Вы находитесь на странице: 1из 2

Maintenance

and Reliability
B. BLUNDELL, Carmagen Engineering Inc.,
a member of the Mistras Group, Rockaway,
New Jersey

Better practices for tank overfill prevention


The 2005 Buncefield and 2009 CAPE- the unique risks of these operations programs than radar technology devices,
CO terminal explosions are two of the • Process control computer due to their potential to sometimes “stick”
most significant storage tank incidents in functionalities specific to tank and in the stilling well when product is being
history. Together, they resulted in dozens sphere operations that may alert transferred into or out of a tank. When
of injuries, and aggregate costs were in operators of abnormal conditions. a mechanical gauge sticks, the tank level
the billions of dollars. Both incidents oc- seen by the operator will appear constant,
curred when tanks were being filled with Level instrumentation. It is essential even though the actual liquid level is still
gasoline, a common operation seen daily that tanks and spheres have reliable level moving. This failure mode was a factor in
at refineries and distribution terminals. instrumentation. Tank gauges must be both the catastrophic Buncefield (FIG. 1)
While each incident presented its own periodically checked against a “manual and CAPECO incidents.
causal factors, a deeper examination re- gauge” (strapping) to validate their accu- A site should have a “bad actor” pro-
veals commonalities. racy. Devices should be calibrated when gram to identify tank and sphere gauges
Personnel involved in each of these the variance between the two readings that have repeated failures and require
scenarios were operating without a func- exceeds a predefined tolerance. As a best further evaluation or upgrades. Expecta-
tioning level instrument on storage tanks, practice, this comparison should be done tions must be clear that any tank gauge
resulting in losses of containment and sig- monthly to ensure the integrity of the data failure, even a mechanical-type gauge that
nificant explosions. In both cases, ensuing provided by the instrument. sticks temporarily, is essentially a “near
investigations determined that personnel A preventive maintenance (PM) pro- miss” that should be documented so that
had failed to recognize the risks and con- gram that is appropriate for the specific the failure can be analyzed, and repairs
sequences of the scenarios. type of level instrument should be in executed. As trends are noted, improve-
The trend of spills related to tank op- place to ensure high-reliability perfor- ments such as instrumentation upgrades
erations might suggest that another inci- mance. Mechanical-type gauges (tape or enhanced PM programs can be execut-
dent like CAPECO or Buncefield is a pos- and float) may require more robust PM ed to improve reliability.
sibility. While these particular incidents
occurred several years ago, tank overfills
are still one of the most common causes
of losses of containment in the industry.
Many companies have begun to recog-
nize the unique risks of operating storage
tanks and spheres, and better practices
have emerged to address these issues. A few
of those practices that may be beneficial to
mitigate the risk of an overflow and the po-
tential consequences are detailed here.
The foundation for a strong system for
overfill prevention should include these
three key elements:
• Reliable level instrumentation to
ensure operations personnel always
know the level and fill, or draft rate,
of a tank
• Robust procedures and work FIG. 1. The 2005 Buncefield terminal explosion in the UK occurred when a tank was being filled
practices to effectively manage without a functional level gauge, resulting in dozens of injuries and costs that exceeded $1 B.

