SL.

No MAIN AREA SUB AREA SUB CON DISCIPLINE RFI NO SUBMITTED DATE INSP DATE TIME

108 722 0 AG1 CI 18-Apr-17 19-Apr-17 13:00

109 722 0 AG1 CI 18-Apr-17 19-Apr-17 13:15

110 722 0 AG1 CI 18-Apr-17 19-Apr-17 13:30

186 722 0 AG1 CI 6-May-17 7-May-17 9:45

201 722 0 AG1 CI 15-May-17 16-May-17 10:45

221 722 0 AG1 CI 20-May-17 21-May-17 8:30

222 722 0 AG1 CI 20-May-17 21-May-17 8:45

280 722 0 AG1 CI 12-Jun-17 13-Jun-17 5:30

286 722 0 AG1 CI 13-Jun-17 14-Jun-17 5:30

287 722 0 AG1 CI 13-Jun-17 14-Jun-17 5:45

302 722 0 AG1 CI 21-Jun-17 22-Jun-17 6:45

328 722 0 AG1 CI 12707 9-Jul-17 10-Jul-17 9:00


329 722 0 AG1 CI 12709 9-Jul-17 10-Jul-17 9:15

330 722 0 AG1 CI 12711 9-Jul-17 10-Jul-17 9:30

347 722 0 AG1 CI 12883 13-Jul-17 15-Jul-17 6:30

348 722 0 AG1 CI 12884 13-Jul-17 15-Jul-17 6:45

362 722 0 AG1 CI 13153 19-Jul-17 20-Jul-17 6:45

373 722 0 AG1 CI 13324 24-Jul-17 25-Jul-17 10:30

374 722 0 AG1 CI 13325 24-Jul-17 25-Jul-17 10:30

375 722 0 AG1 CI 13332 25-Jul-17 26-Jul-17 5:00

376 722 0 AG1 CI 13333 25-Jul-17 26-Jul-17 5:15

379 722 0 AG1 CI 13350 25-Jul-17 26-Jul-17 7:30

380 722 0 AG1 CI 13351 25-Jul-17 26-Jul-17 7:45

381 722 0 AG1 CI 13355 25-Jul-17 26-Jul-17 8:00

388 722 0 AG1 CI 13536 29-Jul-17 30-Jul-17 10:15


389 722 0 AG1 CI 13537 29-Jul-17 30-Jul-17 10:30

398 722 0 AG1 CI 13721 1-Aug-17 2-Aug-17 9:45

399 722 0 AG1 CI 13722 1-Aug-17 2-Aug-17 10:00

418 722 0 AG1 CI 13881 6-Aug-17 7-Aug-17 9:00

441 722 0 AG1 CI 14029 9-Aug-17 10-Aug-17 6:15

501 722 0 AG1 CI 14941 28-Aug-17 29-Aug-17 9:15

504 722 0 AG1 CI 14963 28-Aug-17 29-Aug-17 8:45

505 722 0 AG1 CI 14964 28-Aug-17 29-Aug-17 9:00

515 722 0 AG1 CI 15107 6-Sep-17 7-Sep-17 7:15

521 722 0 AG1 CI 15159 7-Sep-17 9-Sep-17 7:30

522 722 0 AG1 CI 15160 7-Sep-17 9-Sep-17 7:45

545 0 0 AG1 CI 3129 14-Sep-17 16-Sep-17 13:00

567 722 0 AG1 CI 15655 18-Sep-17 19-Sep-17 9:00


573 722 0 AG1 CI 15676 18-Sep-17 19-Sep-17 15:00

574 722 0 AG1 CI 15677 18-Sep-17 19-Sep-17 15:15

631 0 0 AG1 CI 27-Sep-17 28-Sep-17 13:00

632 0 0 AG1 CI 3246 28-Sep-17 30-Sep-17 13:00

633 722 0 AG1 CI 16305 30-Sep-17 1-Oct-17 14:00

634 722 0 AG1 CI 16306 30-Sep-17 1-Oct-17 14:15

636 722 0 AG1 CI 16406 1-Oct-17 2-Oct-17 13:00

637 722 0 AG1 CI 16409 1-Oct-17 2-Oct-17 13:15

644 722 0 AG1 CI 16421 1-Oct-17 2-Oct-17 14:30

645 722 0 AG1 CI 16422 1-Oct-17 2-Oct-17 14:45

648 722 0 AG1 CI 16425 1-Oct-17 2-Oct-17 15:00

650 722 0 AG1 CI 16427 1-Oct-17 2-Oct-17 15:15

665 0 0 AG1 CI 3297 5-Oct-17 7-Oct-17 13:00


680 0 0 AG1 CI 8-Oct-17 9-Oct-17 13:00

685 722 0 AG1 CI 16926 8-Oct-17 9-Oct-17 15:15

686 722 0 AG1 CI 16927 8-Oct-17 9-Oct-17 15:30

687 722 0 AG1 CI 16928 8-Oct-17 9-Oct-17 15:45

737 722 0 AG1 CI 17288 14-Oct-17 15-Oct-17 11:45

738 722 0 AG1 CI 17289 14-Oct-17 15-Oct-17 13:00

752 0 0 AG1 CI 3395 17-Oct-17 18-Oct-17 13:00

768 0 0 AG1 CI 18-Oct-17 19-Oct-17 13:00

781 0 0 AG1 CI 3417 19-Oct-17 21-Oct-17 13:00

834 0 0 AG1 CI 29-Oct-17 30-Oct-17 13:00

887 722 0 AG1 CI 18801 1-Nov-17 1-Nov-17 13:15

889 722 0 AG1 CI 18803 1-Nov-17 1-Nov-17 15:30

890 722 0 AG1 CI 18804 1-Nov-17 1-Nov-17 15:45


891 722 0 AG1 CI 18805 1-Nov-17 2-Nov-17 16:00

895 722 0 AG1 CI 18927 4-Nov-17 5-Nov-17 14:00

896 722 0 AG1 CI 18928 4-Nov-17 5-Nov-17 14:15

897 722 0 AG1 CI 18929 4-Nov-17 5-Nov-17 14:30

898 722 0 AG1 CI 18930 4-Nov-17 5-Nov-17 14:45

900 722 0 AG1 CI 18997 5-Nov-17 6-Nov-17 13:15

901 722 0 AG1 CI 18999 5-Nov-17 6-Nov-17 13:30

902 722 0 AG1 CI 19001 5-Nov-17 6-Nov-17 13:45

903 722 0 AG1 CI 19004 5-Nov-17 6-Nov-17 14:00

922 0 0 AG1 CI 3585 7-Nov-17 8-Nov-17 13:00

978 0 0 AG1 CI 3608 11-Nov-17 12-Nov-17 13:00

1092 722 0 AG1 CI 20743 27-Nov-17 28-Nov-17 14:00

1093 722 0 AG1 CI 20745 27-Nov-17 28-Nov-17 14:15


1094 722 0 AG1 CI 20747 27-Nov-17 28-Nov-17 14:30

1095 722 0 AG1 CI 20749 27-Nov-17 28-Nov-17 14:45

1124 722 0 AG1 CI 20861 29-Nov-17 2-Dec-17 10:00

1125 722 0 AG1 CI 20864 29-Nov-17 2-Dec-17 10:15

1129 722 0 AG1 CI 20971 2-Dec-17 2-Dec-17 13:15

1130 722 0 AG1 CI 20972 2-Dec-17 2-Dec-17 13:30

1131 722 0 AG1 CI 20973 2-Dec-17 2-Dec-17 13:45

1132 722 0 AG1 CI 20974 2-Dec-17 2-Dec-17 14:00

1136 722 0 AG1 CI 20983 2-Dec-17 3-Dec-17 7:30

1138 722 0 AG1 CI 20986 2-Dec-17 3-Dec-17 7:45

1139 0 0 AG1 CI 3798 2-Dec-17 3-Dec-17 14:00

1160 0 0 AG1 CI 3873 10-Dec-17 11-Dec-17 14:00

1165 722 0 AG1 CI 21521 10-Dec-17 11-Dec-17 8:30


1166 722 0 AG1 CI 21540 10-Dec-17 11-Dec-17 8:45

1172 722 0 AG1 CI 21617 11-Dec-17 12-Dec-17 7:15

1196 722 0 AG1 CI 22084 18-Dec-17 19-Dec-17 7:00

1197 722 0 AG1 CI 22086 18-Dec-17 19-Dec-17 7:15

1207 722 0 AG1 CI 22114 18-Dec-17 19-Dec-17 14:30

1208 722 0 AG1 CI 22116 18-Dec-17 19-Dec-17 15:00

1217 722 0 AG1 CI 22385 24-Dec-17 24-Dec-17 15:00

1218 722 0 AG1 CI 22386 24-Dec-17 24-Dec-17 15:15

1248 722 0 AG1 CI 22639 30-Dec-17 31-Dec-17 10:00

1251 0 0 AG1 CI 4062 31-Dec-17 2-Jan-18 14:00

1252 722 0 AG1 CI 22726 3-Jan-18 4-Jan-18 7:00

1261 722 0 AG1 CI 22942 11-Jan-18 13-Jan-18 8:30

1262 722 0 AG1 CI 22943 11-Jan-18 13-Jan-18 8:45


1263 722 0 AG1 CI 22944 11-Jan-18 13-Jan-18 9:00

1264 722 0 AG1 CI 22945 11-Jan-18 13-Jan-18 9:15

1275 722 0 AG1 CI 23333 22-Jan-18 23-Jan-18 10:45

1287 722 0 AG1 CI 23636 4-Feb-18 5-Feb-18 7:45

1288 722 0 AG1 CI 23637 4-Feb-18 5-Feb-18 8:00

1289 722 0 AG1 CI 23684 7-Feb-18 8-Feb-18 7:45

1290 722 0 AG1 CI 23685 7-Feb-18 8-Feb-18 8:00

1291 722 0 AG1 CI 23686 7-Feb-18 8-Feb-18 8:15

1292 722 0 AG1 CI 23687 7-Feb-18 8-Feb-18 8:30

1294 722 0 AG1 CI 23744 11-Feb-18 12-Feb-18 13:00

1295 722 0 AG1 CI 23749 11-Feb-18 12-Feb-18 13:30

1296 722 0 AG1 CI 23753 12-Feb-18 12-Feb-18 14:00

1297 722 0 AG1 CI 23754 12-Feb-18 12-Feb-18 14:15


1298 722 0 AG1 CI 23755 12-Feb-18 12-Feb-18 15:00

1299 722 0 AG1 CI 23756 12-Feb-18 12-Feb-18 15:15

1323 722 0 AG1 CI 24229 15-Mar-18 17-Mar-18 9:30

1326 722 0 AG1 CI 24254 15-Mar-18 17-Mar-18 8:45

1346 722 0 AG1 CI 24444 26-Mar-18 27-Mar-18 8:15

1347 722 0 AG1 CI 24445 26-Mar-18 27-Mar-18 8:30

1348 722 0 AG1 CI 24501 28-Mar-18 29-Mar-18 8:30

1350 0 0 AG1 CI 4471 31-Mar-18 31-Mar-18 14:30

1359 0 0 AG1 CI 4488 3-Apr-18 4-Apr-18 14:30

1373 0 0 AG1 CI 4547 24-Apr-18 25-Apr-18 14:30

1377 722 0 AG1 CI 25134 29-Apr-18 30-Apr-18 8:00

1378 722 0 AG1 CI 25138 29-Apr-18 30-Apr-18 8:30

1379 722 0 AG1 CI 25159 29-Apr-18 30-Apr-18 11:00


226 722 0 AG1 CI 11054 23-May-17 24-May-17 15:15

227 722 0 AG1 CI 11055 23-May-17 24-May-17 15:30

228 722 0 AG1 CI 11056 23-May-17 24-May-17 15:45

1476 722 0 AG1 CI 11994 14-Jun-17 15-Jun-17 9:00

1495 722 0 AG1 CI 12312 28-Jun-17 29-Jun-17 4:15

1496 722 0 AG1 CI 12313 28-Jun-17 29-Jun-17 4:30

1503 722 0 AG1 CI 12481 4-Jul-17 5-Jul-17 5:15

1505 722 0 AG1 CI 12493 4-Jul-17 5-Jul-17 6:30

1506 722 0 AG1 CI 12499 4-Jul-17 5-Jul-17 7:30

1507 722 0 AG1 CI 12501 4-Jul-17 5-Jul-17 7:45

1513 722 0 AG1 CI 12703 9-Jul-17 10-Jul-17 8:30

1514 722 0 AG1 CI 12705 9-Jul-17 10-Jul-17 8:45

1575 722 0 AG1 CI 13549 30-Jul-17 31-Jul-17 5:30


1576 722 0 AG1 CI 13551 30-Jul-17 31-Jul-17 5:45

1577 722 0 AG1 CI 13552 30-Jul-17 31-Jul-17 6:00

1581 722 0 AG1 CI 13714 1-Aug-17 2-Aug-17 8:30

1582 722 0 AG1 CI 13715 1-Aug-17 2-Aug-17 8:30

1583 722 0 AG1 CI 13716 1-Aug-17 2-Aug-17 8:45

1585 722 0 AG1 CI 13719 1-Aug-17 2-Aug-17 9:00

1603 722 0 AG1 CI 13850 5-Aug-17 6-Aug-17 6:30

1604 722 0 AG1 CI 13851 5-Aug-17 6-Aug-17 6:45

1633 722 0 AG1 CI 14309 14-Aug-17 15-Aug-17 8:45

1642 722 0 AG1 CI 14544 20-Aug-17 20-Aug-17 9:15

1660 722 0 AG1 CI 14825 26-Aug-17 27-Aug-17 4:45

1663 722 0 AG1 CI 14829 26-Aug-17 27-Aug-17 5:00

1664 722 0 AG1 CI 14832 26-Aug-17 27-Aug-17 5:15


1675 722 0 AG1 CI 14930 28-Aug-17 29-Aug-17 10:15

1676 722 0 AG1 CI 14931 28-Aug-17 29-Aug-17 10:30

1679 722 0 AG1 CI 14967 28-Aug-17 29-Aug-17 10:00

1687 722 0 AG1 CI 15004 29-Aug-17 30-Aug-17 9:45

1696 722 0 AG1 CI 15105 6-Sep-17 7-Sep-17 7:00

1697 722 0 AG1 CI 15129 6-Sep-17 7-Sep-17 11:15

1698 722 0 AG1 CI 15133 6-Sep-17 7-Sep-17 11:30

1701 722 0 AG1 CI 15175 9-Sep-17 10-Sep-17 14:30

1703 722 0 AG1 CI 15223 9-Sep-17 10-Sep-17 14:45

1704 722 0 AG1 CI 15232 9-Sep-17 10-Sep-17 16:15

1705 722 0 AG1 CI 15233 9-Sep-17 10-Sep-17 16:30

1706 722 0 AG1 CI 15234 9-Sep-17 10-Sep-17 16:45

1721 0 0 AG1 CI 3106 12-Sep-17 13-Sep-17 13:00


1747 722 0 AG1 CI 15682 18-Sep-17 19-Sep-17 16:30

