Вы находитесь на странице: 1из 3

Preheating steel before welding is common practice.

Sometimes we apply heat after we are done


welding as well. Other times we apply heat between passes to maintain the minimum interpass
temperature. Many applications use preheat simply because it is written in the WPS, but not really
understand why it is necessary. Preheating is used primarily to reduce the cooling rate of the weld,
heat affected zone and adjacent base metal. This reduces susceptibility to cold cracking.

Preheating is used for the following reasons:


1. Reduces shrinkage stresses in the weld and heat affected zone (HAZ). This is
especially important in joints that are highly restrained. When a weld bead cools it shrinks
and wants to pull the base material towards it. If the joint is restrained it creates a lot of
stress because the weld is trying to pull the base material. By preheating the HAZ and the
weld cool at similar quenching rates thus reducing the stresses created by shrinkage.
2. Preheating slows down the cooling rate in the 1600⁰F to 1330⁰F range which is the
critical temperature range. This prevents excessive hardening and reduced ductility of both
the weld and the HAZ. When a part is quenched rapidly it forms martensite. Martensite is
hard and very brittle and this will negatively affect the mechanical properties of the
weld. Reduced elongation and lower charpy v-notch values.
3. Preheating slows down the cooling rate down through the 400⁰F range. This allows
for more hydrogen to diffuse out of the weld and HAZ and avoid cracking. Hydrogen can
produce cold cracking while it is present in the weld and HAZ. See post on Hot Cracking vs
Cold Cracking for a more detailed explanation.
If preheat is necessary there are different methods for determining the temperature needed. An
easy one is to reference code books. Another is to ask the manufacturer of the steel. Yet another
way is to use calculators that provide this value based on the chemistry of the steel. For more
read 5 Methods to Determine Preheat Temperature.
Calculators are available for determining the required preheat based on the base material’s chemistry.
It is important to keep in mind that preheating is not as simple as applying heat to the joint to be
welded. If we need to preheat to a temperature of 225⁰F, we need to take the temperature reading
no less than 3 inches away from the joint along its entire length. Everywhere the temperature must
be 225⁰F at a minimum. The thicker the base material the larger the heat sink. So we can’t just
preheat where we’ll start welding and assume the heat of the arc will take care of the rest.

Once the base material thickness exceeds 3 inches the distance from the joint at which the preheat
temperature reading is taken must be equal to the thickness of the base metal. If we are welding
dissimilar thicknesses go with larger value. Also, if you are welding different steels which require
different preheat temperatures always go with the higher of the two. There is an exception to
this. If you are welding quenched and tempered steels always consult with the manufacturer of the
steel. Certain preheat temperatures and interpass temperature may not be exceeded.

The amount of preheat necessary varies depending on the type of material and the material
thickness. Fortunately the American Welding Society and the American Institute of Steel
Construction have established preheat and interpass temperature requirements for commonly
welded structural steels. Interpass temperature refers to the temperature near or around the weld
between passes. The D1.1 Structural Welding Code specifies minimum preheat and interpass
temperatures based on the base material, the thickness and the process to be used. This is on table
3.2 of such code. A similar table can be found on the Procedure Handbook for Arc Welding
(Table 3.3) – Minimum Preheat and Interpass Temperature.

Not sure if preheat is necessary? Here are some things that you should look for, and if present,
consult with your steel supplier, your welding engineer, production manager, or whoever is in
charge of welding operations.

1. The base material is over 1” thick


2. The base material has recently been brought in from outside during cold winter months
3. You are welding outside and the temperature is below freezing.
4. The base material has 30 points of carbon or more

Вам также может понравиться