Вы находитесь на странице: 1из 20

पशशश्चिम कक्षेश त्रिय भभार पक्षेष ण कक्षे न्द्र कक्षे दभारभा ददी गयदी रक्षेश लियभाशबिशलिटदी सहमशत

OCC Status SN KV Regional Grid Elements under Outage

OCC-512 805 CHANDRAPUR - PADGHE HVDC POLE 2

OCC-513 28 400 KHADKA - BABLESHWAR ON TBC @ BABHALESHWAR

OCC-513 765 Solapur Raichur-I

OCC-513 83 400 SSP DHULE- 2

OCC-513 85 400 400 KV Line#1 Main Bay (Bay 3) at TRNEPL

BAY 705 ( TIE BAY OF 765KV INDORE BINA LINE AND


OCC-513 86 765 ICT II) AT INDORE PS

OCC-513 93 220 Kakrapar-Haldarwa II at Haldarwa

OCC-513 94 400 KARAD - TALANDGE CKT 1 ON TBC @ KARAD

OCC-513 95 400 NAGOTHANE - DABHOL 1

OCC-513 96 400 400KV Bina 1 Main CB of 400KV S/s Bhopal

OCC-513 98 400 Itarsi-Indore #2 Line Reactor at Itarsi

OCC-513 100 765 ICT1_765/400kv_PARLI _PPTL

OCC-513 103 400 Wanakbori - Soja line

OCC-513 104 220 220 KV PGCIL Ckt-I at 220 KV S/s Raigarh

OCC-513 105 400KV SUGEN Bus-1

OCC-513 106 400 KV Bus Coupler Bay at Sugen

OCC-513 107 220 Bhilad -TAPS

125 MVAr, 400 KV B/R at Betul with dia to be kept


OCC-513 108 400 open

OCC-513 110 765 ICT2_765/400kv_SOLAPUR

OCC-513 112 220 220KV Gwalior(PGCIL)-Malanpur-I

OCC-513 113 400 400KV Bina-Bhopal-I

OCC-513 114 220 Bay No.. 210 Future Bay at Boisar

OCC-513 115 220 220 KV Transfer Bus at Bhatapara


OCC-513 116 765 SWITCHABLE LR_765kV_DURG 2_KOTRA PS

OCC-513 117 400 ICT1_400/220kv_RAIGARH

OCC-513 119 765 765 KV Wardha-ICT-3 Tie bay 708 at Wardha

OCC-513 121 765 ICT1_765/400kv_DURG PS

OCC-513 122 400 400 KV LANCO1 & Future_TIE_BAY_420 at Bilaspur PS

400kV Nagda Dehgam Ckt I at Dehgam( A/R of Ckt # 2


OCC-513 123 400 & DIA open at both ends also required)

OCC-513 125 400 407 Bus Reactor Main Bay V-Chal PS

OCC-513 127 400 403 Main Bay of 400 kV Bus Reactor at BDTCL Bhopal

220kV side ICT#2 bay (205bay) at Damoh (During


OCC-513 128 220 outage ICT#2 is in service through TBC )

OCC-513 129 400 Nagda-Dehgam Ckt-II at Nagda

OCC-513 130 400 402 Tie Bay(SSP#1-Khargone) at Rajgarh

OCC-513 131 400 400kV MAPUSA Ckt-II MAIN BAY (403) AT KOLHAPUR

OCC-513 132 765 765kV Kotra # 2 & AT#1 Tie Bay (702) at Tamnar PS

50MVAr Non-Switchable Line Reactor of Nagda-


OCC-513 133 400 Dehgam-II at Nagda.

OCC-513 135 400 404 Main Bay of ICT-2 at BDTCL Bhopal

OCC-513 137 400 Nagda-Dehgam Ckt-II at Nagda

OCC-513 138 400 MAIN BAY (420) OF WARDHA (PG) CKT @ WARORA

OCC-513 140 400 Main bay (409) of Tirora - Warora ckt-2 @ TIRORA

OCC-513 141 400 MAIN BAY (409) of EKTUNI CKT-1 @ TAPTITANDA

OCC-513 142 Kawas-vav line 1 (bay 15)

OCC-513 143 765 765kV D'JAIGARH-RANCHI II

OCC-513 144 765 765kV SEONI-BINA

OCC-513 145 220 220 KV ICT II at 220KV S/s Sukha

OCC-513 146 400 Kasor - GPEC line

Non OCC 400 400Kv Vindhyachal ckt 1 at Korba NTPC

Non OCC 400 400Kv Vindhyachal ckt 2 at Korba NTPC


OCC-513 62 400 ICT1_400/220kv_MAPUSA

OCC-513 400 400KV LINE-2 GCEL-MADESERA,DURG(PGCIL)