1748 722 0 AG1 CI 15683 18-Sep-17 19-Sep-17 16:45

1749 722 0 AG1 CI 15684 18-Sep-17 19-Sep-17 17:00

1770 722 0 AG1 CI 15914 24-Sep-17 25-Sep-17 8:00

1773 722 0 AG1 CI 15918 24-Sep-17 25-Sep-17 8:15

1792 0 0 AG1 CI 27-Sep-17 28-Sep-17 13:00

1808 0 0 AG1 CI 3276 3-Oct-17 4-Oct-17 13:00

1810 722 0 AG1 CI 16622 4-Oct-17 5-Oct-17 13:30

1811 722 0 AG1 CI 16623 4-Oct-17 5-Oct-17 13:45

1812 722 0 AG1 CI 16664 5-Oct-17 7-Oct-17 7:00

1813 722 0 AG1 CI 16667 5-Oct-17 7-Oct-17 7:30

1818 722 0 AG1 CI 16710 5-Oct-17 7-Oct-17 16:45

1831 0 0 AG1 CI 8-Oct-17 9-Oct-17 13:00


1833 722 0 AG1 CI 16974 9-Oct-17 10-Oct-17 15:00

1834 722 0 AG1 CI 16975 9-Oct-17 10-Oct-17 15:15

1844 0 0 AG1 CI 3362 12-Oct-17 14-Oct-17 13:00

1856 722 0 AG1 CI 17290 14-Oct-17 15-Oct-17 13:00

1857 722 0 AG1 CI 17291 14-Oct-17 15-Oct-17 13:15

1866 722 0 AG1 CI 17364 15-Oct-17 16-Oct-17 15:00

1867 722 0 AG1 CI 17365 15-Oct-17 16-Oct-17 15:15

1868 722 0 AG1 CI 17366 15-Oct-17 16-Oct-17 15:30

1882 0 0 AG1 CI 3395 17-Oct-17 18-Oct-17 13:00

1887 0 0 AG1 CI 18-Oct-17 19-Oct-17 13:00

1913 0 0 AG1 CI 3452 24-Oct-17 25-Oct-17 13:00

1916 722 0 AG1 CI 18163 24-Oct-17 25-Oct-17 7:00

1917 722 0 AG1 CI 18165 24-Oct-17 25-Oct-17 7:15


1918 722 0 AG1 CI 18167 24-Oct-17 25-Oct-17 7:30

1938 0 0 AG1 CI 29-Oct-17 30-Oct-17 13:00

1940 722 0 AG1 CI 18548 29-Oct-17 30-Oct-17 13:00

1942 722 0 AG1 CI 18551 29-Oct-17 30-Oct-17 13:45

1945 722 0 AG1 CI 18558 29-Oct-17 30-Oct-17 11:30

1946 722 0 AG1 CI 18559 29-Oct-17 30-Oct-17 11:45

1947 722 0 AG1 CI 18560 29-Oct-17 30-Oct-17 13:15

1948 722 0 AG1 CI 18561 29-Oct-17 30-Oct-17 13:30

1960 0 0 AG1 CI 3553 2-Nov-17 4-Nov-17 13:00

1993 722 0 AG1 CI 18925 4-Nov-17 5-Nov-17 13:30

1999 722 0 AG1 CI 18937 4-Nov-17 5-Nov-17 8:30

2003 722 0 AG1 CI 18941 4-Nov-17 5-Nov-17 10:15

2004 722 0 AG1 CI 18942 4-Nov-17 5-Nov-17 10:45


2005 0 0 AG1 CI 3569 5-Nov-17 6-Nov-17 13:00

2027 0 0 AG1 CI 3585 7-Nov-17 8-Nov-17 13:00

2051 0 0 AG1 CI 3608 11-Nov-17 12-Nov-17 13:00

2083 0 0 AG1 CI 3638 14-Nov-17 15-Nov-17 14:00

2108 722 0 AG1 CI 19850 15-Nov-17 16-Nov-17 10:45

2110 722 0 AG1 CI 19865 15-Nov-17 16-Nov-17 14:15

2195 0 0 AG1 CI 3751 26-Nov-17 27-Nov-17 14:00

2209 722 0 AG1 CI 20736 27-Nov-17 28-Nov-17 13:00

2210 722 0 AG1 CI 20738 27-Nov-17 28-Nov-17 13:15

2211 722 0 AG1 CI 20740 27-Nov-17 28-Nov-17 13:30

2212 722 0 AG1 CI 20742 27-Nov-17 28-Nov-17 13:45

2249 0 0 AG1 CI 3798 2-Dec-17 3-Dec-17 14:00

2261 722 0 AG1 CI 21166 3-Dec-17 4-Dec-17 0:00


2262 722 0 AG1 CI 21168 3-Dec-17 4-Dec-17 0:00

2274 722 0 AG1 CI 21253 5-Dec-17 6-Dec-17 13:15

2275 722 0 AG1 CI 21255 5-Dec-17 6-Dec-17 13:30

2276 722 0 AG1 CI 21258 5-Dec-17 6-Dec-17 13:45

2277 722 0 AG1 CI 21262 5-Dec-17 6-Dec-17 14:00

2343 722 0 AG1 CI 21613 11-Dec-17 12-Dec-17 7:00

2345 0 0 AG1 CI 3886 11-Dec-17 12-Dec-17 14:00

2351 722 0 AG1 CI 21775 13-Dec-17 14-Dec-17 8:00

2352 722 0 AG1 CI 21781 13-Dec-17 14-Dec-17 8:30

2353 722 0 AG1 CI 21784 13-Dec-17 14-Dec-17 8:45

2370 722 0 AG1 CI 22101 18-Dec-17 19-Dec-17 10:15

2371 722 0 AG1 CI 22102 18-Dec-17 19-Dec-17 10:30

2372 722 0 AG1 CI 22103 18-Dec-17 19-Dec-17 10:46


2373 722 0 AG1 CI 22104 18-Dec-17 19-Dec-17 11:00

2374 722 0 AG1 CI 22115 18-Dec-17 19-Dec-17 14:45

2375 722 0 AG1 CI 22117 18-Dec-17 19-Dec-17 15:15

2380 722 0 AG1 CI 22154 19-Dec-17 20-Dec-17 8:00

2381 722 0 AG1 CI 22155 19-Dec-17 20-Dec-17 8:15

2392 722 0 AG1 CI 22384 24-Dec-17 24-Dec-17 14:45

2393 722 0 AG1 CI 22387 24-Dec-17 24-Dec-17 15:30

2434 722 0 AG1 CI 22638 30-Dec-17 31-Dec-17 9:45

2435 722 0 AG1 CI 22642 30-Dec-17 31-Dec-17 10:15

2437 0 0 AG1 CI 4071 31-Dec-17 2-Jan-18 14:00

2440 722 0 AG1 CI 22727 3-Jan-18 4-Jan-18 7:15

2455 722 0 AG1 CI 22956 11-Jan-18 13-Jan-18 13:00

2456 722 0 AG1 CI 22957 11-Jan-18 13-Jan-18 13:15


2457 722 0 AG1 CI 22958 11-Jan-18 13-Jan-18 13:30

2458 722 0 AG1 CI 22959 11-Jan-18 13-Jan-18 13:45

2470 722 0 AG1 CI 23334 22-Jan-18 23-Jan-18 11:00

2518 722 0 AG1 CI 24255 15-Mar-18 17-Mar-18 9:00

2519 722 0 AG1 CI 24259 15-Mar-18 17-Mar-18 9:45

2539 722 0 AG1 CI 24495 28-Mar-18 29-Mar-18 7:00

2540 722 0 AG1 CI 24496 28-Mar-18 29-Mar-18 7:15

2541 722 0 AG1 CI 24502 28-Mar-18 29-Mar-18 8:45

2548 0 0 AG1 CI 4472 31-Mar-18 31-Mar-18 14:30

2553 0 0 AG1 CI 4494 4-Apr-18 5-Apr-18 14:30

2561 722 0 AG1 CI 24902 17-Apr-18 18-Apr-18 11:15

2562 722 0 AG1 CI 24905 17-Apr-18 18-Apr-18 11:30

2563 722 0 AG1 CI 24906 17-Apr-18 18-Apr-18 11:45


2564 722 0 AG1 CI 24907 17-Apr-18 18-Apr-18 13:00

2565 722 0 AG1 CI 24908 17-Apr-18 18-Apr-18 13:15

2566 722 0 AG1 CI 24909 17-Apr-18 18-Apr-18 13:30

2576 722 0 AG1 CI 25069 24-Apr-18 25-Apr-18 8:15

2577 722 0 AG1 CI 25070 24-Apr-18 25-Apr-18 8:15

2584 0 0 AG1 CI 4555 25-Apr-18 26-Apr-18 14:30

2589 722 0 AG1 CI 25160 29-Apr-18 30-Apr-18 11:15

2591 722 0 AG1 CI 25249 1-May-18 2-May-18 15:30

2592 722 0 AG1 CI 25255 2-May-18 3-May-18 7:45

2594 0 0 AG1 CI 4597 7-May-18 7-May-18 14:30

2596 0 0 AG1 CI 4608 10-May-18 12-May-18 14:30


DESCRIPTION ITR No SC INSP

(To check elevations and coordinates) as follows, Inspection for excavation & formation level for
Manifold foundation Grid A (12 to 19) Grid B (1 to 29) Grid C (1 to 29) at Pattern-24 (Refer to C-0101X ADAM
highlighted area in the drawing)

Inspection for field density test for Manifold foundation Prior blinding Grid A (12 to 19) Grid B (1 ADAM
to 29) Grid C (1 to 29) at Pattern-24 (Refer to highlighted area in the drawing)

Inspection for Concrete Pouring for Manifold foundation Prior blinding Grid A (12 to 19) Grid B (1 C-0204X ADAM
to 29) Grid C (1 to 29) at Pattern-24 (Refer to highlighted area in the drawing)

Inspection of Concrete Pour for foundation for manifold platform for Grid A (12to 19 ) Grid B (1 C-0210X/C-0204X ADAM
to 29)& Grid C (1 to 29 ) at Pattern-24 (Refer to highlighted area in the drawing)

Inspection for Fixing of reinforcement prior to close formwork for manifold pedestal Grid A (12 to C-0201X ADAM
19) Grid B ( 1to 29) at Pattern-24 (Refer to highlighted area in the drawing)

Inspection for Fixing of ancher bolts formwork & alignment for manifold pedestal from Grid A (12
to 19 ) Grid B (1 to 29) Grid C (1 to 29) at well block-2 pattern-24 (Refer to highlighted area in the C-0201X/C-0203X ADAM
drawing)

Inspection for Concrete pour for manifold pedestal from Grid A (12 to 19 ) Grid B (1 to 29) Grid C
ADAM
(1 to 29) at well block-2 pattern-24 (Refer to highlighted area in the drawing)

Inspection for Surface preparation for manifold Platform foundation 7 Pedestal Grid A (12 to 19) & C-0202X ADAM
Grid B (1 to 29 ) Grid C (1 to 29) at well Block-2 in Pattern-24

Inspection for Bitumen application for manifold Platform foundation & pedestal Grid A (12 to 19) C-0202X ADAM
Grid B ( 1 to 29 ) Grid C ( 1 to 29) at well Block-2 in Pattern-24

Inspection for Laying of 1000 Gauge Polythylene for manifold Platform foundation & pedestal C-0202X ADAM
Grid A (12 to 19) Grid B ( 1 to 29 ) Grid C ( 1 to 29) at well Block-2 in Pattern-24

Inspection for Field density test for first & Final layer 300mm Backfilling of manifold Grid A (12 to ADAM
19) Grid B ( 1 to 29) Grid C ( 1 to 29) at well Block-2 in Pattern-24

Inspection for Excavation & Formation level for Extension manifold foundation from F1(3 to C-0101X C-0203X ADAM
139)F2(4 to 140) F3 (2 to138) F4A(1 to 137) at well Block-02 in Pattern-24
Inspection for Field density Test prior to Bilnding for Extension manifold foundation from F1(3 to ADAM
139)F2(4 to 140) F3 (2 to138) F4A(1 to 137) at well Block-02 in Pattern-24

Inspection for Bilnding Concrete pour for Extension manifold foundation prior to Bilnding from C-0204X ADAM
F1(3 to 139)F2(4 to 140) F3 (2 to138) F4A(1 to 137) at well Block-02 in Pattern-24

Inspection for Fixing of Reinforcement & Alignment of formwork for Foundation Manifold ADAM
Extension F1(3 to 139) F2( 4 to 140) F3( 2 to 138) F4A( 1 to 137) at well Block-2 in Pattern-24

Inspection for concrete pour for Foundation Manifold Extension F1(3 to 139) F2( 4 to 140) F3( 2 to ADAM
138) F4A( 1 to 137) at well Block-2 in Pattern-24

Inspection for concrete Pour For foundation for Manifold Excitation F1(3 to 139) F2(4 to 140) F3(2
ADAM
to 138) F4A(1 to 137) at well Block-2 in Pattern-24

Inspection of Fixing of Reinforcement & Alignment of formwork for foundation Manifold


