Академический Документы
Профессиональный Документы
Культура Документы
Sl.N
CONTENTS Page No
o
B01
Protection & Interlocks 136
0
B01
Modifications &Improvements 173
2
2
1.0 Introduction
Draught systems
Pressure parts
Firing system
Ash separation& disposal
1.0 INTRODUCTION
3
The front and rear wall bottom headers feed the front and rear furnace
wall tubes; the furnace side walls are supplied by the sidewall bottom
headers. All the bottom headers are connected with down comer pipes
by means of supply tubes.
The water in the furnace walls absorbs heat. The resulting mixture of
water and steam is collected in the outlet headers and discharged into
the steam drum through a series of riser tubes. In the steam drum
separation of water and steam takes place. The boiler water mixes with
the incoming water. The saturated steam is led to the super heater
connecting tubes. Passing through the various stages of super heaters,
the steam is superheated to design temperature. From the super heater
outlet header, the superheated steam is led to the turbine via the main
steam lines.
gas travels in two independent streams through ESP where 99% of fly
ash is separated. Subsequently the flue gas is drawn by two single
stage axial flow reaction typeID fans thus to have balanced draught.
The fan is provided variable pitch blading with pneumatic control drive
similar to that in FD fans for regulation of the quantity of flue gases
handled. Flue gas finally discharged through 225 M high stack.
3.2.2Economiser
The purpose of the economiser is to preheat the boiler feed water
before it is introduced into the steam drum, and to recover some of the
heat from flue gases leaving the boiler.
Four banks of horizontal type of economiser are located at the top of
the boiler below the radiant roof. Each section is composed of a number
of parallel tube circuits . All the tube circuits originate from the
economiser inlet header and discharge into the economiser outlet
header. The horizontal banks of the economiser are supported by
steam cooled hanger tubes.
SH2 assemblies are located in the intermediate level of the boiler. SH2
assemblies are provided above RH2 assemblies and below RH1
assemblies.
SH3 assemblies are located above the SH1 and below RH2.
These SH assemblies are horizontal banks and penetrating the
Front/Rear wall to join with headers. These assemblies are supported by
steam-cooled hangers
3.2.4 Reheater
The Reheater is composed of 2 stages, Low temperature reheaterRH1
and high temperature reheater RH2.
RH1 assemblies are located in upper side of the boiler. RH1 assemblies
are provided below the economiser assemblies and above the SH2
assemblies. Final reheater RH2 assemblies are provided above SH3 and
below SH2.These reheater assemblies are horizontal banks and
penetrating the rear wall to join with headers. These assemblies are
supported by steam-cooled hangers.
electromatic relief valve on the superheater main steam line set below
the lowest set superheater safety valve is provided as a working valve
to give an initial indication of excessive steam pressure.
each burner is 4T/hr and the turn down ratio is 4:1.The capacity of
LSHS/HFO and LDO is 30% and 7.5% MCR respectively.
5.0 ASH SEPAPARATION AND DISPOSAL SYSTEM.
5.1 Slag disposal
Each boiler has a slag conveyor running in a trough filled with water to
carry the slag falling in the slag bath at the bottom and discharge it to
the slag channel.
5.2 Ash separation (Electro static precipitator).
In order to minimize the air pollution by fly ash electro static
precipitators are installed. In ESP, ash particles are charged by ions
generated by a corona discharge. The charged ash particles are
deposited on collecting electrodes by electrical forces and are then
removed and disposed off.
5.3 Ash water and ash disposal system.
Wet slag from slag conveyor and ash slurry from ash mixing vessels
pass through open channels and then closed channels to the slurry
pumps. The ash disposal system consists of two ash slurry pump
houses. The ash water ratio required is 1: 25.To meet the water
requirements of ash disposal system, two water sources namely High
pressure water and Low pressure water are supplied through ash
disposal system to all boilers. The slurry is pumped to an ash bund.
SH 1 outlet 485 ºc
SH 2 inlet 430 ºc
SH 2 outlet 515 ºc
SH 3 inlet 495 ºc
SH 3 outlet 540 ºc
RH 1 inlet 360 ºc
RH 1 outlet 505 ºc
10
RH 2 inlet 485 ºc
RH 2 outlet 540 ºc
Volumes
Water contained in the boiler 175,63 m3
Combustion space 39,507 m3
Radiation space 9,171 m3
Super heater 1 5,716 m3
Super heater2 20,13 m3
Super heater 3 7,207 m3
Reheater 1 42,142 m3
Reheater 2 25,457 m3
ECO 1&2 113,71 m3
Total heating surface 307,16 m3
FUEL DATA
Light fuel oil (LDO)
NCV 42000 KJ/Kg
11
Lignite
Gross calorific value GCV 11769 KJ/Kg
Lower calorific valve NCV 10048 Kg/kg
Ash 7%
Water 48.5 %
Volatiles 24 %
Fixed carbon 20.5 %
Grindability 140 hard grove
Ash melting IDP > 950 °c
Ash melting FP >1200 °c
Flow 2.85kg/s
Number 2
Low pressure(nominal pressure) 10 bar
Temperature 50°c
Nominal diameter(DN) 80,100mm
Mesh size of the filter 500µm
PULVERISING SYSTEM
Lignite bunker
Lining kalen
control range 1: 5
Beater Wheel Mills
Manufacturer EVT
Type N 110.60
Design beater wheel mill
Number( per boiler ) 6
18
Slag Conveyor
Manufacturer EVT
Number per boiler 1 no
Motor rating 7.5 k w
Speed 1450 min –1
Electrostatic precipitator
Manufacturer BHEL
Type FAA-66x37.5-
2xlo2125-2
Number per boiler 2 nos
Construction type welded casing
Gas quantity inlet (worst lignite) 480.6 m3/sec
Suction at ESP inlet -22.5 m bar
20
Temperature 157 °c
Moisture in gas (% by weight) 15.84 %
Inlet dust concentration 26.5 g/Nm3
O/L dust concent.with one field out of service 150 mg/Nm3
1.0 INTRODUCTION
burners are mounted in the left and a right wall of the furnace in a single
elevation at 20-meter level.
Two cooling air fans are provided to supply cold atmospheric air to the oil
burners mainly as a protecting medium. They are located in the rear side
of the furnace at 15-meter level. Ultra violet scanners are also mounted
on the oil burner register to monitor oil flame so as to maintain a reliable
and continuous operation of oil burners. The control stations of atomizing
media viz. atomising steam and compressed air are situated near the oil
schemes. Operations of oil burners are initiated from Unit Control Desk.
In any oil burner either LDO or LSHS oil can be burnt. The capacity of oil
firing system has been designed to generate 30% MCR load and 7.5%
M.C.R. Load on the unit with LSHS and LDO respectively.
strainer and a BMS oil valve. The BMS oil valve will open automatically, while
burner is cut in from control desk. It will close automatically when Burner is
cut out and as well as during inadequate combustion conditions.
Whereas the second bypass line, which has a hand, operated valve with an
orifice will permit a maximum return oil flow of 0.5t/h. The BMS return oil line
will be used for oil recirculation before start up of oil burners. The first
bypass line will be used in the event of failure of BMS return valve, where as
the second bypass line permits return oil flow when oil burners are in service.
The BMS return valve can be operated from the unit control desk. It gets
opened automatically when BMS LSHS oil main valve is opened. Automatic
closing of this valve will occur when three or more oil burners are cut in.
A hand-operated valve is provided in the return oil line from the boiler after
the recirculation line connection.
A pump designated as drain oil pump is installed to pump oil to the main
LSHS tanks. In the inlet side of the pump, a filter is provided. Isolation valve
is provided before the filter. In the delivery side of the pump, a discharge
valve and a NRV are provided. The pump is capable of pumping oil at the
rate of 39 liters per minute at a discharge pressure of 5 bar, and driven by a
motor of rating 3ø; 415v; 1.1 K.W. 1415 rpm; 2.65 amps. The delivery line
from the pump joins the LSHS return oil line at 15-meter level.
Such return oil lines from all the Units (4, 5, 6 & 7) are connected as a single
return oil line carrying oil (maximum of 17.l m 3/hr; 130°C) towards FOPH II.
This return oil line and LSHS oil pressure control lines (/Recirculation lines)
tapped before each secondary oil heating station are connected to a single
line carrying hot oil to the LSHS oil main tank area. This line is now branched
into two, and each is connected just before suction heater. Provisions are
available to divert return oil to the tank top whenever the return oil
temperature create problems in the pumping. Necessary hand operated
isolation valves are provided in the return oil schemes for the above
purposes.
30
LSHS oil can be burnt effectively only after proper atomization with steam.
This steam is tapped from auxiliary steam system. In each unit, auxiliary
steam is drawn from the Unit auxiliary steam header through a single line.
From the line, a branch is taken which is again branched into two lines. One
line supplies auxiliary steam as purge steam and the other line feeds
auxiliary steam after certain pressure reduction as atomising steam.
with a hand operated valve will be the reserve for this pressure control valve.
This pressure control station maintains the steam pressure at 10.5 Kg/cm 2 .
A pressure indicator is provided before and after the pressure control valve
and number of pressure transmitters are laid in the bypass line too. The
atomising steam line is connected to “U” shaped main. A line is taken for
each burner and is provided with a hand-operated valve, a ‘Y’ type strainer, a
BMS atomising steam valve and a non-return valve. This line is then
connected to the atomising airline to form a single line to the burner gun. For
operation of any oil burner, selection of atomising medium, either atomising
steam or atomising air for that burner should be done earlier from the control
desk.
Burner valve control station has LDO & LSHS oil lines, atomising air &
atomising steam lines and purging line. In these lines, no. Of BMS valves
have been provided so that operation of oil burner can be carried out in
particular sequence for safety and reliability. The LDO and LSHS oil line
merge together as a single line and is connected to an adopter. Similarly,
atomising air and steam lines join together as a single line connected to the
same adopter. There are two flexible hoses emanating from the adopter, one
carries either LDO or LSHS oil and another carries either atomising air or
steam to the oil burner gun.Purge steam/air line is connected to the oil line.
The purge steam line has two BMS purge valves. Out of them, first valve is
three-way change over valve. This three way change over valve gives free
way for the purge steam to the burners during the purging period only. The
other way is open to atmosphere to drain locked up steam condensate after
BMS atomising valves up to the adopter. The dirt condensate from the three-
way valve of all the burners joins together and is allowed to go as waste.
Each boiler is equipped with four oil burners. The oil burners two in the right
side and two in the left side are located at 20-meter elevation the same as
that of the lower elevation p.f. Burners. Right rear burner is designated as
‘A’, right front as ‘B’, left front as ‘C’ and left rear as ‘D’. The centre-to-centre
distance between two oil burners is 6300mm and they are placed at a
distance of 3150mm from the furnace centre line. The location of oil burners
is so chosen to ensure proximity of each oil burner to two p.f. Burners at the
lower elevation. This facilitates easy ignition of pulverized fuel during
lighting up of a boiler. The oil burner is 3337.5mm away from the nearest
water wall and this avoids flame impingement on the water wall tubes.
The oil burner is of retractable type and is having three concentric tubes, an
inner tube of 70 x 3mm. The length of the burner gun is 2020mm. Inside
the burner gun, two numbers tri-supports are provided at120 degree
intervals, one between the inner and middle tube and the other between
middle and outer tube. The supports are located at 800mm from the burner
tip. This arrangement keeps all the three tubes concentric and prevents any
sagging due to cantilever type support. Atomising steam flows through the
inner tube of the burner, while oil flows through the annular space between
the inner and middle tube and cooling air between the middle and outer
tube.
In one end of the burner gun a nozzle support is welded to the middle tube.
The burner nozzle is positioned and fixed adjacent to the nozzle support by
screwing a nozzle cap to the nozzle support. The other end of the burner gun
is provided with a gun coupling. The gun coupling consists of two parts i.e.
fixed gun coupling and loose gun coupling. The fixed gun coupling, which has
provisions
for connecting oil and steam hoses, is fixed to the cooling air pipe by a split
circular clamp with a bolt. The cooling air tube has an inlet tube of 28x2mm
33
near the fixed gun coupling for connecting the cooling air hose. A grooved
circular ring provided with a rubber “O” ring is welded to the oil pipe of the
burner gun (near the loose gun coupling and). This ring fits in and seals at
the end of the cooling air pipe thus preventing escaping of cooling air. This
arrangement also facilitates removal of burner gun without disturbing cooling
air tube. The burner gun can be inserted into the furnace while cutting in a
burner or retracted while cutting out. This movement is facilitated by the
provision of a pneumatic cylinder with a piston and connecting rod assembly.
The connecting rod assembly moves in sliding sleeve which is welded to the
burner register. Two numbers limit switches provided in the sleeve limit the
movement of the connecting rod assembly and consequently that of the
burner gun connected to it. The length of travel of the gun is 500mm. In the
forward position of the gun, the burner tip remains at 455mm before the
evaporator tube centre line. A flap (a small circular door) is provided at the
end of the gun support pipe (the guide pipe on which the stabilizer vanes are
fixed). This opens when the burner gun is inserted and closes when the gun
is retracted. Thus the burner gun and tip are protected from intense
radiation from the furnace.
The burner nozzle consists of eight numbers ‘Y’ type holes. The atomising
steam supplied to the burner at a constant pressure of 10.5 bar flows through
the inner tube of the burner gun and comes out through the eight nozzle
holes. The velocity of steam increases while passing through the eight
divergent nozzle holes arranged at 45° angular interval. The fuel oil passing
in the middle pipe gets distributed through the 8 holes of the nozzle support
and enters the nozzle holes. The oil stream gets a mixed with the expanding
steam stream in the ‘Y’ type connection, gets atomized and comes out of the
nozzle in a fine spray form.
