Академический Документы
Профессиональный Документы
Культура Документы
HAB 1
ASSEMBLY INSTRUCTIONS
July 2011
INTRODUCTION
Some tools are included in the kit. More basic tools such as shovels should be
supplied by the construction force.
Transportation
Each HAB 1 is dispatched in 4 Crates to the following dimensions
Length = 2300mm Width = 1000mm
Height = 1100mm Weight = 960kg per crate
1
INTRODUCTION
Fill Material
It is recommended that a good fill material is chosen for the wall construction
and fragmentation screen. A well graded construction aggregate, single size
aggregate or sand is ideal. It is important that the material has a moisture
content compatible with good construction practice (it should not be too wet).
You will require approximately 80m3 of fill.
Site preparation
Wherever possible the site should be firm and level. Further detailed on site
requirements can be found at 03.1.
2
01 PARTS
36 x Swivel brackets
HAB 1 – 1018
37 x Sleeves
HAB 1 – 1023
36 x Short swivels
HAB 1 – 1020
50 x Wood screws
HAB 1 – 1046
Poles:
Yellow 40 x eaves pole1325mm long
HAB 1 – 1004
Green 18 x ridge pole 1583mm long
HAB 1 – 1003
Blue 2 x Cross brace poles 2150mm long
HAB 1 – 1009
Red & Black 12 x truss pole 1400mm long
HAB 1 – 1007
Yellow & Green 14 x truss pole 1200mm long
HAB 1 – 1008
White & Blue 12 x truss pole 1050mm long
HAB 1 – 1006
White 12 x Tent poles (2mm Steel) 1.8m long
HAB 1 – 1010
Steel Tubes:
10 x Internal vertical roof beam
support legs 1795mm long
HAB 1 – 1017
4 x Brace coupler
HAB 1 – 1025
1 x HAB 1 - Vent
HAB 1 – 1047
24 x Ratchet straps
HAB 1 – 1040
Plywood sheets
(narrow approx 16 linear metres)
1 x Roll of Tape
1 x Tool kit
Each joint is formed from 2 angled flitch plates, 2 angled roof beams and 4
nuts and bolts. However, only fit the bolts into the 2 centre holes. The outside
holes should be left open to facilitate a later operation.
See the below diagram for an example of a completed 3 piece roof beam.
Note: The ends are cut at an angle. Keep black colour code on the outside ends of beam assembly.
13
02 PRE-ASSEMBLY
Each joint is formed from 2 straight flitch plates and 4 nuts and bolts.
02.3 Fit the half flitch plate to the end of the beam.
14
03 LAYOUT
14m
7m
15
03 LAYOUT
03.2 Lay out the units in the configuration shown. Check dimensions.
To achieve 8.1m the end wall must be pushed out slightly.
Key
3 cell unit with aperture Securing Clip.
and extra 21” cell Shown in position securing
the top of the fragmentation
3 cell unit and screen support tube to the
extra 21” cell HESCO Unit.
4 cell unit and
extra 21” cell
4 cell unit 1.5m
m
8.1
4.8
m
Fragmentation
Screen Support Tube
Note: The 4 cell unit which houses the aperture for the service duct can be fitted at either
end and on either side.
03.3 Check all the walls are in line. A tape and string line is supplied in the kit.
03.4 Assemble and fit 10 fragmentation screen support tubes and bases,
securing into position using the supplied securing clips.
Each support is made up of:
• 1 x 1670mm fragmentation screen support tube
• 2 x fragmentation screen support tube base plate, one filled
with a coil spring
• 1 x securing clip
• 1 x coil spring
Note: Pin required to make up the 3 cell and extra 21" long cell. 21” cell is loose during transit.
16
04 FILLING
04.1 Place 150mm of fill material in the base of the corner cells.
04.5 Place 300mm of fill in each cell. Ensure fill is placed equally in cells
and that no adjacent cell has more than 300mm of fill than its neighbours.
04.6 Continue to place fill in layers in each cell and once practical the fill
should be compacted by foot. This is most likely to be when the fill has
reached around the half way mark.
04.7 Continue to fill the cells compacting each layer of fill in turn.
04.8 The end walls should be filled to within 100mm of the top of the cells.
The side walls should be filled completely and ideally be left with a
25mm surcharge.