Excitation F1(3 TO 139) F1(3 TO 139) F2(4 TO 140) F3(2 TO 138) F4A(1 TO 137) at well Block-2 in C-0201X C-0203X ADAM
Pattern-24

Inspection of Concrete Pouring for foundation Manifold Excitation F1(3 TO 139) F1(3 TO 139) F2(4 C-0210X C-0204X ADAM
TO 140) F3(2 TO 138) F4A(1 TO 137) at well Block-2 in Pattern-24

Inspection for Fixing of reinforcement & Alignment of formwork for Foundation for Manifold C-0201X C-0203X ADAM
Platform F5(4NO) at well Block-2 in Pattern-24

Inspection for Concrete pour for Foundation for Manifold Platform F5(4NO) at well Block-2 in
C-0210X C-0204X ADAM
Pattern-24

Inspection for Excavation & Formation level for Extension Manifold Foundation from F2(142 to
166) F1(142 TO 166) F2(141 TO 165) F3(143 TO 167) F4A(144 TO 168) at well Block-2 in Pattern-24 C-0101X C-0203X ADAM

Inspection for Field density test prior to Bilnding for Extension Manifold Foundation from F2(142
to 166) F1(142 TO 166) F2(141 TO 165) F3(143 TO 167) F4A(144 TO 168) at well Block-2 in ADAM
Pattern-24

Inspection for Bilnding concrete for Extension Manifold Foundation from F2(142 to 166) F1(142 ADAM
TO 166) F2(141 TO 165) F3(143 TO 167) F4A(144 TO 168) at well Block-2 in Pattern-24

Inspection of concrete Pour for foundation for manifold platform F5( 4 NO) at well Block-2 in ADAM
Pattern-24
Inspection of concrete Pour for foundation for manifold Excitation F4A ( 1 to 137) at well Block-2 C-0210X C-0204X ADAM
in Pattern-24

Inspection for Fixing of reinforcement & Alignment of formwork for Foundation for Manifold
Extension F1(3 TO 23) F1( 3 TO 23) F2(4 TO 24) F3(2 TO 22) F4A(1 TO 21) at well Block-2 in C-0201X C-0203X ADAM
Pattern-24

Inspection for concrete pour for Foundation for Manifold Extension F1(3 TO 23) F1( 3 TO 23) F2(4 C-0210X C-0204X ADAM
TO 24) F3(2 TO 22) F4A(1 TO 21) at well Block-2 in Pattern-24

Inspection for Fixing of reinforcement prior to close formwork for manifold Extention F1( 103 TO
139) F1(103 TO 139) F2(104 TO 140) F3(102 TO 138) F4A(107 TO 137) At well Block-2 at Pattern- C-0201X C-0203X ADAM
24

Inspection for Field density test for First & Final Layer 300mm Backfilling of manifold mixing Gatch
ADAM
Grid A (12 TO 19) Grid B (1 to 29) Grid C (1 to 29) at well Block-2 in Pattern-24

Inspection for blinding concrete pour for (ESDV Platform) in manifold area at well block - 2 IN C-0204X ADAM
Pattern-24

Inspection for Excavation & Formation level for ESDV Platform in Manifold area at well block-2 In ADAM
Pattern-24

Inspection for Field density Test Prior to Bilnding for ESDV Platform in Manifold area at well block- ADAM
2 In Pattern-24

Inspection for fixing of Reinforcement prior to close formwork for Manifold Extension F1(3 TO
99,142 TO 166) F1(3 TO 99,142 TO 166)F2(4 TO 100,141 TO 165) F3(2 TO 98,143 TO 167) F4A(1 C-0201X SURESH
TO 97) at well Block-2 in Pattern-24

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal
F1(103 TO 139) F1(103 TO 139) F2(104 TO 140) F3(102 TO 138) F4A(101 TO 137) at well Block-2 in C-0201X C-0203X SURESH
Pattern-24

Inspection for Concrete pour for anchor Bolts for Manifold Extension Pedestal F1(103 TO 139) C-0210X C-0204X SURESH
F1(103 TO 139) F2(104 TO 140) F3(102 TO 138) F4A(101 TO 137) at well Block-2 in Pattern-24

Witness and checked compressive strength crushing tests for Manifold Extension Pedestal With
anchor Bolts F1(103 TO 139), F1,(103, TO 139,), F2(104 TO 140), F3(102 TO 138), F4A(101 TO 137) SURESH
@ Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Inspection for Concrete Foundation Release & Shim Plate Installation for Manifold Platform C-0201X / C-0203X SURESH
Foundation Grid A (12 to 19) Grid B (1 to 29) Grid C (1 to 29) at well Block-2 in Pattern-24
Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal F1(63 C-0201X C-0203X SURESH
TO 99) F1( 63 TO 99) F2(64 TO 100) F3(62 TO 98) F4A(61 TO 97) at well Block-2 in Pattern-24

Inspection for Concrete Pour of anchor Bolts for Manifold Extension Pedestal F1(63 TO 99) F1( 63 C-0210X C-0204X SURESH
TO 99) F2(64 TO 100) F3(62 TO 98) F4A(61 TO 97) at well Block-2 in Pattern-24

Witness and checked compressive strength crushing tests for pipe sleeper pedestal SL24-94010
(23,25,27C,27 TO 34) @ Pattern-24 & Foundation Manifold Extension F2(4 to 24) @ Pattern-25. SURESH
Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Witness and checked compressive strength crushing tests for Manifold Extension Pedestal with
anchor Bolts F1(63 TO 99) F1,( 63, TO 99,) F2(64 TO 100) F3(62 TO 98) F4A(61 TO 97) @ Pattern- SURESH
24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Inspection for Fixing of anchor Bolts formwork & Alignment for Manifold Extension Pedestal F1(3
C-0201X / C-0203X SURESH
TO 59) F1(3 TO 59) F2(4 TO 60) F3(2 TO 58) F4A (1 TO 57) at well Block-2 in Pattern-24

Inspection for concrete Pour for anchor Bolts for Manifold Extension Pedestal F1(3 TO 59) F1(3 TO C-0210X C-0204X OMBION
59) F2(4 TO 60) F3(2 TO 58) F4A (1 TO 57) at well Block-2 in Pattern-24

Inspection for Fixing of anchor Bolts formwork & Alignment for Manifold Pedestal for F5(4 NO) at C-0201X C-0203X SURESH
well Block-2 in Pattern-24

Inspection for concrete Pour for Anchor Bolts for Manifold pedestal for F5 (4 NO) at well Block-2 in C-0210X C-0204X OMBION
Pattern-24

Inspection for Surface Preparation for Manifold Extension F1 (3 TO 139) F1(3 TO 139) F2(4 TO 140)
SURESH
F3( 2 TO 138) F4A (1 TO 137) at well Block-2 in Pattern-24

Inspection for Bitumen Application for Manifold Extension F1 (3 TO 139) F1(3 TO 139) F2(4 TO C-0202X SURESH
140) F3( 2 TO 138) F4A (1 TO 137) at well Block-2 in Pattern-24

Inspection for Fixing of anchor Bolts formwork & Alignment for Manifold Extension Pedestal
F1(142 to 166),F1'(142' to 166'),F2(141 to 165),F3(143 to 167),F4A(144 to 168) at well Block-2 in SURESH
Pattern-24

Inspection for Concrete Pour for anchor Bolts for Manifold Extension pedestal F1( 142 TO 166) F1 C-0210X C-0204X OMBION
(142 TO 166) F2 (141 TO 165 ) F3 (143 TO 167) F4A (144 TO 168) at well Block-2 in Pattern-24

Witness and checked compressive strength crushing tests for Manifold Extension Pedestal With
anchor Bolts F1(103 TO 139), F1,(103, TO 139,), F2(104 TO 140), F3(102 TO 138), F4A(101 TO 137) SURESH
@ Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.
Witness and checked compressive strength crushing tests for Up to Bottom of Plinth Beam for
Substation Package (722-Z-Substation-25119) with anchor Bolts @ Pattern-25,Manifold Extension
Pedestal with anchor Bolts F1(3 TO 59) F1,(3, TO 59,) F2(4 TO 60) F3(2 TO 58) F4A (1 TO SURESH
57),F1( 142 TO 166) F1, (142, TO 166,) F2 (141 TO 165 ) F3 (143 TO 167) F4A (144 TO 168),F5 (4
Nos), Foundation for Pipe sleeper SL24-94010(80,111,115A,117,117A,185,188,190,206) @
Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal
F2(141 TO 165) F1(142 TO 166) F1(142 TO 166) F3(143 TO 167) F4A (144 TO 168) at well Block-2 C-0203X SURESH
in Pattern-24

concrete Prepour Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold
Extension Pedestal F2(141 TO 165) F1(142 TO 166) F1(142 TO 166) F3(143 TO 167) F4A (144 TO C-0201X SURESH
168) at well Block-2 in Pattern-24

concrete pour Inspection for concrete Pour for Pedestal with anchor Bolts for Manifold Extension
Pedestal F2(141 TO 165) F1(142 TO 166) F1(142 TO 166) F3(143 TO 167) F4A (144 TO 168) at well C-0210X C-0204X SURESH
Block-2 in Pattern-24
Inspection for Field Density Test for First to Final Layer 300mm Backfilling of Manifold Extension
Mixing with Gatch F1 (3 to 138) F1(3 to 138) F2(4 to 139) F3(2 to 137) F4A(1 to 136) at well Block-
2 in Pattern-24
C-0101X SURESH

Inspection for Field Density Test for First to Final Layer 300mm Backfilling of Manifold Extension
Mixing with Gatch F1 (142 to 166) F1(142 to 166) F2 (141 TO 165) F3(143 TO 167) F4A(144 TO
168) at well Block-2 in Pattern-24
C-0101X SURESH

Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal Remaining
300mm from The top SL17-92181(40,46,47,50,51,53,54,57,69) SL18-92181(7,8,18,19,21,24,28,30
TO 34,36 TO 46), Pedestal with anchor Bolts for Manifold Extension Pedestal F2(141 TO 165)
F1(142 TO 166) F1,(142, TO 166,) F3(143 TO 167) F4A (144 TO 168), Pipe sleeper Pedestal top of N/A SURESH
Steel SL51-92082 (1 TO 35) @ Pattern-24,Transformer RMU,ACCU1,ACCU2 at Substation Package
(722-Z-substation-25119) Foundation@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in
third party M/S ATS For 07 Days.
Witness and checked compressive strength crushing tests for pipe sleeper pedestal SL24-94010
(23,25,27C,27 TO 34) @ Pattern-24 & Foundation Manifold Extension F2(4 to 24) @ Pattern-25. SURESH
Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Witness and checked compressive strength crushing tests for Manifold Extension Pedestal with
anchor Bolts F1(63 TO 99) F1,( 63, TO 99,) F2(64 TO 100) F3(62 TO 98) F4A(61 TO 97) @ Pattern- SURESH
24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Witness and checked compressive strength crushing tests for Up to Bottom of Plinth Beam for
Substation Package (722-Z-Substation-25119) with anchor Bolts @ Pattern-25,Manifold Extension
Pedestal with anchor Bolts F1(3 TO 59) F1,(3, TO 59,) F2(4 TO 60) F3(2 TO 58) F4A (1 TO SURESH
57),F1( 142 TO 166) F1, (142, TO 166,) F2 (141 TO 165 ) F3 (143 TO 167) F4A (144 TO 168),F5 (4
Nos), Foundation for Pipe sleeper SL24-94010(80,111,115A,117,117A,185,188,190,206) @
Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection for Bilnding concrete for Manifold Extension


(132,169,170,171,172,173,174,175,176,177,176,177,178,179,180,181,182) at well Block-2 Area C-0204X SURESH
in Pattern-24

Inspection for Excavation & Formation Level for Manifold Extension


(132,169,170,171,172,173,174,175,176,177,176,177,178,179,180,181,182) at well Block-2 Area SURESH
in Pattern-24

Inspection for Excavation & Formation Level for Manifold Extension


(132,169,170,171,172,173,174,175,176,177,176,177,178,179,180,181,182) at well Block-2 Area C-0101X SURESH
in Pattern-24
Inspection for Field Density Test Prior to Bilnding for Manifold Extension
(132,169,170,171,172,173,174,175,176,177,176,177,178,179,180,181,182) at well Block-2 Area C-0101X SURESH
in Pattern-24

Inspection for Location & Formation for Electrical Cable Trench for Manifold area South Side at C-0102X SURESH
well Block-2 in Pattern-24

Inspection for Location & Formation for Electrical Cable Trench for Manifold area South Side at C-0101X SURESH
well Block-2 in Pattern-24

Inspection for Location & Formation for Instrument Cable Trench for Manifold area South Side at C-0102X SURESH
well Block-2 in Pattern-24

Inspection for Location & Formation for Instrument Cable Trench for Manifold area South Side at
C-0101X SURESH
well Block-2 in Pattern-24

Inspection for Location & Excavation for Instrument cable Trench for Manifold Area North Side at C-0102X SURESH
Well Block-2 in Pattern-24

Inspection for Location & Excavation for Instrument cable Trench for Manifold Area North Side at C-0101X SURESH
Well Block-2 in Pattern-24

Inspection for Location & Excavation for Electrical cable Trench for Manifold Area (North Side) at C-0102X SURESH
well Block-2 in Pattern-24

Inspection for Location & Excavation for Electrical cable Trench for Manifold Area (North Side) at
C-0101X SURESH
well Block-2 in Pattern-24

Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal Remaining
300mm from The top SL17-92181(40,46,47,50,51,53,54,57,69) SL18-92181(7,8,18,19,21,24,28,30
TO 34,36 TO 46), Pedestal with anchor Bolts for Manifold Extension Pedestal F2(141 TO 165)
F1(142 TO 166) F1,(142, TO 166,) F3(143 TO 167) F4A (144 TO 168), Pipe sleeper Pedestal top of SURESH
Steel SL51-92082 (1 TO 35) @ Pattern-24,Transformer RMU,ACCU1,ACCU2 at Substation Package
(722-Z-substation-25119) Foundation@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in
Witness and checked compressive
third strength
party M/Scrushing
ATS Fortests for Pedestal with anchor Bolts for
28 Days.
Manifold Extension F1(3 TO 23), F1, (3, TO 23,), F2(4 TO 24), F3 (2 TO 22), F4A (1 TO 21) & Pipe
sleeper Pedestal Remaining 300mm from the top SL1-92191 (3,10,13,32,33) SL2-92191(6,7, 8,9,
16A,28,39A,64,86,87A) @Pattern-25,Pipe sleeper Pedestal Remaining 300mm from The top SL7- SURESH
92181(15,19,20,25,26,27,52,56,57,62,63,64,89,93,94,99,124, 125,128 ,129,130, 132, 134, 135,
136) @Pattern-24,Pipe sleeper Pedestal top of Steel SL13-92011 (54) @ Pattern-04. Well Block 2,
K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Inspection for Manual Excavation Hard soil & Formation Level for ESDV Platform in Manifold Area C-0203X SURESH
at Well Block-2 in Pattern-24

Inspection for Excavation & Formation Level for ESDV Platform in Manifold Area at Well Block-2 in C-0101X SURESH
Pattern-24
Inspection for Field Density Test Prior to Bilnding for ESDV Platform in Manifold Area at Well Block- C-0101X SURESH
2 in Pattern-24

Inspection for Bilnding Concrete Pour for ESDV Platform in Manifold Area at Well Block-2 in C-0204X SURESH
Pattern-24

Inspection for Concrete Foundation Release & shim Plate Installation for manifold extantion
Foundation F1 (3 to 139), F1'(3' to 139'),F2(4 to 140),F3(2 to 138),F4A(1 to 137) at well Block-2 in C-0203X SURESH
Pattern-24

Inspection for Concrete Foundation Release & shim Plate Installation for manifold extantion
Foundation F1 (3 to 139), F1'(3' to 139'),F2(4 to 140),F3(2 to 138),F4A(1 to 137) at well Block-2 in C-0207A SURESH
Pattern-24

Inspection for Fixing of Reinforcement & Alignment of Formwork for Foundation ESDV Platform in
C-0203X SURESH
Manifold Area at well Block-2 in Pattern-24

Inspection for Fixing of Reinforcement & Alignment of Formwork for Foundation ESDV Platform in C-0201X SURESH
Manifold Area at well Block-2 in Pattern-24

Inspection for Concrete Pour for Foundation ESDV Platform in Manifold Area at well Block-2 in C-0210X/C-0204 SURESH
Pattern-24

Inspection for Field Density Test for Gatch Filling at Manifold Extension F1 (3 TO 139) F1 (3 TO 139) SURESH
F2(4 TO 140) F3 (2 TO 138) F4A (1 TO 137) at well Block-2 in Pattern-24

Inspection for Concrete Foundation Release & Shim Plate Installation for Manifold Extension
Foundation F1 (142 TO 166) F1 (142 TO 166) F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 168) at C-0203X SURESH
well Block-2 in Pattern-24

Inspection for Concrete Foundation Release & Shim Plate Installation for Manifold Extension
Foundation F1 (142 TO 166) F1 (142 TO 166) F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 168) at C-0207A SURESH
well Block-2 in Pattern-24
Witness and checked compressive strength crushing tests for Pedestal with anchor Bolts for
Manifold Extension F1(3 TO 23), F1, (3, TO 23,), F2(4 TO 24), F3 (2 TO 22), F4A (1 TO 21) & Pipe
sleeper Pedestal Remaining 300mm from the top SL1-92191 (3,10,13,32,33) SL2-92191(6,7, 8,9,
16A,28,39A,64,86,87A) @Pattern-25,Pipe sleeper Pedestal Remaining 300mm from The top SL7- SURESH
92181(15,19,20,25,26,27,52,56,57,62,63,64,89,93,94,99,124, 125,128 ,129,130, 132, 134, 135,
136) @Pattern-24,Pipe sleeper Pedestal top of Steel SL13-92011 (54) @ Pattern-04. Well Block 2,
K300 SRC Concrete cubes in third party M/S ATS For 28 Days.
Witness and checked compressive strength crushing tests for Foundation ESDV Platform in
Manifold Area @ Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 SURESH
Days.

Inspection for Concrete Foundation Release & Insert Plate Installation for manifold Extantion
Foundation F1 (142 TO 166) F1 (142 TO 146) F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 148) at C-0207A SURESH
well Block-2 in Pattern-24
Inspection for Field density test top of Gatch Filling Prior to Laying Gravel at Manifold Extension
F1 (142 TO 166) F1 (142 TO 146) F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 148) at well Block- SURESH
2 in Pattern-24

Inspection for Field Density Test for First to Final Layer (300mm) Backfilling of (ESDV Platfrom) SURESH
mixing with Gatch at manifold Area at well Block-2 in Pattern-24

(To check elevations and coordinates) as follows Inspection for Installed of precast for MOVDB C-0203X SURESH
FITDB NLDB at Manifold Area at well Block-2 in Pattern-24

Inspection for Installed of precast for MOVDB FITDB NLDB at Manifold Area at well Block-2 in C-0208X SURESH
Pattern-24

(To check elevations and coordinates) as follows Inspection for Installed of precast for Light Pole
C-0203X SURESH
at Manifold Area at well Block-2 in Pattern-24

Inspection for Installed of precast for Light Pole at Manifold Area at well Block-2 in Pattern-24 C-0208X SURESH

Inspection For Field density test for first to final layer (300mm) backfilling of (ESDV Platform) C-0101X SURESH
mixing gatch at manifold area at in Pattern-24

Inspection for Concrete foundation release &insert plate installation For (ESDV Platform) in SURESH
manifold area at in Pattern-24

Inspection for Field density test for 4TH to final layer (300mm) backfilling of (ESDV Platfrom)
C-0101X SURESH
mixing with gatch at manifold area at well Block-2 in Pattern-24

Witness and checked compressive strength crushing tests for Foundation ESDV Platform in
Manifold Area @ Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 SURESH
Days.

Inspection for Field density test for final layer (300mm) backfilling for Light Pole (10m) in Manifold C-0101X SURESH
Area at well Block-2 in Pattern-24

(To check elevations and coordinates) as follows Inspection for Excavation & Formation level for C-0203X SURESH
manifold extension CS-(13Nos) at well Block-2 in Pattern-24

Inspection for Excavation & Formation level for manifold extension CS-(13Nos) at well Block-2 in SURESH
Pattern-24
Inspection for Field density test Prior blinding for manifold extension CS-(13Nos) at well Block-2 in SURESH
Pattern-24

Inspection for blinding Concrete for manifold extension CS-(13Nos) at well Block-2 in Pattern-24 SURESH

Inspection for Field Density test For Gravel Filling at manifold Platfrom Grid A (12 TO 19) Grid B (1 SURESH
TO 29) Grid C (1 TO 29) at well Block-2 in Pattern-24

Inspection for Formwork of Grout foundation Manifold extension F1 (3 TO 139) F1 (3 TO 139) F2 (4 C-0401X SURESH
TO 140) F3 (2 TO 139) F4A (1 TO 138) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for foundation Manifold extension F1 (3 TO 139) F1 (3 TO
C-0401X SURESH
139) F2 (4 TO 140) F3 (2 TO 139) F4A (1 TO 138) at well Block-2 in Pattern-24

Inspection for Formwork of Grout foundation Manifold extension F1 (142 TO 167) F1 (142 TO 167) SURESH
F2 (141 TO 166) F3 (143 TO 168) F4A (144 TO 169) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for foundation Manifold extension F1 (142 TO 167) F1 SURESH
(142 TO 167) F2 (141 TO 166) F3 (143 TO 168) F4A (144 TO 169) at well Block-2 in Pattern-24

Inspection for Formwork of Grout Manifold Platfrom Foundation Grid A (12 to 19) Grid B ( 1 to 29) SURESH
Grid C (1 to 29) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for Manifold Platfrom Foundation Grid A (12 to 19) Grid B
SURESH
( 1 to 29) Grid C (1 to 29) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for foundation Manifold extension F1 (47 TO 99) F1 (47 C-0401X SURESH
TO 99) F2 (48 TO 100) F3 (46 TO 98) F4A (45 TO 97) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for foundation Manifold extension F1 (103 TO 139) F1 C-0401X SURESH
(103 TO 139) F2 (104 TO 140) F3 (102 TO 138) F4A (101 TO 137) at well Block-2 in Pattern-24

Inspection for Formwork of Grout foundation Manifold extension F1 (142 TO 166) F1 (142 TO 166) C-0401X SURESH
F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 168) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for Foundation Manifold extension F1 (142 TO 166) F1 C-0401X SURESH
(142 TO 166) F2 (141 TO 165) F3 (143 TO 167) F4A (144 TO 168) at well Block-2 in Pattern-24
Inspection for Formwork of Grout manifold Platform foundation Grid A (1 TO 29) Grid B (1 TO 29) C-0401X SURESH
Grid C ( 1 TO 29) at well Block-2 in Pattern-24

Inspection for Grout mixing and Placing for manifold Platform Foundation Grid A (1 TO 29) Grid B C-0401X SURESH
(1 TO 29) Grid C ( 1 TO 29) at well Block-2 in Pattern-24

Inspection for bitumen application for PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE SURESH


TCPR,Light Pole (10 M) Sheet (1 to 6) & Manifold Area at well Block-2 in Pattern-24

Inspection for Surface Preparation for PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE SURESH


TCPR,Light Pole (10 M) Sheet (1 to 6) & Manifold Area at well Block-2 in Pattern-24

Inspection for Formwork of Grout Foundation for Light Pole (10M 8NO) at Manifold Area at well
C-401X SURESH
Block-2 in Pattern-24

Inspection for Grout mixing and Placing for Light Pole (10M 8NO) at Manifold Area at well Block-2 C-401X SURESH
in Pattern-24

protection for Concrete Surfaces. Inspection For laying of 1000 gauge Polyethylene for
PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE,TCPR,Light Pole (10 M) Sheet (1 to 6) & SURESH
Manifold Area at Pattern-24

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-24. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 01 Days.

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-24. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 07 Days.

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-24. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 28 Days.

Inspection for Concrete Surface Preparation Prior to Epoxy Paint Above The Ground for manifold
extension F1 (142 to 166),F1' (142' to166'), F2 (141 to 165), F3 (143 to 167), F4A (144 to 168) at SURESH
well Block-2 in Pattern-24

Inspection for Concrete Surface Preparation Prior to Epoxy Paint Above The Ground for manifold
extension F1 (3 to 139),F1' (3' to139'), F2 (4 to 140), F3 (2 to 138), F4A (1 to 137) at well Block-2 in SURESH
Pattern-24

Inspection for Concrete Surface Preparation Prior to Epoxy Paint Above The Ground for manifold SURESH
Platform Grid A (12 to 19), Grid B (1 to 29), Grid C (1 to 29) at well Block-2 in Pattern-24
Concrete pour Inspection for Fixing of ancher Bolts Formwork & alignment for manifold pedestal
from Grid A (12 to 19 ) Grid B (12 to 20) Grid C(12 to 20 )at Pattern-24 (Refer to highlighted area C-0201X/C-0203X ADAM
in the drawing)

Concrete prepour Inspection for Fixing of ancher Bolts Formwork & alignment for manifold
pedestal from Grid B (21 to 29) Grid C(21 to 29 )at Pattern-24 (Refer to highlighted area in the C-0201X/C-0203X ADAM
drawing)

Concrete pour Inspection for Concrete pour for manifold pedestal from Grid A (12 to 19 ) Grid B (1 C-0210X/C-0204X ADAM
to 29) Grid C(1 to 29 )at Pattern-24 (Refer to highlighted area in the drawing)

Inspection for Fixing of reuinforcement prior to close formwork for manifold pedestal Grid A ( 1 to C-0201X ADAM
23) Grid B( 1 to 23) Grid C (6 to 17A) at pattern-25 (Refer to highlighted area in the drawing)

Inspection for fixing of ancher bolts formwork & Alignment for manifold pedestal from Grid B (1 to
ADAM
10) Grid C(1 to 10)at Pattern-25

Inspection for concrete pour for manifold pedestal from Grid B (1 to 10) Grid C(1 to 10)at Pattern- ADAM
25

Inspection for concrete pour for manifold pedestal For Grid B (1 to 10) Grid C ( 1 to 10) at well C-0210X C-0204X ADAM
block-2 in Pattern-25

Inspection for Fixing of anchor Bolts formwork & Alignment for manifold pedestal from Grid B ( 1 C-0201X C-0203X ADAM
to 10) Grid C (1,3,5,6,7) at well block-2 in Pattern-25

Inspection for Fixing of anchor Bolts formwork & Alignment for manifold pedestal From Grid B ( 11
C-0201X C-0203X ADAM
to 15) Grid C (11 to 15) at well block-2 in Pattern-25

Inspection for concrete pour of anchor Bolts for manifold pedestal From Grid B ( 11 to 15) Grid C C-0210X C-0204X ADAM
(11 to 15) at well block-2 in Pattern-25

Inspection for Fixing of anchor Bolts formwork & Alignment for manifold pedestal From Grid A (11 C-0201X C-0203X ADAM
to17) Grid B(16 to 21) Grid C (16 to 21) at well Block-02 in Pattern-25

Inspection for Concrete pour for anchor Bolts formwork & Alignment for manifold pedestal From C-0210X C-0204X ADAM
Grid A (11 to17) Grid B(16 to 21) Grid C (16 to 21) at well Block-02 in Pattern-25

Inspection for Excavation & Formation level for manifold Extension F1(26 to 142) F3( 27 to 143) C-0101X C-0203X ADAM
F4A(28 to 144) at well Block-2 in Pattern-25
Inspection for Field density test prior to Bilnding for manifold Extension F1(26 to 142) F3( 27 to ADAM
143) F4A(28 to 144) at well Block-2 in Pattern-25

Inspection for Bilnding concrete for manifold Extension F1(26 to 142) F3( 27 to 143) F4A(28 to C-0204X ADAM
144) at well Block-2 in Pattern-25

