DOOSAN HEAVY INDUSTRIES AND CONSTRUCTION CO., LTD.

Doosan Heavy Industries and Construction Seoul Office


465 Gangnam-Daero, Seocho-Gu, Seoul, 137-920, Korea
TEL : +82-2-513-7222 / FAX : +82-2-513-6693

To : PT Pembangkitan Jawa Bali


Jl. Ketintang Baru No 11 Surabaya 60231
Indonesia

COMMERCIAL INVOICE

In accordance with:
1. Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017 dated 29 March 2017, between PT PLN (Persero) and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) for the Muara Tawar Combined Cycle Power Plant
Block 2, 3, and 4 Add On Project;
2. Novation Agreement dated December 20th, 2017 between PT PLN (Persero), PT Pembangkitan Jawa Bali, and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement
No 0125.PJ/DAN.02.01/DIR/2017, Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On
Project;
3. Amendment No 1 Dated December 20th, 2017 between PT Pembangkitan Jawa Bali and the Consortium of Doosan Heavy Industries
and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017,
Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On Project;

We would like to invoice the following amount :

INVOICE NO : MT-DHI-INV-EXW-MP-001-IDR
DATE OF ISSUANCE : November, 2018
DESCRIPTION : Progress Payment During Manufacture (1st Invoice)

CALCULATION
No Detail Formula Amount
1 Contract Amount for 0 (1) IDR 361,482,846,400.00

2 30.0% Progress Payment During Manufacture (2) = 30% x (1) IDR 108,444,853,920.00

3 92.0% Progress Achieved (3) = 91.4% x (2) IDR 99,717,084,135.00


(Refer to Attachement )

4 Add (4) = (10%) x (3) IDR 9,971,708,413.50


- VAT (10%)
5 Less (5) = (3%) x (3) (IDR 2,991,512,524.05)
- Withholding TAX (3%)
6 Total Payment Amount (5) = (3) + (4) IDR 96,725,571,610.95

AMOUNT DUE IDR 96,725,571,611

Please make above remittance to the following Bank Account :

Name of bank : Mandiri KCP Jakarta


Swifit Code : BMRIIDJA
Account Name : Doosan Heavy Industries & Construction Co., Ltd
Account No : 126-00-0736293-1

Doosan Heavy Industries & Construction Co., Ltd.

YONG SEOK LEE


Consortium Project Manager
DOOSAN HEAVY INDUSTRIES AND CONSTRUCTION CO., LTD.
Doosan Heavy Industries and Construction Seoul Office
465 Gangnam-Daero, Seocho-Gu, Seoul, 137-920, Korea
TEL : +82-2-513-7222 / FAX : +82-2-513-6693

MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


(CONTRACT NO : 0125.PJ/DAN.02.01/DIR/2017)
To : PT PEMBANGKITAN JAWA BALI Our Ref. : MT-DHI-EXW-MP-001-HRSG & DCS
Attn : VERNON SAPALATUA Date : November, 2018
PJS General Manager Unit Pengembangan Usaha From : YONG SEOK LEE
Muara Tawar CCPP Add-On Project Consortium Project Manager
Doosan Heavy Industries &
Cc: 1. Finance Department, PT. PJB Unit Pengembangam Usaha Construction Co., Ltd.
2. Archive

Subject : The Manufacturing Progress Report for HRSG Non-Pressure Part & DCS

Dear Sir,

In accordance with:
1. Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017 dated 29 March 2017, between PT PLN (Persero) and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) for the Muara Tawar Combined Cycle Power Plant
Block 2, 3, and 4 Add On Project;
2. Novation Agreement dated December 20th, 2017 between PT PLN (Persero), PT Pembangkitan Jawa Bali, and the Consortium of
Doosan Heavy Industries and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement
No 0125.PJ/DAN.02.01/DIR/2017, Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On
Project;
3. Amendment No 1 Dated December 20th, 2017 between PT Pembangkitan Jawa Bali and the Consortium of Doosan Heavy Industries
and Construction Ltd-PT Hutama Karya (Persero) relating to Contract Agreement No 0125.PJ/DAN.02.01/DIR/2017,
Dated 29 March 2017 for Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add On Project;

with reference to Book 1 Part 2.3.2.2 Terms of Payment, we herewith submit the MPR document as attached of
for Ex-Works Portion, including :

a) Payable Amount for Goods Manufactured in Indonesia (Ex-Works) IDR 99,717,084,135.00


b) the Manufacturing Progress Report
c) the inspection and test plan check list with photographs

Your prompt review and acceptance would be highly appreciated

Doosan Heavy Industries & Construction Co., Ltd.