Note: The HAB 1-Vent should be fitted into the preformed aperture in the selected end wall
once the fill material is up to that level. Once fitted the filling can continue. This vent will
allow the fitting of air conditioning and heating ducts into the bunker as and when required.
17
05 ROOF SUPPORT
05.1 Place the narrow plywood boards on top of the side walls.
These are designed to spread the weight of the roof over the
complete wall. The next component (the Anchor Assembly)
will sit on top of these boards.
Plywood sheets
(narrow approx 16 linear metres)
Anchor Assembly
18
06 ROOF BEAM
06.1 Take the first of the pre-assembled three piece angled roof beams
and bolt into place on the outside of the first anchor assembly piece.
Only fit the inner bolt, leave the outer bolt clear for a later operation.
19
06 ROOF BEAM
06.2 Continue to position and bolt in the angled roof beams. Each should be
fitted between two anchor assembly pieces. Continue this operation
until all the beams are fitted.
20
07 ROOF INFILL PANELS
07.1 Fit the roof infill panels, smooth side down. The roof infill panels are
designed to interlock as shown below. It is important that each
section is fitted from one end only, placement of the roof infill panels
from each end of one run may result in the failure to match them up
in the middle leading to the requirement to strip out one side.
Safety: No one must stand on the roof whilst placing the panels as the roof will be unstable
and may shift laterally causing a partial collapse.
21
08 VERTICAL SUPPORTS
08.2 Roughly position two internal vertical supports one at each end of the
inside of bunker. They should be positioned just either side of the doors.
Safety: It is important once all the vertical roof support beams are positioned that they
are checked for verticality and that they are adjusted to ensure that they are all taking
an equal load.
1.5m
Vertical Supports
1.5m
22
08 VERTICAL SUPPORTS
08.3 Lift, position and secure the straight roof beams. Once roughly in position
adjust each end to ensure the beam is sat approx 100mm inside the
join in the angled roof beam. This will ensure that the beams are sitting
approx 1.5m apart.
08.4 Carry out this operation to the other side. Spreaders may be required
under the vertical support if the bunker is built on soft ground.
Internal vertical
support being
positioned under a
4 piece roof beam
Cut away showing vertical
support beams approximately
1.98m apart
23
08 VERTICAL SUPPORTS
Safety: Do not attempt to secure the vertical supports until the roof has been stabilised by
the installation of the HESCO end walls at serial 9.2.
08.6 Drill an 8mm hole into the straight roof beam to secure the vertical
support tube to the roof beam.
08.7 Fit and secure the cross bracing. The cross bracing piece comes in 2
parts, a threaded bar and a sleeve. Remove one nut and bolt from each
straight roof beam joint and on one side, remove its opposite number.
08.8 Slide the threaded bar through the hole on one side.
08.10 Insert the threaded bar through the opposite hole and secure by fixing a
washer and nut on each end.
08.11 Carry out the same procedure until all five bracing pieces have been
fitted and secured.
Note: 2 x Sleeve are fitted with door tarpaulins, these should be fitted at the door ways.
24
09 DOORWAY WALLS
09.1 Fit and secure the 2 cell length (with additional 21" long cell)
of Concertainer unit on top of the existing walls either side of
the doorways. Secure by hog ring.
3 Cell Segment
09.2 Place fill, compacting in layers until the units are full.
25
10 FRAGMENTATION SCREEN CONSTRUCTION
10.1 Fit tape over the open ends of the swivel brackets to prevent fill
material ingress.
Correctly positioned
swivel bracket.
10.2 Fit and secure the Swivel brackets onto the anchor assembly pieces.
The brackets are fitted on the:1st, 4th, 6th, 9th, 11th, and the last
angled roof beam.
Safety: For all work on the roof and predetonation screen, personnel are to stand on the
fragmentation screen and not on the HESCO units.
14th
11th
9th
6th
4th
1st
26
10 FRAGMENTATION SCREEN CONSTRUCTION
10.3 Fit swivel brackets in the centre at the same spacing as used
on the outside.
