Contract /
Tender Package Complete Tender Supplier / Signed Agreement
Contract Type Discipline Prices Received Review Prices and Award Contract Lead Time Date Required on Site Agreement Insurances Warranties Comments
& Issued Period Contractor Returned
Number
Resp.
Package No. Items / Works to Procure Delegated to
Person
eg Works, Minor Works, Scheduled Duration Scheduled Duration Scheduled Duration Scheduled
Actual Actual Actual Actual Scheduled Actual
Supply, Plant Hire Date Required Date Required Date Required Delivery
29 Streetlighting - Temp Relocation Minor Works HC Early Works 1/14/2014 Done ad hoc
68 Pavement Aggregate Supply Supply ME Earthworks 9/13/2013 TBC ME & HM - Awaiting Spec. - 2wks
75 Supply Retaining Wall Components RW3 and RW7 Supply HM AM Structures 1/13/2014 stone strong self perform / ICB design build
129 Walkway lighting - Install Lights/Pits & Draw Cables Works AS SN North Power
50 Expansion Joint Supply Supply TS JL Structures 1/30/2014 2w 2/13/2014 1w 2/20/2014 12w 5/15/2014 5/15/2014 Nuralite (WABO),
55 Concrete Placement Works TS JL Structures 3/17/2014 2w 3/31/2014 1w 4/7/2014 2w 4/21/2014 4/21/2014 Conset Construction, VJ Concrete, Brewis Concrete
46 Precast Pre-Stressed Concrete Supply - includes delivery Supply TS Structures 11/14/2013 2w 11/28/2013 11/8/2013 2w 12/12/2013 3m 3/14/2014 3/14/2014 Stahlton, Concrete Structures, Stresscrete
47 Precast Concrete Supply - includes delivery Supply TS Structures 11/21/2013 2w 12/5/2013 11/8/2013 1w 12/12/2013 3m 3/14/2014 3/14/2014 Stahlton, Concrete Structures, Stresscrete, Wilco, Wilson
60 Pavement Strip Drain Supply Supply HC Earthworks 9/13/2013 Date required TBC. ACO
FH, Brian Perrys, Spiral Drillers, Hauraki Piling. --> VO to BP. ME to
62 Causeway Ground Improvements - CFA Piling Works ME Earthworks 9/13/2013
compile special conditions
54 Concrete & Asphalt Cutting/Coring/Drilling Works TS Structures 12/9/2013 2w 12/23/2013 11/8/2013 2w 1/6/2014 1w 1/13/2014 1/13/2014 A1 Kiwi Cutters, Lowery --> All let
1 Ground Investigation - Geotechnical Drilling Minor Works AS Investigation 11/21/2012 11/23/2012 McMillans Drilling 9500712 Yes Yes Contracts in place
2 Ground Service Locator Minor Works AS Investigation Underground Service Locators 9500594 No Contracts in place
3 Bridge Investigation - Coring Works Minor Works TS Investigation 11/21/2012 11/23/2012 A1 Kiwi Cutters & Drillers Contracts in place
4 Bridge Investigation - Laboratory Testing Minor Works TS Investigation 11/30/2012 12/7/2012 OPUS Contracts in place
5 Labour Hire Works GH/RC Early Works Various Various Yes Yes
7 Earthmoving Plant Hire Plant Hire GH/JC Early Works 4/16/2013 Heavy Hire NZ 9501032 Yes Yes Contract signed 3/10, plant to mobilised on to site 7/10.
