Академический Документы
Профессиональный Документы
Культура Документы
1. Identify the attribute that is NOT normally associated with the job of functional
manager.
b) The functional manager is responsible for deciding what resources will be devoted to
accomplishing the task.
c) The functional manager is administratively responsible for deciding how something will be
done.
d) The functional manager is responsible for deciding who will do the work.
Ans: a Section Reference: 3.1 Project Management and the Project Manager
2. According to the authors, the analytic method, when applied to systems, focuses on
__________.
Ans: d Section Reference: 3.1 Project Management and the Project Manager
a) a direct, technical supervisor knowledgeable in the technology of the process being used
b) both generalist/facilitator and have a high level of technical competence in the science of the
project
1
MGO 634 F20 Quiz 4 of 10 Fall 2015
ans: b Section Reference: 3.1 Project Management and the Project Manager
4. According to the authors, three major questions face the project manager with respect
to synthesizing the requirements of a project. Identify the item that is NOT listed as one
of the three major questions.
Ans: b Section Reference: 3.1 Project Management and the Project Manager
Ans: c Section Reference: 3.1 Project Management and the Project Manager
6. The project manager's responsibilities are broad and fall primarily into three separate
areas. Responsibilities to _____________ is NOT one of these.
d) special-interest groups
Ans: d Section Reference: 3.1 Project Management and the Project Manager
7. The project manager must make trade-offs between project progress and process.
Conceptually, this involves trade-offs between the __________ functions.
2
MGO 634 F20 Quiz 4 of 10 Fall 2015
8. During the __________ stage of the project lifecycle, there is no significant difference
in the importance that project managers place on the three goals of cost, time, and
scope.
a) main
b) formation
c) buildup
d) phaseout
9. According to the authors the project manager should be more skilled at __________.
a) general management
b) technology
c) synthesis
d) analysis
Ans: c Section Reference: 3.1 Project Management and the Project Manager
10. According to the authors, of all the characteristics desirable in a project manager,
__________ is the most important.
a) availability
1. A party to a conflict will usually be satisfied when the level of frustration has been
__________.
b) lowered to the point where no action against the other party is contemplated
3
MGO 634 F20 Quiz 4 of 10 Fall 2015
c) lowered because the party realizes the hopelessness of continuing the conflict
2. Most of the conflicts that involve the organization and outsiders have to do with
__________.
a) interpersonal differences
c) technical differences
3. Conflicts within the organization typically differ from conflicts with outsiders in one
important way. As far as the organization is concerned, these conflicts are __________.
4. Which one of the following choices was NOT identified by the authors as one of the
reasons why organizations enter into partnership arrangements with each other?
a) avoidance of litigation
4
MGO 634 F20 Quiz 4 of 10 Fall 2015
6. During project formation, the organizational structure selected will have a major
impact on the ways in which conflicts are handled. Lack of clarity about the relative
power/influence/authority of the PM and the functional managers is a major component
of all conflicts involving __________.
a) contractual obligations
b) property rights
c) budgeting
Ans: d Section Reference: 4.2 Conflict and the Project Life Cycle
7. During project build-up, the project should move from a general concept to
__________.
a) implementation of plans
c) a project charter
d) a project contract
Ans: b Section Reference: 4.2 Conflict and the Project Life Cycle
8. During project build-up, if the project is independent and standalone, the project
manager seeks a commitment of __________ from the functional departments.
a) work
b) materials
c) people
d) budgets
Ans: c Section Reference: 4.2 Conflict and the Project Life Cycle
9. During project build-up, if the project is functionally tied down, the project manager
seeks a commitment of __________ from the functional departments.
5
MGO 634 F20 Quiz 4 of 10 Fall 2015
a) work
b) materials
c) people
d) budgets
Ans: a Section Reference: 4.2 Conflict and the Project Life Cycle
10. The need to manage interfaces and to correct incompatibilities is likely to create
technical conflicts during the __________ phase of the project lifecycle.
a) project formation
b) project buildup
c) main program
Ans: c Section Reference: 4.2 Conflict and the Project Life Cycle
11. __________ problems are comparatively rare during project phaseout because most
have been solved or bypassed earlier.
a) Resource
b) Schedule
c) Authority
d) Technical
Ans: d Section Reference: 4.2 Conflict and the Project Life Cycle
12. Personality conflicts during project phase-out are often caused by __________.
c) pressure to complete the project and anxiety about leaving the project
Ans: c Section Reference: 4.2 Conflict and the Project Life Cycle