10.4 Fit M16 nuts and bolts to all remaining empty positions and secure.
27
11 FRAGMENTATION SCREEN FILL
11.1 Place geotextile strips over the roof. The geotextile is placed to prevent
fill material dropping through any small gaps in the roof. It also adds
strength to the fragmentation screen. The geotextile should be wrapped
around the detonation support brackets and then secured by using
the HAB 1 clips.
Note: Placement of geotextile cover over the roof infill panel, wrapping around the swivel
brackets and securing by means of the HAB 1 Clip.
11.2 Place 450mm of fill material on the roof. Fill to the top of the
swivel bracket. Try to leave the edges clear at this time, this
will assist later when the plywood sheets are fitted to the side.
28
12 DETONATION SCREEN
12.1 Remove the tape from the end of the swivel brackets.
12.2 Fit 1050mm long truss poles (white & blue) into the outside swivel brackets.
12.3 Fit 1200mm long truss poles (yellow & green) into the two centre rows
of swivel brackets.
12.4 Fit 1400mm long truss poles (red & black) into the remaining swivel brackets.
(Two outside centre rows).
Truss poles.
29
12 DETONATION SCREEN
12.5 Fit and secure a short swivel coupling to the ends of all truss poles.
Diagram showing the truss poles in position when joined to the ridge poles.
12.6 Fit six 1583mm ridges poles (green) in the position shown above.
30
12 DETONATION SCREEN
12.8 Fit ten 90˚ cross over joints to each side and then 20 in the centre.
12.9 Fit forty 1325mm eaves poles (as shown). Use sleeves to join the
eaves poles together.
31
12 DETONATION SCREEN
12.11 Fit and secure side brace poles. These are designed to prevent the
predetonation screen from racking. The pole should be fitted from top to
bottom on one side and bottom to top on the opposite. Brace coupler
clamps are provided to secure the poles to the truss poles.
Note: The pole goes from top to bottom on one side and
goes from bottom to top on the other. Example of side brace poles
on truss pole.
32
12 DETONATION SCREEN
12.12 Slide 2 pieces of ply across the gable end of the pre-detonation screen.
These sheets fit between the 3 cell segments and the frame. The ply
should slide far enough in so that it does not protrude out the side.
12.13 Fit plywood boards along the sides. Two men should pass the boards
up to one man on the fragmentation screen. The boards should extend
until they overlap the end cells by half of their depth. There will be a
requirement to overlap some of the plywood sheets. Where this is the
case the boards should be secured together by screws or roof ties.
All other boards should be secured to the pre-detonation frame.
Safety: All work should take place from the inside of the frame.
12.14 Pull fill material to the edges of the fragmentation screen ensuring
that there is a uniform 450mm of soil cover over the complete roof.
12.15 Fill and place sand bags along the wall up against the Anchor
Assemblies. Approx 30 sand bags will be required on each side.
33
12 DETONATION SCREEN
12.16 Fit the plywood boards number 1-4 to the roof. The boards should be
secured by drilling through the ply on either side of the supporting
eaves poles and then fixed by using the supplied roof ties.
15 7 1
11 5
13 8 2
14 9 3
12 6
16 10 4
Sandbags
12.17 Once boards 1-4 have been placed and secured the tent roof (tarpaulin)
should be lifted by loading shovel onto boards 2 and 3. The tent roof
should then be unfurled as subsequent boards are placed and secured.
12.18 Place and secure boards 5 and 6 and unfurl the tent roof to the edge.
Continue fitting and securing board and unfurling the tent roof
as you progress.
34
12 DETONATION SCREEN
12.19 Boards 13 and 14 should be fitted and secured. The tent roof should
be unfurled over them and then boards 15 and 16 fitted and secured.
Safety: It is important that the above procedure is followed for the placing and securing of
the plywood sheets and the tent roof. This ensures that no one has to climb onto the roof.
The plywood will only support 65kg/m2
35
13 DOORWAY FRAGMENTATION WALLS
13.2 Fill the end walls in the same manner as the main walls.
Fill until 100mm from the top.
13.3 Fit and secure the small 5 cell units on top. Secure by hog rings.
36
13 DOORWAY FRAGMENTATION WALLS
13.5 Place A1 and A2 crates together for connection, then B1 and B2 also.
Position but do not secure and tighten the two 220mm long bolts and
nuts in the lower holes of the crate then position the four 180mm long
bolts in the side and top holes. Do not tighten.