Cooling air for the oil burners is supplied by a separate fan called Scanner air
fan. There are two-scanner air fans located at 15 meter level rear side. Of
this, one will be in service and the other will be reserve. This fan handles air
at the rate of 0.133Kg/s and develops a pressure of 62.9-milli bar. One fan is
driven by 3; 415V A.C. motor while the other is driven by 220 volts D.C.
Air drawn from atmosphere by the fan is discharged through pipings to the oil
burners for cooling. Cooling air fed to the annular space between middle and
outer tube comes out of the burner tip through the small annular space
between the nozzle cap and outer tube of the gun. This ensures continuous
cooling of the burner gun as well as protection of burner tip against excessive
heating buy furnace radiation.
Combustion air supply for the burners is taken from the secondary air
distribution boxes through two circular ducts. Each of these two ducts
coming vertically downwards from the secondary air box divides into two and
takes a 90-degree bend and goes below 15-meter platform. Just below the
burner it rises upwards. A flow meter of ventury type is installed in the
circular duct just below the 15 meters level.A pneumatically operated damper
is provided in the air supply duct. The burner air duct joins the burner air
register through a square duct. This square duct is divided into two.
Normally about 10% , of the burner air is supplied
remaining portion of the square duct. The primary air quantity can be
adjusted by a hand-operated shut off flap at the entry. Adjustment of this
flap is done during commissioning in order to feed combustion air required to
start ignition of oil air mixture. This damper is then permanently fixed at the
particular position. It will not be necessary to modify the position of it for the
various ranges of load.In the burner air register, primary air flows through a
circular duct (of diameter 508mm) surrounding the burner gun. In this duct 8
stabiliser vanes are there, fixed to the gun support pipe in order to create
vortex motion to the primary air for through mixing with oil spray. The
secondary air gets supplied through the annular space in between the
primary air duct and the outer duct of 910mm diameter for complete
combustion.
A blue tinted view glass is provided for each oil burner at 7° angle. This
facilitates inspection of burner flame. Recently IR scanners are placed in the
place of burner view glass in order to have reliable operation on IR scanner.
The DURAG ultraviolet radiation flame controller D-UV 400 monitors are
provided for oil burners. Each monitor is at 570mm on left or right side of oil
gun at an inward angle of 7 degree. This flame monitor monitors oil and / or
gas flames. The unit operates in the spectral range of 190 to 270nm. and
therefore is largely unaffected by daylight and radiation from hot refractory
faces. The self-monitoring feature guarantees that the ‘flame out’ signal will
always be initiated if flame failure occurs (one set or two sets of contacts will
open). The response sensitivity is adjustable within a range of 100:1 in ten
steps. The sensitivity selector switch and circuitry is duplicated giving the
possibility of adjusting the unit for two
separate ‘safe time’ limit adjustments. The circuit design employed ensures
absolute operational reliability, even with flames, which emit very low UV
radiation levels. The nearly linear relationship between UV intensity and
flame signal makes extremely good differentiation (selectivity) possible.
Flame differentiation is further improved by the small scanning angle of the
UV receiver, about 6 degrees, which permits simple and effective alignment
of the receiver to the UV source. Several flames in one fire box can be
monitored simultaneously by using one unit for each flame and arranging the
receivers to view only their respective flame. It is also possible to
simultaneously scan a flame with two UV receivers connected to a single
controller.
timer unit, which determines the ‘safe time’. As circuit outlets, two reversing
contact sets are provided. The flame relay and self-monitor relay contacts
are internally wired in series.
13.3 IGNITORS
13.3.1 General
With oil burners, the optimum position of the ignition tip is in general at the
edge of the fuel spray zone just after the vortex vanes or flame stabilizer
disc.The absolute position can be best determined by adjusting the axial
position of the tip by hand in the field with an axial movement of the lance.
When firing the fuel, an adequate oil preheat temperature (90-130degreeC)
must be provided. To minimize wear and tear at the ignition tip, the lance
should be withdrawn out of the flame region and the device seethed off as
soon as successful ignition is achieved. The operational life of the tip is 10 6
ignition impulses, which is equivalent to 14 hours service at the higher
ignition frequency sequence. High temperatures and burn out in the flame
zone lead to increased wear at the ignition tip.
The ignition tip of the ignition device should only remain in the fuel air
mixture during the ignition process until the flame is established. After
successful ignition, the tip must be withdrawn from the combustion zone.
The ignitor gun can be inserted or retracted by a device called pneumatic
position cylinder. It comprises of a cylinder with a reciprocating piston and a
rail frame assembly with a roller carriage. The reciprocating piston rod is
connected to the roller carriage and the roller carriage carries the ignitor gun
pipe through split circular clamps. The roller carriage runs over the rails like,
frames in the assembly for insertion / retraction. This actuation is made by
admitting dry compressed air (Instrument air) at either ends of the cylinder
through separate airlines. In each airline, a solenoid valve operated by 48V
DC is provided for supply / cut off air so that the gun insertion / retraction will
be effected.
This retraction unit withdraws the ignition tip back by 300mm. By means of
this Unit, the exact positioning of the ignition tip to suit the ignition process
can be accomplished. The lance must be arranged such that when in
withdrawn position, the ambient temperature at the tip does not exceed 600
° C.
39
14.1 Ignitors
Number of ignitors 4
Type High Energy Ignition
Device
(D - HG 400 – 500)
Make DURAG, Germany
15.1 Introduction
Lignite has been burnt in the steam generators of Thermal station II/
Stage –II by adopting direct injection without separating water vapors . There
are six independent firing units in the boiler and each firing unit comprises of
a boiler bunker, three plate belt feeders, a conveyor belt feeder, a resuction
duct, a beater wheel, a pulverized fuel duct and two pulverized fuel burners.
The mills are located around the furnace and the pulverized fuel burners are
mounted on all the four sides of furnace wall at two elevations so that the p.f
burners axes form tangents to an imaginary circle of 1.5 m diameter in the
center of furnace like “ a vertical cylinder fire ball ‘. Two after burning grates
provided at the furnace bottom collect and burn unburnt lignite particles
escaping from combustion chamber.
15.2 Boiler bunkers
S ix boiler bunkers are arranged inline in front of the furnace and these
bunkers are getting lignite supply from conveyors namely 21A1, 21A2, 21B1,
21B2. The bunker top is at 32 ML and its bottom extends up to 19.5 ML.
There are three hoppers at its bottom. The walls of the bunker are provided
with steep slope so that the stored lignite will flow down smoothly by gravity.
The maximum height of bunker is 11.5 m. 31 needle gates in two layers 16
in the top and 15 in the bottom can be inserted at the bottom of either side
of hopper to isolate the hopper, and hence totally 186 needle gates are to be
inserted for complete isolation of the bunker before any maintenance work
is carried out at boiler bunker bottom.
One of the frequent problems encountered in the lignite fired boilers is
interruption of lignite supply to the mills to lignite choking in bunkers. This is
eliminated as the inner walls of the bunkers are lined with material KALEN
1006 (10 mm thick), which has anti -Sticking property.
42
7. Check the beater wheel door, seal between resuction duct and mill
door for any lignite powder leakage i.e. Puffing.
8. Check the mill inspection door openings, access cover for leakage
of lignite powder.
9. Check the oil temperature in bearing housing.
10. Check the mill outlet temperature i.e. 120-180ºC.
15.6 Periodical inspection
The interior component of the mill, especially the beater plates are likely
to have wear during operation and hence need periodical inspection. It is
recommended to arrange for such mill inspection at a time when the
respective mill is out of service i.e. kept as standby.
15.7 Fire hazards in mill
If there is a sudden increase in mill exit temperature (>250ºC) when the
lignite flow to the mill remains unchanged a fire in the mill may be suspected.
This may be prevented by controlling AMT viz.
1. By increasing mill hot air flow .
2. By increasing lignite-feeding rate.
Caution is to be taken against admission of cold air into the system. No door
or covers of the mill should be opened. In case the fire could not be put off,
the mill is to be stopped. In case of fire in the classifier, the respective mill
should be stopped. The fire inside classifier is allowed to continue so that the
trapped dust is burnt out. In order to prevent overheating, exterior portion
the mill may be pinched with water.
15.8 Shutting down the mill
The mill may have to be stopped in case of any one of the following:
1. During planned shut down of the unit
2. For partial load reduction in the unit
3. For carrying out preventive maintenance of the milling system
4. During break down of the mill.
During normal planned shutdown of the mill, the feeders should be stopped
first and then the mill should be emptied. When the mill is to be released for
45
The beater wheel mill adopted in stage-II steam generators are of EVT, type
110-60 self induced suction beater wheel mill ,N-Beater wheel mill suitable
for grinding the coals with moisture content up to 70%. 110- number
denoting twice the mill nominal through-put in metric ton/hour 55t/hr. 60-
number denoting one tenth of mill speed in revolution per minute.
The Beater wheel mill functions simultaneously as a pulveriser and as fan
wheel. They are designed for heaviest loads and roughest operation. An
electric motor of rating 3Ø, 6.6 KV, 600 KW, 600rpm drives the mill through a
fluid coupling. The beater wheel mill mainly consists of 1) flue gas resuction
duct 2) mill door section 3) beater wheel and its casing4) Bearing and its
lubrication 5) drive and its coupling 6) classifier 7) mill spring foundation
The mill door section is intended to receive the lignite preheated by hot gas
and distributes it around the inner edge of the beater wheel plates. This
section consists a mobile housing, seal collar, traveling gear and the beater
wheel protection device.
16.3 Beater wheel and its casing
The lignite size is reduced to predetermined value along with permissible
moisture. The hot gas drawn from the furnace mixes with lignite and heat it
till it reaches the beater wheel. This heating of lignite makes thermal
disintegration of lignite particles. When this mixture gets distributed around
inner edge of the beater wheel plates, impact and attrition action between
lignite and the beater plates effects the pulverization by which a large portion
of the internal moisture of the lignite being ground is simultaneously
released.
16.4 Bearing and lubrication system
The overhung beater wheel mill shaft is supported through two numbers of
self aligning roller bearings. The bearings are kept in a bearing housing which
acts as oil reservoir.A mill shaft driven lub oil pump is installed in the bearing
housing. In addition, a motor driven lub oil pump is provided. The discharge
of both pumps connected to form a single line. The flow of lub oil is directed
by using a flow diverting lever. In each line, a filter, and a lub oil cooler are
installed.Auxillary-cooling water is used in each oil cooler as a cooling
medium.
16.5 Drive and its coupling
Beater wheel mill is driven by a squirrel cage motor manufactured by M/S.
BHEL, India. Each motor has a rating of 3 phases, 6.6 KV, 600KW.It runs at
600rpm. The beater wheel mill is driven through a fluid coupling. This
coupling is mainly intended to reduce mill motor starting current as well as to
act as mechanical overloading protection for the motor. The torque from the
motor is transmitted by means of a closed circuit fluid stream from the
impeller to the turbine wheel. This fluid circuit is contained in a chamber,
which consists of the running wheels and the coupling casing. A flow is
necessary for a transmission of torque, and this is produced by a difference in
48
rotational speed between the impeller and the wheel, which is known as slip.
As a result of this slip the coupling gets warm up in operation.
The major bulk of feed water is taken from condenser and pumped to the
deaerator by the condensate extraction pumps. The dearator where dissolved
oxygen in water is removed acts as the suction vessel for the boiler feed
pumps. Three numbers of feed pumps of 400m 3/hr capacity each are
provided in each unit. Two out of these three pumps will be in service taking
water from dearator at 161°c and supplying it to the boiler through 2
numbers of high-pressure heaters, where the water is heated to a
temperature of 245°c using steam. The feed water then goes to feed control
station where the quantity of water required to be supplied to the boiler is
regulated according to the drum level. The water then flows to the
economiser and gets heated further.
4.1 Economiser
The feed water from feed water control station is preheated further in the
non-steaming economiser located at the top of the furnace. It consists of two
stages viz. economiser1 and economiser 2 kept one below the other. In
economiser1, the feed water travels downwards as against the upwards flow
of flue gases thus adopting a counter flow pattern, where as in economiser 2,
feed water and flue gases travel in upwards direction (parallel)). There are
112 coils of tubes in each
50
stage. The temperature of feed water is raised from 245°c to 330°c. The
drum water taken can be circulated to inlet header of Eco-2 by a line called
eco- recirculation line. The feed water comes from the outlet header of eco-2
through 2 pipes, forming a common header below the drum called feed
manifold. From the feed manifold feed water enters the drum through 22
pipes.
4.2 Circulation system
The preheated feed water after economiser enters the circulation system. It
consists of a drum, 84 down comers, 12 bottom headers, 688 water wall
tubes, 5 top headers, and 112 over flow pipes. The rate at which water is
supplied compared to the steam generated is represented by the term
“circulating ratio”. Its value is 7.
4.3 Boiler Drum
The boiler has a single drum mounted on top with its centerline at 79.9 meter
level. The drum is of about 1.8 m and 15m length. The shell thickness is
135mm at top half and 150mm at its bottom half. It is designed to with stand
a maximum pressure of 180 ata. And its operating pressure is 167 ata. Two
numbers of steel rod of 125mm fixed to the column above support the drum.
This arrangement, which provides free expansion, is known as hanger
suspension. Water fed to the drum is taken out through 84 down comers. The
water and steam mixture raising up from the water wall tubes enter through
112 over flow pipes into the two wet steam chambers of the drum. Steam
and water are separated by 72 cyclone separators, of which 36 are connected
to the front and another 36 to rear wet steam chambers. The steam then
goes to the steam chamber at the top of the drum and water goes to the
bottom of the drum.
