2 Materials
Conform with approved Proj. Specifications / Proj. Quality Engineer/ AGC Inspection of Material delivered to
2.1 Check materials delivery Every Delivery H W S
material approval request Plan /Material Approval QC Site (MIR)
Verify lay-out of the pipeline, elevation and location of the Visual Inspection Dimension as indicated in Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.1.2 Every line H W R
(plumbing), fittings and fixtures and Survey the approved drawing Drawing QC QC-ME-007
Dimension as indicated in Proj.Specifications /Approved Before Every Engineer/ AGC Request for Inspection (RIW),Form
5.1.3 Visual inspection of sand bedding prior to pipe laying (U/G) Visual Inspection H W R
the approved drawing Drawing Pipe laying QC QC-ME-007
As per joint details in the Engineer/ AGC Request for Inspection (RIW),Form
5.1.4 Welding visual inspection(if any) Visual Inspection Quality Control Manual Each Joint H W R
approved drawing QC QC-ME-007
Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) CC -CONSTRUCTION CONTRACTOR (AGC))
W - Witness (attendance expected, signature on check sheet) R - Record review PC - PRIME CONTRACTOR (BAE SYSTEM)
Form: QC-ITP-01
Issuance: 01
TINS-GEN-ITP-M-0003-R00 1 of 4 Revision: 01
PROJECT QUALITY PLAN
Dimension as indicated in Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.1.5 Check hangers and supports spacing and installation Visual Inspection Every Supports H S R
the approved drawing Drawing QC QC-ME-007
Verify lay-out of the pipeline and location of the floor drain, As indicated in the Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.2.1 Visual Inspection Every Pipe H W R
clean-out, other fittings and fixtures. approved drawing Drawing QC QC-ME-007
Visual Inspection As indicated in the Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.2.2 Visual inspection of sand bedding prior to pipe laying Every line H S R
and Survey approved drawing Drawing QC QC-ME-007
Check tightness/connection of pipes to its fittings and other As indicated in the Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.2.3 Visual Inspection Each Joint H S R
ancillaries. approved drawing Drawing QC QC-ME-007
Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) CC -CONSTRUCTION CONTRACTOR (AGC))
W - Witness (attendance expected, signature on check sheet) R - Record review PC - PRIME CONTRACTOR (BAE SYSTEM)
Form: QC-ITP-01
Issuance: 01
TINS-GEN-ITP-M-0003-R00 2 of 4 Revision: 01
PROJECT QUALITY PLAN
Proj.Specifications /Approved Each Section Engineer/ AGC Request for Inspection (RIW),Form
5.2.6 Piping Gravity Test Visual Inspection No leak at test H H R
Drawing b/w Manholes QC QC-ME-005
5.3 Fixtures
Check installation setting and leveling of plumbing/sanitary Dimension as indicated in Proj.Specifications /Approved Engineer/ AGC Request for Inspection (RIW),Form
5.3.1 Visual Inspection Every Fixtures H W R
fixtures the approved drawing Drawing QC QC-ME-002
Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) CC -CONSTRUCTION CONTRACTOR (AGC))
W - Witness (attendance expected, signature on check sheet) R - Record review PC - PRIME CONTRACTOR (BAE SYSTEM)
Form: QC-ITP-01
Issuance: 01
TINS-GEN-ITP-M-0003-R00 3 of 4 Revision: 01
PROJECT QUALITY PLAN
Visual inspection for sanitary fixture workmanship and Dimension as indicated in Proj.Specifications /Quality Control Engineer/ AGC Request for Inspection (RIW),Form
5.3.2 Visual Inspection Every Fixtures H W R
appearance the approved drawing Manual/Approved Drawing QC QC-ME-002
Dimension as indicated in
Check waste and service couplings to all equipments and Proj.Specifications /Quality Control Engineer/ AGC Request for Inspection (RIW),Form
1.5.3 Visual Inspection the approved drawing/ Every Fixtures H W R
fixtures. Manual/Approved Drawing QC QC-ME-002
product manual
Dimension as indicated in
Check all traps and seals are intact to fixtures, leave all clean Proj.Specifications /Quality Control Engineer/ AGC Request for Inspection (RIW),Form
1.5.4 Visual Inspection the approved drawing/ Every Fixtures H W R
and tidy Manual/Approved Drawing QC QC-ME-002
product manual
Functioning properly as per Proj.Specifications /Quality Control Engineer/ AGC Request for Inspection (RIW),Form
1.5.6 Final Inspection Visual Inspection Each Segment H W R
requirements Manual/Approved Drawing QC QC-ME-002/005
Legend: H - Hold Point (Signature required to proceed) S - Surveillance (random attendance, no signature) CC -CONSTRUCTION CONTRACTOR (AGC))
W - Witness (attendance expected, signature on check sheet) R - Record review PC - PRIME CONTRACTOR (BAE SYSTEM)
Form: QC-ITP-01
Issuance: 01