Вы находитесь на странице: 1из 2

TESTING COMMISIONING REPORT

HEAT EXHANGER
Project _______________________
FM/IK/ODR/MEP-011-15 Rev: 0 Halaman 1 dari 1

Location : _______________________________ Equipment No. : _____________________________


Level : _______________________________ Service : _____________________________
Test Date : _______________________________ Drawing Ref. : _____________________________
Report Date : _______________________________

Heat Exchanger Data :


Manufacture : ________________________ Heat Water
Type : ________________________ - Ent. Temp : ________________________
Capacity : ________________________ - Lvg. Temp : ________________________
Cold Water Pressure Drop
- Ent. Temp : ________________________ - Cold : ________________________
- Lvg. Temp : ________________________ - Heat : ________________________

Test Result :

Unit Cleaning : Yes No

Bolt & Nut Tightening : Yes No

Cooling :

- Cold - Ent. Temp : ______________________ ° C


- Lvg. Temp ______________________ ° C
- Press Drop : ______________________ Bar

- Heat - Ent. Temp : ______________________ ° C


- Lvg. Temp : ______________________ ° C
- Press Drop : ______________________ Bar

Temp. Control System : Yes No

Pressure Control System : Yes No

Test Result Equipment Test Comments

Approved

Not Approved

Re- Tested

Approved by, Checked by, Tested by,

_________________________ _________________________ _________________________

1 of 2
2 of 2