4.4 Down comers
84 down comers pipes from the drum are connected to four main down
comers through which drum water travels down. The four main down comers
located one in each corner of the furnace branches off into 22 smaller pipes
each at the bottom and join the bottom headers. 5 headers are arranged in
three elevations in left and right side and one header for front and rear side.
Water wall tubes emanate from these 12 bottom headers.
51
Steam at a temperature of 405°c leaving the SH1 outlet header in two pipes,
one on left and one on right side travels through desuperheaters on its way
to SH2 inlet header. Feed water taken just before feed water control station at
a temperature of 245°c is used as spray in the desuperheaters to control the
steam temperature and bring it down to 389°c
5.2 Superheater II
Finally the steam travels through SH3 coils comprising of 2 coils of 16 tubes
each. It forms single loop, increasing steam temperature to 540°c. parallel
flow pattern is adopted in this super heater section.
6.0 REHEATERS
Since the maximum temperature of super heated steam admitted to the
turbine gets restricted to 535-540°c range because of metallurgical
constraints, in high pressure units, it is customary to have reheating
arrangement to improve cycle efficiency as well as to ensure that the steam
expansion will not be too wet steam after expansion in the high pressure
turbine is taken off to the reheater sections arranged in the boiler furnace
and heated to the initial temperature itself before admission to the
intermediate pressure turbine. In these steam generators, single reheating is
done before I.P turbine only. Two reheaters is
through two cold reheat pipes and enters the inlet of reheater 1 at a pressure
of 37.1 kg/cm2 and temperature of 342.7°c .The steam flow will be about
596.7 t/hr.
In reheater1, there are 56 coils of 10 tubes each. Counter flow takes place in
double loop. Reheater 2 consists of 56 coils of 5 tubes each. Parallel flow
pattern is adopted here and the steam temperature is raised in this stage to
540°c from here, steam at a pressure of 36.01kg/cm2 and at temperature
540°c flows through two hot reheat pipes to the I.P turbine.
7.0 SAFETY VALVES
To safeguard the pressure parts against hazardous pressure increase, 9 safety
valves are provided out of which 3 safety valves are at top of the drum, 2
safety valves on main steam lines, one safety valve on cold reheat lines and
3 safety valves on hot reheat lines.
All the safety valves are of direct spring loaded type and one of the safety
valves on the main steam lines is of electromatic safety valve. It could be
opened/closed through solenoid operated valves. The set pressure of all the
safety valves for opening are as under
Relieving
Equipment Opening pressure
capacity
Safety valve 1 181.0 Kg/cm2 183.5 T/hr
Safety valve 2 183.0 Kg/cm2 187.0 T/hr
Safety valve 3 185.4 Kg/cm2 189.0 T/hr
Safety valve 4 168.4 Kg/cm2 166.5 T/hr
Safety valve 5 165.9 Kg/cm2 104.0 T/hr
Safety valve 6 50.0 Kg/cm2 200.0 T/hr
Safety valve 7 47.25 Kg/cm2 157.0 T/hr
Safety valve 8 47.72 Kg/cm2 158.7 T/hr
Safety valve 9 48.67 Kg/cm2 161.9 T/hr
AIR CIRCUIT
General arrangement of AP fan (Axial profile)
The stage two boilers, AP type fans are chosen for FD fans balanced draught
system. The AP fan consists of
1. Suction chamber
54
2. Impeller housing
3. Main bearings
4. Rotor with adjustable blades
5. Pitch control unit
6. Guide wheel housing with guide vanes and
7. Diffuser
Suction chamber
The fan suction is of double inlets with wire mesh coverings. The suction
chamber is made of fabricated walls with rectangular as well as circular in
cross sections. The rectangular one connects fan suction point and the
circular one connects the impeller housing by flexible expansion joint.
Impeller housing
It is a casing having accurate inner dimensions so as to have close
tolererance. The casing is horizontally split to provide easy inspection and
maintenance. Profiled hollow stiffeners are provided for routing oil pipes,
cables. The hub of the inlet housing, core of the fan housing and of the guide
wheel housing, the pitch control mechanism in the diffuser core and the shaft
protection tubes in the inlet bend are mounted within to protect the main
bearings, pitch control mechanism
Main Bearings
The fan rotor is supported on cylindrical roller bearings assembled in bearing
housing. An angular contact ball bearing is assembled along with cylindrical
roller bearing on drive side to absorb axial thrust. The monoblock bearing
housing is bolted to the bearing supports in the fan housing assembly. These
bearings are lubricated and cooled by a lub and control oil system. The shaft
passages in the bearing housing are sealed off radial sealing rings with a
labyrinth seal.
The main shaft is a forged piece with a tapered end for accommodating hub
disc, one end of the fan shaft is connected to the intermediate shaft and on
free end impeller is mounted. In the free end of fan shaft, impeller hub is
mounted. The hub has 23 blades assembly, which are fixed, on its periphery.
Each blade assembly consists of a blade, a blade shaft and a blade shaft
bearing. At the end of the blade shaft, a cranking lever is fitted. Each blade
assembly is rotated freely on its shaft bearings. All the blade assemblies are
connected to a slide pad. It is a disc with a groove in its periphery. Suitable
rotating units are fixed to these grooves on the periphery where cranking
levers of all blade assemblies get connected. When slide pad moves
horizontally, then this horizontal movement is converted into rotary
movement of blades simultaneously through equal rotation.
Pitch Control Mechanism.
The pitch control mechanism comprises of a hydraulic servomotor and an
external actuator connected to hydraulic servomotor. Hydraulic servomotor
consists of a cylinder assembly and piston assembly. The cylinder assembly is
mounted on the fan impeller hub. It houses piston assembly. Whenever fan
rotates, the cylinder assembly together also rotates. The piston assembly
comprises of a control rod, a control slide and a piston integrated with the
slide pad. The control rod is of stepped shaft with three drilled holes in its
axis. Out of three holes, one is to supply oil, the other is to return the oil and
the third is to drain leak off the oil. This control rod is kept on bearings, which
are housed inside the control slide, so that the control rod can slide inside the
control slide freely with a help of an external actuator. This actuator consists
of mechanical linkages, and the links are actuated by pneumatic drive, and
provision is also available at local to operate manually. The supply, return and
drain oils to the control rod are made through flexible hoses in this system.
Outlet guide vane unit
It is a fabricated and machined casing with guide vanes. This unit is also
divided along the axis and connected to the impeller casing as well as
diffuser assembly through flexible joints.
56
Diffuser
Diffuser is also a fabricated assembly stiffened with ribs and flanges. It is
supported on the foundation plates through welded feet. It consists of
a casing and a core. This assembly is isolated from the ducting by means of
flexible joints.
Rigiflex coupling
The fan shaft is coupled to motor shaft with rigiflex coupling. This coupling is
all steel coupling designed to compensate mounting and operating
inaccuracies.
GAS PATH
Furnace in the boiler is of single pass design with more or less square in cross
section. All heat transfer elements are located one above the other and the
air heaters in the flue gas path before ESP . The furnace is made to form tight
enclosure using membrane type water walls. The left and right side walls of
the furnace are vertically straight and at top of the furnace, the left and right
side walls make”L” bend thus forming the roof of the furnace. At the bottom,
front and rear water walls form a hopper portion from 16.5 m elevation to 7.9
m elevation to facilitate collection of slag and unburnt lignite over the beds of
after burning grates.
The gas travels upwards in the furnace and reaches 8 metre diameter gas
duct through a rectangular opening of 11500x6000mm at 74.4m level in the
rear top of the furnace. In this zone,rear evaporator wall tubes overlap with
each other to give way for flue gases to travel to second pass.
SH1, SH3, RH2, SH2, RH1, ECO2 and ECO1 are engaged one after another in
gas flow path in the furnace. Evaporator tubes are bent to form wall box to
accommodate the following essentials in the related areas of the furnace.
1. After burning grate’s opening bottom 1 nos
2. Oil burners 4 nos
58
Suction chamber
The fan suction is of double inlets with wire mesh coverings. The suction
chamber is made of fabricated walls with rectangular as well as circular in
cross sections. The rectangular one connects fan suction point and the
circular one connects the impeller housing by flexible expansion joint.
60
Impeller housing
It is a casing having accurate inner dimensions so as to have close
tolererance. The casing is horizontally split to provide easy inspection and
maintenance. Profiled hollow stiffeners are provided for routing oil pipes,
cables. The hub of the inlet housing, core of the fan housing and of the guide
wheel housing, the pitch control mechanism in the diffuser core and the shaft
protection tubes in the inlet bend are mounted within to protect the main
bearings, pitch control mechanism etc from high temperature gas.
Main Bearings
The fan rotor is supported on cylindrical roller bearings assembled in bearing
housing. An angular contact ball bearing is assembled along with cylindrical
roller bearing on drive side to absorb axial thrust. The monoblock bearing
housing is bolted to the bearing supports in the fan housing assembly. These
bearings are lubricated and cooled by a lub and control oil system. The shaft
passages in the bearing housing are sealed off by radial sealing rings with a
labyrinth seal.
Rigiflex coupling
The fan shaft is coupled to motor shaft with rigiflex coupling. This coupling is
all steel coupling designed to compensate mounting and operating
inaccuracies.
pumps each of having capacity 200 lpm at 20kg/cm2 located outside the oil
reservoir with suction line immersed in tank. Out of 2 pumps, one will be in
service, the other is standby. In the discharge line of each pump a pressure
relief line is taken and connected to the oil reservoir. After this, these delivery
lines join together carrying oil to the cooler unit. Before the cooler unit a
pressure reservoir is mounted in order to absorb the pressure peaks during
initial start up of the pump.
The oil-cooling unit consists of two oil coolers, which are kept one below the
other. Each cooler cools the incoming lub and control oil with the help of
auxiliary cooling water. The cooled oil from the cooler is taken to a filtering
unit. There are two filters unit, and one will be in service and the other
standby. The oil after the filtering unit divides into two, one line feeding oil to
the pitch control unit and the other line feeding oil to main bearings after a
pressure reduction done at pressure control unit
Silencers
Fans are major noise producing equipments. Silencers provided in the suction
and discharge ducts of the forced draught fans. The silencers employed at
the discharge ducts of ID fan are of absorptive silencer, consisting of
perforated rectangular plates packed with mineral wool.
Cooling air fans
Induced draught fans handle high temperature gas. The hot gases may heat
fan shaft, bearing housing as well as pitch control unit. In order to avoid such
heat transfer to above components, supply of cooling air is resorted to. Each
induced draught fan is equipped with two cooling air fans, one will be in
service, the other reserve. The cooling air is blown over parts, so as to
prevent heat transfer from gas.
Guillotine damper
Guillotine type of discharge damper is provided at the discharge of ID fans.
This type of dampers are selected to have complete isolation of ID fans for
maintenance works, when the other fan is in service. This damper consists of
a frame work connected to discharge on one side and silencer on the other
side. The frame portion is supplied with atmospheric air by means of gate
63
SCAPH specification
No. of SCAPH/boiler Two
Manufacturer M/S C.Doctor & Co
Type finned tube type2
Construction type horizontal
64
Air preheaters are provided with octagonal casing to enclose the rotor. The
housing panels of eight fabricated sections of height 2.41metres are bolted
and welded to the hot and cold end connecting plates to form an integral
structure. There are two main pedestals and two side pedestals each
consisting of two support feet for transmitting the entire air heater load to
the support steels.axial seal plates of the axial sealing system are also
secured to the main pedestals.the expansion arrangements help to support
the heater on a horizontal plane and to permit the housing to expand freely
during hot condition of heaters.
Connecting plate center sections
The upper connecting plate center section is located at hot end of the air
heater, mainly houses guide bearing and bifurcating sector plates which
carry the radial sealing system components. The lower connecting plate
center section is located at cold end which carries the support bearing
thereby the load of rotor and the radial sealing system called cold end sector
plates.
Rotor and heating elements
The hollow post of the rotor bolted to rotor form the rotor shaft. The
verticality of the shaft and also its centering between connecting plate splits
keep the rotor in level and at proper elevation. The rotor is radially divided
66
There are two-drive motors AC motor. The AC motor of rating 3 phase, 415V,
11.0KW, 1450rpm, and 20.5amps.a common reduction gearbox with speed
reduction ratio of 110.7:1 is kept for these motors. A bibby coupling couples
the A.C motor and gearbox where a fluid coupling is present to transmits the
drive
Sealings
In the air preheater air is under pressure in the airside and flue gas is under
vacuum. This static pressure differential makes the air to leak in the gas
stream. This leakage air decreases the gas temperature and increases the
FD/ID fan loading. Hence prevention of air leakage to be ensured at all points.
The sealing arrangement consists of radial seal, axial seal circumferential
seal rotor post seal axial seal plate to sector plate static seal. They have been
devised to minimize air leakage to gas stream in the air preheater.
Bearing-lubrication and cooling system
The vertical rotor shaft is kept installed over two bearings namely support
bearing and guide bearing. The support bearing is provided at the bottom of
the rotor shaft. The bearing is of the self-aligning type. The support bearing
gets its lubrication oil from the support bearing beneath it. It is capable of
holding 150 liters of oil.
The guide bearing is located at the top of the rotor shaft. This bearing
provides the radial location to the rotor and permits its thermal expansion in
the axial direction. Guide bearing is designed to take up a large expansion of
67
the rotor post and also to carry the in board end of hot end sector plate for
tracking. This is spherical roller bearing capable to house 20 liters.
Cleaning device
Since the heating elements are compiled very lightly, the fly ash particles are
deposited over them. Such deposits not only increases the resistance for flow
of air and gas, but also corrode the heating elements. Inorder to remove
these soot and ash deposits, cleaning device is resort to.