Hydrocarbon Processing | JULY 2018 47


Maintenance and Reliability

For higher-risk tanks, such as those these elements (e.g., increasing impeller quire a clear mitigation plan to manage the
in hazardous product service or those size in pumps) should similarly include an risk, as well as communication of the out-
near roadways or waterways where a spill evaluation of high-level alarm setpoints, if age to a site supervisor. Management must
may have an immediate public impact maximum fill rates are increased. be aware of the ongoing exposure to ensure
(FIG. 2), a secondary (redundant) means that appropriate maintenance resources are
of measurement should be in place. If the Management systems/procedures. allocated to address it.
primary gauge is lost, these independent Operating procedures that stipulate re-
instruments can continue to provide data quirements when a storage tank is filling Process control computer capability.
on tank product levels. Such instruments or drafting should be in place. These re- For larger facilities, alarm capabilities spe-
have become a minimum standard in the quirements include specific expectations cific to tank operations are critical. Many
industry for new installations. regarding response to alarms, loss of con- functionalities are common in the tank in-
To determine which tanks should have tainment and other abnormal conditions. dustry that are effective aids to operators.
redundant level devices, a facility should As a better practice, for specific high-risk Distributed control systems (DCSs) fea-
conduct a hazard analysis of each tank to operations where the consequences of a ture applications that can recognize when a
define the probability of a gauge failure valve misalignment may be a significant level stops moving on a tank, which may be
and the potential consequences of a spill. health, safety or environmental (HSE) an indication that a mechanical gauge (tape
High-level alarm setpoints in tanks event (FIG. 3), prescriptive checklist pro- and float) has stuck in the stilling well dur-
should be based on a technical evaluation, cedures must be considered to ensure ing the product transfer. For sites that have
taking into consideration key factors that consistent execution. a large number of tanks with mechanical
will enable personnel to proactively re- When a level instrument is believed gauges, this type of alarm can be a key aid in
spond to an alarm. These elements include to be providing erroneous data, product alerting operators that a gauge has failed.
maximum filling rates, as well as operator transfers into or out of the tank should be Another functionality within some
response times needed to isolate a tank to stopped by default. However, there may DCSs that can be an effective tool for op-
prevent a spill.1 Any change to an alarm set- be some instances where a strong busi- erators is a rate change alarm, which is trig-
point must go through a rigorous change ness incentive prompts the continued uti- gered when the computer detects a signifi-
management process to ensure proper lization of the tank. cant flowrate change during a pumping. A
technical review of the proposed modifi- In those cases, a risk-based, out-of-ser- significant change in pumping rate may be
cation. In addition, facility modifications vice gauge procedure should always be in an early indication of a problem in the field
that might significantly change either of place to standardize the expectations for that warrants investigation.
monitoring the liquid level. A sound pro- Similarly, an inactive tank movement
cedure can include an alternate means for alarm that alerts operators when a tank that
monitoring tank inventory (e.g., manual is not part of an ongoing product transfer
gauging) and a defined frequency for the begins to fill or draft can also be an effective
alternate monitoring. tool to identify problems, such as valve align-
When determining the frequency for ment issues or another abnormal condition.
monitoring, factors to consider include These recommended practices can be
filling rate, and where the product level is implemented to reduce the risk of a po-
located in the shell. Tanks filling at high tential incident. Facilities that have not ex-
rates, and in the top third of their capac- perienced a tank overfill event can be con-
ity, should be monitored more frequently. sidered fortunate, and focusing resources
FIG. 2. Tanks that border public roads or Mass balances to calculate tank levels on the three fundamentals referenced here
waterways may carry a higher consequence if based on assumed fill rates should never may help reduce the probability of an inci-
an overfill occurs. Redundant level instruments be the sole barrier to prevent an overflow. dent in the future.
should be considered in the event of the loss Another considered mitigation is to reduce
of the primary gauge on these tanks. LITERATURE CITED
the maximum fill height of the tank (e.g., re- 1 API/ANSI Standard 2350, “Overfill protection
duce the fill height by 20%). This can pro- for storage tanks in petroleum facilities,” 4th Ed.
vide an additional layer of protection while
the gauge is out of service. ROBERT BLUNDELL has more than
Operating a tank without a functional 35 yr of experience in marine
terminal and tank farm operations,
level instrument is considered a high-risk and served as a mid-level manager
activity similar to the loss of other HSE with ExxonMobil before retiring in
critical instrumentation. Many sites han- 2013. He was the Marine Terminal
dle out-of-service level devices on tanks in Manager at the Baytown refinery,
and served as the Chairman of the ExxonMobil North
the same manner that safety instrumented American Marine Terminal Managers Committee for 8
system (SIS) bypasses are managed, with yr. He has conducted dozens of marine terminal,
clearly defined mitigation plans while this midstream, refinery and chemical plant assessments
around the world, and is a certified Assessor for the
FIG. 3. Tank facility operations bear a critical layer of protection is out of service.
API Process Safety Site Assessment Program. He now
significant HSE exposure if risks are not As a recommended better practice, the serves as a Senior Advisor with Carmagen
effectively managed. loss of a gauge on a filling tank should re- Engineering Inc.

48 JULY 2018 | HydrocarbonProcessing.com

Вам также может понравиться