Вы находитесь на странице: 1из 8

SERVICE CONNECTION EXPENSES

MAINLINE CONNECTION/S

A. MATERIALS:
QTY ITEMS PRICE TOTAL

1 pc Ball Valve 1/2" @ 338.68 P 338.68


2 pcs Plastic Adaptor 1/2" @ 27.60 55.20
2 pcs Plastic Elbow 1/2" @ 33.61 67.22
1 pc Plastic Street Elbow 1/2" @ 38.33 38.33
1 pc Plastic Elbow Reducer 3/4" x 1/2" @ 43.70 43.70
2 pcs Plastic Nipple 1/2" x 12" @ 64.27 128.54
3 mtrs P.E. Tubing 1/2" @ 14.95 44.85
3 pcs Thread Sealant (Teflon Tape) @ 12.65 37.95
1 pc Water Meter 1/2" @ 550.85 550.85
1 pc ***Saddle Clamp 3 x 1/2" @ 227.31 227.31
SUBTOTAL 1,532.63

B. LABOR

SRWD Plumber (2 person)


1 day @ 627.94 627.94

Computation
Plumber 1 @ 809.91 per day 809.91
Plumber 2 @ 1,073.91 per day 1073.91
1883.82
3 Connection/s per day ÷ 3.00
627.94
Excavation & Backfill
1 connection @ 130.00 130.00
SUBTOTAL 757.94

TOTAL (MC + LC) 2,290.57


10%, OCM 229.06
TOTAL COST P 2,519.63

SAY P 2,500.00

Note:
*** Size of Saddle Clamp if for computation purpose/s.
SERVICE CONNECTION EXPENSES

TRAVERSE CONNECTION/S

A. MATERIALS:
QTY ITEMS PRICE TOTAL

1 pc Ball Valve 1/2" @ 338.68 P 338.68


2 pcs Plastic Adaptor 1/2" @ 27.60 55.20
2 pcs Plastic Elbow 1/2" @ 33.61 67.22
1 pc Plastic Street Elbow 1/2" @ 38.33 38.33
1 pc Plastic Elbow Reducer 3/4" x 1/2" @ 43.70 43.70
2 pcs Plastic Nipple 1/2" x 12" @ 64.27 128.54
8 mtrs P.E. Tubing 1/2" @ 14.95 119.60
3 pcs Thread Sealant (Teflon Tape) @ 12.65 37.95
1 pc Water Meter 1/2" @ 550.85 550.85
1 pc ***Saddle Clamp 3 x 1/2" @ 227.31 227.31
SUBTOTAL 1,607.38

B. LABOR

SRWD Plmber (2 person)


1 day @ 627.94 627.94

Computation
Plumber 1 @ 809.91 per day 809.91
Plumber 2 @ 1,073.91 per day 1073.91
1883.82
3 Connection/s per day ÷ 3.00
627.94
Excavation Backfill
1 connection @ 130.00 130.00
SUBTOTAL 757.94

TOTAL (MC + LC) 2,365.32


10%, OCM 236.53
TOTAL COST P 2,601.85

SAY P 2,600.00

Note:
*** Size of Saddle Clamp if for computation purpose/s.
Timeframe of activity/ies

Nature of Activity Duration of Activity Remarks

Application for New Service Connection


Mainline 10 days upon receipt of application
Traverse 10 days upon receipt of application

Leak / Repair
Mainline Immediately upon receipt of M.O.
PET / Service Connection
Urgent Immediately upon receipt of M.O.
Non-urgent 2 days upon receipt of M.O.
Ball Valve upon receipt of M.O.
Urgent Immediately upon receipt of M.O.
Non-urgent 2 days upon receipt of M.O.
Stand Pipe Immediately upon receipt of M.O.
Tailpiece Immediately upon receipt of M.O.
Meter Lifting 3 days upon receipt of M.O.
Meter Alignment 3 days upon receipt of M.O.
Blow-of Immediately upon receipt of M.O.

Inspection/Investigation
High Consumption 5 days upon receipt of M.O.
Fast/Continuous rotation of meter Immediately upon receipt of M.O.
Strong Air Pressure Immediately upon receipt of M.O.
No Water Immediately upon receipt of M.O.
Odorous/dirty/rusty water Immediately upon receipt of M.O.

Other Request/Complaints
Flushing Immediately upon receipt of M.O.
Meter accuracy Checking upon receipt of M.O.
result of calibration 2 days upon receipt of M.O.
replacement of meter 3 days upon receipt of M.O.
Installation of blow-of 5 days upon receipt of M.O.
Pull-out of Meter 2 days upon receipt of M.O.
Meter Relocation 5 days upon receipt of M.O.
List of Contractor

For Extension of Pipelines

1. Eirish
2. Rommel Abrigo

For Excavation of New Service Connection

1. Rommel Abrigo
SERVICE CONNECTION EXPENSES

TRAVERSE CONNECTION/S

A. MATERIALS:
QTY ITEMS

1 pc Ball Valve 1/2"


2 pcs Plastic Adaptor 1/2"
2 pcs Plastic Elbow 1/2"
1 pc Plastic Street Elbow 1/2"
1 pc Plastic Elbow Reducer 3/4" x 1/2"
2 pcs Plastic Nipple 1/2" x 12"
8 mtrs P.E. Tubing 1/2"
3 pcs Thread Sealant (Teflon Tape)
P 2,500.00
1 pc Water Meter 1/2"
1 pc Saddle Clamp 3 x 1/2"

B. LABOR

1. Excavation
2. Tapping
3. Backfill

Prepared by:

Edgardo V. Torres
Senior Project Planning & Dev't. Of.
Prepared by: Checked by: Noted by:

Engr. Reymond N. Igaya Engr. Juanita I. Inductivo Engr. Numeriano M. Castañeda Jr.
Engineer A Production Head General Manager
Castañeda Jr.

Вам также может понравиться