8 Contract Cartage (Haul Trucks) Plant Hire JC/ME Early Works 4/4/2013 Gleeson & Cox 9500442 Yes Yes Complete
11 Crane Hire Plant Hire TS JL Early Works 4/17/2013 4/15/2013 7d 4/26/2013 4/22/2013 5/3/2013 5/3/2013 5/6/2013 5/6/2013 NZ Crane Group 9500136 Yes Yes N
12 Hiab Hire Plant Hire JC/TS Early Works 4/19/2013 2w 5/3/2013 4/12/2013 5/10/2013 4/26/2013 JC Walker 9500091 Yes Yes Mackenzie, AJ Walker
13 Vacuum Excavation Hire Works HM DB Early Works 4/11/2013 4/11/2013 4d 4/15/2013 4/16/2013 4/18/2013 Done Hydrotech 9500340 Yes Yes
14 Street Sweeper / Road Cleaner Hire Plant Hire JC DC Early Works FH - AKL
16 Surveyors Works ME Early Works 3/1/2013 K & N Surveyors 9500854 Yes Yes
17 Traffic Control Works PN/HM Early Works Done Action Traffic 9501089 Yes Yes Self perform day works with project owned and operated TMAs
18 Fencing - Farm type for TAPC Minor Works HM Early Works Done John Crouch 9500048 Yes Yes
19 Fencing - 2.4m High for Compound (Design, Supply & Install) Works HM Early Works Done John Crouch 9500048 Yes Yes
20 Supply of Site Office Buildings Supply HM Early Works FH / Portacom 9500133 Yes Yes
22 Supply of Precast Concrete Barriers (TTM) Supply HM Early Works Done CSP Nil
25 Connection of Services to Site Compound - Electrician Minor Works HM Early Works Done Peter Brydon 9500231 Yes Yes
26 Connection of Services to Site Compound - Plumber Minor Works HM Early Works Done Windybank 9500241 Yes Yes
27 Pre-Condition Survey Assessment Minor Works TS JL Early Works 4/17/2013 5/1/2013 4/26/2013 5/7/2013 5/3/2013 5/21/2013 5/13/2013 5/27/2013 ACH Consulting 9500229 Yes Yes N ACH Consulting
28 Demolition of Existing Properties Works TS JL Early Works 4/17/2013 4/23/2013 2w 5/1/2013 5/1/2013 5/10/2013 5/23/2013 5/20/2013 5/27/2013 Nikau Contractors 9500248 Yes Yes N Ward, Nikau
35 Temporary Works Design - General Professional Services TS Design 7/11/2013 2w 7/25/2013 1w 8/1/2013 6w 9/12/2013 9/12/2013 ACH Consulting 9500801 Yes Yes
36 Staging Platform for Bridge Piling - Steelwork Supply TS JL Structures 8/12/2013 1w 8/19/2013 1w 8/26/2013 3w 9/16/2013 9/16/2013 Hire from Concrete Structures
41 Concrete Supply (inc Testing) Supply TS Structures 4/26/2013 4/24/2013 3w 5/17/2013 5/3/2013 2w 5/31/2013 8/5/2013 8/26/2013 Allied Concrete 9500415 Yes Yes Allied, Atlas, Stevenson
42 Reinforcement Supply and fix Supply TS Structures 5/17/2013 5/27/2013 2w 5/31/2013 6/13/2013 1w 6/7/2013 8/26/2013 Fletcher Reinforcing 9500650 Yes Yes Fletcher Reinforcing, Steel & Tube, Sim Reinforcing
45 Stressing Bar Supply Supply TS JL Structures 12/14/2013 2w 1/11/2014 1w 1/18/2014 1m 2/15/2014 2/15/2014 Contech, Post Tensioning & Grouting (PT&G)
52 Concrete Pump Hire Works TS JL Structures 6/10/2013 7/9/2013 2w 6/24/2013 7/17/2013 1w 7/1/2013 8/27/2013 Pioneer Concrete Pumps 9500704 Not signed correctly Ian Howe Conc Pumps, Premier Concr Pumping, AAA Pro Pumps
56 Site Clearance (Vegetaion) Works AS Earthworks 4/8/2013 Treescape 9500132 Yes Yes Contracts in place
57 Wick Drain Installation Works ME Earthworks 8/5/2013 Brian Perry 9500517 Yes Yes Being finalised with BPC
63 General Fill Supply - Brookby, Whitford and Stephensons Supply ME Earthworks 8/16/2013 Brookby Brookby setup - others supplies required
64 Revetment Rock Supply - Winstones Supply ME Earthworks 8/16/2013 Winstones 9500736 No Ridge Road / Perrys and Winstones to be setup / VB / Holcim
65 Woodhill Sand Supply Supply ME Earthworks 8/30/2013 Woodhill 9501118 N/a N/a Contract and samples required
66 Lightweight Fill (Pumice Sand) Supply - Winstones Supply ME Earthworks 8/30/2013 Winstones 9500736 No Winstones - Pukekawa / Puni
93 Supply of Steel Barriers for TTM Supply HM Early Works Done Hiwaycare Yes Yes
94 Soil stabilising Works HM Early Works Hiway Stabilizers 9500113 Yes Yes Hiway Stablisers
97 Geotechnical Drilling / Instrumentation Works ME Earthworks 8/1/2013 McMillans Drilling 9500712 Yes Yes Contractors previously setup as Boaart Longyear
98 Supply of VCC Instrumentation Equipment Supply TS Structures 8/20/2013 Advanced Instrument Services 9500844 Yes Yes
99 Supply of Steel Casings for Piles Supply TS JL Structures 9/20/2013 1w 9/27/2013 3d 9/30/2013 5w 11/4/2013 11/4/2013 Asmuss Contract to be negotiated and drafted
100 Hyrdoseeding for sed control Works HM Finishing Done Chelsea Landscpes 9500265 Yes Yes
Contract /
Tender Package Complete Tender Supplier / Signed Agreement
Contract Type Discipline Prices Received Review Prices and Award Contract Lead Time Date Required on Site Agreement Insurances Warranties Comments
& Issued Period Contractor Returned
Number
Resp.
