Академический Документы
Профессиональный Документы
Культура Документы
Tokyo, Japan
Bangladesh:
Building a national PPP Program
April 2016
Page 2 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
Bangladesh 7th Five Year Plan (FY2016-2020)
“To become a
Post 2015 targets Annual Average Reduction of head Additional Jobs
middle integrated
income country Growthby 2021
count poverty ratio created
and a
developed country by 2041”
Enablers
Government of Bangladesh th
7 Five
Total Investment Private Sector Infrastructure PPP
Requirement Investment FinancingYear Plan (published Dec
(annual) 2015)
(%of GDP)
Page 3 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
Understanding Public Private Partnerships
and Operation
Private Supply
Management
Public Supply
Management
and Maintain
DBFOM/BOO
Joint Venture
Outsourcing
Agreements
Agreements
Concession
Regulated
Affermage
Leasing /
Service
Utility
BOT
Page 4 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
History of partnerships with private sector
Up to 1995 1996 – 2004 2005 - 2009 2010 - On going
Centrally
Phase
(e.g. KAFCO) (e.g. Haripur 360MW (e.g. RPCL 70MW) (e.g. Transport, Port,
& Meghnaghat 450 Power, Health, Zones,
Health MW power plants) Port Projects Civil Accommodation,
(e.g. BIRDEM, Heart (e.g. Teknaf Land Port) Housing, Tourism)
Foundation) RoadHaripur
Projects Mayor Mohammad
360 MW Power Plant
Hanif Flyover
(e.g. Hanif Flyover)
Page 5 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
A New Framework for PPP: Key Reforms
Centralised regulatory
Injection of targeted
unit and program
and catalytic funding
champion
support
Financial Institutional
Support Changes
Public and private
sector transaction
execution capacity Capacity Regulatory
enhancement
Development Changes
Project
Preparation Streamlined approval
Structured process with and integrated policy
expert support for framework
project development
Page 6 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
The PPP Process
Process applied for implementation of PPP projects
Appoint subject
matter experts
Monitor (1)
implementation; Screen
apply lessons
(2)
learnt (7)
Expert
Monitor
Appt. Pick projects
suitable for PPP
CCEA
Meet conditions Approval
precedent for (6) (3) Ensure technical
financial close Finance Feasibility and commercial
viability
Page 7 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
Creating the Conditions for Investor Confidence
Market
Sounding
Investor
Promotions
Pre-Bid
Meetings
PPP Act Contract & Bid Transaction Advisors Marketing
(Sep 2015) Documents
Page 8 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
PPP AuthoritySupport
Government Governance Arrangement
for PPP Projects
PPP projects are centrally monitored to Government will identify land
ensure constraints are pro-actively requirement and acquire at own cost
addressed
Land Resettlement (if required )
Centralised will be done by Government
Key clauses to Acquisition
protect investment
Monitoring after due consultation and
necessary compensation
included in PPP
Contracts
Investor
Protection Resettlement
Full technical,
Access to financing Long Term PPP Detailed commercial and
from dedicated Program financial studies
Government owned
Financing Access Feasibility Study carried out by
banks internationally
appointed
consultants to ensure
viability and
bankability
Incentive Viability Linked Project
Incentives Package being Package Gap Delivery
developed covering
financial benefits and
Financing All linked projects (e.g.
regulatory support Subsidy utilities shifting) will be
carried out by government
(Where required) Government can at its own cost
provide additional financial subsidy
Page 9 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
Bangladesh PPP Program Summary
5 5 43 Projects
17
1 (US$14bn*)
7
May '12 May '13 May '14 May '15 Jan '16
* Estimated ** Approximately (Data as at January 2016) (excludes power sector projects - summary in annex)
Page 10 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
Enhancing International Profile of the PPP Program
Asia-Pacific Forum on
Public-Private
Partnerships for Transport
Asia-Pacific Forum21-22
Infrastructure
Development
onJanuary
Public-
“Selected
“One
“Specially
“One
“One of 34byemerging
ofof UNECE
Asiantoto
countries
4invited
2015
IMPLEMENTING
Private Partnerships THE UN 2030
forThailand
Bangkok,
with
share showcase
the
best
countries
market necessary
practice
with
countriesthe
AGENDA THROUGH
Transport Infrastructure EFFECTIVE,
Development PEOPLE
6TH PEOPLE’S FIRST
REPUBLIC OF CHINA –
framework
for
most
case
invitedestablishing
vibrant
study for 17
PPP
of SDG
to showcase
PPPinfrastructure
ADB KNOWLEDGE-SHARING PLATFORM
21-22 PUBLIC
January
WORKSHOP ON 2015 PRIVATE
DEEPENING PUBLIC-PRIVATE national
consistent PPP
programs”
PPP
development”Centres”
model”
PARTNERSHIPS IN ASIA AND THE PACIFIC
Bangkok, PARTNERSHIPS
Thailand
financing support ”
25-28 November 2014 Beijing
IMPLEMENTING THE UN 2030
PPP OPENS NEW November
January 2014THROUGH EFFECTIVE,
2015
June 2015
AGENDA
HORIZONS March 2016
September 2015 PEOPLE FIRST
PUBLIC PRIVATE
PARTNERSHIPS
3016 March
February 2016– 1 April 2016,
30 March – 1 April 2016,
ESA Campus
Geneva, Switzerland
Beirut, Lebanon
ASIAN DEVELOPMENT BANK Geneva, Switzerland
Page 11 PPP Project Pipeline Update 1st Meeting of the Board of Governors
PPP Contacts Signed
Commercial
PPP Projects Contract Signed Construction Start
Operation
(3) Haemodialysis Centre at NIKDU January 2015 August 2015 June 2016 (forecast)
(4) Haemodialysis Centre at CMCH January 2015 August 2015 June 2016 (forecast)
(5) Kaliakor Hi-Tec Park (Lot 2 & 5) June 2015 February 2016
Page 13 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
PPP Transaction Advisor Appointment
CA
(3-4) Occupational Disease. Hosp. Health Devlpmt. Proc. Aprv.
CA
(5) Kamlapur Hospital Health Aprv.
Civil CA
(8) Jhilmil Residential Area
Accomod.
Development Proc. Aprv.
CA
(9) LPG Bottling Plant Energy Aprv.
Page 14 Bangladesh: Building a National PPP Program Japan Bangladesh Joint Dialogue
“We look forward to working in partnership with you in
building the infrastructure foundation of Bangladesh.
Contact Details:
Syed Afsor H. Uddin
Chief Executive Officer
PPP Authority (Prime Minister’s Office)
51-52 Mohakhali,
Dhaka 1212, Bangladesh
Tel: +88 02 9898530
Email: ceo@pppo.gov.bd