Вы находитесь на странице: 1из 3

MANAGING RISK IN UNDERGROUND ENGINEERING, TRANSPORTATION AND SOFTWARE DEVELOPMENT

Project Risk Management and


Madrid’s New Airport
By Paul Callender, Manchester, UK 44-(0)161-200-5000, paulcallender@hotmail.com

H oping for the best, preparing for the worst, and anticipating possible
scenarios—PB is providing a three-tiered comprehensive risk
management program for the $3.5 billion expansion of Madrid’s Barajas Airport.

The Barajas Airport is undergoing substantial expansion in • Manage and monitor residual and secondary risks (including
response to a rise in predicted demand from today’s 30 million risks inherent in the risk mitigation strategy)
passengers per annum to more than 70 million by 2025. The • Improve confidence in contract estimates, budgets and
project, known as Plan Barajas, consists of two new runways, allowances
associated aprons and taxiways, a new terminal building, a • Provide a robust completion date for the project
satellite terminal with an automated people mover and an
• Develop contingency plans, estimates and trigger dates
automated baggage handling system. Contractors have started
construction on several of the primary work packages, such as the • Evaluate the probable effects of external projects
new passenger terminal, satellite building and the car parking • Establish a process for communicating key issues.
facilities. The remaining work packages are in various stages
of progress ranging from design up to tender stage (bidding). Application
PB’s program management team, headed by Peter Wright, Our team developed the following three-tiered risk management
recognised the need for a project risk management program that approach that was tailored to Barajas’ substantial size and
would provide a structured approach to identifying and evaluating complexity. This approach became necessary due to the complex
risks and a procedure for developing and implementing risk nature of the project (more than 25 individual projects and more
mitigation strategies. A comprehensive proposal was presented than 1000 individual contracts). It has the benefit of enabling
and accepted by the client, permitting the commissioning of our users to pin point specific risks without losing sight of the overall
group to develop and implement a risk management procedure project objective.
tailored to the requirements of Plan Barajas.
The process that we developed and follow for each level
Objectives (see Figures 1 and 2 on the following page) is as follows.
• Level 1: Global Project. The project as a whole is examined,
Project risk management is a fundamental element of the overall including its objectives and the potential risks to achieving
project management strategy. The principal aim of the process is those objectives. Risks identified and evaluated at this level may
to ensure that the project meets its objectives with an acceptable require a change in strategy or reassessment of the global cost/
risk exposure while providing value to the client. programme estimates. Any changes would then feed into the
principal projects. An example of a global-level risk encountered
Project risk management is most effective when applied early in is the potential for late approval of the environmental impact
the project life cycle, preferably at the outset of the project before study, an event that could possibly require a rescheduling of the
any significant commitments have been made. For Plan Barajas, work packages to ensure the new airport opens on time. Scenarios
we were able to develop a risk management process that identifies have been developed looking at the various options available.
and responds to potential problems with sufficient lead-time to • Level 2: Principal Projects and Interfaces. This level goes
avoid crises. into more detail by examining the individual objectives of each
primary project and how the project interfaces with the other
The principal objectives of this process are to:
projects. Risks identified at the project level may include project
• Enable a formal and systematic approach to identifying risks scope changes in the new terminal building to accommodate
and uncertainties that might impact delivery of Plan Barajas peak passenger flows following the introduction of the new
• Evaluate the probable effects of identified risks and large aircraft (Boeing 380X). Results from this analysis may
uncertainties to support risk prioritisation require changes to the individual contracts, timescales and
• Develop a targeted risk mitigation or risk removal strategy budgets or allowances against potential risks.

PB Network January 2002 56


MANAGING RISK IN UNDERGROUND ENGINEERING, TRANSPORTATION AND SOFTWARE DEVELOPMENT

Plan Global Objective 1 Global Risk 1


LEVEL 1 Barajas Global Objective 2 Global Risk 2
Global Objective Z Global Risk Z

Priciple Proj. Obj. 1 Priciple Proj. Risk 1


Proposal Proposal Priciple Proj. Obj. 2 Priciple Proj. Risk 2
LEVEL 2
Project 1 Project X
Priciple Proj. Obj. Z Priciple Proj. Risk Z

Contract Objective 1 Contract Risk 1


LEVEL 3 Contract Contract Contract Contract Contract Objective 2 Contract Risk 2
1 2 3 y
Contract Objective Z Contract Risk Z

