M/s Shapoorji Pallonji Real Estate M/s Shapoorji Pallonji Engineering & Construction

JOY VILLE TOWER 6


Name of Work : ELECTRICAL WORKS
PROJECT

Location : Joy Ville - Virar West.


7th FLOOR
Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.
Site Conditions:
SITE

Normal Day Rainy Day


Qty
WORK ACTIVITY
LOCATION UOM
PROGRESS DESCRIPTION T C B
Back Box Fixing Nos. 14 14 0
Vertical Conduiting Nos. 25 25 0
1 2 BHK ( L) Apt -1
Slab Conduiting Pts 28 0 28
Rope Pulling 5th FLOOR Pts 28 0 28
Back Box Fixing Nos. 12 12 0
Vertical Conduiting Nos. 22 22 0
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 0 26
Rope Pulling 5th FLOOR Pts 26 0 26
Back Box Fixing Nos. 12 12 0
Vertical Conduiting Nos. 22 22 0
3 2 BHK ( S) Apt -3
Slab Conduiting Pts 26 26 0
Rope Pulling 5th FLOOR Pts 26 0 26
Back Box Fixing Nos. 14 14 0
Vertical Conduiting Nos. 25 25 0
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 28 0
Rope Pulling 5th FLOOR Pts 28 0 28
Back Box Fixing Nos. 14 14 0
Vertical Conduiting Nos. 25 25 0
5 2 BHK ( L) Apt -5
Slab Conduiting Pts 28 28 0
Rope Pulling 5th FLOOR Pts 28 0 28
Back Box Fixing Nos. 12 12 0
Vertical Conduiting Nos. 22 22 0
6 2 BHK ( S) Apt -6
Slab Conduiting Pts 26 26 0
Rope Pulling 5th FLOOR Pts 26 0 26
Back Box Fixing Nos. 12 12 0
Vertical Conduiting Nos. 22 22 0
7 2 BHK ( S) Apt -7
Slab Conduiting Pts 26 26 0
Rope Pulling 5th FLOOR Pts 26 0 26
Back Box Fixing Nos. 14 14 0

8 2 BHK ( L) Apt -8
Vertical Conduiting Nos. 25 25 0
8 2 BHK ( L) Apt -8
Slab Conduiting Pts 28 0 28
Rope Pulling 5th FLOOR Pts 28 0 28
DESCRIPTION Unit Received Consumed
1 25 mm Black Conduit Mtr 6900 4115
2 25 mm Grey Conduit Mtr 900 0
3 20 mm Black Conduit Mtr 10800 7560
4 20 mm Grey Conduit Mtr 4500 2324
5 32 mm Black Conduit Mtr 2000 1406
6 2 M GI BACK BOX Nos 500 330
7 3 M GI BACK BOX Nos 250 128
8 4 M GI BACK BOX Nos 70 24
9 6M GI BACK BOX Nos 150 140
10 8M GI BACK BOX Nos 170 116
11 12 M GI Back BOX Nos 30 0

Note : - Site Related Issue to be written with justifications for Prepared by:
improvements w.r.t Agency.
CONSTRAINTS

Miss.Priyanka

___________________

Date:
ering & Construction
DAILY PROGRESS REPORT
DATE:- 10/21/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_


.
Site Conditions: Slushy Dry
TODAY TOTAL
MANPOWER
TOMORROW
TILL
PLANNED ACHIEVED PLANNED 8M
ACHIEVED PLANNED ACHIEVED

0 14 0% 100% 3

0 25 0% 100%
28 0 100% 0%
28 0 100% 0%
0 12 0% 100% 1
0 22 0% 100%
26 0 100% 0%
26 0 100% 0%
0 12 0% 100% 1
0 22 0% 100%
0 26 0% 100%
26 0 100% 0%
0 14 0% 100%
0 25 0% 100%
0 28 0% 100%
28 0 100% 0%
6 6
0 14 0% 100%
0 25 0% 100%
0 28 0% 100%
28 0 100% 0%
0 12 0% 100%
0 22 0% 100%
0 26 0% 100%
26 0 100% 0%
0 12 0% 100%
0 22 0% 100%
0 26 0% 100%
26 0 100% 0%
0 14 0% 100%
0 25 0% 100%
28 0 100% 0%
28 0 100% 0%
Balance
2785
900 Note :-
3240
2176 1. All the Work Permits are prepared before sign off
594 2.Tool Box Talk is Conducted on Daily Basis & submitted
170 3.Head Count is taken before signing off this DPR.
122 4.Everyday evening the activity for the next day is planned 5 o clock
46 with Spcl & team for co-ordination.
5. Workfronts are discussed and forecasted to optimize labour
10 resources
6.Any shortage of Materials will be informed in advance atleast 3 - 4
54 Weeks
30 2 weeks before based on the available Data.