In air preheater, a steam soot blower is installed at the bottom in the gas side
only. The cleaning device consists of a motor coupled to a gear driven crank
mechanism, which oscillate the swivel header carrying the nozzle pipe. There
are two nozzles at the end of nozzle pipe. The nozzles are facing upwards i.e.
the cold end of heating elements. A rotary point in the supply line permits
free motion of the swivel header while connected to the source of steam.
Steam for RAPH is obtained from auxiliary steam header or from internal
source(PRDS)at 70 metre level.RAPH soot blower is driven by a motor of
rating 3 phase,415V,0.18KW,1360rpm,0.65Amp.
Washing device
Air preheater fires start, initially with the ignition of combustible deposits
within, the heat transfer surface. This initial burning may occur within the
cold or hot end heating elements depending on where the deposit build up
occurs.
Two water lines from thermal power station’s fire water system are tapped in
each boiler area, one for RAPH’A’ and the other for RAPH’B’. Each tapping has
a common isolating valve near RAPH and then it gets divided into two. One
branch is entering into the hot end and the other two cold end of gas side of
RAPH .the hand operated valve and strainer are provided in each branch.
It is a device, which is used to give a signal when the rotor is slowed down or
stopped. It is not advisable to stop the rotor in hot condition since the heat
elements are subjected to hot gases on one side and cold air on the other
side. This may cause unequal expansion of the rotor and pose problem for
restarting of the rotor.
Principle of operation
This consists of control unit, vane operated limit switch and three vanes
mounted on the support trunnion. When the RAPH is at normal speed, the
vanes pass through the limit switch causing the control unit to deliver no
signal to alarm unit. if vanes fail to pass within the set time interval a relay in
the control unit will give signal to the control unit to alert the operating
person that the rotor is slowing down.
69
Soot blowers have been widely used as efficient tools of cleaning exterior
portion of boiler tubes. The requirements of soot blowers are
1.effecting cleaning
2.reliability
3.easy maintenance
4.low cost in operation & maintenance.
The types, size, number of blowers required, their locations, nature of
blowing medium, pressure of blowing medium and the periodicity of the
operation are decided taking in to consideration the design factors of the
boiler, the fuel used and the nature and quantum of deposits etc.
Normally one of the following is used for soot blowing medium.
1. Compressed air
2. Saturated or super heated steam,
70
3. Water.
SOOT BLOWER TYPES:
1.fixed position blowers,
2.short-retactable blowers and
3.long retractable blowers.
Fixed position blowers are those, which are fixed permanently inside the
boiler. There are two types namely fixed non-rotary and rotary. Fixed position
rotary blowers are installed only in low temp region. Non-rotating fixed
position blowers are specified for hard to reach areas of the boiler where fly
ash can accumulate and cannot be removed by normal gas flow.
In higher temp Zones, where temp is 960°c and above, the soot blower gun
cannot be allowed to remain inside the furnace and hence retractable type
blowers should be used. Wall blowers or small blowers or short retractable
are used to clean the furnace walls. Their nozzles penetrate for a small
distance beyond furnace wall and rotate 360° covering a circular area of tube
surface around it.
Long retractable blowers are installed for cleaning tube-banks in the high
temperature zone of the boiler. They have two opposing nozzles at the end of
the lance, which is designed to penetrate half the boiler width or full width in
case of smaller furnaces.
The Boilers of thermal power station-II/II stage employ three different types of
soot blowers and two different media. The evaporator tubes are provided with
water soot blowers utilizing the service water at a pressure of 12 to 14 bars
as the medium. They are short retractable blowers extending into the interior
furnace wall by about 350mm and are provided with two different speeds and
water lance system.
The super heater and reheater tubes are cleaned by super heater steam as
the medium. The blowers employed there are long retractable type blowers.
For cleaning the RAPH deposits, wall mounted lance type blowers are
provided at cold end baskets of RAPH.Though they can be classified as fixed
position lance type, since they are always kept inside, these blowers are
71
provided with a swing action to ensure effective cleaning of the entire RAPH
elements.
With hard-bonded deposits expected on the water wall section, water jet de
slaggers (soot blowers) have been chosen for this section. In addition to high
impingement forces, water blowers provide the added feature of thermal
shock, which aids the removal of the deposit through shock cooling and
cracking. The
blower speed, insertion and retraction speed, water pressure and jet nozzle
diameter are to be selected so as to prevent any adverse effect of thermal
stress due to water impingement directly on bare tube or dust coated tubes.
WATER SOOT BLOWERS
The water blowers are of type SK58E. They are retractable wall mounted
type. For cleaning the evaporator tube surfaces, 42 numbers of water soot
blowers are provided. Out of which four blowers were removed and water
lance blowers were installed in their locations. The remaining blowers are
located at eight elevations, 12 blowers in each left and right side, and 7
blowers each in front and rear side of the boiler furnace.
The service water for blowing is supplied at a pressure of 12 bar with one of
the two pumps available at zero ML. the rate of consumption of water per
blower is 416 kg and the rate of consumption per hour is 4068 kg. Each
blower covers a radius of 2500 mm effectively cleaning the evaporator tube
surface around the particular blower. As and when the blower is operated the
nozzle tube of the equipment moves into the furnace by 700 mm and returns
back to its original position. The water jet coming out of the single nozzle
cleans the water wall tube surface.
OPERATING PRINCIPLE OF THE BLOWER
The soot blower nozzle is normally kept outside the membrane walls. When
the soot blower motor is started, the motor runs at high speed. The rotary
movement transmitted by the gears and screw socket causes the threaded
nozzle tube to move helically forward into the furnace chamber at a high
speed. As soon as the nozzle has passed the tube wall sufficiently, (i.e. about
350 mm travel on reaches `start’ blowing position), the blower valve opens.
At this position, the motor speed is changed over to low speed by a time
72
relay. The nozzle tube advances slowly to its front-end position (i.e. another
350 mm travel). Water will be coming out throughout this phase of operation,
but at different velocities.
On reaching the front-end position, the motor direction is reversed. At the
same time the speed also gets changed over from low to high speed. The
entire return travel (i.e. 700mm) of the nozzle tube is at a higher speed.
During the return travel, the blower valve will be closed fully only when the
spray nozzles passes the position “ start of blowing”.
The water jet escaping the nozzles obliquely backwards impinges on the tube
wall in a small tapered angle. Due to this small angle and to the low pitch of
the screw tube (20 mm per rotation), it is ensured that the water jets are
overlapping each other several times.
The soot blowers should normally be operated in sequence in the direction of
the flue gas stream. The duration of operation of each blower is 12 minutes
which is distributed as follows:
Forward fast travel 120 seconds
Forward slow travel 360 seconds
Backward fast travel 120+120 seconds
Blowing time (360+120) seconds
= 480 seconds
The total operating time of all the 38 blowers in sequence will be 7 hours and
36 minutes.
The frequency of blowing depends on the rate at which deposits accumulate
on the heating surfaces. The correct frequency of blowing can only be
established from continuous observation of the deposits and checking of the
steam and flue gas temperatures.
If the water blowers are used rarely, they should still be put into operation
once a week without admitting water to keep the moving parts, especially the
electric drive, in good working condition.
Soot blower pumps
A multi stage centrifugal pump with horizontal shaft supplies the water
required by soot blowers and these pumps take their suction from the service
waterbus at 3.5 bar. The pumps are designed with a suction head of 1.6 m
73
rear end, the BACKWARD limit switch gets pressed and the blower gets
switched off. On completion of operation of all blowers
1) The isolating valve is to be closed
2) The pump is to be stopped
NOTE:
1.In manual mode, only one blower can be operated at a time.
2.The running blower can be retracted for emergency by pressing
BACKWARD limit switch at local.
3.Another forward travel can be initiated only after the blower reaches
the rest position.
NOTE:
1.The blower which is already having a fault will be skipped during
automatic programme if not selected.
2.If a fault occurs on the operating blower during the automatic
programme run,
a) The running blower retracts immediately.
b) The nature of the blower is indicated (e.g. over current, limit switch
fault, running time fault etc.) in the panel with flashing light.
c) Accept the alarm.
d) When the blower reaches the rest position, on pressing the ‘reset’
push button it restarts the automatic sequence and the next blower will start
operation.
Water supply fault
1. Water supply fault appears if pressure does not develop within 85
seconds from starting the water-filling programme. On accepting the
fault, the annunciation gets cancelled.
Limit switch fault:
This fault occurs on any one of the following four conditions.
1.When ‘ forward’ command is given but the blower does not leave the
backward limit switch with in 10 seconds. This may happen due to one of the
following reasons.
a) MCC switch OFF or fuse failure at MCC.
75
NOTE:
To protect the nozzle tube from softening or bending, it must be cooled
by water as it travels forwards and backwards within the boiler. It is to be
ensured that the blowers are operated only when the pipe system is on-
78
pressure. Generally a pressure switch and the function of the blowing valves
monitor the water pressure by a water flow switch.
11. Periodical inspections are to be done to ensure that
i. There is no water leakage during operation from any
connection.
Capacity y : 24 m3 /hr
Pressure : 21.0 kg/cm2
Drive motor : 3, 415 v; 27kw ;2900
rpm.
The Soot blowers are RKS 81E of long retractable lance type blower employed
for cleaning the super heater, reheater and economizer tube banks. Though
provision is made for sixty blowers at present 42 blowers ,21 on the right and
21 on the left provided for cleaning in 7 elevations,6 blowers are thus in each
elevation 3 on each side .Blowers are located at the following places
Elevation location.
45.4 meter SH3 Middle
50.49 meter Between RH2 & SH2
53.38 meter SH2 Middle
58.95 meter RH1 Middle
64.35 meter Between Economiser bottom and RH1 bank
67.84 meter Between Economiser bottom and Middle bank
71.31 meter Between Economiser middle bank and top bank.
80
The medium used is superheated steam at 16 bar pressure .The steam can
be taken from the inlet header of reheater 1 after due pressure reduction or
from auxiliary steam header. The consumption of steam per blower is 809
Kg .The consumption rate per cycle is 11.16 Kg/Hr for 2 blowers. Duration of
operation of one blower is 9 minutes and 3 seconds. Total time for completion
of one cycle is 3 hours 10 minutes and 3 seconds.
PRINCIPLE OF OPERATION
Two blowers in each tier, one at right and one at left will be simultaneously
operated. Each blower will cover about half the furnace width as they travel
in. The blower has a lance tube with two ventury nozzles through which
steam is blown on the tube bundles around the particular blower .The lance
tube will be moving into the flue gas pass, with a rotating movement and
then returns back to its original position. During this the nozzles perform a
helical movement. The advancement of the lance tube per revolution can be
adjusted on the basic of the spacing of the heating surfaces. The two
opposed nozzles and the spreading blowing jets ensure complete cleaning
coverage during the whole movement of the lance tube.
STEAM SUPPY ARRANGEMENT
The blowing medium can be taken either from Reheater 1 inlet header or
from auxiliary steam header. From RH1 inlet header, steam at a pressure of
about 36-37-bar pressure is reduced to 16 bar and taken to the common
header. A safety valve is provided in this header to take care of system
pressure.
The steam line is then bifurcated and goes to right and left side of the
furnace for soot blowers.
Working cycle of the steam soot blower
81
Before starting, the carriage is in rest at its rear end position .The lance tube
is completely drawn off from the boiler and the nozzles will be outside the
vertical tube walls of the boiler. When the motor is started the lance tube
starts rotating.
At the same time, the carriage releases the rear limit switch moves
forward on two track beam rails and projects the lance tube into the flue gas
pass. Just when the nozzles enter inside the furnace gas path, the trip pin on
the perforated bar will be hitting the cam and actuating the steam valve to
open. Steam gets admitted through the nozzles and cleans the tubes around.
During the forward travel of the carriage, the feed tube support is actuated
and that provides the intermediate support for the feed tube, while the lance
tube is moving far into the furnace .As the blower carriage moves forward,
the cable carriage follows and moves by half the distance.
The carriage continues to project until the nozzles reach the front end
position reaches the front end position and reverses the direction of rotation
of the motor Due to reverse rotation the blower lance now start retracting.
During the reverse travel the feed tube support gets disengaged. Shortly
before the nozzles reaches the boiler wall the blower valve closes and cut off
the blowing medium. The rear end limit switch cut off the supply to the motor
as soon as the lance tube comes to the original rest position. Simultaneously
the cable carriage also retraces and comes to the original position.
Operation of steam soot – blowers.
The operating time for each pair of blowers is 543 seconds.
The total duration of operation of all steam soot blowers will be 543 X 21 =
11,403 seconds or 3 hours 10 minutes and 3 seconds .On the basis of
experience gained during operation, selective operation of necessary to use
all the soot blowers for one cycle.
Periodical inspection of soot blowers operation.
During the operation of the soot blowers, the following should be checked
periodically.
82
Whenever the soot blowers are kept idle for longer period, the soot blowers
shall be started once in two weeks in order to check the operation of the
motor and the equipment.
Whenever the soot blowers are kept idle for longer periods or when any unit
is repaired, then the valves of the responses of pressure & temperature
protection as well as the interlocks are to checked.
Before planned shut down of a boiler, the soot blowing shall be performed.
During shut down of the boiler, the tubes in the surrounding of the soot
blowers should be checked for any wear. If any bright spots or erosions can
be seen on the tubes, the number of cycles of operation shall be decreased.
The steam –pressure in the lance tube of the soot blowers can also be
decreased as much as.
Problems in soot blowers and their elimination.
If and when the soot blowers, gets tripped at the middle of operation, due to
some mechanical defects, the soot blowers overload relays will respond and
move the carriage block back as long as it arrives into original end position.