13.6 Slide the two 2m timber beams into the fork lift recess on the crate,
push fully through from A1 to A2. This may require hammering in.
13.8 Lift each pair of wooden crates A1, A2, B1 and B2 by means of the
loading equipment fitted with fork attachment and place them centrally
over the doorway.
13.9 Place 450mm of fill material in the base of the crates over each doorway.
Pull the tent fabric to the edge of the open box.
Note: The interior of the crate may require lining with geotextile to prevent fill material loss.
13.10 Place two sheets of ply to close the top of the box.
Secure using the supplied screws.
13.11 Pull the remainder of the tent roof over the end of the bunker.
13.12 Fit the 4 steel tubes with outer doorway tarpaulin against the base
of the wooden crate. Secure by cable tie and or sandbags.
37
14 WATERPROOF COVERING
14.1 Slide the tent poles into the sleeve of the tent cover.
Place 2 at each end and 5 on each side.
Tent pole
14. 2 Identify the securing positions, mark the tent cover fabric and then cut
to expose the tent poles. Thread the ratchet strap webbing through the
welded mesh and then over the tent pole.
Example of
ratchet strap
Marking and then cutting the tent cover to gain access to the tent poles
for the ratchet strap.
38
14 WATERPROOF COVERING
14.3 Once all the ratchet straps are fitted they should be tightened securely.
14.4 Secure the tent roof over the crates by screws into the crate.
39
15 MAINTENANCE
15.1 As discussed earlier the plywood will only sustain a load of 65kg/m2,
therefore, when snow accumulates it should be cleared when it reaches
a depth of 150mm. Information stickers have been affixed to the internal
longitudinal beams to ensure that future occupants are aware of this fact.
15.2 The following action must be carried out if the bunker suffers either a
direct hit or near miss
• All predetonation and fragmentation screen nuts and bolts and grub
screws must be checked for tightness. Information stickers have been
affixed to the internal longitudinal beams to ensure that future
occupants are aware of this.
• Ratchet straps should be checked for security. The welded mesh can be
damaged by the ratchet strap due to the bounce effect that the blast causes.
Where this is the case the strap should be moved to an undamaged
portion of welded mesh.
• The ten vertical support tubes supporting the long roof beams should
be checked for damage and replaced if required. If removal and
replacement is required the roof beam should be propped on either side
of the tube to be replaced before it is removed.
15.4 If the bunker is to be in place for some time (in excess of 2 years)
particularly in a harsh UV environment, then additional protection for
the geotextile in the HESCO units may be required. Additional protection
can be provided by shading of the structure from the sun, application of
UV CAM™ or cement slurry.
40
16 REPAIR PROCEDURES
Figure 4 Figure 5
41
16 REPAIR PROCEDURES
Note: It may be necessary to fit additional coils to increase the length of the repair panel
to enable the coils to be overlapped and a joining pin fitted.
Figure 4 Figure 5
42
16 REPAIR PROCEDURES
• Support frame
• Plywood sheets
• Waterproof tarpaulin secured by steel poles and ratchet straps
16.7 Access to the roof space should be gained. All roof joints and couplings
should be checked for serviceability and tightness. Poles should be
replaced where required.
43
16 REPAIR PROCEDURES
Safety: The plywood used as the predetonation screen only has a load limit of 65kg per m².
If you are to walk on or put weight on the existing sheets then additional sheets should be
placed to act as crawling boards.
44
16 REPAIR PROCEDURES
• Using the ropes pull the tent cover over the roof until it hangs down
the same distance as the originally placed cover
• Slide the tent poles into the sleeve of the cover
45
17 DISMANTLING INSTRUCTIONS
As with all construction tasks there are some inherent risks regarding
Health and Safety. Task Commanders must ensure that all relevant and
practical Health and Safety precautions are taken.
46
17 DISMANTLING INSTRUCTIONS
All of the HAB 1 material when stripped out in a methodical manner can
be reused. As material is removed and stored a note should be taken of these
items which cannot be used again. Replacement items can be sourced from
HESCO Bastion Ltd.
17.1 Prelims:
• Ensure the HAB 1 is emptied of all equipment and material.