Package No. Items / Works to Procure Delegated to
Person
eg Works, Minor Works, Scheduled Duration Scheduled Duration Scheduled Duration Scheduled
Actual Actual Actual Actual Scheduled Actual
Supply, Plant Hire Date Required Date Required Date Required Delivery
102 Traffic Management Subcontractor Works PN Services 8/7/2013 1wk 8/14/2013 8/14/2013 1wk 8/21/2013 Action Traffic 9501089 Yes Yes Tender recommendation issued and approved
103 Machine Guidance Gear Works GH JC Earthworks 8/23/2013 8/16/2013 1 week 8/23/2013 9/2/2013 Trimble of Lieca To be finalised this week
104 Owner Operator - Earthworks Works GH JC Earthworks Luke Glamuzina To be finalised this week
105 Project Sign Minor Works PN Traffic 9/6/2013 41525 9/6/2013 Directions
106 Line Removal - Strip Hog Machine Works PN Traffic Traffic Systems Ltd
115 Air Monitoring Professional Services BD Services 9/27/2013 9/27/2013 41544 9/27/2013 9/27/2013 9/30/2013 41547 Watercare
117 Percussion Drilling for Wick Drain Obstructions Works ME ME Earthworks 10/23/2013 10/23/2013 41571 10/24/2013 10/24/2013 10/25/2013 41572 Inline Drilling Received Procurement required urgently due to plant safety issues with Intorock drilling
119 Temporary Staging Inspection & Sign-off Minor Works TS JL Structures 11/4/2013 Holmes Consulting Group In conjunction with Temp Staging Supply through Concrete Structures
118 Timber Pile supply and instalation Works ME ME Markovina Piledriving Ltd
10 Barge Hire Plant Hire AS Early Works Total Marine Action thro Boarts contract
23 Supply of Anti-Gawk Screens Supply HM Early Works Not required. Fence to be installed to peds and nothing required EB
24 Supply of TTM Devices Supply PN/HM Early Works Done Purchased from NMV
34 Temporary Works Design - Piling Staging Professional Services TS Design Included with Supply from Fletcher
37 Staging Platform for Bridge Piling - Decking Supply TS Structures 8/26/2013 1w 9/2/2013 1w 9/9/2013 1w 9/16/2013 9/16/2013 Included as a part of #36
40 Installation of Micro Piles - NO LONGER REQUIRED Works TS Structures McMillan Drilling Services, Spiral Drillers, Pendletons
43 Steelfixing - NOT REQUIRED: PART OF SUPPLY PACKAGE Works TS Structures Fletcher Reinforcing, Steel & Tube, Sim Reinforcing
48 Delivery of Bridge Beams & Precast Elements - includes delivery Works TS Structures 10/25/2013 2w 11/1/2013 1w 11/8/2013 2w 11/22/2013 11/25/2013 Include as part of Precast Supply Packages #46 & #47
58 Wick Drain Supply (if not included in Works Contract) Supply ME Earthworks 5/15/2013 Included in subcontract
61 Subsoil Drain Install (if not self performed) Works ME Earthworks 9/13/2013
76 Supply & Install Noise Wall Works TS AS Finishing 11/1/2014 Gibbons, Belaire, Total Infrastructure
49 Bridge Bearings Supply Supply TS JL Structures 5/31/2014 2w 6/14/2014 1w 6/21/2014 8w 8/16/2014 8/16/2014 Pacific Rubber Systems
51 Timber Supply for Causeway Deck Supply TS JL Structures 7/7/2015 Not required until 2015
82 Supply of Permanent Precast Concrete Barriers Supply ME Finishing 2/4/2014 Colin Battley - reviewing programme
83 Supply & Install Guardrail Works HM AM Finishing 3/17/2014 John Crouch (SS only), Troy Wheeler (SS & IN)
89 Motorway lighting - Install Lights/Pits & Draw Cables Works HC Finishing 1/27/2014
112 GNRI - Temporary Barriers Variation AS AS/RC/GA - conc barrier requirements for temp layout