If the steam pressure decreases during operation, then the soot blowers
should be brought back by means of the hand-wheel placed on the rear shaft
outlet of the driving motor after switching off supply to the motor.
Steam must not be shut off from the soot blowers as long as the carriage
does not come back to the rear end rest position.
If the soot blower drive, over runs the rear limits –switch, the motor will not
get tripped and hence the lance tube will be in rotation .The longitudinal
movement, however will get terminated since the pinion will come out of the
gear rack breaking contact. In such a situation.
The motor should be switched-off
83
The carriage should be physically moved and the pinion of the carriage and
the gear rack should be engaged.
The carriage should be brought to original position by operating the hand
wheel.
The limit switch should be checked for operation. The failure of electric
system should be eliminated.
If the front limit switch did not work and the motor did not reverse, the
carriage will bring the soot blower to stop at the end of the rail. The
longitudinal movement will be now terminated but the blowers continues to
rotate. In this case the following operation will have to be carried out.
The cooling of the lance tube of the soot blower is to be done by ensuring
steam supply to the blower
The motor should be kept in continuous services, till the carriage is brought
to original position
The timing device in the local control box will commence the return
movement of the carriage by changing motor direction. If this does not take
place it can be initiated from local control Board.
After bringing back the carriage to its original position.
Steam soot blowers –operating instructions.
On receiving the FORWARD command, the blowers travel in the forward
direction, which is indicated by FORWARD lamp. After about 270 seconds, the
forward limits switch gets pressed and the blowers comes back automatically
at the same speed, which is indicated by “ BACKWARD “ lamp .On reaching
the back position the BACKWARD limit switches gets pressed, the blowers
stops and “ ALL BLOWERS IN INITIAL POSITION” appears in the control panel.
WATER LANCE SYSTEM
Introduction
Any solid fuel generally contains in –combustible mineral matter (ash). On
combustion of fuel, this ash is separated. It also results in formation of soot.
They adhere over the heat transfer surfaces of the boiler and reduce the heat
transfer and subsequently the boiler efficiency. One mm layer of slag on a
boiler tube acts like a 6 mm layer of refractory.
84
The removal of such deposits from the heat transfer surfaces of a boiler is
imperative. The strength of the attachment of slag to the tubes is influenced
by temperature, physical contour of the surfaces, force of impact and melting
characteristics of the slag. The presence of ash with low melting points and
catalysts like sulphur, iron oxide and alkali metals, which lowers the ash
fusion temperature are the main factors quantifying slagging. Slagging is
usually associated with radiant heat transfer surfaces in and around the
furnace.
As per the design, the lignite ash of TPS –II has the following characteristics:
(i) Initial deformation temperature : 1050 to 1200 ºC
(ii) Hemispherical temperature : over 1200 ºC
(iii) Fluid state temperature : >1350 ºC
The water lance cools the opposite face of the furnace wall by means of
directing water jet through a specially designed high capacity nozzle. The
water jet directed on to the furnace wall where upon it follows a prescribed
and controlled impact pattern across the relevant surfaces. The horizontal
and vertical swiveling action of the blowing lance guarantees that the water
jet is uniformly directed over large areas. This precludes the needing for
numerous soot blowers. The stored programme in the control system makes
it possible to bypass critical sections of the furnace walls with the blowing jet
and also gives continuous monitoring of this facility. In addition, the control
system monitors blowing pressure, closing of blowing valve and spindle
movement to warrant careful cleaning action. Here cleaning of slagging in
entire water wall surface is meticulously programmed and stored.
The lance system is supplied by CLYDE BERGE MANN , GERMANY.
Principle of operation
The water lance soot blowers serves for removal of slag incrustations on the
furnace walls of boiler units that are fired with brown coal. A concentrated
water jet crossing the furnace and hitting the slagged water wall area, during
the boiler units operation performs the cleaning. While the water jet impinges
the slagging area, due to high kinetic energy, it hits the fouling area. Also the
water jet penetrates the slag through pores in it and quenches the slag in the
process. It creates a difference in thermal expansion at contact area between
the water wall and slag material. Also due to evaporation effect, the slag
physically enlarges in volume, causing it to expand and lose its adherence to
the tube. It results in dislodging of slag from the furnace wall. Hence the
water jet should penetrate across the thickness of the slag, then only it can
create a difference in thermal expansion. If the depth of slagging is more, the
quenching effect of the slag will not reach the entire depth. In that case
dislodging is difficult.
Arrangement of lance
The combustion zone of the boiler furnace is divided in to two sections
vertically (from 17 to 31 meters elevation and 31 to 40 meters elevation)
and along the center of sidewalls so that the whole combustion zone is made
as four parts. A lance does the cleaning of each part. There are four water
86
lances installed in each boiler (7x210MW) in TPS-II. The lances are mounted
in front and rear water walls only at 27 m and 33 m elevations at the centre
of the wall. Each lance will take care of cleaning of slag on the opposite wall
and opposite side of each water wall.
The water lance blower’s frame is firmly connected to the boiler wall. It is
composed of two parallely aligned and vertically standing box profiles, which
are firmly bolted to both the horizontal- interconnecting frames. The vertical
shaft slides over the two parallel horizontal shafts mounted at top and bottom
of it.
The top horizontal guidance shaft is driven by a worm gear motor flanged to
the frame at the right side. The movement of the bottom guidance shaft is
transmitted through a chain, which is enclosed in the right side vertical
frame. The vertical guidance shaft is driven by another worm gear motor
flanged to the vertical guidance mechanism provides the water lance soot
blowers stability, serves to precisely fix the horizontal guidance’s, to fasten
the water lance blower to the furnace wall and to receive all further sub-
assemblies.
The guidance mechanism consists of a guidance tube, a threaded spindle
with spindle nut and dog. The guidance tubes are protected against dirt by
expansion bellows.
The movement of the lance in the horizontal direction is monitored by the
pulse transmitter mounted at the end of horizontal guidance shaft. The
movement of the lance in the vertical direction is monitored by the pulse
transmitter mounted at the bottom end of vertical guidance shaft. These
speed sensors are inductive proximity switches (Non Contact type).
On the boiler side, the lance tube is firmly connected to the connection
boxes, by cordon joint via a blow through tube for protection of the nozzle. A
blowing tube guidance bush is connected to the vertical guidance shaft.
Lance blowing tubes movement is realized via the blowing tube guidance
bush. The lance tube just slides inside the guidance bush. At the other end of
87
the lance blowing tube a swivel joint, which is provided with ball bearing so
that it adjusts itself with the connecting entry.
The entire cleaning path of water jet of the lance system is programmed in
software. The programmed control guarantees the adaption of the blow figure
to the geometrical shape of the furnace, the control of water supply and the
monitoring function.
Two inductive proximity switches are provided, one for horizontal reference at
the right bottom and the other at the right top for vertical reference.
Water supply system
Source of water for lance operation is service water at 3.0 to 4.0 Ksc
pressure. The pressure is raised using 6/5- stage water soot blower pump.
Any one of the two water soot blower pumps will be in service. The discharge
of the water soot blower pump is connected to the suction of lance booster
pump. It is a 4 stage centrifugal pump.
The pump is provided with three motorized shut off valves, one at suction of
the pump, another at discharge and the third at bypass or recirculation line of
the booster pump. This system is installed in boiler zero meter elevation.
Water supply is made to individual lances through a connecting pipe system.
At each lance a hand operated valve, a strainer and a solenoid operated
blowing valve are provided. T o monitor the water pressure in the main line, a
pressure transmitter is provided before the hand operated valve of lance at
top rear wall. Four separate pressure transmitters are provided after the
blowing valve one for each lance.
Normally, a 13.3 mm nozzle is provided in the lance tube. It can also be
replaced with a 14 mm nozzle. The Lances are numbered as follows.
Rear wall top 33 meters elevation- 1
Bottom 27 meters elevation- 3
Front wall top 33 meters elevation- 2
Bottom 27 meters elevation- 4
88
4. Pressure after blowing valve is > Max. (12 bar) for more than 8 seconds
Probable causes of the fault
1. Pressure transmitter root valve closed
2. Pressure transmitter defective / cable defective / no continuity
3. Water line isolation valve closed
4. Pressure actually inadequate due to hose puncture etc.
5. Blowing valve limit switch cable shorted or earth fault
6. Limit switch / micro switch defective
7. Air supply problem
8. Solenoid valve / SOV cable / plug problem
c) Impulse trouble vertical
This fault appears if, the vertical impulse from speed (proximity) sensor
(Input I 0.0) is continuously logical ‘1’ or logical ‘0’ for more than 0.5
seconds after vertical (up / down) command (Q 13.0 or Q 13.2) is given.
i.e. if the interval between any two impulses of vertical motor proximity
sensor exceeds 0.5 seconds when vertical motor command exists, this
fault is set.
Probable causes of the fault
1. Speed (proximity) sensor is defective
2. Sensor gap more or not uniform
3. Sensor cutting plate damaged or bent or loose
4. Cable or termination defective
5. Vertical Motor not moving
6. Lance reached bottom end position due motor DOR reversal
7. Lance reached top end position but top reference point sensor has
not sensed
8. Vertical Motor gets overload due to mechanical or electrical problem
9. PLC output module channel defect
d) Impulse trouble horizontal
This fault appears if, the horizontal impulses from speed (proximity)
sensor (Input I 0.1) is continuously logical ‘1’ or logical ‘0’ for more than
0.5 seconds after horizontal (left / right) command (Q 13.5 or Q 13.7) is
given.
95
i.e. if the interval between any two impulses of horizontal motor proximity
sensor exceeds 0.5 seconds when horizontal motor command exists, this
fault is set.
Probable causes of the fault
1. Speed (proximity) sensor is defective
2. Sensor gap more or not uniform
3. Sensor cutting plate damaged or bent or loose
4. Cable or termination defective
5. Horizontal Motor not moving
6. Lance reached left end position due motor DOR reversal
7. Lance reached right end position but right reference point sensor
has not sensed
8. Horizontal Motor gets overloaded due to mechanical or electrical
problem
9. PLC output module channel defect
The cleaning effect of the lance system on the water wall surfaces has
to be monitored continuously. The frequency of soot blowing depends on the
type and extent of contamination of the heating surfaces. If the cleaning
effect is not sufficient, blowing frequency (number of cycles) and / or blowing
pressure or the amount of water (by changing the nozzle size) are to be
increased. Also frequency of electrical power supply to lance motor can be
reduced in frequency converter. If the blowing pressure drops below a
minimum limit value, the operation of the blower is not possible. It means the
water jet will not penetrate and quench the slagging across its depth.
SPECIFICATIONS:
Name : Water lance soot blower
Type : WATER LANCE BLOWER 90
(maximum swiveling angle)
Blowing medium : Service water
Blowing pressure : 16 bar
Operating range of pressure : 16 to 24 bar
Frequency of operation
of lance motor : 45/50/55 Hz
98
Mounting : B3
Power : 15 KW
Speed : 2935 rpm
Current : 28 amps
Voltage : 415 V
Ventilation :TEFC(Totally enclosed fan cooled)
Functions in Desk Operating Console
Name of the button : Function
F1 : Operation menu
F2 : Observe menu
F3 : Failure information
F4 : Spare
F5 : Release
F6 : Acknowledge Failure /Reset
F7 : ON/Open/Start
F8 : OFF/Close /Stop
When red LED lights up in desk operating console, it means communication
between control system &operating unit is failed. It can be restored by
switching the control system once from stop to run. (Module off/on once).
The operation status of valves (Suction ,Discharge and bypass valve , status
of booster pump) can be seen in desk operating console ( Opening, open,
closing, close, ON, Off)
The operation of the lance with running part figure is displayed when lance is
in operation.
At the starting of each lance operation main pressure is displayed in console,
afterwards blowing pressure of the blower in operation is displayed.
Rating : 75KVA,/59KW
Input A.C Voltage / Current : 415V/181A
Out put A.C Voltage /Current : 70KV/ 1A
3) Rapping motors
d) The flue gas entering the ESP being misty due to incomplete flue
combustion particularly at the time of initial boiler operation
Accumulation of such dust deposited not only causes reduction of
precipitator efficiency, but also result in unstable operation rapid corrosion
of electrodes and failure of insulators
Shut down
1. When the gas temperature drops to the acid dew point of the gas ,the
transformer should be switched off
2. The rapping motor, should be run for at lest 30 minutes after switching
off the power to the transformers
3. The fly ash evacuation system (Ash mixing Vessels) should be in
service until all the hopper are completely emptied
4. Only when the precipitator internals have cooled down to a safe level,
the access doors should be opened duly following the interlock
sequence . Access door must be opened with caution as hot ash may
fall out
5. During shut down all the internals should be inspected for
a) Snapped or loose wires
b) Excessive ash accumulation
c) Displacement of shock bars guides and collecting. Electrodes
d) Any other abnormality
6. During short duration shutdown, when no work is expected. Inside ESP,
ESP inlet and outlet damper should be kept Closed .The casing doors should
not be opened .This helps in retaining as much heat as possible and thus
reduces the precipitator start up time .The heaters need not be switched off
during such conditions
7. If an inspection of ESP is required during short duration shutdown, the
door are to be closed as soon as the internals checks are completed. In this
case heaters may have to be switched off for carrying out inspection.
Warning
105
Emitting electrodes
106
Rapping system
1.The plain bearing in the rapping shaft is to be checked for wear. When
the wear is more then 8mm,it is to be replaced. During such replacement,
it is preferable to replace the complete set of plain bearing ,since retaining
some old bearing will result in excessive wear on the new ones. When
replacing the bearings, alignment should be maintained.