• Turn off, disconnect and remove all electrical supplies and
any other services installed.
47
17 DISMANTLING INSTRUCTIONS
• Pull the waterproof tent cover free from the wooden crate covering
the doorways.
• Pull the waterproof tent cover from the roof and roll up for future use.
Note: The wooden crate with sand fill weighs approx 2.9 tonnes. Some material may have
to be unloaded prior to removing the crate from above the doorway.
48
17 DISMANTLING INSTRUCTIONS
Safety: On removal, plywood should be lowered to the floor and not thrown. It is important
when removing the roof plywood that the persons stand on the fill material and do not walk
on the plywood.
49
17 DISMANTLING INSTRUCTIONS
Eaves pole
Truss poles
Safety: All poles should be lowered to the ground and not thrown.
Swivel bracket.
50
17 DISMANTLING INSTRUCTIONS
• Slacken off and remove the nut and bolt securing the roof beam
support to the roof beam.
• Slacken off and remove the six central vertical support poles.
51
17 DISMANTLING INSTRUCTIONS
• Two persons support one roof support beam while two others
remove the vertical supports.
• Repeat this procedure for the other beam.
• Disassemble beam.
52
17 DISMANTLING INSTRUCTIONS
53
17 DISMANTLING INSTRUCTIONS
• Remove bolts securing the roof beams to the Anchor Assembly pieces.
• Remove each roof beam as it becomes free.
• Disassemble each roof beam.
• Remove the anchor beam assemblies
• Remove small section of plywood from the top of the side walls.
Note: Check all components are cleared from the HAB 1 and stowed in the two crates prior to
proceeding further.
54
17 DISMANTLING INSTRUCTIONS
• The cell being remove is still attached to the unit at one corner;
this will act as a hinge, allowing the cell panels to be turned away
from the released fill material.
• Bulldoze the released fill material away from the wall. Continue this
process until the wall has been completely removed.
• Remove the concertainer unit cell material, and clean, inspect and
repair any damaged panels as required. Reassemble and re-palletise
the units ready for transportation or storage.
55
17 DISMANTLING INSTRUCTIONS
Pin to be removed
Note: It is important the area around the cell to be split is free from even the smallest obstruction.
This allows the cell to be opened freely.
17.11 Tidy and clear site of all equipment, fill material and debris.
56
COMPLETED HAB 1
Completed HAB 1
57
COMPLETED HAB 1
Completed HAB 1
Note: Above pictures shows the generation 1 round HAB poles which are now square for
increased strength.
58
HESCO Bastion Ltd
41 Knowsthorpe Way
Cross Green Ind. Est.
Leeds LS9 0SW
United Kingdom
Disclaimer
The information contained in this publication is provided by HESCO Bastion Ltd
('HESCO') or is derived from sources that HESCO reasonably believes to be reliable
and accurate or are otherwise expressions of independent third party opinion.
Whilst HESCO has made reasonable efforts to ensure the accuracy, completeness
and relevance of such information, any reliance on it, in whole or in part, is entirely
at the risk of the party using it and it will not rely on such information in substitution
for making all proper and necessary enquiries from HESCO or other relevant third
parties. The selection, configuration and installation of any of HESCO’s products on
site is not HESCO’s responsibility and, HESCO, its directors, employees, agents,
distributors, suppliers or contractors shall not be liable for any failure of any of
HESCO’s products caused by improper installation.
At the sole and absolute discretion of HESCO, the contents of this publication are
subject to change at any time without notice.
Copyright Notice
Certain material featured in this document is subject to copyright protection.
Any lawful reproduction of such material is subject to obtaining prior written
permission from HESCO Bastion Ltd. Any requests for such permission should be
made in writing.
Patents
HAB 1 is covered by patent nos. 2145064, 1992768 (UK) and 7856761 (US); and is subject to
application nos. 0803661.8 (UK) and 12/595,436 (US) and other international equivalents.
Trade Marks
HESCO, Concertainer and HAB are registered® trade marks of HESCO Bastion Ltd.
Quality Standards
HESCO Bastion Ltd manufactures to quality standards ISO 9001 (1987),
BS 5750 Part 1 (1987) and EN 29001 (1987) certificate no. 910654.
08.07.11