Prepared by: Checked by Approved by


Miss.Priyanka Mr.Benadict Joshua Mr.Sagar A L

_______________ ___________________ ___________________

Date: Date:
6M 4M 3M 1&2M

2 1 2 6

3 2 5

3 3 5
M/s Shapoorji Pallonji Engineering &
M/s Shapoorji Pallonji Real Estate
Construction
JOY VILLE TOWER 7
Name of Work : ELECTRICAL WORKS
PROJECT

Location : Joy Ville - Virar West.


10th FLOOR
Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.
Site Conditions:
SITE

Normal Day Rainy Day


Qty TODAY
WORK ACTIVITY
LOCATION UOM
PROGRESS DESCRIPTION T C B PLANNED

Back Box Fixing Nos. 12 12 0 0


Vertical Conduiting Nos. 24 24 0 0
1 3 BHK Apt -1
Slab Conduiting Pts 29 29 0 0
Rope Pulling 8th FLOOR Pts 29 29 0 0
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 22 22 0 0
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 26 0 0
Rope Pulling 8th FLOOR Pts 26 0 26 26
Back Box Fixing Nos. 14 14 0 0
Vertical Conduiting Nos. 25 25 0 0
3 2 BHK ( L) Apt -3
Slab Conduiting Pts 28 28 0 0
Rope Pulling 8th FLOOR Pts 28 0 28 28
Back Box Fixing Nos. 14 14 0 0
Vertical Conduiting Nos. 25 25 0 0
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 28 0 0
Rope Pulling 8th FLOOR Pts 28 0 28 28
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 22 22 0 0
5 2 BHK ( S) Apt -5
Slab Conduiting Pts 26 26 0 0
Rope Pulling 8th FLOOR Pts 26 0 26 26
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 24 24 0 0
6 3 BHK Apt -6
Slab Conduiting Pts 29 29 0 0
Rope Pulling 8th FLOOR Pts 29 0 29 29
DESCRIPTION Unit Received Consumed Balance
1 25 mm Black Conduit Mtr 6900 4115 2785
2 25 mm Grey Conduit Mtr 900 0 900
3 20 mm Black Conduit Mtr 1080 7560 -6480
4 20 mm Grey Conduit Mtr 4500 2324 2176
5 32 mm Black Conduit Mtr 2000 1406 594
6 2 M GI BACK BOX Nos 500 330 170
7 3 M GI BACK BOX Nos 280 128 152
8 4 M GI BACK BOX Nos 70 24 46
9 6M GI BACK BOX Nos 150 140 10
10 8M GI BACK BOX Nos 170 116 54
11 12 M GI Back BOX Nos 30 0 30

Note : - Site Related Issue to be written with justifications for Prepared by:
improvements w.r.t Agency.
CONSTRAINTS

Miss.Priyanka

___________________

Date:
DAILY PROGRESS REPORT
DATE:- 10/21/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_

nditions: Slushy Dry


TODAY TOTAL MANPOWER
TOMORROW
TILL
ACHIEVED PLANNED 8M 6M
ACHIEVED PLANNED ACHIEVED

12 0% 100% 1 3
24 0% 100%
29 0% 100%
29 0% 100%
12 0% 100% 1 3
22 0% 100%
26 0% 100%
0 100% 0%
14 0% 100% 1 3
25 0% 100%
28 0% 100%
0 100% 0%
6 6
14 0% 100%
25 0% 100%
28 0% 100%
0 100% 0%
12 0% 100%
22 0% 100%
26 0% 100%
0 100% 0%
12 0% 100%
24 0% 100%
29 0% 100%
0 100% 0%

Note :-

1. All the Work Permits are prepared before sign off


2.Tool Box Talk is Conducted on Daily Basis & submitted
3.Head Count is taken before signing off this DPR.
4.Everyday evening the activity for the next day is planned 5 o clock
with Spcl & team for co-ordination.
5. Workfronts are discussed and forecasted to optimize labour
resources
6.Any shortage of Materials will be informed in advance atleast 3 - 4
Weeks
2 weeks before based on the available Data.

Checked by Approved by
Mr.Benadict Joshua Mr.Sagar A L

___________________ ___________________

Date: Date:
`

4M 3M 1&2M

3 5

2 5

3 5