COMMERCIAL INVOICE
In accordance with:
1. Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017 dated 29 March 2017, between PT PLN (Persero) and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) for the Muara Tawar Combined Cycle Power Plant
Block 2, 3, and 4 Add On Project;
2. Novation Agreement dated December 20th, 2017 between PT PLN (Persero), PT Pembangkitan Jawa Bali, and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement
No 0125.PJ/DAN.02.01/DIR/2017, Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On
Project;
3. Amendment No 1 Dated December 20th, 2017 between PT Pembangkitan Jawa Bali and the Consortium of Doosan Heavy Industries
and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017,
Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On Project;
INVOICE NO : MT-DHI-INV-EXW-MP-001-IDR
DATE OF ISSUANCE : November, 2018
DESCRIPTION : Progress Payment During Manufacture (1st Invoice)
CALCULATION
No Detail Formula Amount
1 Contract Amount for 0 (1) IDR 361,482,846,400.00
2 30.0% Progress Payment During Manufacture (2) = 30% x (1) IDR 108,444,853,920.00
Subject : The Manufacturing Progress Report for HRSG Non-Pressure Part & DCS
Dear Sir,
In accordance with:
1. Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017 dated 29 March 2017, between PT PLN (Persero) and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) for the Muara Tawar Combined Cycle Power Plant
Block 2, 3, and 4 Add On Project;
2. Novation Agreement dated December 20th, 2017 between PT PLN (Persero), PT Pembangkitan Jawa Bali, and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement
No 0125.PJ/DAN.02.01/DIR/2017, Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On
Project;
3. Amendment No 1 Dated December 20th, 2017 between PT Pembangkitan Jawa Bali and the Consortium of Doosan Heavy Industries
and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017,
Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On Project;
with reference to Book 1 Part 2.3.2.2 Terms of Payment, we herewith submit the MPR document as attached of
for Ex-Works Portion, including :
(A) (B) = (A) x 30% ⒞ #2-1 ⒞ #2-2 ⒞ #3-1 ⒞ #3-2 ⒞ #3-3 ⒞ #4-1 ⒞ #4-2 ⒞ #4-3 (D) = (B) x (C)
IDR IDR % % % % % % % % IDR
1.11 Heat Recovery Steam Generator (HRSG) 8 set 284,331,562,598
1.11.a Anchor Bolts & Embedded Materials 8 set 23,883,851,000 7,165,155,300 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 7,165,155,300 MPR-DS-HRSG-001
1.11.b-1 Duct/Casing & Column/Beams( #2-1~ #3-2) 4 set 20,308,272,600 100.0% 100.0% 100.0% 100.0% 20,308,272,600 MPR-DS-HRSG-002
135,388,484,000
1.11.b-2 Duct/Casing & Column/Beams( #3-3~ #4-3) 4 set 20,308,272,600 100.0% 99.6% 100.0% 97.6% 20,166,114,692 MPR-DS-HRSG-003
1.11.c Exhaust Stack 8 set 68,523,906,598 20,557,171,979 100.0% 100.0% 98.2% 98.2% 98.2% 91.9% 91.9% 91.9% 19,793,986,970 MPR-DS-HRSG-004
1.11.d Drum Supports 8 set 22,699,865,000 6,809,959,500 100.0% 100.0% 100.0% 100.0% 100.0% 98.1% 98.1% 98.1% 6,761,438,539 MPR-DS-HRSG-005
1.11.e Drum Enclosure 8 set 8,458,864,000 2,537,659,200 100.0% 100.0% 98.1% 98.1% 98.1% 85.3% 85.3% 85.3% 2,379,689,915 MPR-DS-HRSG-006
1.11.f Stairtower (included Elevator structure) 8 set 12,688,296,000 3,806,488,800 100.0% 100.0% 100.0% 100.0% 100.0% 89.8% 89.8% 88.2% 3,653,277,626 MPR-DS-HRSG-007
1.11.g Ladder & Platforms 8 set 8,458,864,000 2,537,659,200 100.0% 100.0% 97.9% 97.9% 97.9% 74.5% 74.5% 74.5% 2,275,011,473 MPR-DS-HRSG-008
1.11.h Pipe Rigid Support 8 set 4,229,432,000 1,268,829,600 98.2% 98.2% 86.8% 86.8% 86.8% 60.5% 60.5% 60.5% 1,012,367,418 MPR-DS-HRSG-009
Sub Total 85,299,468,779 100.0% 100.0% 99.3% 99.3% 98.7% 92.3% 92.3% 92.0% 83,515,314,533 (1), 98%
2.3 DCS 77,151,283,802
2.3.a DCS Hardware 8 set 28,069,761,683 8,420,928,505 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 5,894,649,954 MPR-DS-DCS-001
2.3.b DCS Software 8 set 25,821,656,185 7,746,496,856 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 5,422,547,800 MPR-DS-DCS-002
2.3.C PC & PC Acc. 8 set 3,283,009,282 984,902,785 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 689,431,950 MPR-DS-DCS-003
2.3.D Network Equipment & Cabinets 8 set 19,976,856,652 5,993,056,996 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 4,195,139,898 MPR-DS-DCS-004
Sub Total 23,145,385,142 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 16,201,769,602 (2), 70%
NOTE : Above table has been prepared for invoicing 'MT-DHI-INV-EXW-MP-001-IDR' in accordance with Clause 2.3.3.3 of Attachement 6. in EPC contract agreement.
Manufacturing Progress Report
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress
Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
DCS Hardware
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 25.5
DCS Hardware
Total % Progress (actual) 80 100 100 100 - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 22.75
DCS Hardware
Total % Progress (actual) 80 100 100 100 - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 22.75
Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
DCS Software
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
DCS Software
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
DCS Software
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23
Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
PC & PC Acc
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
PC & PC Acc
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
PC & PC Acc
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23
Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23
No. : / / 2018
Today on , 2018 in accordance with the Term Pada hari ini, , 2018, berdasarkan Tata Cara
of Payment, Muara Tawar Combined Cycle Power Plant Pembayaran, Muara Tawar Combined Cycle Power Plant
Block 2,3 & 4 Add-On Project, Contract No. 0125. Block 2,3 & 4 Add-On Project, Contract No. 0125.
PJ/DAN.02.01/DIR/2017 dated 29 March 2017, Doosan PJ/DAN.02.01/DIR/2017 tanggal 29 Maret 2017,
Heavy Industries & Construction Co.,Ltd., is entitled to Doosan Heavy Industries & Construction Co.,Ltd.,
receive the Progress Payment during Manufacture for berhak menerima Proses Pembayaran atas untuk Ex-
Ex-Work Manufacturing Progress Portion through Work Manufacturing Progress melalui T/T sebagai
T/T as follows: berikut:
Total Payable /
: IDR 99,717,084,135
Yang Dibayarkan
Doosan Heavy Industries & Construction Co., Ltd. PT PEMBANGKITAN JAWA BALI
, 2018 , 2018