YONG SEOK LEE


Consortium Project Manager
Payable Amount for Goods Manufactured in Indonesia (Ex-Works)
650MW MUARA TAWAR CCPP BLOCK 2,3&4 ADD ON PROJECT

As of 31th October, 2018

Total Payable amount


Contract Price Manufacturing Manufacturing Manufacturing Manufacturing Manufacturing Manufacturing Manufacturing Manufacturing
for Manufacturing Payable Amount
(Ex Work) Progress Progress Progress Progress Progress Progress Progress Progress
Progress
Item No. Description Qty Unit Remarks

(A) (B) = (A) x 30% ⒞ #2-1 ⒞ #2-2 ⒞ #3-1 ⒞ #3-2 ⒞ #3-3 ⒞ #4-1 ⒞ #4-2 ⒞ #4-3 (D) = (B) x (C)
IDR IDR % % % % % % % % IDR
1.11 Heat Recovery Steam Generator (HRSG) 8 set 284,331,562,598
1.11.a Anchor Bolts & Embedded Materials 8 set 23,883,851,000 7,165,155,300 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 7,165,155,300 MPR-DS-HRSG-001
1.11.b-1 Duct/Casing & Column/Beams( #2-1~ #3-2) 4 set 20,308,272,600 100.0% 100.0% 100.0% 100.0% 20,308,272,600 MPR-DS-HRSG-002
135,388,484,000
1.11.b-2 Duct/Casing & Column/Beams( #3-3~ #4-3) 4 set 20,308,272,600 100.0% 99.6% 100.0% 97.6% 20,166,114,692 MPR-DS-HRSG-003
1.11.c Exhaust Stack 8 set 68,523,906,598 20,557,171,979 100.0% 100.0% 98.2% 98.2% 98.2% 91.9% 91.9% 91.9% 19,793,986,970 MPR-DS-HRSG-004
1.11.d Drum Supports 8 set 22,699,865,000 6,809,959,500 100.0% 100.0% 100.0% 100.0% 100.0% 98.1% 98.1% 98.1% 6,761,438,539 MPR-DS-HRSG-005
1.11.e Drum Enclosure 8 set 8,458,864,000 2,537,659,200 100.0% 100.0% 98.1% 98.1% 98.1% 85.3% 85.3% 85.3% 2,379,689,915 MPR-DS-HRSG-006
1.11.f Stairtower (included Elevator structure) 8 set 12,688,296,000 3,806,488,800 100.0% 100.0% 100.0% 100.0% 100.0% 89.8% 89.8% 88.2% 3,653,277,626 MPR-DS-HRSG-007
1.11.g Ladder & Platforms 8 set 8,458,864,000 2,537,659,200 100.0% 100.0% 97.9% 97.9% 97.9% 74.5% 74.5% 74.5% 2,275,011,473 MPR-DS-HRSG-008
1.11.h Pipe Rigid Support 8 set 4,229,432,000 1,268,829,600 98.2% 98.2% 86.8% 86.8% 86.8% 60.5% 60.5% 60.5% 1,012,367,418 MPR-DS-HRSG-009
Sub Total 85,299,468,779 100.0% 100.0% 99.3% 99.3% 98.7% 92.3% 92.3% 92.0% 83,515,314,533 (1), 98%
2.3 DCS 77,151,283,802
2.3.a DCS Hardware 8 set 28,069,761,683 8,420,928,505 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 5,894,649,954 MPR-DS-DCS-001
2.3.b DCS Software 8 set 25,821,656,185 7,746,496,856 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 5,422,547,800 MPR-DS-DCS-002
2.3.C PC & PC Acc. 8 set 3,283,009,282 984,902,785 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 689,431,950 MPR-DS-DCS-003
2.3.D Network Equipment & Cabinets 8 set 19,976,856,652 5,993,056,996 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 4,195,139,898 MPR-DS-DCS-004
Sub Total 23,145,385,142 85.0% 85.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 16,201,769,602 (2), 70%