Figure 1: Overview of Project Risk Management Plan

• Level 3: Individual Contracts and Their Interfaces. At this


level, risks are identified within each contract and in the
interfaces with other contracts. Contract-level risks are
specific to the particular contract. Identified risks to date
include inadequately defined interfaces between contracts Figure 2: Project
that impact directly on the efficiency of each contract. Risk Analysis and
Management Cycle
Methods Risks identified at each level are fed into a risk register (defined
on page 23) written specifically for Plan Barajas by using a
Phase One: Baselining. This phase of the risk management
Microsoft Access database.
procedure prepared for Plan Barajas was to baseline the project,
confirming the project objectives and parameters. This step proved Phase Four: Response. Risk responses, mitigation strategies and
very useful as it ensures that all staff members have a common contingency plans are developed for all intolerable risks. Each
understanding of the project and provides a reference point against contingency plan identifies the particular trigger date and conditions
which to measure progress. Levels of tolerance were also formalised associated with the risk to enable implementation of the mitigation
establishing the level of risk Plan Barajas is willing to accept. plan in sufficient time to minimise the risk to an acceptable level.
For example, a change in passenger forecasts of, say, ±30 percent
Phase Two: Risk Identification. This phase is carried out by might require the team to redesign passenger areas to accommodate
using the tried and tested method of brainstorming. Structured these figures if the probability of this risk occurring is high. The
one-day workshops are convened with the relevant stakeholders mitigation plan would identify trigger dates and conditions for
and project staff, and risks are identified and categorised, and implementation of a scope change that would cause the least
their potential causes and effects are detailed. This information is disruption to the project.
fed directly into a spreadsheet using a laptop and screen projector.
Phase Five: Risk Management. This phase of the process is
Phase Three: Risk Evaluation. A preliminary evaluation of the fundamental to its success. As situations change and the project
risks is undertaken with ratings of between 1 (low) and 5 (high) progresses, new risks become evident, existing risks are re-
being assigned for the probability of occurrence and its potential evaluated and trigger dates and conditions are monitored closely
impact. Risks that are evaluated as being intolerable are then for activation of mitigation plans. Monthly status reports that high-
subjected to a more rigorous quantitative analysis using light the current status of each risk and the combined effects of
techniques such as Monte Carlo analysis1. The Plan Barajas the risks identified on the project are produced and communicated
is using two software programs for the quantitative analysis. to each division. The status report also details risk trends, indicating
• Crystal Ball Pro. This spreadsheet-based analysis tool uses the level of proactive management being instilled by each division
Monte Carlo techniques modelled on an Excel spreadsheet. as they come to terms with the philosophy of risk management.
It is ideal for modelling cost scenarios and probabilities.
• Pertmaster Professional. This software also uses the principals Summary
of Monte Carlo analysis but applies them to a program schedule
for modelling time-based scenarios and their combined effect on The project risk management process for Plan Barajas, which is
the program. programmed for inauguration in March 2004, has been up and
running for almost a year now. Within this relatively short time
1
Monte Carlo is a method of analysing stochastic (governed by the laws of probability) we have been able to allow the client and his staff to concentrate
processes that are so difficult that a purely mathematical treatment is not practical. The their efforts on critical issues that could jeopardise the project’s
method relies on the random calculation of values that fall within a specified probability
distribution, often described by using three estimates: minimum, most likely and maximum. (continued on the following page)

57 PB Network January 2002


MANAGING RISK IN UNDERGROUND ENGINEERING, TRANSPORTATION AND SOFTWARE DEVELOPMENT

Controlling Risks of Introducing


Lessons Learned New Signalling Equipment in the UK
(continued from page 55)
To date, the fundamental lesson learned from the application
of a structured project risk management process on a project
as large and complex as Plan Barajas is the level of resources
induced current was significantly less than the threshold voltage
required to actively control and monitor risks at the outset. Each of the relays and that, as such, would not cause their inadvertent
intolerable risk identified requires a structured mitigation plan. operation.
Should the trigger conditions occur, the mitigation plan requires
implementation—activities that draw on both time and effort of Cross-Acceptance. The concept of cross-acceptance has been
the available resources. difficult to get to terms with for both the project and the
acceptance bodies. Because it is still a new concept for the UK
Advice to anyone who is preparing to implement a risk management rail industry, the boundaries of where and how it can be used
procedure is to make realistic estimates for the level of resourcing are still being defined and there are not many people who are
required, not only within the consultant’s team but the reciprocal
experienced in using it.
time and effort required on the client’s side as well. Once a
procedure has been established, however, resources are
allocated more effectively (i.e., prioritising activities that
An example of where this has made a big impact is with hazard
have a direct impact on the achievement of the projects identification. Normally with a new system or product we would
objectives). A well implemented project risk management try to find as many potential hazards as possible. With cross-
procedure encourages a more proactive attitude acceptance we do not identify hazards associated with the “core”
within the workforce and management of a project, product (i.e., the product that is not modified for use in the UK) as
minimising the fire fighting culture that is these are assumed to already be of sufficiently low risk. We can
evident in many complex projects. argue that this is so by claiming that the acceptance procedures
used in Italy for that “core” product ensure that these risks have
already been sufficiently mitigated. Therefore, we apply the hazard
objectives. In so doing, we have also been able to emphasise the identification processes only on the differences between then
need for a proactive management regime, looking for areas of Italian application and the Manchester South application
potential failure and ensuring that measures are in place in a time- (i.e., where the product has been modified for use in the UK).
ly manner to avoid them. There is, therefore, a significant risk to the project if the cross-
acceptance argument does not hold up to scrutiny, as the basis
Applying a structured, risk-based approach to project management of the product safety cases will be substantially undermined.
provides an effective and thorough mechanism for delivering an
efficient, timely, and cost effective project. In essence, project risk
management provides a structured methodology that enables the
Conclusion
project manager to make informed decisions at each juncture, to
Manchester South is an extremely challenging project as it aims to
proactively address issues and concerns, and to have contingency
introduce high technology systems within project timescales, using
plans and mitigation strategies ready for implementation prior to
new concepts. Safety is of paramount importance, and the evidence
the occurrence of a risk. ◆
that new systems are safe is scrutinised more than ever before in
light of recent rail accidents in the UK. By a process of continual
improvement, however, the project has now developed to a point
Paul Callender is a principal consultant with PB’s Manchester office.
where the teams are focussed and have clear and achievable
He graduated from Kingston University in 1995 with an MSc in pro-
objectives. ◆
ject management and law and has been employed within a number of
industries, including rail, aeronautical, highways and manufacturing,
and as a contractor in Dubai. Since graduating, he has been employed
primarily as a project manager and was responsible for the preparation Karl Virden joined PB in 2000 and is based in PB Infrastructure
of the 20-year upgrade strategy for the London Underground Network. Limited in the Manchester office (UK) as part of the Risk Management
Consulting group. A member of the Safety and Reliability Society, he
is currently working full-time on the Manchester South Alliance as the
Hazard Log Manager in his first major project both with PB and in
the rail industry.

PB Network January 2002 58

Вам также может понравиться