2.The worn out shaft could be replaced along with the bearing. After the
replacement, the rapping system should be test run to establish
satisfactory performance and the bolt as and nuts must be locked by tack
welding
3.The hammer and arm assembly shall be inspected for excessive wear on
hammer /pins worn-out assemblies are to be replaced .the inner arm of
the should be locked by tack welding the bolts and nuts .the hammer
should be so fixed that they hit at the center of the shock pad beam
4.The SKF bearing assembly in the rapping drive system normally requires
no maintenances. However if the bearing is disturbed for replacement of
any components, the following procedure should be adopted for assembly.
I. The Plummer block top and bottom housing and other internals are
to be cleaned
107
II. The end seals, adopter sleeve and the bearing are to be inserted
into the shaft and should be placed on the bottom half of bearing
III. The seals are to be fixed in the corresponding grooves and the
bearing must be locked by guide rings
IV. The nut of the adopter sleeve is then tightened and locked by
bending one tooth of the washer to the slot of the nut
V. Grease is to be applied to one third volume of the housing and
then top housing should be closed .lithium based grease grade 3
of IS 1002 such as IOC MOBILUX –3 or SERVOGEM –3 or HP BEACON
–2 can be used
Electrical system
General
Before commencing work on any electrical equipment ear thing
devices must be connected to all high voltage parts. the end of the
cable on ear thing rod must always be connected to earth before the
rods are applied
Insulators
The following checks are to be carried out for upkeep of insulator
1.The insulators are to be inspected for cleanliness and rigidity of
metal parts
2.Dusty insulators should be cleaned with carbon tetrachloride and
dried
3.Cracked insulators ,if any should be replaced
4.Bushing insulator and pin insulator of the disconnecting switch can
be easily replaced after removing the fixed screws.
5.Support insulators can be removed and replaced with the help of
lifting tool and alignment jig.
Heating elements
Normally the heating elements required very little maintenance.
Failure of the heating elements can occur either due to ingress of
moisture or water into the terminal box or due to damage caused by
hammering
108
Gas temperature
The gas temperature at the ESP should be maintained sufficiently high
since operation of the precipitator at gas temperature below the acid
dew point results in the following
Rapping frequency
If the rapping frequency is insufficient dust accumulation will be there on the
electrodes .Too high a rapping frequency will dislodge the dust layer before
formation of agglomerates resulting in re-entrainment and puffs through the
stack .Hence the time intervals between the raps for the various fields are to
be optimally chosen to permit building of a sufficiently thick layer ,so that
when rapped ,the dust is dislodged in the form of agglomerates
Oil combustion
During initial startup ,unburnt oil ,if any may get carried over and form a
coating on the electrodes in the ESP. This fouling of this electrodes reduce the
precipitator operating voltage due to high electrical resistivity.so the
precipitator performance gets affected and remain poor until the oil vaporizes
and the layer gets rapped off, which usually takes a few weeks time. Also the
unbrunt oil in the ESP poses the danger of fire hazard. Hence low current
setting (without any flashover) are recommended during oil firing
Dust concentration in flue gases
The dust concentration in the gases is much higher in the front part of the
precipitator then in the rear .the current distributions is influenced by the
dust concentration ,where it is high, the current is suppressed ,i.e. .inlet fields
will take less current then the outlet fields
Hopper evacuation
Incomplete hopper evacuation is a major causes for the precipitator mal-
function .if the hopper are not emptied regularly ,the dust will buildup to the
high tension emitting system causing shorts. also the dust can push the
internals up causing misalignment of the electrodes .though the hopper are
designed for a storage capacity of 8 hours under MCR conditions. the hopper
should not be regarded as a storage space for collected dust and ash
accumulation in the hopper should not be allowed
Air conditioning of control cabins
111
The mixture of water and ash fall to the slag bath. There is a hand-operated
damper in each sluiceway, which can be adjusted accordingly.
Immersion dampers
The furnace bottom is having a set of dampers known as immersion dampers.
They are mainly provided to connect/disconnect furnace bottom to the slag
bath. It consists of six hydraulically operated flaps. When they are kept
vertically straight, these flaps immerse in the water in slag bath, which
prevents any air ingress into the furnace.
Slag bath
The slag bath is nothing but a tub of size 1880mmx10000mm filled with
water. All the sides of the bath is vertical except rear side, here in a slope is
given for easy discharge of slag. The slag bath bottom plate has fusion cast
basalt lining. The slag bath is filled with water upto a level1275mm from the
bottom. Service water is supplied to this bath apart from preventing air
ingress into the furnace, ensures effective quenching and also disintegration
of fused large size particles. the make up to the slag bath is done
continuously. A slag conveyor is provided to discharge quenching slag from
the bottom of the slag bath to the slag channel. A 3 phase, 415V, 7.5KW,
1445rpm, 14 amps motor installed in a separate platform drives ad rive
sprocket fixed at the end of inclined plater at the rear via a safety clutch and
a gear box
Fly ash collection hoppers
Taking ash content in the lignite as 12%, about 24 tonnes of fly ash particles
are generated per hour. Estimated bottom ash in the boiler is 3.6 t/hr, where
as fly ash is 20.4 t/hr.This fly ash will be collected in different parts of the gas
path viz below second pass duct, below RAPH, below ESP and below chimney.
Dry ash collection
In ESP, the hoppers of first two fields are connected to the rotary feeder
through the inclined adopter. It can be replaced by an inverted ‘Y’ piece with
one outlet pipe leading to the ash mixing vessel and other to the dry ash
collection for the purpose of dry ash collection
114
Rotary feeder
The maximum quantity of fly ash particles are separated from the flue gas in
the first field of ESP and a moderate quantity are being collected in the
second field;
whereas in the other fields, the quantity will be less. In order to dispose
uniformly ash particles stored in the hoppers of first two fields of ESP a
special type of ash scooping device known as rotary feeder is provided.
Rotary feeder consists of an impeller having radial blades. This feeder is
located just below the ESP hopper after the plate isolation valve the ash
scooped by the rotary feeder is then discharged to Ash mixing vessel.
Ash mixing vessels
Ash mixing vessels are provided below ash hoppers to mix ash and water into
slurry. There are fifty-two ash-mixing vessels in each boiler.
Ash mixing vessel comprises of three chambers known as
1.Regulating chamber
2.Mixing chamber
3.Discharge chamber
The discharge from slag conveyor falls into the channel and this is the
starting point of slag channel. The channel is provided with a slope of 1:75. A
low-pressure water jet is provided at the starting point of the channel in order
to transport slag in the channel. The slurry from gas duct ash mixing vessel
and RAPH ash mixing vessels joins this slag channel. Numbers of high-
pressure water jets are provided in the channel to ensure free flow of slurry.
Number of HP water jets provided for each boiler is 40. The main channel is
located at a minimum depth of two meters and are covered with RCC slab.
The channel which is of 482mm wide is provided with walk ways of size
759mm on one side and 259mm on other side which facilitate cleaning. the
two main channels of boiler 4 and 5 join together and enters a slurry
chamber. from this chamber, slurry can be diverted to any of three slurry
115
sumps. From each of these sumps, a set of slurry pumps pumps out the slurry
to the ash bund.
There are six low pressure water pumps out of which four low pressure(L.P)
water pumps will be kept in service and the other two as reserve. Each low-
pressure water pump is of two stage vertical pump, with 550m3/hr at 7.0
kg/cm2
Seal water system provides seal water to protect the pump’s gland seals
against erosion and also top increase the life of gland seal. there are two seal
water pumps, which are installed in the ash slurry pump house1 . Each pump
delivers at the rate of 180m3/hr at pressure of 19.5 kg/cm2.the pump is of
horizontal centrifugal multistage pump.
Drain pumps
Two number of vertical drain pumps are provided in each ash slurry pump
house to pump out accumulated water and ash mixture in the ash drain sump
to the plant sewage drain each pump is capable of delivering at the rate of
80 m3/hr at a pressure of 1.5 kg/cm2.
117
Corrosion:
Corrosion can be defined as the destruction of metal by chemical or electro
chemical action. Corrosion process can be broadly classified as
1. Chemical corrosion
2. Electro chemical corrosion.
Chemical corrosion:
It arises due to purely chemical processes and occurs subsequent to direct
interaction between metal and surroundings without generation of electric
current.
Electro chemical corrosion:
This originates when metal is attacked by electrolytic solutions and is
characterized by the flow of current from one part of metal to another.
Oxygen corrosion:
Presence of dissolved oxygen in boiler water is dangerous to the boiler
heating surfaces. Oxygen enters into the system through ingress in
condenser and as dissolved O2 in water, which is system, make up.
Processes of mutual oxide conversion accompanied by a change of valence
can under some conditions lead to honey comb corrosion. This is nothing
but sharply pronounced local destruction of metal (i.e.) pitting, where
volume of corrosion product is larger than iron. This out growth over the pits
appears like honeycomb.
Carbon dioxide corrosion:
The other corrosive agent that may find its way to boiler water is
carbondioxide. CO2 is generated itself by the decomposition of carbonates
and bicarbonates introduced in feed water.
Acid corrosion:
Some inorganic salts MgCL2 dissolve in water and produce acidity with
precipitation of Mg (OH) 2which reacts with iron and produce ferrous
chloride and hydrogen. Ferrous chloride gets reduced in water as ferrous
hydroxide and produce HCL. Thus a chain of reactions takes places
producing corrosive acids like HCL.
120
Sludge formation:
In order to prevent scale formation, chemicals are dozed into boiler water,
which converts scale-forming salts into soft suspended solids.
This continuous sedimentation of suspended solids and sometimes
corrosion products, wear metals from bearings, impeller and pump shafts
or mill scales and dirt left in the vessel at start up forms loose, soft deposits
in water wall header called sludge.
This type of deposits often bakes on water wall tubes impeding the
circulation of water. This effect is aggravated by contaminants including oil,
ferric oxide, basic magnesium phosphate and various silicates that serve as
binders.
Steam contamination:
Carry over:
The phenomenon of transfer of substances (sodium, silica and carbon di-
oxide) present in water, which is called carry over of salts. The amount of
salt carry over in steam is influenced by pressure and temperature of
boiler. The solubility of some substances is considerably higher at higher
temperature and pressures.
Carry over is said to be of the droplet kind when impurities get into steam
mostly with boiler water droplets taken away from drum. Droplets of
moisture originate in the drum of a boiler unit as a result of two processes
namely breaking of water and destruction of steam bubbles.
Water usually breaks into particles as the jets of the steam –water mixture
entering the steam space of the drum strike all kinds of baffles and
partitions that are placed on the paths of jets so as to quench their kinetic
energy. Such impacts result in the formation of droplets of different size.
The higher the velocity of a steam water mixture jet entering the drum, the
finer the droplets that forms as the jet strikes a baffle. Fine droplets are
easily entrained by the steam leaving the drum. That is why in designing
and constructing drum internals, water-breaking processes must be
minimized or precluded together.
The second source of formation of droplets is the rupture of steam bubbles,
when the steam- water mixture is introduced into the drum below the level
121
SILICA IN STEAM/
PH SILICA IN WATER
(%)
12 0.55
11 0.77
10 1.02
9 1.25
8 1.48
7 1.73
Addition of certain salts like sodium chloride, sodium sulphate and tri
sodium phosphate to boiler water causes the concentration of silica in
steam to decrease. The amount of silica introduced into the system by
mechanical carry over however is negligible at pressures above 35 ksc
compared to that volatilized.
The concentration of silica in boiler water may be controlled in three
ways.
1. Limiting the ingress of silica to feed water by careful control of
D.M plant.
2. Controlling the silica level of the boiler water by blow down.
3. By limiting the ingress of silica bearing materials into the feed
and boiler system.
Caustic embitterment:
Hydroxyl ion in contact with metal under stress causes the deterioration
and eventual failure of the metal by a process of embrittlement. This was
common in riveted boilers but with advent of welded, stress-relieved boiler,
this phenomenon has become rare.
125
Phosphate dozing
To prevent the formation of hard scale and form in its place a soft sludge
type precipitate, a softening chemical is added to the boiler water. This is
accomplished by the addition sodium phosphate which precipitates calcium
and magnesium salts and maintains them in soft non-adherent sludge
condition, which can be removed through blow down.
Among the phosphate salts, Tri-sodium phosphate is chosen for a specific
reason i.e. if we select any other phosphate salt another alkali should be
dozed to maintain the alkalinity of the water, whereas the excess Tri-
sodium phosphate hydrolysis to give sodium hydroxide.
Inter crystalline corrosion and caustic embitterment in the boiler is due to
excess alkalinity of boiler water. This danger is avoided with the use of Tri-
sodium phosphate. We know that excess phosphate by hydrolysis, become
sodium hydroxide resulting in increasing alkalinity.
Before the sodium hydroxide exceeds the danger limit (i.e. 3-6%), the
process of hydrolysis of Na3 PO4 slows down with increase in the
concentration of Noah and the reverse reaction will ensue. So it is seen that
po4 dozing prevents scale formation and also maintains the necessary
alkalinity in boiler water.
Certain recent studies have indicated that excess dozing of Tri-sodium
phosphate forms phosphate ions which have harmful effect on the
protective magnetite (Fe3o4) layer that is formed on the metal surfaces by
the action of hydrazine and the metal is no longer protected but is exposed
to corrosion.
In highly concentrated alkali protective film of magnetite dissolves forming
a mixture of ferrite and hypo ferrite, the following Table lists suitable
phosphate residuals in boiler at various pressures up to 140.6 ksc together
maximum permissible hardness in the corresponding feed water.
PO4&N2H4 storage tanks &dozing pumps are provided for all the four
boilers.
The phosphate dozing rate is to be adjusted such a slight excess
phosphate value is maintained in the boiler to avoid scale formation and
also to ensure magnetite is not removed. The dozing is done by one of the
two reciprocating pumps provided for each boiler.