TOTAL PAYABLE AMONT 99,717,084,135 (3), 92.0% = (1) + (2)

NOTE : Above table has been prepared for invoicing 'MT-DHI-INV-EXW-MP-001-IDR' in accordance with Clause 2.3.3.3 of Attachement 6. in EPC contract agreement.
Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-001
Sub-Supplier : Nooter Eriksen (PT Swadaya Graha)
Status Date : 31 October, 2018
Materials : 1.11.a. Anchor Bolts & Embedded Materials

Material Material cutting and assembly blast and final Total


Material Weight Progress welding packing EXW ready
order receipt preparation fit-up paint inspection Progress

7% 25% 15% 15% 25% 5% 2% 4% 2% 100%


Anchor Bolts & Embedded
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100%
Materials(#2.1~#4.3)
Total Weight [Ton] 108 108

TOTAL PROGRSS : 100%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-002
Sub-Supplier : Nooter Eriksen (PT Swadaya Graha)
Status Date : 31 October, 2018
Materials : 1.11.b-1. Duct/Casing & Column/Beams

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

7% 20% 15% 11% 22% 3% 5% 4% 5% 2% 4% 2% 100%


Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#2.1)
Total Weight [Ton] 363 363
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#2.2)
Total Weight [Ton] 363 363
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#3.1)
Total Weight [Ton] 363 363
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#3.2)
Total Weight [Ton] 363 363

TOTAL PROGRSS : 100%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-003
Sub-Supplier : Nooter Eriksen (PT Sanggar Sarana Baja)
Status Date : 31 October, 2018
Materials : 1.11.b-2. Duct/Casing & Column/Beams

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

7% 20% 15% 11% 22% 3% 5% 4% 5% 2% 4% 2% 100%


Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#3.3)
Total Weight [Ton] 363 363
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 95 95 95 100%
(#4.1)
Total Weight [Ton] 363 362
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 100 100 100 100 100%
(#4.2)
Total Weight [Ton] 363 363
Duct/Casing & Column/Beams
Total % Progress (actual) 100 100 100 100 100 100 100 100 92 83 81 61 98%
(#4.3)
Total Weight [Ton] 363 354

TOTAL PROGRSS : 99.3%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-004
Sub-Supplier : Nooter Eriksen (PT Swadaya Graha)
Status Date : 31 October, 2018
Materials : 1.11.c. Exhaust Stack

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

7% 25% 23% 15% 15% N/A 7% N/A N/A 2% 4% 2% 100%


Exhaust Stack
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 2 : #2.1,#2.2)
Total Weight [Ton] 255 255
Exhaust Stack
Total % Progress (actual) 100 100 100 100 100 - 95 - - 90 80 80 98%
(Block 3 : #3.1,#3.2,#3.3)
Total Weight [Ton] 383 376
Exhaust Stack
Total % Progress (actual) 100 100 100 100 90 - 60 - - 60 50 50 92%
(Block 4 : #4.1,#4.2,#4.3)
Total Weight [Ton] 383 352

TOTAL PROGRSS : 96.3%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-005
Sub-Supplier : Nooter Eriksen (PT. Danwo)
Status Date : 31 October, 2018
Materials : 1.11.d. Drum Supports

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

8% 25% 25% 15% 15% N/A 4% N/A N/A 2% 4% 2% 100%


Drum Support
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 2 : #2.1,#2.2)
Total Weight [Ton] 114 114
Drum Support
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 3 : #3.1,#3.2,#.33)
Total Weight [Ton] 171 171
Drum Support
Total % Progress (actual) 100 100 100 100 100 100 - - 80 75 75 98%
(Block 4 : #4.1,#4.2,#4.3)
Total Weight [Ton] 171 168

