of the equipment and the operators
in identifying failures and recovering from
Implement operational standards: through them.
NCE implementation, factories will create The test can be performed mainly during the
important standards and routines to eliminate FAT, while running or dry cycling the
losses and sustain results. It includes CIL, equipment, inducing or simulating a failure.
Centerlining, Planned Maintenance, etc. Then confirm that the failure has been
properly identified and that the operator can
Those standards, when incorporated as
restart the equipment.
inputs to new projects, will also help the
prevention of losses as from the start-up.
ES 2 days EF
Eqpt. A
SMED Eqpt. A
Eqpt. B
Changeover Changeover
Eqpt. Z
Planned
LS LF
losses
Planned
Start/Shutdown Start/Shutdown
20%
Plan. Maint. Plan. Maint.
losses
ES 3 days EF
35%
3 days
FMEA Eqpt. B
65% Asset Intensity
Eqpt. A Breakdowns
Unplanned
Unplanned
Breakdowns LS LF
Waste/Rework Waste/Rework
LS LF
Eqpt. Z
Eqpt. A
ES 2 days EF
Eqpt.
B
Qx Matrix Eqpt. Z
LS LF
DELIVERABLES
Activities Deliverables
Pareto of losses from previous projects,
Pareto of losses from existing similar
operations,
Understand losses List of taggings put in existing similar
equipment,
List of operational standards (CIL, Centerlining,
etc.)
Clear targets at KPIs and PPIs level
Appropriated contribution analysis,
Set Target
demonstrating that the deliverables of the PPIs
will ensure the KPI results.
Operational standards implemented (CIL,
Centerlining, etc.)
Achievement of targets defined, through the
Prevent losses
loss elimination activities identified (SMED,
GSTD, FMEA, etc.) and performed from the
design.
Share Improvements fully part of the project scope and that the
persons in charge of the implementation
have the required level of competence.
Once the decision is made to select an
improvement for reapplication beyond the Adherence to the Standards should be
“Local” level then it has to be communicated controlled during Design, Implementation
in a structured way to all the areas and Start-Up phases by the relevant authority
concerned, depending of the type of depending of the level of Standards
Standards impacted. (Category Specific, Generic, Local). This can
be done through specific “Design Reviews”,
The Responsible for proper communication
as described in the “Project Management
remains the Standard Owner.
Foundations” system. Final validation is
required prior to Start-Up.
For the technical Improvements, a specific
tool - called Maintenance Prevention Data
Base (MPDB) - has been designed in order Collect Project Feedback
to support effectively the sharing process.
This is a central and global searchable Why / purpose:
database which is accessible by all Nestle
users. The MP DataBase is structured by The purpose of this activity is to capture
Product category (as defined per NWSM) learnings from a project (positive learnings or
and based on the standard functional location negative ones) in order to prevent similar
(FLOC) structure established for each of defects to happen in future projects (or even
these category through the Modularization in the following steps of the same project) as
process. well as to reapply positive learnings.
The learnings and feedbacks provided may
impact all level of Standards.
Once validated by the Standard Owner, the
documents created during the MoC process
(MP Datasheet, SOP) can be uploaded on Description:
the MPDB then shared within the community To generate, analyse and communicate
concerned by this change depending of its feedbacks on a Project, several sub-activities
type (Generic, Category Specific). can be performed at different time of the
project lifecycle and with different impacts or
benefits, as following:
Implement required Standards
Analyse Project Learnings
Why / purpose:
Once the Pre-Project Review has been
This activity consist in capturing the learnings
performed and clear alignment has been built
at each step during project’s lifecycle. The
on which Standards must be applied and
learnings can be either positives ones that
which learnings has to be taken into account
can be reapplied (Best Practices) or negative
and replicated, it is key to implement in a
ones (Defects).
flawless and consistent way.
Positive learnings have to be recorded and
share among the community in the more
Description: appropriate manner in order to ensure
The responsibility of project team is to ensure replication or Standards Improvement.
the identified Standards and learnings are
For the Defects, a detailed Analysis has to be Perform Project Final Evaluation
performed. It consists in identifying in which
project step each defect were found and in
The final evaluation of the Project and its
which project step the defect would have
results is performed at different level and
been avoided.
with different timeline depending of the
An evaluation of the impacts of each defect purpose. The following elements can be
on the 5 dimensions of Manufacturing mentioned.
Excellence has to be carried on as well as a
Root Cause Analysis.
Perform Technical Post Project
During Project preparation or execution,
Evaluation
learnings and changes are captured at each
project milestone and analysis is performed The scope of this activity is primarily technical
by the project team. Here the main purpose (technology and project management) and
aims to summarize the project achievements
is to prevent similar defects to happen during
compared with the agreed success criteria.
the next project steps. This may require
changes in the Project Management Plan.
