METHOD OF STATEMENT
SEMBCORP MARINE
-SUPPLYING OF 2 x 15T DOUBLE GIRDER EOT CRANE
Engineer PM GM
Table of Contents
1. Introduction
2. Scope
3. Purpose
4. Responsibilities
5. Safety Procedures
6. Crane Specification
7. Reference
8. Methodology
9. Delivery and Installation of Rails on to the runway
10. Installation of 15T DG EOTC
a. Delivery of Crane structures, Hoist and components to the site
b. Offloading and Assembling of Cranes structures, Hoist and component
c. Utilization of the Mobile Crane for Installation
d. Installation of the end-carriages on to the runways
e. Installation of the crane-girder on to the end-carriages
f. Installation of the Hoist and service platform
g. Electrical works on the accessories, components and devices of the EOTC crane structure
h. Testing & Commissioning
i. Maintenance
1. Introduction
This Method statement is submitted here for the purpose of better understanding to the
client as to how different elements of the project will be executed through disciplined
approach by Jenmon International Pte Ltd for the Installation of 2 x 15T DG EOT Crane at
Robotic Workshop.. It will act as a communication among various parties and personnel
involved in the project, giving an idea of methods, procedures, safety measures and prudent
techniques that will be adopted for successful completion of the works. Serving as a working
document, the Method Statement shall identify the responsibilities of the contractor and its
staff and also ensure that quality of works meet the standard specification.
2. Scope
The Scope of the Method Statement covers the Methodology, Sequence of Work, Materials
and Equipment that shall be used for the Installation of 15T Double Girder Overhead
Travelling Crane.
3. Purpose
The Purpose of this Method of Statement is to provide specific work instructions from the
Delivery stage, preparation stage, installation stage, commissioning stage and also the
safety and environment controls associated with these works. A flow chart of the work
activities is presented on the following page to show the sequence of activities involved.
4. Responsibilities
All works will be overseen by Project Manager, Project Engineers or Team Leaders
executed by the sub-contractor, Jenmon International Pte Ltd. Lifting operations shall be
executed and controlled by competent certified training personnel; Safety Supervisor, Lifting
Supervisor, Signal man and Rigger.
5. Safety Procedures
The activity which requires safe work procedures are as follows:-
b) Lifting Operations
These works requiring lifting operations shall be executed and controlled by competent
certified trained personnel; Safety Supervisor, Lifting Supervisor, Signal man and Rigger.
c) Working at Height
Workers working at height on top of the boom lift shall be executed and supervised
by competent certified trained personnel; Safety Supervisor and Signalman /
Banksman.
6. Crane Specification
Gantry Crane Specification takes reference as Design Drawing. Design Drawing with Crane
Specification is attached in Appendix C: Crane Specification.
7. Reference
-Attached lifting Plan.
8. Methodology
a) Check and confirm the straightness of the runway and leveling from the beginning
point to the end from the alignment report by Runway Sub-contractor.
b) For the marking of the straight-line on the runways will be conduct by the workers
using the boom lift in order to install the Sq. rails on the runway beam according
by crane span-length.
c) Lorry (Jenmon) will be using for the delivery of Rails and offloading shall be done by
manually. Mobile crane shall be used the lifting up rail on top of the runway beams
(within SWL).
d) Delivery route will be using Singtec Main-Gate, in order to go in to the site access.
e) Site supervisor and installation team shall monitor the deliver and lift-up the
installation of Rails.
f) Once Rails lift up to above of runway level, welder will start the tack- welding of the rail
to the runway by using boom-lift. After that, welder will precede the fillet welding of Sq.
rail to the runways. (This will be offset fillet-weld)
g) During installation of the Sq. rails must be stand by fire-extinguisher, fire blanket and
look-out man.
a) Delivery and offloading of Crane structures, Hoist and components to the site
-1 unit of long trailer will be using for the delivery of girder structures, hoist and component.
The list of delivery materials as shown as below
Crane main girder – 2 pcs
Crane end-carriage - 2 Pcs
Crane Service platform – 1 set (completed)
Crane Hoist with components – 1 set
b) Offloading of the main girder, hoist and components
-1 unit of the 50T mobile crane will be using for the offloading of the crane structures,
service platform, hoist and component. (Subject to use 2 units of lorry crane)
-Offloading at designated area and proper barricaded (or) signaled
-Refer to the lifting plan for offloading of crane structure and components.
-After that install the support bracket (50x 50x5mm) on the runway using tack-weld in order to
secure the end-carriage with the runways.
-Check the alignment and leveling of the end-carriage in order to install the main girders.
g) Electrical Works on the Accessories, Components and Devices of the Gantry Crane Structure
- Installation of all other components on the gantry crane with boom lift.
-Connect electrical termination inclusive welding of bas bar bracket and assembly of bas bar
brackets.
-Install electrical/control equipment such as pendent, festoon system onto the crane control
panel / box.
-Hoist electrical termination will be done by customer. Internal electrical termination includes
hoist to control panel, festoon system and etc.
-All joined parts to be checked properly, secured tightly and bolted accordingly.
-Hoist motor, limit switches, long travel motor, cross travel motor shall be tested for the
functionality and the brakes efficiency at a level.
-MOM-PE/AE shall conduct load testing and measure girders deflection for the gantry crane in
accordance with 125% overload of it SWL under MOM Authorised requirement.
-MOM-PE/AE shall register & issued with the approved load test LM certificate from MOM upon
passing the load test. (subject to UEN or Workplace registration requirement)
-Refer to Fig:6 for the load testing and commissioning of the gantry crane
a. Maintenance
John / Anand
Safety supervisor
Sara
Managing Director
General Manager
General Manager
Project Manager
WSHC
a) All necessary measures will be implemented as per Risk Assessment Table attached
in the Appendix A.
All operations will be carried out in accordance with the site safety plan and specifically the
following will be ensured:-
All personnel working on site will wear the required PPE and will have attended the site
induction course (unless required).
Any personnel working at height (>2m) will required to wear a safety harness.
The installation company will provide suitably qualified lifting supervisor, rigger & signal
man and welders, a copy of their MOM qualify certification for which will be provided to
MOM, if requested.
After erection and commissioning of the gantry cranes, the installation company will
issue a lifting certificate endorsed by a MOM-PE/ AE.
Welders and any other persons working at height (>2m) are required to wear safety
hardness and hooked on secured anchor-points at all times.
Qualified personnel will be involved in the planning and execution of heavy lifts.
Competent and certified operators will be engaged including lifting supervisor, crane
operator and riggers.
Cranes, slings and shackles will be used compatible with achieving safe working load
requirements.
Mobile cranes/ Lorry crane will be set up levelled and within safe working radius on firm
and even ground, with outriggers fully extended and sit on metal foot pads.
Crawler crane parking area and travelling route must be concrete route and sufficient
space as no obstruction things at all times.
Ensure to check the tower crane all of hoisting and turning radius, prior to use for the
installation of the crawler crane.
15. Appendix
A. Risk Assessment