TOTAL PROGRSS : 99.3%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-006
Sub-Supplier : Nooter Eriksen (PT. Danwo)
Status Date : 31 October, 2018
Materials : 1.11.e. Drum Enclosure

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

8% 25% 25% 15% 15% N/A 4% N/A N/A 2% 4% 2% 100%


Drum Enclosure
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 2 : #2.1,#2.2,#2.3)
Total Weight [Ton] 67 67
Drum Enclosure
Total % Progress (actual) 100 100 100 100 100 - 100 - - 80 75 75 98%
(Block 3 : #3.1,#3.2,#3.3)
Total Weight [Ton] 101 99
Drum Enclosure
Total % Progress (actual) 100 100 100 85 80 - 25 - - 20 20 20 85%
(Block 4 : #4.1,#4.2,#4.3)
Total Weight [Ton] 101 86

TOTAL PROGRSS : 93.7%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-007
Sub-Supplier : Nooter Eriksen (PT. Danwo)
Status Date : 31 October, 2018
Materials : 1.11.f. Stairtower

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

8% 25% 25% 15% 15% N/A 4% N/A N/A 2% 4% 2% 100%


Stairtower without Elevator
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
structure (Block 2 : #2.1)
Total Weight [Ton] 41 41
Stairtower with Elevator structure
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 2 : #2.2)
Total Weight [Ton] 58 58
Stairtower without Elevator
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
structure (Block 3 : #3.1,#3.2)
Total Weight [Ton] 82 82
Stairtower with Elevator structure
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 3 : #3.3)
Total Weight [Ton] 58 58
Stairtower without Elevator
Total % Progress (actual) 100 100 100 100 100 - 45 - - 90%
structure (Block 4 : #4.1,#4.2)
Total Weight [Ton] 82 74
Stairtower with Elevator structure
Total % Progress (actual) 100 100 100 100 100 - 5 - - 88%
(Block 4 : #4.3)
Total Weight [Ton] 58 51

TOTAL PROGRSS : 96.0%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-008
Sub-Supplier : Nooter Eriksen (PT. Danwo)
Status Date : 31 October, 2018
Materials : 1.11.g. Ladders and Platforms

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

8% 25% 25% 15% 15% N/A 4% N/A N/A 2% 4% 2% 100%


Ladders and Platforms
Total % Progress (actual) 100 100 100 100 100 - 100 - - 100 100 100 100%
(Block 2 : #2.1,#2.2)
Total Weight [Ton] 138 138
Ladders and Platforms
Total % Progress (actual) 100 100 100 100 100 - 90 - - 85 80 70 98%
(Block 3 : #3.1,#3.2,#3.3)
Total Weight [Ton] 207 203
Ladders and Platforms
Total % Progress (actual) 100 100 100 60 50 - - - 75%
(Block 4 : #4.1,#4.2,#4.3)
Total Weight [Ton] 207 154

TOTAL PROGRSS : 89.7%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-HRSG-009
Sub-Supplier : Nooter Eriksen (PT. Swadaya)
Status Date : 31 October, 2018
Materials : 1.11.h. Pipe Rigid Support

Material Material cutting and assembly stud/pin blast and insulation liner final Total
Material Weight Progress welding packing EXW ready
order receipt preparation fit-up welding paint assembly installation inspection Progress

9% 25% 20% 15% 18% N/A 5% N/A N/A 2% 4% 2% 100%


Rigid supports
Total % Progress (actual) 100 100 100 100 100 - 95 - - 80 80 80 98%
(Block 2 : #2.1,#2.2)
Total Weight [Ton] 108 106
Rigid supports
Total % Progress (actual) 100 100 90 85 80 - 60 - - 60 50 50 87%
(Block 3 : #3.1,#3.2,#3.3)
Total Weight [Ton] 163 141
Rigid supports
Total % Progress (actual) 100 100 50 40 40 - 30 - - 30 20 20 61%
(Block 4 : #4.1,#4.2,#4.3)
Total Weight [Ton] 163 99

