10.4 BOILER CONTROL CURVES

Fluidizing nozzles 04.01.2005


Primary air temperature before air preheater, coal 04.01.2005
Primary air temperature before air preheater, bark 04.01.2005
Measured total air flow, coal 04.01.2005
Measured total air flow, bark 04.01.2005
Primary air flow (Fluidizing air), coal 04.01.2005
Primary air flow (Fluidizing air), bark 04.01.2005
Lower secondary air flow, coal 04.01.2005
Lower secondary air flow, bark 04.01.2005
Air distribution, coal 04.01.2005
Air distribution, bark 04.01.2005
Recirculation gas flow 26.01.2005
O2 vol-%, wet flue gas 04.01.2005
Limestone feeding 04.01.2005
Control curve for steam coil air preheater 09.02.2005

0 2005 - 08 - 30 T. Anttonen
Muut. Pvm Laatinut Pvm Tarkastanut Pvm Hyväksynyt
Rev. Date Prepared by Date Reviewed by Date Approved by
KLY-1 1997-05 P:\582-RAPP-PB3\int\Kayttoonotto\käyttöohje\Operation and Maintenance Manuals\Folder
2\10.4 Boiler control curves list.doc
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

 Kvaerner Power Oy, Tampere, Finland 2005

Вам также может понравиться