TIME SCHEDULE PELAKSANAAN PEKERJAAN ASSESSMEN GEDUNG LOTTE MART

Uraian Pekerjaan OKTOBER NOVEMBER


NO. Jumlah Titik Progress
Ground Floor 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Visual Test 100%
Ultrasonic Pulse Velocity (UPV) 50 90%
NDT
Scanning Rebar 50 100%
Core Drill (CD) 6 100%
DT
Concrete Breakout (CB) 6 67%
Loading Test 1
Pengecekan Lendutan
2 Mezanine
Visual Test 100%
Ultrasonic Pulse Velocity (UPV) 50 100%
NDT
Scanning Rebar 50 100%
Core Drill (CD) 6 0%
DT
Concrete Breakout (CB) 6 0%
Loading Test 1 0%
Pengecekan Lendutan
3 First Floor
Visual Test
Ultrasonic Pulse Velocity (UPV) 50 84%
NDT
Scanning Rebar 50 84%
Core Drill (CD) 6 0%
DT
Concrete Breakout (CB) 6 0%
Loading Test 1 0%
Pengecekan Lendutan 0%

NOTE :
1 Laporan Hasil Asesmen dan Analisis akan dilaksanakan dalam kurun waktu 1 November-30 November 2018