Supplier MAT2
Capacity 80L/hr, 200kg/cm2
Motor 2.2 KW, 1430rpm, reciprocating type
Normally one pump will be in service for each unit and the other is kept as
stand by. The suction line from the tank has an isolating valve, after which
it branches off into two; one going to each pump; there is a valve and a Y
type strainer in the suction side of the pump. The two discharge lines are
joined together and are taken to the boiler drum. The stroke of the pump
can be adjusted so as to vary the discharge quantity of Po 4 solution
depending on the Po4 values in the boiler water. The stroke adjustments
can be effected by means of the hand wheel provided in the pump.
It is to be noted that feeding of phosphate solution is done by adding it to
the drum water and not to the feed water. There are two reasons. The scale
forming matter may prematurely precipitate and deposit in the feed lines
heaters and economizers if Po 4 is added to the feed water. Also the
solubility of certain salts decrease at high temperature. As water
temperature tends to be near the maximum value in the drum solubility of
salts is minimum and hence are likely to precipitate.
Hydrazine dozing:
Another important internal treatment is dosing of hydrazine into
feed water for preventing corrosion. Corrosion can be prevented by the
isolation of metal fro the environment. Removing O 2 and Co2 by mechanical
deaeration and dosing N2H4 to feed water, which removes even traces of O 2
from the
feed water and also form a thin protective coating on the metal
surfaces is the practice adopted in our boilers.
Deaeration
129
attacks non-ferrous metals like copper and alloys of copper. This reaction can
cause severe corrosion in condenser and water heaters constructed of copper
alloys. Further damage is done to boiler tubes by the soluble copper
ammonia ion, which adheres on steel and becomes a cathode and causes the
surrounding and underlying iron to dissolve.
The ammonia returns to the steam system to function again as a transfer
agent for copper. The following table lists the residual s of hydrazine that can
be maintained at various pressures. Concentrations in excess of the upper
values in the table decompose to ammonia. Increasing the feed rate of
hydrazine, thus increase the amount decomposed and the concentration of
ammonia in the steam.
Equilibrium concentration of hydrazine
Drum
63.27 Residual
0.1-0,15
70.3 0.1-0.15
105.45 0.05-0.1
140.6 0.05-0.1
175.75 0.02-0.03
210.90 0.01-0.02
Out of the two pumps of each unit, one will be in service and the other is
kept as stand by. The N2 H4 line joins the feed pump suction line from
Deaerator. The line has an isolating valve and a non- return valve.
Model PR15
Manufacturer VK Pumps
Capacity 100L/hr
Pressure 36kg/cm2
Motor 0.5 kW, 1400rpm
Sampling system
The function of the sampling system is to provide samples characterizing
the water and steam at various locations for the quality control. Unless the
sample is true and reliable, the results of analysis would be incorrect. So, a
minimum continuous sample flow is effected for periodical collection for
132
analysis. There are totally eight sampling points for the boiler as described
below.
1. Condensate:
Sample is collected from the common delivery line of condensate extraction
pumps at about ‘O’ meter level
2. Boiler feed pump (suction) water:
Sample is collected before the N2H2 dozing point in the boiler feed pump
suction line at about 13.5 meter level.
3. Feed water (to economiser):
Sample is taken in feed water inlet line to economizer at about 44metre
level.
4. Drum water:
Samples are taken from CBD at 23 ml.
5. Saturated steam:
Sample is taken from 2nd saturated steam pipe to super heater 1 inlet
header at about 85 meter level.
6. Superheated steam:
Samples are taken from main steam line sample interconnection pipe at
about 44 meter level.
8. DM water: Sampling is taken at CST.
All the sampling lines are bought to the sampling station located at 6-meter
level of boiler main building. The sampling lines are usually made of stainless
steel so that the line will not have any corrosion etc.
Each sampling line is provided with 2 hand-operated valves, one at tapping
point and another at the sampling station called the primary and secondary
valves respectively. Periodically samples are collected and tested at Express
lab.
In the sampling station, sample cooler has been provided for each sampling
line. The samplings temperature should be reduced and the steam samples
are to be condensed so as to facilitate easy handling.
133
This is achieved in sample coolers where the samples flowing through coils, is
cooled by Auxiliary cooling water stream surrounding the coils.
The auxiliary cooling water for sample coolers is taken from ACW booster
pump.
NH3 1.0
Dis.O2 <0.00
5
PO4 6
Introduction
In a modern power plant continuous and reliable operation of various
auxiliaries of a unit becomes necessary and this calls for an elaborate system
of protections and interlocks to ensure that either a defect in an equipment
or an operation error do not cause damage to the equipment. Protections are
provided to trip the boiler in case of faults so that the faulty equipment is
isolated without causing further damage. Interlocking is provided to switch in
the reserve equipment in case of a tripping of the running equipment to
enable continuity of supply.
Protections for steam generator
Drum level high
If the boiler drum level is more than +330mm for 5 seconds or more, the
boiler will trip. Three protection contacts are provided out of which 2 contacts
should be made for the protection to act.
The contacts are
Level transmitter
Level switch
Hydrastep
Very high tripping signal will be given only when both channels gets
energized.
Auto stopping
Cooling air fan will stop automatically when
1) I.D fan is switched off and the condition exists for 5
minutes and
2) All the bearing temperatures are less than 500c
137
Auto stopping
The lub.oil pump will trip
1) If the oil level in the lubricating oil tank is less than the preset mini
mum level
4) After 5 minutes after stopping of the corresponding ID fan provided all
the three bearing temperatures are less than 50ºc
3) When damper after RAPH (AD2A/2B) in closed condition and FD fan A/B
is running for more than 120 sec.
4) Furnace pressure is more than +15millibar
5) FD fan motor bearing temperature exceeds 90ºc
6) FD fan bearing temperature exceeds 110ºc
7) Oil level in the tank is less than preset minimum level
Interlocking of Air/Gas dampers
Gas side dampers
1) When ID A/B, is started the corresponding gas damper 1A/1B opens
automatically
2) When one of the two ID fans trips or its is stopped and the other is
running, the corresponding gas damper (1A/1B) will close
automatically
3) When both ID fans trips, both gas dampers 1A,1B remain open
4) The gas damper 2A/2B will open automatically-when ID fan A/B is
started
5) When both ID fans are stopped, then both the dampers GD2A/2B will
open automatically
6) Whenever ID fan A/B trips, the corresponding discharge damper
2A/2B will close automatically, if the other fan is running
Air side dampers
1) When FD fan A/B is started, the discharge damper 1A/1B will open
automatically
2) When both FD fan trips both the damper will open automatically
3) When FD fan A/B fans trips or is stopped and the other fan is
running, the respective discharge damper (AD1A/1B) will close
Air way free logic
Air way free condition is satisfied only if,
1) FD fan A/B is running
2) Damper after FD fan A/B (AD1A/1B) is opened
3) Damper after RAPHA/B (AD2A/2B) is opened
Flue gas way free logic
Flue way free condition is satisfied only if,
140
III. FD FANS
1) Corresponding ID Fan to be kept ‘ON’ status with simulator, Gas
dampers to be kept open.
2) Simulator to be provided for the FD fan 6.6 KV breakers for P&I checking
without actual starting.
142
IV. MILLS
After completion of Mechanical, Electrical and Instruments and Refractory
works in Mill and confirming concerned LCs in deposited /returned condition.
Simulator to be provided in 6.6 KV breaker of that mill to check P&I without
actual starting. Necessary simulations to be done for mill test ‘ON’
1) With simulator ‘ON’ condition by making Mill bearing temperature
motor/coupling side high for Annunciation and Very high for trip will be
checked.
2) With simulator ‘ON’ mill motor bearing temperature DE/NDE high
annunciation and very high trip will be checked by making respective
contacts.
3) Mill trip by applying local latch and not starting in latched condition.
4) Mill O/L temperature V.high time delay trip will be confirmed by making
respective contact.
1) By making 2/3 contacts with all combinations of very low and very high
furnace pressure switches trip, signal to boiler will be confirmed.
2) Furnace pressure low and high annunciation will be checked by making
respective switch contact.
3) Drum level very low/very high trip, EBD valves auto opening/closing,
Drum level high/low annunciation will be checked during boiler filling
before lighting up or during hydro test.
4) Boiler trip for CRH temp L/R>370 ºC will be checked by making
respective switch contact.
BO11.OPERATING GUIDELINES
144
TEST PROCEDURE:
1. Open common isolation valve in Boiler filling line in Boiler House. Open
Boiler Fill line to water side drain header and SH drain header isolation
valves.
2. After informing Turbine Board gradually open CT Pump discharge header to
boiler filling line isolation valve in CT Pump discharge header (while
opening, pump current to be monitored with walkie-talkie in order to avoid
pump overloading. Close CT Pump recirculation valve.)
3. Close SH Start up vents, SH and ECO Air vents one by one after air
releasing.
4. Finally close SH 1 inlet header air vent after air releasing.
150
4. Close CT pump discharge header to Boiler Fill Line valve, Boiler Fill Line
common isolation valve and Boiler Fill Line to RH drain header isolation
valves
5. Close all RH drain valves.
6. Start Boiler Feed Pump. Open BFP interstage valve.
7. Open RH spray common isolation valve (R64) and pressurise the
contour by opening any one of RH spray control valves at the rate of 1
ksc/min.
8. Hold the pressure at the required level for about 15 min and observe
any puncture in RH contour.
9. After locating the puncture if any, reduce the pressure at the rate of 1
Ksc/min and kill the pressure. Stop Boiler Feed pump.
10. Open RH air vents and drain the contour.
11. Normalise RH safety valve gagging.
12. Close valve R-64 and HOV situated before it.
13. Open CRH, HRH before PTD drains and close after complete
draining. Remove PTD after ensuring complete draining.
14. Open V-SB 53 isolation valve.
PASSIVATION PROCEDURE
1. Reduction of load according to the schedule along with
pressure reduction (120 ksc/520 deg.,).
2. De-synchronise the unit after reducing load with HP/LP bypass
system.
3. Start Forced cooling of the boiler. Keep one series of fans, one
BFP and one Circulating water pump. Inform generator board engineer
to switch off all ESP fields.
4. PRDS system to isolated. All injection valves of SH/RH system
to be kept closed.(hand tightened).
5. Chemical staff shall be informed for dozing and analysis after
tripping the turbine.
6. Light up the boiler at drum pressure 40 Ksc. Start dozing
hydrazine in drum and in feed pump suction at drum pressure 30 Ksc.
153
Adjust the firing with two oil burners (oil pressure ≈10 Ksc at burner
header) and maintain 30 Ksc drum pressure by tuning HP/LP bypass.
7. Passivation commences when the concentration of N 2 H4 in
drum reaches 200 ppm. This will continue for 24 hrs. During
passivation.N2 H4 concentration in condensate may be carefully
maintained.
8. Hydrazine dozing will be stopped after 22 hrs. Of passivation.
The boiler is to be boxed up after two hours.
9. During the period of passivation, oil burners shall be changed
over once in 4 hrs. Firing should be controlled to maintain the steam
flow at the rate of 50 to 70 T/hr.
10. RAPH soot blowing to be carried out twice in a shift.
11. Hourly readings, chemical values and other parameters to be
recorded during passivation.
12. After completion of passivation, boiler should be boxed up and
naturally cooled up to 3 Ksc pressure in drum or 140 ºC metal
temperature. Then boiler has to be hot drained. Service water,
Firewater have to be added to the outlet of IBD tank to reduce N 2 H4
concentration to the required level.
After draining the boiler fully, one series of fans may be started for cooling
the furnace.
15. Then gradually raise the SH3 O/L pressure upto 165.7 Ksc and
check the ERV automatic opening. If necessary adjust the open/close.
Record the Open/Close pressure and reduce the pressure to 100 Ksc.
16. SV5 floating completed.
17. Remove SV4 gagging.
18. All safety valves floating completed.
19. Protections already bypassed are to be normalized immediately.
a. Drum level very high –boiler trip to be normalized.
b. SH/RH conditions not fulfilled status to be normalized.
c. HP Bypass trip open to be normalized.
d. Drum level very high to scoop minimum to be bypassed.
Guidelines:
During safety valve floating, drum level to be carefully maintained and
monitored.
Hand popping to be carried out for all safety valves before floating.
While closing HP/BP close LP B/P also to maintain the RH pressure.
While opening HP B/P open LP B/P also to avoid LPBP overload/RH SV
opening.
Any other persons other than safety valve floating crew, not to be
allowed near safety valve floor while floating.
While closing HPBP close LPBP also to maintain RH pressure.
While opening HPBP open LPBP also to avoid LPBP overload/ RHSV
open.
Probable ranges of HPBP opening & pressure: -
40% -- 150 Ksc
30% -- 160 Ksc
20% -- 170 Ksc
10% -- 180 Ksc
Refractory drying (after Major overhaul)
Required conditions:
1. Boiler is to be made ready for light up after shutdown.
2. No L.C is pending for light up.
3. All manholes, peepholes are to be kept closed.
157
PROCEDURE:
1. Boiler interlocking (General) to be simulated for starting mills.
2. Simulate sec. Air temp > min contact.
3. Start one series of Fans.
4. Charge corresponding SCAPH.
5. Start the mills, which are to be dried in presence of maintenance
staff and local staff. Check lub oil system and mill healthiness.
6. Keep airflow at 30% MCR (about 250 T/hr) and air temperature at
SCAPH O/L to the max possible extent.
7. Keep mill O/L temperature at 60 ºC for 8 hrs.
8. After 4 hrs since the starting of available mills for refractory
drying, Boiler contour filling may be started through Boiler Feed
pump with deaerated water at 70 ºC.