During Project Closure, a final exercise also Perform Post-Launch Analysis
has to be performed. This exercise should be The review visit covers all the issues and items
performed by a cross-functional teams with which relate to effective and efficient technical
representatives from technical, commercial transfer of the product and process into
operations, from the R&D brief stage through the
and management so that leanings can be
development phase, the factory trials, the
shared quickly throughout the organization. industrialization, the launch period and the post-
To support the Project Learning Analysis, a launch period.
specific tool (called Project Defect Analysis -
PDA) has been developed. Further details on
how to perform this analysis and how to use Perform Business Post Project
the PDA tool can be found in the ED-221.30. Evaluation
The scope of this evaluation is primarily
financial and commercial and aims to
Update Defects Prevention Checklist
summarize the project achievements
compared with the expected targets.
All the defects identified during the Project
Learnings Analysis and related to existing
Standards must be discussed with the
concerned Standard Owners and trigger Use of Learnings from Projects
some changes for improvements if required.
Moreover, for each technical Standards, a Learnings from projects can be used in
Defect Prevention Checklist can be built. different ways at different levels and for
This Checklist which comprises technical different purposes, as explained below.
YES / NO questions and ensures that the Learnings from the project used for the
previous identified Defects are not repeated. next steps of this project
It will be used by the respective Standard Learnings from the project used as inputs
Owner in order to guide, coach and challenge for other running or future projects (in the
the project teams during project preparation same factory, in the same category, in the
and execution. market or even at global level).
Learnings from all the projects at factory
or market level used as inputs for the
understanding of project results (1st step
DELIVERABLES
Activities Deliverables
At Market/Category level
Process in place to share learnings from
projects across factories and Project
teams.
DELIVERABLES
Activities Deliverables
DESCRIPTION
Why / purpose Description:
The Operations & Start-Up Management The multifunctional project teams should
system defines the way for early understand the current risks and synergies
manufacturing engagement in projects. between the factory and the project by
Besides the focus on equipment and analysing the Current Operation Assessment
construction, aiming for vertical start-up also (COA). At same time they should lead the
requires a thorough preparation of all capture of inputs from the factory
operational aspects such as people hiring stakeholders that can enable the project to
and training, recipes, materials as well as prevent existing losses from Loss Tree
processes, compliance requirements, Analysis (LTA), as described in the Waste
methods and organization structure. Prevention System.
This system contains the procedures and By doing this activity the project teams will
activities required to plan, prepare and ensure that existing experience and learning
execute the start-up of new or modified are available to make the project successful
operations (equipment and/or product) and at the same time prepares the landscape
regarding people, methods and materials. in the factory to embrace the changes that
the project will provide.
ACTIVITIES For projects taking place in TPM factories, it
is important to consider TPM competencies
Collect manufacturing input to design
required to deliver the AM Step 3 level as
Understand Compliance requirements
required.
Prepare Quality & Food Safety
Set GLOBE/IT preparation
Set Maintenance and Spares Understand Compliance
Define Supply, Demand & Materials
requirements
readiness
Set Line Labour Mapping and staffing
needs Why / purpose:
Provide Manufacturing, Product and To ensure that the project team understands
Process Competencies the potential compliance risks that the
Define Start-up sequence and protocols existing factory site has, and ensure that the
project is prepared to address any
compliance requirements. This will enable
not only the project to be successful but to
Collect Manufacturing Input to ensure the factory compliance is enabled and
design sustained by the projects.
Prepare Quality & Food Safety Set Maintenance and Spare Parts
Description: Description:
It is critical to ensure that there is a clear The Commissioning Plan provides the details
mapping of resources required by the line, for the installation qualification (IQ) e.g. the
and that this is properly recruited during the safety checks, the I/O test, the functional
line construction to be able to prepare them. tests, and the operational qualification (OQ)
of the installed equipment. The optimal
Provide manufacturing, product settings of the equipment are documented,
and the maintenance plans are prepared in
and process competences SAP. Finally, the training of the factory staff
is completed. The Qualification Plan covers
Why / purpose: the release of the line by SHE and QA and
covers the initiation of the industrial trials for
The product and process Mastership
the capability of the process and the
competencies required for every position in
operators, as well covering the final validation
the new/modified line as well as for the
of SOPs (Standard Operating Procedures)
supporting staff (QA, Maintenance, etc.)
for operation and maintenance. It also
should be planned and executed. Depending
includes the test that the line can operate at
on the project complexity, the competences
nominal speed and committed asset intensity
can include business and functional
level for a period a time a defined in the
competences.
project success criteria. Finally, the first
saleable production lot is technically
Description: approved. The Verification plan comprises
The standard package coming from the the monitoring of the project success criteria,
category, should include the technology and the assessment of the level of training
deployment materials to develop the and skills of the factory staff, as well as the
competency of the factory staff. A Training final documentation of the Manufacturing
plan and competency measure should be Dossier.
DELIVERABLES
Activities Deliverables
Collect Manufacturing Input to design Manufacturing design review