Вы находитесь на странице: 1из 7

IEEE papers may be distributed within the authors' companies without violating the IEEE copyright.

External distribution is a violation of the


IEEE copyright agreement. There are some additional author privileges; refer to the copyright agreements for clarification where necessary.
IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS 1

Substation Grounding Transfer of


Potential Case Studies
Duane Leschert, Senior Member, IEEE, George Iwasykiw, Member, IEEE, and Ron Derworiz, Member, IEEE

Abstract—Industrial substation grounding studies usually as- IEEE 80 refers to the highest calculated GPR for a given
sume a simple isolated substation, follow the routine IEEE 80 case. When multiple potentials at different locations within the
design and analysis procedures using the software tools bundled calculation area are discussed, they should be referred to as
with the power systems analysis suite of choice, and carry on
with the rest of the project. However, there can be complications surface potentials, but often, the term GPR is used for these
to substation grounding designs. This paper discusses two case surface potentials.
studies where a ground fault in one substation generates a voltage A person standing on the surface of the substation is exposed
that is transferred to other areas. The issues are assessed using to a voltage potential between his feet (step potential Es ) due to
common software tools supplemented with simple spreadsheet the difference in surface potentials at each foot. The permissible
calculations. Some common limitations of the standard software
tools, when applied to these more complex problems, are discussed step potential is a function of body withstand capabilities, body
in this paper, along with appropriate workarounds. Mitigation resistance, and the resistance of any special insulating material
methods are discussed. on the surface of the substation. Similarly, the touch potential
Index Terms—Current split, ground potential rise (GPR), Et is calculated for a person standing in the substation area
grounding, split factor, step and touch potential, substation and touching a metallic object bonded to the ground system.
grounding, transfer of potential. Ultimately, the tolerable step and touch potentials are deter-
mined by the tolerable resultant current through a person’s body
(10 mA). Hence, in dealing with unacceptable calculated volt-
I. I NTRODUCTION
ages, the most readily modified parameter is usually the resis-

T HE grounding system of industrial substations is typically


designed in accordance with IEEE 80, the IEEE Guide for
Safety in AC Substation Grounding [1], supplemented by IEEE
tivity of the insulating layer on the surface of the substation.
(For details of these calculations, refer to [1].)
These parameters (GPR, Es , Et ) are calculated by readily
142 (“The Green Book”) [2]. available software for a number of points (e.g., 1 m apart)
IEEE 80 is focused on personnel and equipment safety when within the substation boundaries and assessed against the
electric currents are flowing into the earth. It considers power tolerable limits for that system.
system frequency (50–60 Hz) events. Although fault currents The main focus of IEEE 80 is the safety of a single substation
do decay, conventional ground system analysis assumes that as an independent entity. There are references in IEEE 80 to
the initial (subtransient) fault current is maintained at that same interconnection issues (e.g., see Fig. 1), which are sometimes
high level for the duration of the fault under consideration. overlooked in the design of industrial substations. A standard
A ground fault current is considered to flow through the requirement in IEEE 80 is to address any instances of transfer
bonding and grounding conductors, through the grounding of potential outside of the substation. This paper discusses
electrodes, through the earth in the vicinity of the substation, to this issue of transfer of potential from the perspective of the
“remote earth.” IEEE 80 provides a methodology to calculate petrochemical industry.
the effective resistance Rg of the grounding system to remote In an IEEE 80 grounding analysis, there are a number of
earth. The fault current flowing through this system results in assumptions that are appropriate for a single isolated sub-
a ground potential rise (GPR) of the substation with respect station, but are not always appropriate when assessing mul-
to remote earth. Strictly speaking, the term GPR as used in tiple interconnected grounding systems. For example, in an
isolated substation, the dimensions are small enough that the
error in ignoring the resistance of the horizontal conductors
is insignificant. However, this is often incorrect when con-
Manuscript received June 19, 2013; accepted October 1, 2013. Paper sidering interconnected substations at large complexes, which
2013-PCIC-488, presented at the 2013 IEEE Petroleum and Chemical Industry
Technical Conference, Chicago, IL, USA, September 23–25, and approved may involve distances on the order of a few kilometers. In
for publication in the IEEE T RANSACTIONS ON I NDUSTRY A PPLICATIONS an isolated substation, typically, there is only one uniform
by the Petroleum and Chemical Industry Committee of the IEEE Industry surface treatment (e.g., a layer of washed crushed rock 150 mm
Applications Society.
D. Leschertand G. Iwasykiw arewith WorleyParsons, Edmonton, AB T6E 5S2, deep). This surface treatment may extend some small distance
Canada (e-mail: Duane.Leschert@WorleyParsons.com; George.Iwasykiw@ outside the substation limits, but rarely extends over the entire
WorleyParsons.com). surface of the larger facility. These assumptions are generally
R. Derworiz is with Shell Canada Energy, Fort Saskatchewan, AB T8L 3T2,
Canada (e-mail: rderworiz@ieee.org). incorporated into software tools often used for industrial sub-
Digital Object Identifier 10.1109/TIA.2015.2463793 station design. While there are specialized software packages
0093-9994 © 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
2 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS

Fig. 1. IEEE 80-2000 figure 13.

available, which eliminate these and many other limitations, it


is not necessary to resort to these specialized tools for many
industrial applications, as long as some simple adjustments
are used. For some more complex grounding situations, the
specialized (and substantially more expensive) software tools
are needed.

II. C ASE S TUDY 1: I NTERCONNECTED S UBSTATIONS


A. Description of the Facility Fig. 2. Simplified one-line diagram.

This application is at a large oil refining complex. Power is


supplied to the refinery from a utility owned 138-/25-kV sub- (ground mesh). The new substation equipment is in a shop-
station. This utility substation contains two 138-/25-kV trans- fabricated steel building installed on driven steel piles; addi-
formers, some 138-kV breakers, and associated equipment. tional ground rods and conductors are installed as necessary.
There are two incoming 138-kV circuits and two outgoing Each substation has a surface treatment adequate for the needs
138-kV circuits. The outgoing circuits are interconnected to of that substation; there are multiple surfaces encountered
other portions of the refinery complex. between the existing substations and the new substation.
Adjacent to the utility substation is the refinery 25-kV power
distribution switchgear, complete with its own grounding sys-
B. Challenges in Analysis
tem, which is effectively interconnected with the utility ground-
ing system, since the two systems are adjacent to each other. The available fault current at the new (remote) substation
A new 25-kV distribution substation is subfed from the main is 400 A; this would result from a single-line-to-ground fault
distribution substation by armored cable over 1 km in length. in the new substation. As the two supply transformers can
The two grounding systems are effectively interconnected both only be paralleled for a fraction of a second due to automatic
by grounding conductors internal to the power cables and tripping of one of the main breakers in this situation, an 800-A
by external insulated interconnecting grounding conductors. A single-line-to-ground fault could only exist for the short time
simplified power single line diagram is shown in Fig. 2. it takes to automatically trip one breaker. Even this rare 800-A
The 138-/25-kV transformers are delta/wye connected with fault is not difficult to manage with a very simple grounding
neutral grounding resistors of 400 A each. The 138-kV system design. However, a ground fault on the 138-kV portion of
is solidly grounded at its source, which is another utility substa- the utility substation can result in a GPR of 2532 V at the
tion a few kilometers away, and is interconnected by overhead utility substation. This voltage will be transferred to the new
lines. The entire 25-kV distribution system is arranged as a remote substation by the interconnecting bonding conductors
secondary selective system with all tie breakers normally open. described earlier and is limited only by the impedances of
The existing facility utilizes traditional ground rods and these interconnecting conductors and the associated grounding
a buried horizontal grid of interconnected bare conductors systems.
LESCHERT et al.: SUBSTATION GROUNDING TRANSFER OF POTENTIAL CASE STUDIES 3