Inspection for Surface preparation for manifold Platform Grid B(1 to 10) Grid C (1 to 10) at well C-0202X ADAM
Block-2 in Pattern-25

Inspection for Excavation & Formation level for Manifold Extension F1(3 TO 23) F1( 3 TO 26) F2(4 C-0101X C-0203X ADAM
TO 27) F3(2 TO 22) F4A(1 TO 21) at well Block-2 in Pattern-25

Inspection for Field density test prior to Bilnding for Manifold Extension F1(3 TO 23) F1( 3 TO 26)
ADAM
F2(4 TO 27) F3(2 TO 22) F4A(1 TO 21) at well Block-2 in Pattern-25

Inspection for Bilnding concrete for Manifold Extension F1(3 TO 23) F1( 3 TO 26) F2(4 TO 27) F3(2 C-0204X ADAM
TO 22) F4A(1 TO 21) at well Block-2 in Pattern-25

Inspection for Surface Preparation for Manifold Platform Grid A (11 to 17) Grid B (11 to 27) Grid C C-0202X ADAM
(11 to 27) At well Block-2 at Pattern-25

Inspection for Bitumen Application for Manifold Platform Grid A (11 to 17) Grid B (11 to 27) Grid C-0202X ADAM
C (11 to 27) At well Block-2 at Pattern-25

Inspection For Fixing of Reinforcement & Alignment of formwork for Foundation manifold
C-0201X C-0203X ADAM
Extension F1(26 to 102) F3(27 to 103) F4A(28 to 104) at well Block-2 in Pattern-25

Inspection for fixing of reinforcement & Allignment of formwork for foundation manifold
extension F1(3 to 23) F1-(106 to 142) F2(4 to 24) F3(2 to 22 , 107 to 143) F4A(1 to 21, 108 to 144) ADAM
at well block-2 in pattern-25

Inspection for Excavation and formation level for manifold extension F1(26 to 142) F2(25 to 141) C-0101X C-0203X ADAM
F5(4 NO) at well block - 2 IN Pattern-25

Inspection for Field density Test for manifold extension Prior blinding fromF1(26 to 142) F2(25 to ADAM
141) F5(4 NO) at well block - 2 IN Pattern-25

Inspection for blinding concrete for manifold extension F1(26 to 142) F2(25 to 141) F5(4 NO) at C-0204X ADAM
well block - 2 IN Pattern-25
Inspection for Field density Test for Manifold Extension Prior to Blinding from F2(4 to 24) at well ADAM
block - 2 IN Pattern-25

Inspection for blinding concrete for Manifold Extension F2(4 to 24) at well block - 2 IN Pattern-25 C-0204X ADAM

Inspection for Excavation & Formation level for Manifold Extension F2(4 to 24) at well block-2 In C-0101X C-0203X ADAM
Pattern-25

Inspection for Fixing of Reinforcement prior to close formwork for Manifold Extension (F1(26 TO C-0201X ADAM
142) F2(25 TO 141)F4(4 no) at well Block-2 in Pattern-25

Inspection for Fixing of Reinforcement prior to close formwork for manifold Extension F1926 TO
C-0201X SURESH
142) F3(28 TO 144) at well Block-2 in Pattern-25

Inspection for Fixing of Reinforcement & Alignment of Formwork for Foundation Manifold C-0201X C-0203X SURESH
Extension F1(26 TO 142) F2(25 TO 141) F4(145,146) F5(4 NOS) at well Block-2 in Pattern-25

Inspection for concrete pour for Foundation Manifold Extension F1(26 TO 142) F2(25 TO 141) C-0210X C-0204X SURESH
F4(145,146) F5(4 NOS) at well Block-2 in Pattern-25

Inspection for Fixing of Reinforcement & Alignment of formwork for Foundation Manifold C-0201X C-0203X SURESH
Extension F3 (2 to 22) at well Block-2 in Pattern-25

Inspection for concrete pour for Foundation for Manifold Extension F3(2 to 22) at well Block-2 in
SURESH
Pattern-25

Inspection for Excavation & Formation Level for Manifold Extension F2(151,152) at well Block-2 in C-0101X SURESH
Pattern-25

Inspection for Field density test prior to Bilnding for Manifold Extension F2(151,152) at well C-0204X SURESH
Block-2 in Pattern-25

Inspection for Bilnding Concrete pour for Manifold Extension F2(151,152) at well Block-2 in C-0204X SURESH
Pattern-25

Witness and checked compressive strength crushing tests for foundation for pipe sleeper SL51-
92192 (13 TO 43) & Foundation Manifold Extension F1(26 TO 142) F2(25 TO 141) F4(145,146) F5(4 SURESH
NOS)@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.
Inspection for Fixing of reinforcement & Alignment of formwork for Foundation Manifold C-0201X C-0203X SURESH
Extension F2(4 to 24) at well Block-2 in Pattern-25

Inspection for Concrete pour for Foundation Manifold Extension F2(4 to 24) at well Block-2 in C-0210X C-0204X SURESH
Pattern-25

Inspection for Fixing of reinforcement prior to close formwork for Manifold Extension F1(26 TO 82) C-0201X SURESH
F1(26 TO 82) F2(25 TO 81) F3(27 TO 83) F4A(28 TO 84) at well Block-2 in Pattern-25

Inspection for Fixing of Reinforcement & Alignment of formwork for Foundation Manifold C-0201X C-0203X SURESH
Extension F2 (151,152) at well Block-2 in Pattern-25

Inspection for concrete Pour for Foundation Manifold Extension F2 (151,152) at well Block-2 in
SURESH
Pattern-25

Witness and checked compressive strength crushing tests for pipe sleeper pedestal SL24-94010
(23,25,27C,27 TO 34) @ Pattern-24 & Foundation Manifold Extension F2(4 to 24) @ Pattern-25. SURESH
Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Witness and checked compressive strength crushing tests for foundation for pipe sleeper SL51-
92192 (13 TO 43) & Foundation Manifold Extension F1(26 TO 142) F2(25 TO 141) F4(145,146) F5(4 SURESH
NOS)@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection for concrete Foundation Release & insert Plate Installation for manifold extension
foundation SL5-
92191(1F,6,7,9,10,11,14,15,15A,15B,28,29,30,32,33,36A,36B,36C,47H,48,50,52,53,55,56,57,59A, C-0207A C-0203X SURESH
59B,59D,63A) SL13-92191(2,4,8,10,12,16,27,28,29,27A,28,29,27A,30,32,33,35,37,38,39,40,42) at
well Block-2 in Pattern-25
Inspection for concrete Foundation Release & insert Plate Installation for manifold extension
foundation SL5-
92191(1F,6,7,9,10,11,14,15,15A,15B,28,29,30,32,33,36A,36B,36C,47H,48,50,52,53,55,56,57,59A, SURESH
59B,59D,63A) SL13-92191(2,4,8,10,12,16,27,28,29,27A,28,29,27A,30,32,33,35,37,38,39,40,42) at
well Block-2 in Pattern-25

Inspection for concrete Foundation Release & insert Plate Installation for manifold extension
foundation SL6-92191(4 to 12,14,15,15A,15B,16 to 19,30 to 30 to SURESH
34,36A,36B,40,52,53,55,56,57,60,61,63A) SL14-92191(4,5,8 to 11,15A,18,22,23,24,28,29,30,32 to
42) at well Block-2 in Pattern-25

Inspection for concrete Foundation Release & insert Plate Installation for manifold extension
foundation SL7-92191(6,8,9,10,11,13A,15A,17A,27,28,29,31,32,33,34,36A , SURESH
36B,39,40,50,51,52,54,55,56,57,60,61,62A,65) SL9-92191(1F,9F,17F,23) at well Block-2 in Pattern-
25

Inspection for concrete Foundation Release & shim Plate Installation for manifold platform SURESH
foundation grid A(11 to 17),Gridb(1 to 27),Grid C(1 to 27) at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Up to Bottom of Plinth Beam for
Substation Package (722-Z-Substation-25119) with anchor Bolts @ Pattern-25,Manifold Extension
Pedestal with anchor Bolts F1(3 TO 59) F1,(3, TO 59,) F2(4 TO 60) F3(2 TO 58) F4A (1 TO SURESH
57),F1( 142 TO 166) F1, (142, TO 166,) F2 (141 TO 165 ) F3 (143 TO 167) F4A (144 TO 168),F5 (4
Nos), Foundation for Pipe sleeper SL24-94010(80,111,115A,117,117A,185,188,190,206) @
Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.
Inspection for Concrete Foundation Release & Shim Plate Installation for Manifold Platform C-0203X SURESH
Foundation Grid A (11 to 17) ,Grid B (1 to 27) , Grid C (1 to 27) at well Block-2 in Pattern-25

Inspection for Concrete Foundation Release & Shim Plate Installation for Manifold Platform C-0207A SURESH
Foundation Grid A (11 to 17) ,Grid B (1 to 27) , Grid C (1 to 27) at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Pedestal with anchor bolts for
manifold extension F1(26 to 62),F1'(26' to 62'),F2(25 to 61) F3(27 to 63) @ Pattern-25. Well Block SURESH
2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.
Inspection for Field Density Test for First to Final Layer 300mm Backfilling of Manifold Extension
Mixing with Gatch SL8-92191(5 TO 13,15,15A,15B,16,18,29 TO 36,36A,41,42,43,51 TO
61,62A,64A,66,67A) at well Block-2 in Pattern-25
C-0101X SURESH
Inspection for Field Density Test for First to Final Layer 300mm Backfilling of Manifold Extension
Mixing with Gatch SL7-92191(1C,6 TO 13,13A,15A,17A,18,19, 23C,24C,27 TO 36,36A,36B,39 TO
43,46C,47C,52 TO 61,62A,64 TO 68,69C) at well Block-2 in Pattern-25

C-0101X SURESH

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedeatal
F1(66 TO 82) F1(66 TO 82) F2(65 TO 81) F3(67 TO 83) F4A (28 TO 84) F4(145) AT well Block-2 in C-0203X SURESH
Pattern-25

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedeatal
F1(66 TO 82) F1(66 TO 82) F2(65 TO 81) F3(67 TO 83) F4A (28 TO 84) F4(145) AT well Block-2 in C-0201X SURESH
Pattern-25

Inspection for concrete pour for Pedestal anchor Bolts for Manifold Extension Pedeatal F1(66 TO SURESH
82) F1(66 TO 82) F2(65 TO 81) F3(67 TO 83) F4A (28 TO 84) F4(145) AT well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal Remaining
300mm from The top SL17-92181(40,46,47,50,51,53,54,57,69) SL18-92181(7,8,18,19,21,24,28,30
TO 34,36 TO 46), Pedestal with anchor Bolts for Manifold Extension Pedestal F2(141 TO 165)
F1(142 TO 166) F1,(142, TO 166,) F3(143 TO 167) F4A (144 TO 168), Pipe sleeper Pedestal top of N/A SURESH
Steel SL51-92082 (1 TO 35) @ Pattern-24,Transformer RMU,ACCU1,ACCU2 at Substation Package
(722-Z-substation-25119) Foundation@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in
third party M/S ATS For 07 Days.
Witness and checked compressive strength crushing tests for pipe sleeper pedestal SL24-94010
(23,25,27C,27 TO 34) @ Pattern-24 & Foundation Manifold Extension F2(4 to 24) @ Pattern-25. SURESH
Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal top of steel
SL51-92191(8,10 TO 20,36,37,39,40,41,42,43,44) & Pedestal with anchor Bolts for Manifold SURESH
Extension F1(66 TO 82) F1,(66, TO 82,) F2(65 TO 81) F3(67 TO 83) F4A (28 TO 84) F4(145) @
Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 Days.

Inspection for Surface Preparation for Manifold Extension F1(26 TO 83),F1(26 TO 83) F2(25 TO 81) C-0202X SURESH
F3(27 TO 83) F4A(28 TO 84) at well Block-2 in Pattern-25

Inspection for Bitumen Application for Manifold Extension F1(26 TO 83),F1(26 TO 83) F2(25 TO 81) C-0202X SURESH
F3(27 TO 83) F4A(28 TO 84) at well Block-2 in Pattern-25
Inspection for Laying of 1000 Gauge Polythylene for Manifold Extension F1(26 TO 83),F1(26 TO 83) C-0202X SURESH
F2(25 TO 81) F3(27 TO 83) F4A(28 TO 84) at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Up to Bottom of Plinth Beam for
Substation Package (722-Z-Substation-25119) with anchor Bolts @ Pattern-25,Manifold Extension
Pedestal with anchor Bolts F1(3 TO 59) F1,(3, TO 59,) F2(4 TO 60) F3(2 TO 58) F4A (1 TO SURESH
57),F1( 142 TO 166) F1, (142, TO 166,) F2 (141 TO 165 ) F3 (143 TO 167) F4A (144 TO 168),F5 (4
Nos), Foundation for Pipe sleeper SL24-94010(80,111,115A,117,117A,185,188,190,206) @
Pattern-24. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection For Concrete Pour for Pedestal with anchor Bolts for Manifold Extension F3 (87 to 143) C-0210X C-0204X SURESH
F4A (88 to 144) at well Block-2 in Pattern-25

Inspection for Concrete Pour for Pedestal with anchor Bolts for Manifold Extension F1(86 to 142) C-0210X C-0204X SURESH
F1(86 TO 142) F2(85 TO 141) F4(146) F2 (152) F5(4 Nos)at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal F3(87
C-0203X SURESH
TO 143) F4A (88 TO 144) at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal F3(87 C-0201X SURESH
TO 143) F4A (88 TO 144) at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal F1 C-0203X SURESH
(86 TO 142) F1(86 TO 142) F2(85 TO 141) F4(146) F2(152) F5(4 NOS) at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts Formwork & Alignment for Manifold Extension Pedestal F1 C-0201X SURESH
(86 TO 142) F1(86 TO 142) F2(85 TO 141) F4(146) F2(152) F5(4 NOS) at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Pedestal with anchor bolts for
manifold extension F1(26 to 62),F1'(26' to 62'),F2(25 to 61) F3(27 to 63) @ Pattern-25. Well Block SURESH
2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection for Field Density test for First to Final Layer 300mm Backfilling of Manifold Extension
F1(26 TO 141) F1(26 TO 142) F2(25 TO 141) F3(27 TO 143)F4A (28 TO 144) at well Block-2 in C-0101X SURESH
Pattern-25