TOTAL PROGRSS : 79.7%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-DCS-001
Sub-Supplier : PT. Honeywell
Status Date : 31 October, 2018
Materials : 2.3.a. DCS Hardware

Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
DCS Hardware
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 25.5
DCS Hardware
Total % Progress (actual) 80 100 100 100 - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 22.75
DCS Hardware
Total % Progress (actual) 80 100 100 100 - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 22.75

TOTAL PROGRSS : 71.0%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-DCS-001
Sub-Supplier : PT. Honeywell
Status Date : 31 October, 2018
Materials : 2.3.b. DCS Software

Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
DCS Software
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
DCS Software
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
DCS Software
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23

TOTAL PROGRSS : 71.0%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-DCS-001
Sub-Supplier : PT. Honeywell
Status Date : 31 October, 2018
Materials : 2.3.C. PC & PC Acc

Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
PC & PC Acc
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
PC & PC Acc
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
PC & PC Acc
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23

TOTAL PROGRSS : 71.0%


Manufacturing Progress Report

Project : MUARA TAWAR CCPP BLOCK 2, 3 & 4 ADD-ON PROJECT


Report Number : MPR-DS-DCS-001
Sub-Supplier : PT. Honeywell
Status Date : 31 October, 2018
Materials : 2.3.d. Network Equipment & Cabinets

Fabrication
Engineer- Material / Material final EXW Total
Material Weight Progress
ing order Manufacturi receipt inspection ready Progress
ng
% 25% 18% 16% 11% 20% 10% 100%
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 100 - 85%
(Block 2 : 2units)
Total Weight [Ton] 30 - 26
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 3 : 3units)
Total Weight [Ton] 35 - 23
Network Equip. & Cabinets
Total % Progress (actual) 80 100 100 100 - - 65%
(Block 4 : 3units)
Total Weight [Ton] 35 23

TOTAL PROGRSS : 71.0%


PAYMENT CERTIFICATE BERITA ACARA PEMBAYARAN

No. : / / 2018

Today on , 2018 in accordance with the Term Pada hari ini, , 2018, berdasarkan Tata Cara
of Payment, Muara Tawar Combined Cycle Power Plant Pembayaran, Muara Tawar Combined Cycle Power Plant
Block 2,3 & 4 Add-On Project, Contract No. 0125. Block 2,3 & 4 Add-On Project, Contract No. 0125.
PJ/DAN.02.01/DIR/2017 dated 29 March 2017, Doosan PJ/DAN.02.01/DIR/2017 tanggal 29 Maret 2017,
Heavy Industries & Construction Co.,Ltd., is entitled to Doosan Heavy Industries & Construction Co.,Ltd.,
receive the Progress Payment during Manufacture for berhak menerima Proses Pembayaran atas untuk Ex-
Ex-Work Manufacturing Progress Portion through Work Manufacturing Progress melalui T/T sebagai
T/T as follows: berikut:

Total Ex-Work Portion /


: IDR 361,482,846,400
Porsi Asing
Total Payable Value /
: IDR 108,444,853,920
Nilai Pengiriman
Payable Percentage / 30% of Equipment Value /
:
Prosentase dibayarkan 91.4% of Progress Achievement

Total Payable /
: IDR 99,717,084,135
Yang Dibayarkan

Empat Puluh Tiga Miliar Lima Ratus Delapan Puluh


Forty Three Billion Five Hundred Eighty Eight Million
Delapan Juta Dua Puluh Delapan Ribu Lima Ratus
Twenty Eight Thousand Five Hundred Forty Six Rupiah
Empat Puluh Enam Rupiah

CONTRACTOR / KONTRAKTOR : OWNER / PEMBERI KERJA :

Doosan Heavy Industries & Construction Co., Ltd. PT PEMBANGKITAN JAWA BALI
, 2018 , 2018

YONG SEOK LEE Vernon Sapalatua Tampubolon


Consortium Project Manager PJS General Manager Unit Pengembangan Usaha