at a remote substation in its zone 2 or 3 region; hence, a 1-s


fault duration was assumed.
A two-layer soil model is used. This area is subject to frost
depths of up to 3 m in winter. The resistivity of frozen soil
is taken as ten times that of unfrozen soil. Both summer and
winter soil conditions are modeled, but the winter condition
with a top layer of frozen soil yields the worst case grounding
analysis results.
The initial analysis found this substation design to be unac-
ceptable. To manage the high GPR calculated for any significant
Fig. 3. Ground fault current sharing. amount of current shared with the existing substation, with
high touch and step voltages, an extensive copper mesh with
many additional ground rods plus a surface layer of nominal
The utility substation has an effective resistance to remote 50-mm washed crushed granite would be required. Based on
earth (Rg ) of 0.09 Ω and a potential ground fault current of this information, an in situ earth resistivity test was performed.
25 000 A (IF and Rg1 in Fig. 3). The bonding conductors This resulted in a much more manageable soil resistivity of
in each of the two cables feeding the new substation have a 28 Ω · m for unfrozen soil, which emphasizes the importance
resistance of 1.213 Ω. The interconnecting ground conductors of accurate soil resistivity data for any grounding system study,
have a resistance of 0.381 Ω; thus, the effective resistance of as clearly stated in IEEE 80.
these three parallel paths to the new substation is 0.234 Ω (R12 It was also determined that the utility protection scheme
in Fig. 3). included differential protection on all 138-kV feeders, with in-
In general, mutual coupling through the earth between sub- stantaneous tripping. Thus, the fault duration could be reduced
stations should be considered. For case study 1, where the sub- to a minimal relay operating time plus the breaker operating
stations are separated by over a kilometer, mutual coupling is time.
clearly not significant. However, for smaller separations, it may When the new substation grounding grid was analyzed with
become an issue. A quick assessment of the need to consider these more realistic values, its equivalent resistance to remote
mutual coupling can be made by examining the earth potential earth was calculated to be 0.35 Ω in the winter and 0.23 Ω in
plots of each substation. The distance from the substation at the summer.
which the earth potential is reduced to a nominal low value The interconnected ground system is represented in simpli-
is taken to define the region within which any object may be fied form in Fig. 3.
affected by the earth potential due to a fault at that substation. The resistance to remote earth of each substation (Rg1 , Rg2 )
Where fault currents can be connected to earth at each substa- is considered to be independent. If the substations were close to
tion, a reasonable assessment can be made by superimposing each other, there would be a mutual coupling effect to consider.
the earth potential plots of the two substations, assuming each is With two substations separated by over a kilometer, mutual
an isolated substation. Areas where the resultant earth potential coupling for the case studied is negligible. The fault current
is higher than the criteria voltage will need further investigation. IF at the utility substation (Substation A in Fig. 3) is shared by
The limiting voltage from mining code CSA M421-2011 [6] is the two ground systems in proportion to the ratio of resistances,
100 V and is a reasonable criteria voltage in the absence of other as shown in the network in Fig. 3. The ratio of fault current
guidance. through each grounding system is called the split factor.
The new substation building is constructed on driven bare The calculated ground network currents, for the ultimate
steel piles with a minimum length of 15 m. Interconnections 138-kV fault of 25 kA in winter conditions, are 21.7 kA in
between these piles are by the large structural steel building the 138-kV network and 3.34 kA in the new 25-kV substation
members. Relevant steel connections are welded. There is a network. This is substantially above the 400- or 800-A ground
minimal bare copper grid in the substation yard, interconnect- fault current available due to a local 25-kV fault in the new
ing the building with a loop around an outdoor transformer substation and must be accommodated by the design of the new
and the fence. There is a loop of bare copper 1 m (measured grounding network.
horizontally) outside the fence. The fence and transformer Ground surface potentials are plotted in Fig. 4 for the worst
loops have conventional ground rods at key locations. case condition. The resulting worst case GPR at the new substa-
The geotechnical report for the new substation area indicates tion due to this fault current is 1178 V. The nominal resistivity
that the soil is Unified Soil Classification System (USCS) types of the surface material is 200 Ω · m. This results in no step
SM and SC. Type SM is a silty sand, and type SC is a clayey potential issues. However, in some areas, there could be a touch
sand. IEEE 142-2007 lists typical soil resistivities for some potential issue, if there were anything installed in that portion
USCS soil types in Table 4.2. Typical soil resistivities for type of the yard. (Worst case touch potentials are plotted in Fig. 5.)
SM range from 100 to 500 Ω · m, and for type SC, they range There are locations of high touch potential located more than a
from 50 to 200 Ω · m. meter outside the fence, which are acceptable as this is greater
Initially, the ground fault protection on the 138-kV utility than a person’s unaided touch distance. There are also some
feeders was unknown; thus, it was assumed that a ground fault locations of high touch potential in some open areas of the yard,
at the utility substation would be interrupted by a distance relay where there is nothing installed. If desired, these touch potential
4 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS

Fig. 4. Case study 1, worst case earth potential plot.