Inspection for Concrete Pour for Pedestal with anchor Bolts for Manifold Extension F1(3 TO 23) F1 C-0210X C-0204X SURESH
(3 TO 23) F2(4 TO 24) F3 (2 TO 22) F4A (1 TO 21) ,at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts formwork & Alignment for Manifold Extension Pedestal F1 (3 C-0201X SURESH
TO 23), F1(3 TO 23), F2(4 TO 24), F3(2 TO 22) F4A (1 TO 21) at well Block-2 in Pattern-25

Inspection for Fixing of anchor Bolts formwork & Alignment for Manifold Extension Pedestal F1 (3 C-0203X SURESH
TO 23), F1(3 TO 23), F2(4 TO 24), F3(2 TO 22) F4A (1 TO 21) at well Block-2 in Pattern-25
Witness and checked compressive strength crushing tests for Pedestal with anchor Bolts for
Manifold Extension F1(86 to 142), F1,(86, TO 142,), F2(85 TO 141), F4(146), F5(4 Nos) & F3 (87 to SURESH
143), F4A (88 to 144) @ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS
For 07 Days.
Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal Remaining
300mm from The top SL17-92181(40,46,47,50,51,53,54,57,69) SL18-92181(7,8,18,19,21,24,28,30
TO 34,36 TO 46), Pedestal with anchor Bolts for Manifold Extension Pedestal F2(141 TO 165)
F1(142 TO 166) F1,(142, TO 166,) F3(143 TO 167) F4A (144 TO 168), Pipe sleeper Pedestal top of SURESH
Steel SL51-92082 (1 TO 35) @ Pattern-24,Transformer RMU,ACCU1,ACCU2 at Substation Package
(722-Z-substation-25119) Foundation@ Pattern-25. Well Block 2, K300 SRC Concrete cubes in
Witness and checked compressive
third strength
party M/Scrushing
ATS Fortests for Pedestal with anchor Bolts for
28 Days.
Manifold Extension F1(3 TO 23), F1, (3, TO 23,), F2(4 TO 24), F3 (2 TO 22), F4A (1 TO 21) & Pipe
sleeper Pedestal Remaining 300mm from the top SL1-92191 (3,10,13,32,33) SL2-92191(6,7, 8,9,
16A,28,39A,64,86,87A) @Pattern-25,Pipe sleeper Pedestal Remaining 300mm from The top SL7- SURESH
92181(15,19,20,25,26,27,52,56,57,62,63,64,89,93,94,99,124, 125,128 ,129,130, 132, 134, 135,
136) @Pattern-24,Pipe sleeper Pedestal top of Steel SL13-92011 (54) @ Pattern-04. Well Block 2,
K300 SRC Concrete cubes in third party M/S ATS For 07 Days.
Witness and checked compressive strength crushing tests for Pipe sleeper Pedestal top of steel
SL51-92191(8,10 TO 20,36,37,39,40,41,42,43,44) & Pedestal with anchor Bolts for Manifold SURESH
Extension F1(66 TO 82) F1,(66, TO 82,) F2(65 TO 81) F3(67 TO 83) F4A (28 TO 84) F4(145) @
Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection for Field Density test for first & Final Layer (300 mm) bac filling of MANIFOLD
EXTENSION F1(3 to 23),F1'(3' to 23')F2(4 to 24),F3(2 to 11),F4A(1 to 21) at well Block-2 in Pattern- C-0101X SURESH
25

Inspection for surface preparation for MANIFOLD EXTENSION F1(3 to 23),F1'(3' to 23')F2(4 to C-0202X SURESH
24),F3(2 to 11),F4A(1 to 21) at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Pedestal with anchor Bolts for
Manifold Extension F1(86 to 142), F1,(86, TO 142,), F2(85 TO 141), F4(146), F5(4 Nos) & F3 (87 to SURESH
143), F4A (88 to 144) @ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS
For 28 Days.

Inspection for Manual Excavation Hard soil & Formation Level for ESDV Platform in Manifold Area C-0203X SURESH
at Well Block-2 in Pattern-25

Inspection for Excavation & Formation Level for ESDV Platform in Manifold Area at Well Block-2 in
C-0101X SURESH
Pattern-25

Inspection for Field Density Test Prior to Bilnding for ESDV Platform in Manifold Area at Well Block- C-0101X SURESH
2 in Pattern-25

Inspection for Bilnding Concrete Pour for ESDV Platform in Manifold Area at Well Block-2 in C-0204X SURESH
Pattern-25

Witness and checked compressive strength crushing tests for Pedestal with anchor Bolts for
Manifold Extension F1(3 TO 23), F1, (3, TO 23,), F2(4 TO 24), F3 (2 TO 22), F4A (1 TO 21) & Pipe
sleeper Pedestal Remaining 300mm from the top SL1-92191 (3,10,13,32,33) SL2-92191(6,7, 8,9,
16A,28,39A,64,86,87A) @Pattern-25,Pipe sleeper Pedestal Remaining 300mm from The top SL7- SURESH
92181(15,19,20,25,26,27,52,56,57,62,63,64,89,93,94,99,124, 125,128 ,129,130, 132, 134, 135,
136) @Pattern-24,Pipe sleeper Pedestal top of Steel SL13-92011 (54) @ Pattern-04. Well Block 2,
K300 SRC Concrete cubes in third party M/S ATS For 28 Days.

Inspection for Fixing of Reinforcement & Alignment of formwork for foundation (ESDV Platfrom) in C-0201X SURESH
Manifold at Well Block-2 in Pattern-25
Inspection for Fixing of Reinforcement & Alignment of formwork for foundation (ESDV Platfrom) in C-0203X SURESH
Manifold at Well Block-2 in Pattern-25

Inspection for Location & Excation Levels for Electrical cable Trench at manifold area at well Block- C-0101X SURESH
2 in Pattern-25

Inspection for Location & Excation Levels for Electrical cable Trench at manifold area at well Block- SURESH
2 in Pattern-25

Inspection for Location & Excation Levels for Electrical cable Trench at manifold area at well Block- SURESH
2 in Pattern-25

Inspection for Location & Excation Levels for instrument cable Trench at manifold area at well
C-0101X SURESH
Block-2 in Pattern-25

Inspection for Field Density Test for First to Final Layer (300mm) Backfilling of (ESDV Platfrom) SURESH
mixing with Gatch at manifold Area at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Foundation ESDV Platform in
Manifold Area @ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 07 SURESH
Days.

(To check elevations and coordinates) as follows Inspection for Excavation & formation Level for C-0203X SURESH
MOVDB,FITDB,NLDB AT manifold Area at well Block-2 in Pattern-25

Inspection for Field density test prior to blinding for MOVDB,FITDB,NLDB AT manifold Area at
C-0101X SURESH
well Block-2 in Pattern-25

Inspection for blinding Concrete Pour for MOVDB,FITDB,NLDB AT manifold Area at well Block-2 C-0204X SURESH
in Pattern-25

(To check elevations and coordinates) as follows Inspection for Excavation & Formation level for C-0203X SURESH
MOVDB,FITDB,NLDB at Manifold Area at well Block-2 in Pattern-25

Inspection for Excavation & Formation level for MOVDB,FITDB,NLDB at Manifold Area at well C-0101X SURESH
Block-2 in Pattern-25

Inspection for Field density test prior to blinding for MOVDB,FITDB,NLDB at Manifold Area at well SURESH
Block-2 in Pattern-25
Inspection for blinding Concrete Pour for MOVDB,FITDB,NLDB at Manifold Area at well Block-2 in C-0204X SURESH
Pattern-25

(To check elevations and coordinates) as follows Inspection for Installed of precast for Light Pole C-0203X SURESH
at Manifold Area at well Block-2 in Pattern-25

Inspection for Installed of precast for Light Pole at Manifold Area at well Block-2 in Pattern-25 C-0208X SURESH

(To check elevations and coordinates) as follows Inspection for Installed of precast for C-0203X SURESH
MOVDB,FITDB,NLDB at Manifold Area at well Block-2 in Pattern-25

Inspection for Installed of precast for MOVDB,FITDB,NLDB at Manifold Area at well Block-2 in
C-0208X SURESH
Pattern-25

Inspection For Field density test for first to final layer (300mm) backfilling of (ESDV Platform) C-0101X SURESH
mixing gatch at manifold area at in Pattern-25

Inspection for Concrete foundation release &insert plate installation For (ESDV Platform) in SURESH
manifold area at in Pattern-25

Inspection for Field density test for Gatch Filling at manifold extension F1 (3 TO 23,26 TO 142) F1
(3 TO 23,26 TO 142) F2 (4 TO 24,25 TO 141) F3 (2 TO 22,27 TO 143) F4A (1 TO 21,28 TO 144) at C-0101X SURESH
well Block-2 in Pattern-25

Inspection for Field density test for 4TH to final layer (300mm) backfilling of (ESDV Platfrom)
C-0101X SURESH
mixing with gatch at manifold area at well Block-2 in Pattern-25

Witness and checked compressive strength crushing tests for Foundation ESDV Platform in
Manifold Area @ Pattern-25. Well Block 2, K300 SRC Concrete cubes in third party M/S ATS For 28 SURESH
Days.

Inspection for Field density test for final layer (300mm) backfilling for Light Pole (10m) in Manifold C-0101X SURESH
Area at well Block-2 in Pattern-25

(To check elevations and coordinates) as follows Inspection for Excavation & Formation level for C-0203X SURESH
manifold extension CS-(13Nos) at well Block-2 in Pattern-25

Inspection for Excavation & Formation level for manifold extension CS-(13Nos) at well Block-2 in SURESH
Pattern-25
Inspection for Field density test Prior blinding for manifold extension CS-(13Nos) at well Block-2 in SURESH
Pattern-25

Inspection for blinding Concrete for manifold extension CS-(13Nos) at well Block-2 in Pattern-25 SURESH

Inspection for Field Density test For Gravel Filling at manifold Platfrom Grid A (11 TO 17) Grid B (1 SURESH
TO 27) Grid C (1 TO 27) at well Block-2 in Pattern-25

Inspection for Surface Preparation for PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE C-0202X SURESH


TCPR,Light Pole (10 M) Sheet (1 to 6) & Manifold Area at well Block-2 in Pattern-25

Inspection for bitumen application for PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE


SURESH
TCPR,Light Pole (10 M) Sheet (1 to 6) & Manifold Area at well Block-2 in Pattern-25

Inspection for Formwork of Grout Foundation for Light Pole (10M 8NO) at Manifold Area at well C-0401X SURESH
Block-2 in Pattern-25

Inspection for Grout mixing and Placing for Light Pole (10M 8NO) at Manifold Area at well Block-2 C-0401X SURESH
in Pattern-25

protection for Concrete Surfaces. Inspection For laying of 1000 gauge Polyethylene for
PP,MOVDB,FITDB,NLDB,AJB,NJB,NDB,P1,P3,FENCE,TCPR,Light Pole (10 M) Sheet (1 to 6) & SURESH
Manifold Area at Pattern-25

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-25. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 01 Days.

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-25. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 07 Days.

Inspection for Formwork of Grout for manifold Platform Foundation Grid A (11 to 17), Grid B (1 to C-0401X SURESH
27), Grid C (1 to 27) at well Block-2 in Pattern-25

Inspection for Grout mixing and Placing for manifold Platform Foundation Grid A (11 to 17), Grid B SURESH
(1 to 27), Grid C (1 to 27) at well Block-2 in Pattern-25

Inspection for Formwork of Grout Foundation manifold exxtension F1 (3 to 23), F1' (3' to 23'), F2A SURESH
(4 to 24), F3 (2 to 22), F4A (1 to 25) at well Block-2 in Pattern-25
Inspection for Grout mixing and Placing for Foundation manifold exxtension F1 (3 to 23), F1' (3' to SURESH
23'), F2A (4 to 24), F3 (2 to 22), F4A (1 to 25) at well Block-2 in Pattern-25

Inspection for Formwork of Grout Foundation manifold exxtension F1 (26 to 142), F1' (26' to 142'), SURESH
F2A (25 to 141), F3 (27 to 143), F4A (28 to 144) at well Block-2 in Pattern-25

Inspection for Grout mixing and Placing for Foundation manifold exxtension F1 (26 to 142), F1' SURESH
(26' to 142'), F2A (25 to 141), F3 (27 to 143), F4A (28 to 144) at well Block-2 in Pattern-25

(To check elevations and coordinates) as follows, Inspection for concrete foundation release &
Shim plate installation For manifold extantion foundation F3C (6 nos), CF8 (1), F20 (1), F3A (1), F18 SURESH
(1) at Pattern-25

Inspection for concrete foundation release & Shim plate installation For manifold extantion
SURESH
foundation F3C (6 nos), CF8 (1), F20 (1), F3A (1), F18 (1) at Pattern-25

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
Light Pole 10M-08Nos,at Manifold Area @ Pattern-25. Well Block-2,Master Flow-928, Grout SURESH
cubes in third party M/S ATS For 28 Days.

Inspection for Formwork of Grout manifold Platform Grid A (11 to 17), Grid B (1 to 27), Grid C (1 to C-0401X SURESH
27) at well Block-2 in Pattern-25

Inspection for Formwork of Grout foundations Manifold Extension F1 (3 to 23), F1' (3' to 23'), F2 (4 SURESH
to 24), F3 (2 to 22), F4A (1 to 20) at well Block-2 in Pattern-25

Inspection for Grout mixing and Placing for manifold Platform Grid A (11 to 17), Grid B (1 to 27),
C-0401X SURESH
Grid C (1 to 27) at well Block-2 in Pattern-25

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
manifold Platform foundation Grid A (11 to 17), Grid B (1 to 27), Grid C (1 to 27) @ Pattern-25. SURESH
Well Block-2,Master Flow-928, Grout cubes in third party M/S ATS For 01 Days.