9. After 8 hrs of drying with SCAPH and ensuring normal working
drum level, Boiler may be lighted up with one OB with minimum
oil flow. Cut in another OB preferably in combination of A and C or
B and D.
10. Raise the Mill O/L temperature from 60 ºC to 120 ºC at the
rate of 15 ºC /hr by raising the firing rate gradually and with the
help of hot air.
11. Change the combination of OB’s once in 4 hrs.
12. Frequently check for any oil leak or fire at local.
13. RSB is to be operated with AST source once in 4 hrs.
14. Raise the mill O/L temp from 120 to 200ºC at the rate of
20ºC/hr and maintain at 200 ºC for 8 hrs with the use of hot
air/cold air dampers if necessary.
158
RAPH washing
RAPH washing can be done either during shut down period or during normal
operation of a steam generator as the situation warrants. In both the cases
RAPH should be kept in continuous service but isolated from the system
(i.e.) without load.
Preparatory works
1. Avail RAPH water washing pump supply.(If the unit is not in service,
check the water washing line inside RAPH and nozzles for its
healthiness).
2. Reduce load to 50% if the unit is in full load.
3. Stop ID/FD fans of the particular RAPH to be washed.
4. Close AD2/GD1.
5. Ensure the isolation valves in water washing lines of all other three
RAPHs are in closed condition.
6. Keep open ESP first row AMV plate dampers.
7. Remove gas side ash mixing vessel from its position in order to avoid
choke. Ensure gas side plate damper in open condition.
8. Keep open-air side, drain line plate valve or ‘Y’ piece dummy flange.
9. Keep the FD fan drain flange open.
10. RAPH washing line, strainer and line drain after valve in 15ML to
be closed.
Water washing sequence
1. Open the suction valve of RAPH water washing pump. Keep close
discharge valve.
2. RAPH water washing pump to be started, gradually open discharge
valve.
159
Test procedure
1. Keep open FD Fan bottom drain flange.
2. Keep open RAPH airside hopper ‘Y’ piece dummy.
3. Open inspection doors before and after SCAPH.
160
The aim of the control loop is to ensure proper Unit level coordination
between the two main plant auxiliaries, the Boiler and the Turbine, to attain
economical and safe running of the plant.
We decide the control loop into 5 sub-loops.
1. Load set point guidance including Unit Master
2. Run-back Load limit and Rate generation
3. Boiler Load control (pressure control)
4. Mode of operation
5. Fuel flow control
In addition the output of the Unit Master is given back to the ALC through a
galvanic isolating module TET-30. The target load is subjected to a MAX and
MIN selection. For this purpose, MAX and MIN Load preselectors along with
their digital indicators have been provided on the control desk.
The frequency deviation corrects the Unit demand (target load) by providing
a bias to the target Load signal. The bias is equivalent to change in MW
output, which is necessary to bring back the frequency to the rate value. A
5% droop in the frequency is equivalent to 0 to 100% change in Load.
Therefore a proposed range of frequency deviation measurement is –5 to 5%,
which implies –2.5 Hz to 2.5 HZ for a 50 Hz system.
a) For a frequency deviation greater than +/- 15% (of the frequency
range) an additive bias equivalent to the change in Load corresponding
to 15% frequency deviation is directly given to the output of GNI
(SPCM). Thus on immediate change in Unit Load set point to the Boiler
is achieved. This output after a MAX/MIN cut off is the Unit Load set
point for a Boiler and Turbine controls.
s bias
eviation
b) For frequency deviation within the band of +/- 15% bias is only given to
the output of SPCM (GNI) and no influence is execute on the target value
Z0 of the GNI. The frequency corrections bypassed when the turbine follow
mode or run back mode is in operation. This can be done manually.
The target value Z0 for the SPCM (set point computation module, GNI) is
switched to either frequency corrected Unit demand signal from the Unit
Master or EHC Load set point or the MW generated or Boiler demand (Boiler
162
This is done to ensure that the Unit load set point balance to the MW
generated in Turbine follow mode and the Boiler Master output in the case of
Boiler follow mode.
In the turbine follow mode the turbine load controller is inactive and
switching from this mode to co-ordinated mode (LC to auto/active) it must be
ensured that the LC has correct set point to avoid Jump (i.e., X wflc= 0).
Therefore the Unit Load set point must be balanced to MW generated. The
boiler master is also in manual in turbine follow mode and switching to the
co-ordinated mode the Boiler Master goes to auto and it must have Unit set
point corresponding to the actual MW.
In the Boiler follow mode the turbine Load controller (Zc) is in manual/auto
changing the mode to co-ordinated results in switching the LC to auto. The
boiler demand while in the Boiler follow mode is the true representation of
the Load generated must be made available to the Load controller at set
point to avoid bumps at the LC output. The boiler master is in auto both in
Co-ordinated and boiler follow mode. In case turbine is in Local operation the
EHC Load set point is switches as the target value of GNI (SPCM) to ensure
that in this mode of operation the same set point is there for Boiler and
Turbine.
The RUN UP (GU) and RUN DOWN (GD) gradient for the SPCM are computed
based on the upper and lower temperature margins of the turbine stress
evaluator and a manually preset Unit load rate. In addition the RUN BACK
RATE is also taken into consideration while deciding the GU and GD of the
SPCM (after MAX selection with Down Grad). A digital indicator has been
provided to display the manually preselected unit load rate. The MAX and MIN
163
unit load limits adjustable from the desk provide the MAX and MIN cut off’s
for the SPCM also.
NOTE: The frequency influence, the directional blocking signal and the ALDC
(Automatic Load Despatch Centre) signals are bypassed from the main
control loop.
The SPCM module has two directional release inputs +/-F 24. The absence of
any one of them inhibits the SPCM to integrate in that particular direction
(Run Up or Run Down) the computation of these two binary signals is based
on the control deviation of the sub-ordinate control loops being greater than
or lesser than preselected limits.
The output of the GNI (SPCM) is subjected to further MAX/MIN cut off by the
desk preset MAX/MIN unit load limits and Unit capability signal. The signal
thus generated forms the Unit Load Set point, which is made available to the
Boiler and Turbine controls. A double indicator is provided to display the Unit
capability signal and the Unit load setpoint for the Boiler. In addition a digital
indicator display the Unit load set point for the turbine is compared with the
EHC setpoint and in case of deviation (each unit load setpoint) load reduction
by Turbine is initiated. This Unit Load setpoint signal after correcting with the
DP correction (a small bias of 7.5 MW will be given to the Load setpoint
depending upon the pressure deviation) is made available to the Turbine
controls.
The Unit capabilities in terms of Load generation are calculated by this run
loop based on the availability/healthiness of various plant auxiliaries. The
Load rating of each plant auxiliary is preselected using software
potentiometers. By load rating we mean the % by which the Load set point
has to be reduced due to the low availability of particular auxiliary.
signal Load reduction by Turbine and Turbine Trip are also used in this sub-
loop to bring the Unit capability down to a preselected MIN value.
The binary output of this Limit Value Detector indicate that the Unit capability
based on e.g., ID fan availability is less than the Unit load set point. Each
type of auxiliary (ID, FD, BFP) has a preselected run back rate set using
software potentiometer. The Binary signals from the Limit value detector
mentioned above, switches through this preselected run back rate to MAX
selector. The output of this MAX selector is the run back rate and is made
available to the Load set point guidance sub loop for down gradient (GD)
calculated.
The Load set point obtained from the Load set point guidance sub loop is
processed further here as the feed forward signal of the Master Pressure
(LOAD) controller. In order to enhance the response of the Boiler and to
shorter the Mill/firing system response times, the largest value Z 0 of the GNI
in the Load set point guidance sub loop is routed through a derivative unit,
then multiplied by the preset Unit load rate and added to the Unit Load
setpoint using Pamplifier. A sector switches through either the output of the
Pamplifier described above or below Boiler Load index as feed forward signal
to the Pchannel of the boiler master depending upon the mode of operation
ie, Boiler follow mode (or Co-ordinated mode)
The set point for the HP bypass control is generated by adding a fixed preset
value to the throttle setpoint in case of either two condition “Load rejection or
Turbine Trip” under normal operating condition the HP bypass control
pressure set point is same as throttle pressure setpoint. A digital indicator
has been provided to display the throttle set point.
The Unit can be operated in the following 4 different modes:
Coordinated mode
In which Boiler controls the pressure and the turbine controls the Load. Boiler
master will be in auto (by receiving the MW/Load set point as the Pchannel
signal) and provides the Boiler demand signal to the fuel master and load
controller on Turbine will be in auto and controls the MW for which the load
set point will be issued from the Boiler
In which Boiler master will be in auto, controlling the pressure (by receiving
the Boiler load index/steam flow as the Pchannel signal) and provides the
boiler demand signal to the Fuel Master and Load Controller on Turbine will be
in manual (LP mode and Load control active) i.e., turbine on local and
controls the MW for which a load set point will be issued from the turbine
desk (EHC Load set point delayed Load reference).
In this mode, the Unit Load set point is Run down to Unit Capability signal and
switches the controls to Turbine Follow mode. The Boiler Master is bypassed
and output of the SPCM (which is nothing but the Unit Capability signal) is
directly provided as the demand signal to the Fuel Master. The run back IN
ACTION lamp will disappear when the Unit Capability signal matches to the Y n
166
i.e., output of the SPCM (when the MW generated signal becomes lesser than
the Unit Capability signal which has to come down from the previous normal
Load set point to this MW generated signal at a run back rate). The turbine
controls must also be switched to pressure control. The various run back used
in this control loops are BFP, FD, ID, CEP, Mills, Gen CB trip and Load rejection
trip.
Runback mode will come only when the loop is in Co-ordinated mode.
Mode of Turbine
Boiler Master
operation Controls
The mode of operation logic sub loop has the responsibility deciding the
mode of operation
167
The sub loop process manual commands together with other binary
information obtained from other sub loops to drive the desk mounted
annunciating modules & to effect auto/manual switching of the turbine/boiler
controls. Manual setting of various modes is done through single push button
modules mounted on the desk. The logic is so arranged that with the setting
of one mode of operation from a particulars push button reset all the
operation modes.
The feeder speed signals of Mill A to F are subjected to first order delay
circuit and a P amplifier scamps up all the signals to form the total coal flow
signals. A limit value detector is provided to monitor the total coal flow signal
for the BMS. The total fuel signal is computed by adding the oil flow signal.
The fuel master receives its setpoint from MIN computation of the boiler
demand signal (boiler master output) and the total airflow signal. The total
level flow signal computed as mentioned above is the controlled variable.
The output of the fuel master is given to the feeder speed control loops for all
the mills.
The fuel master receives its setpoint from the MIN computation of the Boiler
Demand Signal (Boiler Master Output) and the total fuel flow (The sum of the
feeder speed signals of mills A to F and the oil flow) signal is the controlled
variable. When the fuel master is in AUTO, its output is limited to a maximum
of 72%.
Boiler master
controller is bypassed and the output of GNI (which is essentially the unit
capability Signal) will go as the Demand Signal to the fuel master.
Air master
The demand signal is biased and subjected to a max selection to ensure that
the demand signal doesn’t go below 40%. This signal now is the set point for
P11 controllers of each plate belt feeder and belt conveyor.
Binary interventions from the BMS has been in the control loop and
commands like lower /raise, out of main are transmitted from BMS to the
controller logic of the feeder speed controller.All the plate belt feeder and belt
conveyor of all the mills has separate controller.
Calorific correction
A three push button module is provided on the control desk, which can be
kept in either Manual or Auto. When in manual, with the operation of Push
buttons, a small amount of bias will be added directly to Fuel Master (action
will be very fast). When in auto, depending on the Lignite Flow/MW generated
ratio, correction signal will be automatically added to the Fuel Master. If the
RED-LED on the control tile flashes (in the absence of the release signal) by
varying the push button (lignite flow), we can match the lignite flow/MW
generated signal such that the RED-LED lignite flow will flash to change the
Calorific correction control to Auto.
Procedure to be followed for changing the modes
Manual Setting of Various modes is done through single push button modules
mounted on the desk, with the setting of one mode of operation from a
particular push button module, resets all the other operation modes. If a
particular mode is selected, the lamp for that mode blinks at a 2Hz.until the
control has reached the selected mode. This is however not applicable to
Runback mode.
Initially the Unit has to be kept in the Turbine follow mode by pressing the
Turbine follow mode push button, in which Boiler Master will be in manual and
puts the Turbine IP mode (Pressure Control active). For this we have to ensure
that the pressure deviation becomes zero. (By varying the throttle pressure
set point for a while and normalizing afterwards.)
Then we have to press the Boiler follow mode push button, which changes
the Boiler Master to auto and puts the Turbine in LP mode and Load Control
Active. For this we have to ensure that the Load controller deviation in the
Turbine becomes zero.(By varying the EHC Load set point on the Turbine desk
170
Immediately after the Boiler follow mode, we have to press the Coordinated
Mode Push Button which keeps the Boiler Master in Auto and issues the load
set point to the Turbine controls from the Boiler /CMC directly to the Turbine.
Pressure is controlled by the Boiler, and the Load is controlled by the Turbine.
(Before changing to Coordinated mode, the Unit Master signal has to be
matched to the EHC Load set point.
When the unit is in coordinated mode, if any of the auxiliaries trips, the run
back mode will come into service automatically which changes the unit to go
to the turbine follow mode.
5) The release signal for the Air Master is >/= 3 Seconds, Air Damper
Controllers should be in Auto.
6) The release signal for the fuel master is >/= 3 of the following signals:
9) If Run back occurs, the FD PCD’s position will be limited by 85% (Auto
limitation)
172