Fig. 5. Case study 1, worst case touch potential plot.

issues can be resolved with a better surface material (nominal III. C ASE S TUDY 2: I NTERCONNECTED P ROCESS P LANT
resistivity of at least 1000 Ω · m).
A. Description of the Facility
Worst case calculation results are summarized in Table I.
These worst case results required the worst case future 138-kV This application involves new pipeline pumping stations
ground fault. Present fault levels did not result in unacceptable installed as part of a pipeline extension project. Each pumping
touch or step voltages anywhere inside the new substation. station includes a utility substation with a delta/wye connected
LESCHERT et al.: SUBSTATION GROUNDING TRANSFER OF POTENTIAL CASE STUDIES 5

TABLE I TABLE III


C ASE S TUDY 1 C ALCULATION R ESULTS C ASE S TUDY 2 C ALCULATION R ESULTS

TABLE II
Another software limitation, which is not a problem for the
K EY M ODELING D ATA : C ASE S TUDY 2 case analyzed, is that the software is only able to accommodate
one surface treatment (resistivity, depth). As there is gravel over
the entire surface of the process plant, this is not a problem.
However, in many process facilities, the surface treatment can-
not be treated as uniform. In such a situation (which is encoun-
tered when assessing the step and touch potentials outside the
fenced graveled area of the pipeline pumping station studied),
transformer, typically 115 kV, solidly grounded to 6.9-kV re- the software used will correctly calculate GPR and surface
sistance grounded, a small number of 6.9-kV pipeline pumps, potentials. One approach is to perform multiple iterations of the
and associated equipment and support buildings. The entire calculation, using each of the surface materials involved in one
facility is installed on bare driven steel piles 55 ft long and of the iterations, and then manually combine the resulting step
interconnected with insulated 4/0 copper conductors. The utility and touch potential results. Another approach is to manually
substation has a traditional buried bare copper grounding mesh. calculate step and touch potentials based on the calculated sur-
The utility substation surface material is 6 in of crushed rock. face potentials, although this can involve a significant effort for
The pumping station is covered with 6 in of gravel, of a lesser many applications. If neither of these approaches is acceptable,
specification. then the specialized software will be required.
There are ground interconnections between the utility substa-
tion and the pumping facility, both intentional (ground conduc-
tors) and less obvious (metal cable tray carrying 6.9-kV cables C. Calculation Results
from the substation to the electrical buildings). Thus, a fault in The calculation results are summarized in Table III.
the utility substation will result in a transfer of potential to the GPR and touch potentials are shown graphically in
process facility and needs to be investigated to ensure worker Figs. 6 and 7, respectively.
safety. It is noteworthy that the calculated touch potentials at places
Several typical pumping stations were modeled. The station approached, but did not exceed, the allowable potential. This
with the highest GPR is presented in this paper. is attributed to the insulating qualities of the surface material.
The utility substation and process plant grounding systems Thus, it is concluded that transfer of potential from the sub-
are adjacent to each other and were modeled as one integrated station, while real, does not pose a problem for this facility.
grounding system. Key modeling data are shown in Table II. Had these calculated touch potentials not been acceptable, our
options to improve our calculations and minimize the effect
of overly conservative assumptions would have been to calcu-
B. Challenges in Analysis
late each grounding grid (utility and process plant) separately,
With the utility and process plant grounding grids adjacent attempt an assessment of mutual coupling, and combine the
to each other, there is a mutual coupling effect. Modeling the results as for the new substation in case study 1 earlier, or to
grids as a single entity is an attempt to include these mutual resort to specialized modeling software.
effects. The software used performs a finite-element analysis of
the grounding system modeled and does appear to include these
IV. C ONCLUSION
mutual coupling effects for the model we created. One caution
is that this software (and apparently other similar software from It is important to clearly understand the assumptions and
many sources) assumes that the entire fault current can be limitations of each of the software tools employed in perform-
injected into the grounding grid at any given location. This is a ing a grounding analysis. It is equally important to ensure that
valid assumption for a substation design, but is excessive for the the system analyzed be modeled in such a manner that the
model we created where the process facility and the substation desired analysis can be completed adequately. Some software
are modeled together. There are provisions in the software to tool limitations can be resolved using supplementary tools.
model unconnected elements, such as a fence or a buried pipe, Transfer of potential out of a substation grounding system
which are not bonded to the ground grid, but interconnections can be a significant safety risk, even when the secondaries
between two grids, such as to only inject the maximum fault of all transformers in that substation are resistance grounded.
current into one grid, are not easily modeled. We were able There are practical analytical tools available to assess the risk
to work around this limitation, but there are some applications involved, and there are limitations to the common software
where this could become a serious limitation, forcing the use of tools usually used for grounding system analysis, which must
specialized (and significantly more expensive) software. be considered.
6 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS

Fig. 6. Case study 2, earth potential plot.

Fig. 7. Case study 2, touch potential plot.

When the supply substation is sufficiently remote from the to remote earth, may be sufficient. This is illustrated in case
affected facility such that mutual earth coupling between the study 1. Each grounding grid can be studied as an independent
grounding systems is negligible, a simple network of resistive grid using available software, and the results combined as
elements, considering each grounding grid as a single resistance illustrated.
LESCHERT et al.: SUBSTATION GROUNDING TRANSFER OF POTENTIAL CASE STUDIES 7

When mutual coupling effects are not negligible, it may Duane Leschert (S’72–A’78–M’05–SM’09) re-
be possible to model the two ground grids as a single entity. ceived the Bachelor of Applied Science degree in
electrical engineering from The University of British
However, the inherent assumptions of the utilized software Columbia, Vancouver, BC, Canada, in 1975.
must be dealt with. In our software, these limitations included He is currently the Chief Electrical Engineer
a single surface treatment capability and the assumption that for power systems with WorleyParsons, Edmonton,
AB, Canada.
one fault current is injected anywhere in the grid. These are
discussed in case study 2.
The software limitation of capability to allow only one
surface treatment, where multiple surfaces must be analyzed
in different portions of the grid, can be managed by multiple
analysis runs and manual combination of the results. Where the
injection of excessive fault current into the process plant grid is George Iwasykiw (M’12) received the B.Eng.
degree from Lakehead University, Thunder Bay,
causing analysis difficulties, it may become necessary to model ON, Canada, in 1991.
the grids separately and independently assess mutual coupling He is currently a Senior Electrical Engineer with
effects. In some situations, it will become necessary to resort to WorleyParsons, Edmonton, AB, Canada.
specialized software tools.

R EFERENCES
[1] IEEE Guide for Safety in AC Substation Grounding, IEEE 80-2000,
2000.
[2] IEEE Recommended Practice for Grounding of industrial and Commercial
Power Systems (IEEE Green Book), IEEE 142-2007, 2007.
[3] IEEE Recommended Practice for Determining the Electric Power
Station Ground Potential Rise and Induced Voltage from a Power Fault, Ron Derworiz (S’92–M’93–SM’12) received the
IEEE 367-1996, 1996. B.Sc. degree in electrical engineering from the Uni-
[4] J. E. T. Villas, D. Mudhedhar, V. R. Fernandes, and A. C. Magalhaes, versity of Alberta, Edmonton, AB, Canada, in 1992.
“Ground grid design of a transition station system—A typical example He is currently the upgrader facility Electrical
of fault transfer,” IEEE Trans. Power Del., vol. 5, no. 1, pp. 124–129, Engineering Manager with Shell Canada Energy,
Fort Saskatchewan, AB. He has authored three IEEE
Jan. 1990.
[5] N. Nichols and D. D. Shipp, “Designing to avoid hazardous transferred papers.
Earth potentials,” IEEE Trans. Ind. Appl., vol IA-18, no 4, pp. 340–347,
Jul./Aug. 1982.
[6] Use of Electricity in Mines, CSA M421-2011, 2011.

Вам также может понравиться