Witness and Checked Compressive Strength Crushing tests for Grouting cubes(50x50x50mm) for
manifold Platform foundation Grid A (11 to 17), Grid B (1 to 27), Grid C (1 to 27) @ Pattern-25. SURESH
Well Block-2,Master Flow-928, Grout cubes in third party M/S ATS For 07 Days.
QC SUBMIT RETURNED
PIL INSP SUBMITTED CPY INSP DATE TO PIL SUP STATUS DATE FROM
DATE TO DC COMPANY COMPANY

SURVEYOR 22-Apr-17 AJITH 23-Apr-17 HARIDAS APPROVED

RODOLFO 22-Apr-17 RICKY 23-Apr-17 HARIDAS APPROVED AS NOTED

RODOLFO 26-Apr-17 N/A N/A HARIDAS APPROVED

RODOLFO 10-May-17 RICKY 11-May-17 HARIDAS APPROVED

EDWIN 18-May-17 HAFIZ 17-May-17 HARIDAS APPROVED

SURVEYOR 24-May-17 HAFIZ 30-May-17 HARIDAS APPROVED

EDWIN 27-May-17 N/A N/A HARIDAS CANCELLED

EDWIN 17-Jun-17 N/A N/A HARIDAS APPROVED

EDWIN 14-Jun-17 N/A N/A HARIDAS APPROVED

EDWIN 14-Jun-17 N/A N/A HARIDAS APPROVED

RODOLFO 10-Jul-17 N/A N/A HARIDAS APPROVED

SURVEYOR 13-Jul-17 HAFIZ 17-Jul-17 HARIDAS APPROVED


RODOLFO 15-Jul-17 HAFIZ 15-Jul-17 HARIDAS APPROVED

RODOLFO 15-Jul-17 HAFIZ 15-Jul-17 HARIDAS APPROVED

SURVEYOR REJECTED

RODOLFO CANCELLED

RODOLFO 24-Jul-17 N/A N/A N/A CANCELLED

SURVEYOR 26-Jul-17 AJITH 27-Jul-17 HARIDAS CANCELLED

RODOLFO 26-Jul-17 RICKY 27-Jul-17 HARIDAS APPROVED

SURVEYOR 29-Jul-17 HAFIZ 6-Aug-17 HARIDAS APPROVED

RODOLFO 31-Jul-17 RICKY 1-Aug-17 HARIDAS APPROVED

SURVEYOR 26-Jul-17 AJITH 27-Jul-17 HARIDAS APPROVED

RODOLFO 29-Jul-17 RICKY 30-Jul-17 HARIDAS APPROVED

RODOLFO 3-Aug-17 N/A N/A HARIDAS APPROVED

RODOLFO 31-Jul-17 N/A N/A TOUFIC CANCELLED


RODOLFO 31-Jul-17 RICKY 1-Aug-17 HARIDAS APPROVED

SURVEYOR 6-Aug-17 AJITH 6-Aug-17 HARIDAS APPROVED

RODOLFO 6-Aug-17 RICKY 6-Aug-17 HARIDAS APPROVED

RODOLFO 12-Aug-17 HAFIZ 12-Aug-17 ROBERT APPROVED

RODOLFO 17-Aug-17 N/A N/A ROBERT APPROVED

RODOLFO 17-Sep-17 N/A N/A ROBERT APPROVED

SURVEYOR 31-Aug-17 CANCELLED

RODOLFO 6-Sep-17 RICKY 7-Sep-17 MARWAN APPROVED AS NOTED

NOEL 16-Sep-17 HAFIZ 16-Sep-17 ROBERT APPROVED

SURVEYOR 11-Sep-17 HAFIZ 12-Sep-17 ROBERT APPROVED

NOEL 11-Sep-17 HAFIZ 11-Sep-17 ROBERT APPROVED

RODOLFO 28-Sep-17 RICKY 28-Sep-17 N/A APPROVED

SURVEYOR 7-Oct-17 AJITH 7-Oct-17 IMRAN APPROVED AS NOTED


SURVEYOR 24-Sep-17 AJITH 24-Sep-17 ROBERT APPROVED

RODOLFO 25-Sep-17 HAFIZ 25-Sep-17 ROBERT APPROVED

RODOLFO 21-Oct-17 RICKY 21-Oct-17 N/A APPROVED

RODOLFO 21-Oct-17 RICKY 21-Oct-17 N/A APPROVED

RODOLFO 10-Oct-17 AJITH 10-Oct-17 IMRAN APPROVED

RODOLFO 5-Oct-17 HAFIZ 5-Oct-17 HARIDAS APPROVED

SURVEYOR 10-Oct-17 AJITH 9-Oct-17 IMRAN APPROVED

RODOLFO 5-Oct-17 HAFIZ 5-Oct-17 HARIDAS APPROVED

RODOLFO 12-Oct-17 N/A N/A IMRAN REJECTED

RODOLFO 7-Oct-17 HAFIZ 7-Oct-17 HARIDAS APPROVED

SURVEYOR 11-Oct-17 N/A N/A MOUSSA CANCELLED

RODOLFO 5-Oct-17 HAFIZ 5-Oct-17 HARIDAS APPROVED

RODOLFO 16-Oct-17 RICKY 16-Oct-17 N/A APPROVED


RODOLFO CANCELLED

SURVEYOR 22-Oct-17 AJITH 22-Oct-17 IMRAN APPROVED

RODOLFO 12-Oct-17 HAFIZ 12-Oct-17 IMRAN APPROVED

RODOLFO 14-Oct-17 HAFIZ 14-Oct-17 IMRAN APPROVED

RODOLFO 7-Nov-17 HAFIZ 7-Nov-17 IMRAN APPROVED

RODOLFO 7-Nov-17 HAFIZ 7-Nov-17 IMRAN APPROVED

RODOLFO 8-Nov-17 RICKY 8-Nov-17 N/A APPROVED

RODOLFO 6-Nov-17 RICKY 6-Nov-17 N/A APPROVED

RODOLFO 6-Nov-17 RICKY 6-Nov-17 N/A APPROVED

RODOLFO 10-Mar-18 HAFIZ 10-Mar-18 N/A APPROVED

RODOLFO 9-Nov-17 HAFIZ 9-Nov-17 IMRAN APPROVED

RODOLFO 5-Nov-17 N/A N/A IMRAN CANCELLED

RODOLFO 4-Nov-17 HAFIZ 4-Nov-17 IMRAN APPROVED


RODOLFO 11-Nov-17 RICKY 11-Nov-17 N/A APPROVED

SURVEYOR 9-Nov-17 AJITH 9-Nov-17 GUPTA APPROVED

RODOLFO 8-Nov-17 HAFIZ 8-Nov-17 IMRAN APPROVED

SURVEYOR 9-Nov-17 AJITH 9-Nov-17 GUPTA APPROVED

RODOLFO 8-Nov-17 HAFIZ 8-Nov-17 IMRAN APPROVED

SURVEYOR 12-Nov-17 AJITH 12-Nov-17 MARWAN APPROVED

RODOLFO 12-Nov-17 HAFIZ 12-Nov-17 IMRAN APPROVED

SURVEYOR 12-Nov-17 AJITH 12-Nov-17 MARWAN APPROVED

RODOLFO 8-Nov-17 HAFIZ 8-Nov-17 IMRAN APPROVED

RODOLFO 4-Dec-17 RICKY 4-Dec-17 N/A APPROVED

RODOLFO 29-Nov-17 RICKY 29-Nov-17 N/A APPROVED

SURVEYOR 29-Jan-18 AJITH 29-Jan-18 IMRAN APPROVED

DHARMA 29-Nov-17 ZAFAR 29-Nov-17 IMRAN APPROVED


DHARMA 30-Nov-17 ZAFAR 30-Nov-17 IMRAN APPROVED

DHARMA 30-Nov-17 ZAFAR 30-Nov-17 IMRAN APPROVED

SURVEYOR 11-Jan-18 AJITH 11-Jan-18 IMRAN APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

SURVEYOR 28-Dec-17 AJITH 28-Dec-17 IMRAN APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

ANWAR 25-Dec-17 N/A N/A IMRAN CANCELLED

SURVEYOR 2-Jan-18 AJITH 2-Jan-18 MURUGAN APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

RODOLFO 2-Jan-18 RICKY 2-Jan-18 N/A APPROVED

ANWAR 27-Dec-17 RICKY 27-Dec-17 N/A APPROVED

RODOLFO 20-Dec-17 ZAFAR 20-Dec-17 MURUGAN APPROVED


ANWAR 25-Dec-17 N/A N/A MURUGAN CANCELLED

RODOLFO 19-Dec-17 N/A N/A MURUGAN CANCELLED

SURVEYOR 31-Dec-17 AJITH 31-Dec-17 MURUGAN APPROVED

ANWAR 24-Dec-17 ZAFAR 24-Dec-17 MURUGAN APPROVED

SURVEYOR 27-Dec-17 AJITH 27-Dec-17 MURUGAN APPROVED

ANWAR 24-Dec-17 ZAFAR 24-Dec-17 MURUGAN APPROVED

ANWAR 30-Dec-17 ZAFAR 30-Dec-17 MURUGAN APPROVED

ANWAR 27-Dec-17 N/A N/A MURUGAN CANCELLED

ANWAR 4-Jan-18 ZAFAR 4-Jan-18 MURUGAN APPROVED

RODOLFO 18-Jan-18 RICKY 18-Jan-18 N/A APPROVED

DHARMA 9-Jan-18 ZAFAR 9-Jan-18 MURUGAN APPROVED

SURVEYOR 18-Jan-18 AJITH 18-Jan-18 MURUGAN APPROVED

RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED


RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED

RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED

RODOLFO 28-Jan-18 N/A N/A N/A CANCELLED FDT TEST NOT REQUIRED GRAVEL THICKNES

RODOLFO 13-Feb-18 ZAFAR 13-Feb-18 ROBERT APPROVED

RODOLFO 18-Feb-18 ZAFAR 18-Feb-18 ROBERT APPROVED AS NOTED

RODOLFO 12-Feb-18 N/A N/A ROBERT REJECTED

RODOLFO 12-Feb-18 N/A N/A ROBERT CANCELLED

RODOLFO 12-Feb-18 N/A N/A ROBERT REJECTED

RODOLFO 12-Feb-18 N/A N/A ROBERT CANCELLED

RODOLFO 17-Feb-18 ZAFAR 17-Feb-18 ROBERT APPROVED AS NOTED

RODOLFO 17-Feb-18 ZAFAR 17-Feb-18 ROBERT APPROVED AS NOTED

RODOLFO 17-Feb-18 ZAFAR 17-Feb-18 ROBERT APPROVED

RODOLFO 21-Feb-18 ZAFAR 21-Feb-18 ROBERT APPROVED AS NOTED


RODOLFO 18-Feb-18 REHAN 18-Feb-18 ROBERT APPROVED

RODOLFO 21-Feb-18 ZAFAR 21-Feb-18 ROBERT APPROVED AS NOTED

RODOLFO 12-Apr-18 N/A N/A ROBERT CANCELLED

RODOLFO 12-Apr-18 N/A N/A ROBERT CANCELLED

RODOLFO 5-Apr-18 ZAFAR 5-Apr-18 ROBERT APPROVED

RODOLFO 5-Apr-18 ZAFAR 5-Apr-18 ROBERT APPROVED

RODOLFO 5-Apr-18 N/A N/A ROBERT CANCELLED

ANWAR 23-Apr-18 RICKY 23-Apr-18 N/A APPROVED

ANWAR 23-Apr-18 RICKY 23-Apr-18 N/A APPROVED

RODOLFO 19-May-18 RICKY 19-May-18 N/A AWAITING FOR SIGN

RODOLFO 1-May-18 N/A N/A ROBERT CANCELLED

RODOLFO 1-May-18 N/A N/A ROBERT CANCELLED

RODOLFO 1-May-18 N/A N/A ROBERT CANCELLED


EDWIN 25-May-17 AJITH 27-May-17 HARIDAS APPROVED

EDWIN 25-May-17 AJITH 27-May-17 HARIDAS APPROVED

EDWIN 27-May-17 RICKY 28-May-17 HARIDAS APPROVED

NOEL 18-Jun-17 HAFIZ 18-Jun-17 HARIDAS APPROVED

SURVEYOR 6-Jul-17 N/A N/A HARIDAS CANCELLED

RODOLFO 4-Jul-17 N/A N/A HARIDAS CANCELLED

RODOLFO 6-Jul-17 HAFIZ 8-Jul-17 HARIDAS APPROVED

SURVEYOR 8-Jul-17 HAFIZ 16-Jul-17 HARIDAS APPROVED

SURVEYOR 8-Jul-17 HAFIZ 16-Jul-17 HARIDAS APPROVED

RODOLFO 6-Jul-17 HAFIZ 8-Jul-17 HARIDAS APPROVED

SURVEYOR 11-Jul-17 HAFIZ 16-Jul-17 HARIDAS APPROVED

RODOLFO 15-Jul-17 HAFIZ 15-Jul-17 HARIDAS APPROVED

SURVEYOR 1-Aug-17 AJITH 2-Aug-17 HARIDAS CANCELLED


RODOLFO 1-Aug-17 RICKY 2-Aug-17 HARIDAS APPROVED AS NOTED

RODOLFO 5-Aug-17 N/A N/A HARIDAS APPROVED

RODOLFO 6-Aug-17 HAFIZ 12-Aug-17 ROBERT APPROVED

SURVEYOR 6-Aug-17 HAFIZ 14-Aug-17 ROBERT APPROVED

RODOLFO 3-Aug-17 RICKY 3-Aug-17 HARIDAS APPROVED

RODOLFO 8-Aug-17 N/A N/A ROBERT APPROVED

RODOLFO 12-Aug-17 HAFIZ 12-Aug-17 ROBERT APPROVED

RODOLFO 10-Aug-17 N/A N/A ROBERT APPROVED

SURVEYOR 19-Aug-17 HAFIZ 22-Aug-17 ROBERT APPROVED

SURVEYOR 24-Aug-17 HAFIZ 27-Aug-17 ROBERT APPROVED

SURVEYOR 29-Aug-17 AJITH 29-Aug-17 ROBERT APPROVED

RODOLFO 30-Aug-17 RICKY 31-Aug-17 ROBERT APPROVED AS NOTED

RODOLFO 30-Aug-17 N/A N/A N/A APPROVED


RODOLFO 30-Aug-17 RICKY 31-Aug-17 GUPTA APPROVED

RODOLFO 17-Sep-17 N/A N/A ROBERT APPROVED

SURVEYOR 31-Aug-17 AJITH 31-Aug-17 ROBERT APPROVED

RODOLFO 6-Sep-17 HAFIZ 6-Sep-17 N/A APPROVED

NOEL 14-Sep-17 HAFIZ 14-Sep-17 ROBERT APPROVED

SURVEYOR 10-Sep-17 AJITH 11-Sep-17 ROBERT CANCELLED

NOEL 10-Sep-17 HAFIZ 10-Sep-17 ROBERT APPROVED

NOEL 12-Sep-17 N/A N/A ROBERT CANCELLED

RODOLFO 10-Oct-17 N/A N/A N/A CANCELLED

SURVEYOR 12-Sep-17 HAFIZ 13-Sep-17 ROBERT APPROVED

NOEL 14-Sep-17 RICKY 16-Sep-17 ROBERT APPROVED AS NOTED

NOEL 20-Sep-17 HAFIZ 20-Sep-17 ROBERT APPROVED

RODOLFO 28-Sep-17 RICKY 28-Sep-17 N/A APPROVED


SURVEYOR 24-Sep-17 HAFIZ 24-Sep-17 ROBERT APPROVED

RODOLFO 24-Sep-17 HAFIZ 24-Sep-17 ROBERT APPROVED

RODOLFO 25-Sep-17 HAFIZ 25-Sep-17 ROBERT APPROVED

SURVEYOR 28-Sep-17 AJITH 30-Sep-17 HARIDAS APPROVED

RODOLFO 1-Oct-17 N/A N/A N/A CANCELLED

RODOLFO 21-Oct-17 RICKY 21-Oct-17 N/A APPROVED

RODOLFO 16-Oct-17 RICKY 16-Oct-17 N/A APPROVED

SURVEYOR 11-Oct-17 AJITH 11-Oct-17 HARIDAS APPROVED

RODOLFO 15-Oct-17 HAFIZ 15-Oct-17 IMRAN REJECTED

RODOLFO 15-Oct-17 HAFIZ 15-Oct-17 IMRAN REJECTED

RODOLFO 15-Oct-17 HAFIZ 15-Oct-17 IMRAN REJECTED

RODOLFO 7-Oct-17 N/A N/A HARIDAS REJECTED

RODOLFO CANCELLED
SURVEYOR 17-Oct-17 AJITH 17-Oct-17 IMRAN APPROVED

RODOLFO 12-Oct-17 HAFIZ 12-Oct-17 IMRAN APPROVED

RODOLFO 29-Oct-17 RICKY 29-Oct-17 N/A APPROVED

RODOLFO 23-Oct-17 HAFIZ 23-Oct-17 IMRAN APPROVED

RODOLFO 2-Nov-17 HAFIZ 2-Nov-17 IMRAN APPROVED

SURVEYOR 22-Oct-17 AJITH 22-Oct-17 IMRAN APPROVED

RODOLFO 18-Oct-17 HAFIZ 18-Oct-17 HARIDAS APPROVED

RODOLFO CANCELLED

RODOLFO 8-Nov-17 RICKY 8-Nov-17 N/A APPROVED

RODOLFO 6-Nov-17 RICKY 6-Nov-17 N/A APPROVED

RODOLFO CANCELLED

RODOLFO 28-Oct-17 HAFIZ 28-Oct-17 IMRAN APPROVED

RODOLFO 28-Oct-17 HAFIZ 28-Oct-17 IMRAN APPROVED


RODOLFO 28-Oct-17 HAFIZ 28-Oct-17 IMRAN APPROVED

RODOLFO 10-Mar-18 HAFIZ 10-Mar-18 N/A APPROVED

RODOLFO 2-Nov-17 HAFIZ 2-Nov-17 IMRAN APPROVED

RODOLFO 2-Nov-17 HAFIZ 2-Nov-17 IMRAN APPROVED

SURVEYOR 5-Nov-17 AJITH 5-Nov-17 IMRAN APPROVED

RODOLFO 1-Nov-17 HAFIZ 1-Nov-17 IMRAN APPROVED

SURVEYOR 5-Nov-17 AJITH 5-Nov-17 IMRAN APPROVED

RODOLFO 1-Nov-17 HAFIZ 1-Nov-17 IMRAN APPROVED

RODOLFO 23-Nov-17 RICKY 23-Nov-17 N/A APPROVED

DHARMA 26-Nov-17 ZAFAR 26-Nov-17 IMRAN APPROVED

RODOLFO 9-Nov-17 HAFIZ 9-Nov-17 IMRAN APPROVED

RODOLFO 7-Nov-17 HAFIZ 7-Nov-17 IMRAN APPROVED

SURVEYOR 9-Nov-17 AJITH 9-Nov-17 IMRAN APPROVED


RODOLFO 29-Nov-17 RICKY 29-Nov-17 N/A APPROVED

RODOLFO 4-Dec-17 RICKY 4-Dec-17 N/A APPROVED

RODOLFO 29-Nov-17 RICKY 29-Nov-17 N/A APPROVED

RODOLFO CANCELLED

RODOLFO 10-Dec-17 HAFIZ 10-Dec-17 IMRAN APPROVED

RODOLFO 19-Nov-17 HAFIZ 19-Nov-17 IMRAN APPROVED

RODOLFO 2-Jan-18 RICKY 2-Jan-18 N/A APPROVED

SURVEYOR 3-Dec-17 AJITH 3-Dec-17 IMRAN APPROVED

DHARMA 29-Nov-17 ZAFAR 29-Nov-17 IMRAN APPROVED

DHARMA 30-Nov-17 ZAFAR 30-Nov-17 IMRAN APPROVED

DHARMA 30-Nov-17 ZAFAR 30-Nov-17 IMRAN APPROVED

RODOLFO 2-Jan-18 RICKY 2-Jan-18 N/A APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED


SURVEYOR 10-Dec-17 YOUSUF ALI 10-Dec-17 MURUGAN APPROVED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

SURVEYOR 10-Dec-17 YOUSUF ALI 10-Dec-17 MURUGAN REJECTED

SURVEYOR 14-Dec-17 YOUSUF ALI 14-Dec-17 MURUGAN REJECTED

RODOLFO 7-Dec-17 ZAFAR 7-Dec-17 IMRAN APPROVED

RODOLFO 19-Dec-17 N/A N/A MURUGAN CANCELLED

ANWAR 27-Dec-17 RICKY 27-Dec-17 N/A APPROVED

SURVEYOR 21-Dec-17 YOUSUF ALI 21-Dec-17 MURUGAN APPROVED

RODOLFO 18-Dec-17 RICKY 18-Dec-17 MURUGAN APPROVED

RODOLFO 17-Dec-17 ZAFAR 17-Dec-17 ROBERT APPROVED

SURVEYOR 26-Dec-17 YOUSUF ALI 26-Dec-17 MURUGAN APPROVED

ANWAR 24-Dec-17 ZAFAR 24-Dec-17 MURUGAN APPROVED

RODOLFO 20-Dec-17 HAFIZ 20-Dec-17 MURUGAN CANCELLED


ANWAR 25-Dec-17 ZAFAR 25-Dec-17 MURUGAN APPROVED

SURVEYOR 8-Jan-18 AJITH 8-Jan-18 MURUGAN APPROVED

ANWAR 24-Dec-17 ZAFAR 24-Dec-17 MURUGAN APPROVED

SURVEYOR 4-Jan-18 AJITH 4-Jan-18 MURUGAN APPROVED

ANWAR 25-Dec-17 ZAFAR 25-Dec-17 MURUGAN APPROVED

ANWAR 30-Dec-17 ZAFAR 30-Dec-17 MURUGAN APPROVED

ANWAR 27-Dec-17 N/A N/A MURUGAN CANCELLED

ANWAR 4-Jan-18 ZAFAR 4-Jan-18 MURUGAN APPROVED

ANWAR 4-Jan-18 ZAFAR 4-Jan-18 MURUGAN APPROVED

RODOLFO 18-Jan-18 RICKY 18-Jan-18 N/A APPROVED

DHARMA 9-Jan-18 ZAFAR 9-Jan-18 MURUGAN APPROVED

SURVEYOR 18-Jan-18 AJITH 18-Jan-18 MURUGAN APPROVED

RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED


RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED

RODOLFO 17-Jan-18 N/A N/A MURUGAN CANCELLED

RODOLFO 28-Jan-18 N/A N/A N/A CANCELLED FDT TEST NOT REQUIRED GRAVEL THICKNES

RODOLFO 14-Apr-18 ZAFAR 14-Apr-18 ROBERT APPROVED

RODOLFO 12-Apr-18 N/A N/A ROBERT CANCELLED

RODOLFO 5-Apr-18 ZAFAR 5-Apr-18 ROBERT APPROVED

RODOLFO 3-Apr-18 HAFIZ 3-Apr-18 APPROVED AS NOTED

RODOLFO 5-Apr-18 N/A N/A ROBERT CANCELLED

RODOLFO 11-Apr-18 RICKY 11-Apr-18 N/A APPROVED 19-Apr-18

ANWAR 23-Apr-18 RICKY 23-Apr-18 N/A APPROVED

ANWAR 23-Apr-18 ZAFAR 23-Apr-18 RODNEY CANCELLED 23-Apr-18

ANWAR 22-Apr-18 N/A N/A GUPTA CANCELLED

ANWAR 23-Apr-18 ZAFAR 23-Apr-18 RODNEY CANCELLED 23-Apr-18


ANWAR 22-Apr-18 N/A N/A GUPTA CANCELLED

ANWAR 23-Apr-18 ZAFAR 23-Apr-18 RODNEY CANCELLED 23-Apr-18

ANWAR 22-Apr-18 N/A N/A GUPTA CANCELLED

SURVEYOR on going

ANWAR 29-Apr-18 N/A N/A GUPTA CANCELLED

RODOLFO 19-May-18 RICKY 19-May-18 N/A AWAITING FOR SIGN

ANWAR 26-Apr-18 HAFIZ 26-Apr-18 ROBERT APPROVED

RODOLFO 5-May-18 N/A N/A GUPTA CANCELLED

RODOLFO 5-May-18 ZAFAR 5-May-18 RAMESH APPROVED AS NOTED

RODOLFO on going

RODOLFO on going
NEW STATUS
REASON PIL & PMC INSP (APPROVED AS NOTED NEW DATE Remarks
TO APPROVED)

CIJE

ATTACH SURVEY REPORT RICKY APPROVED 27-Jan-18 CIJE

CIJE

CIJE

CIJE

CIJE

WORK NOT READY CIJE

CIJE

CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

NOT READY CIJE

CANCELLED BY SUBCONTRACTOR CIJE

REPEATED RFI CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

WORK NOT COMPLETED CIJE

HAFIZ APPROVED 7-Mar-18 CIJE

CIJE

CIJE

CIJE

CUBE CIJE

EPOXY ABOVE GROUND NOT DONE Not CIJE


CIJE

CIJE

CUBE CIJE

CUBE CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

NOT READY CIJE

CIJE

CUBE CIJE
SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CUBE CIJE

SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE

CIJE

CIJE

CIJE
CIJE

Electrical trench

Electrical trench

Electrical trench

Electrical trench

Electrical trench

Electrical trench

Electrical trench

Electrical trench

CUBE CIJE

CUBE CIJE

CIJE

CIJE
CIJE

CIJE

Not CIJE

Not CIJE

CIJE

CIJE

CIJE

CIJE

Not CIJE

Not CIJE

CUBE CIJE

CUBE CIJE

CIJE
NOT READY CIJE

DOUBLE RFI CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

FDT TEST NOT REQUIRED GRAVEL THICKNESS ONLY 50MM TO BE COMPACTED ONLY CIJE

CIJE

HAFIZ APPROVED 1-May-18 CIJE

CIJE

WORK NOT READY CIJE

CIJE

CIJE

HAFIZ APPROVED 1-May-18 CIJE

HAFIZ APPROVED 1-May-18 CIJE

CIJE

HAFIZ APPROVED 1-May-18 CIJE


CIJE

HAFIZ APPROVED 1-May-18 CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CUBE CIJE

CUBE NOT CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

CIJE

CIJE

CIJE

CONCRETE NOT POUR CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

HAFIZ APPROVED 26-Feb-18 CIJE

CIJE
CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

WRONG DESCRIPTION CIJE

CIJE

CIJE

RICKY APPROVED 12-Nov-17 CIJE

CIJE

CUBE CIJE
CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CUBE CIJE

CIJE

WORK NOT COMPLETE CIJE

WORK NOT COMPLETED CIJE

WORK NOT COMPLETED CIJE

Not CIJE

SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE


Not CIJE

Not CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE

CIJE

CUBE CIJE

SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE

CIJE

CIJE
CIJE

SUBCONTRACTOR NOT SUBMIT RFI AS ON 27-DEC-17 CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CIJE

CIJE

CIJE

CIJE
CUBE CIJE

CUBE CIJE

CUBE CIJE

RFI NOT SUBMITTED AS ON 11-MAR-18 CIJE

CIJE

CIJE

CUBE CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CIJE
CIJE

Electrical trench

Electrical trench

Electrical trench

Electrical trench

DOUBLE RFI CIJE

CUBE CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

DOUBLE RFI CIJE


CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

FDT TEST NOT REQUIRED GRAVEL THICKNESS ONLY 50MM TO BE COMPACTED ONLY CIJE

CIJE

CIJE

CIJE

CIJE

CIJE

CUBE CIJE

CUBE CIJE

CIJE

CIJE

CIJE
CIJE

CIJE

CIJE

Not CIJE

Not CIJE

CUBE NOT CIJE

CIJE

NOT YET DONE CIJE

CIJE

CUBE Not CIJE

CUBE Not CIJE