NON OCC 400 DBPL SWITCHYARD BUS B

Additional
approved 800 Champa-Kurukshetra Pole 1
outage
OCC-513 29 400 Padgha - Kalwa ckt - 2

OCC-513 400 400KV Irarsi-Indore #1 Line Reactor

VSTPS -SATNA LINE# 2 ( Stage-II, BAY No. 26) at VSTPS


OCC-513 82 end

OCC-513 84 400 315 MVA ICT bank-I at 400 KV S/s Khedamara.

OCC-513 87 765 ICT1_765/400kv_PUNE(GIS)

OCC-513 88 DGEN 400kV Bus B and Bus Coupler Bay 413

OCC-513 89 400 400 KV ICT # 1 at Gwalior with dia to be kept open

OCC-513 91 400 Bay 419(Future Main bay) at Khandwa SS

VSTPS -SATNA LINE# 2 Line Reactor ( Stage-II, BAY No.


OCC-513 92 26) at VSTPS end

OCC-513 38.5 STATCOM-2 (602 BAY) at Satna

OCC-513 38.5 STATCOM-1 (601 BAY) at Satna

OCC-513 400 Dabhol-Nagothane Line-2

OCC-513 99 400 Kasor-Chorania line

400kV NSPCL -RAIPUR LINE-2 & 400kV Bus -2 at


OCC-513 101 400 NSPCL

OCC-513 102 400 Bus-Coupler ( Hadala SS)

OCC-513 109 220 Ostro-Bhachau#2 Line at Bhachau

OCC-513 111 400 Asoj - Kosamba

OCC-513 118 400 765/400KV_ICT1_MAIN_BAY_410 at Seoni

OCC-513 120 765 765kV D'JAIGARH-BILASPUR

OCC-513 124 400 500MVA ICT-2 at Itarsi SS (Dia shall be kept open)

OCC-513 126 400 Bina-Satna-2 Line at Bina


OCC-513 134 220 ICT-2 at Pirana with dia to be kept open

OCC-513 136 400 Bina-Satna-2 Line at Bina

OCC-513 139 400 CHANDRAPUR 2 - WARORA CKT-2

OCC-513 147 Mouda-Wardha LINE-1 (bay 405 and 406)

OCC-513 148 400kV Kudgi-Kolhapur-1

OCC-513 765 765 kV Bus-1 at Aurangabad SS

OCC-513 765 765 kV Bus-2 at Aurangabad SS

OCC-513 32 400 BABHALESHWAR - PADGHE 1

NON OCC 400 EMCO -BHADRAWATI LINE #1( AR IN N/A mode)

OCC-513 33 220 PUSAD - WARDHA (PG)

OCC-513 35 400 Bhinmal- Zerda

OCC-513 36 400 MUNDRA-JETPUR # 1

OCC-513 37 765 SATNA-ORAI

OCC-513 38 220 BHUGAON - WARDHA (PG)

OCC-513 39 400 PARLI-SOLAPUR (LAMBOTI)

OCC-513 90 400 MAIN BUS - 1 @ KORADI

OCC-513 97 400 CHANDRAPUR 2- KUMBHARGAON (NANDED) CKT - 1


For Date 4-Dec-18 On Date 2-Dec-18

From Date From Time To Date To Time Basis

Approved
Continuou
30-Nov-18 9:30 7-Dec-18 18:00 s
Continuou
1-Dec-18 9:00 5-Dec-18 17:00 s

1-Dec-18 9:00 31-Dec-18 18:00 Daily

3-Dec-18 8:00 4-Dec-18 18:00 Continue

Continuou
3-Dec-18 9:00 4-Dec-18 18:00 s

3-Dec-18 9:00 4-Dec-18 18:00 DAILY

3-Dec-18 9:00 7-Dec-18 18:00 Cont.

Continuou
3-Dec-18 10:00 7-Dec-18 17:00 s

3-Dec-18 8:00 13-Dec-18 18:00 Daily

3-Dec-18 9:00 15-Dec-18 18:00 Continue

3-Dec-18 9:00 16-Dec-18 18:00 Cont.

4-Dec-18 10:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 0:00 Daily

4-Dec-18 8:00 4-Dec-18 17:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 21:00 Daily

4-Dec-18 9:00 4-Dec-18 17:00 Daily

4-Dec-18 9:00 4-Dec-18 17:00 Daily

4-Dec-18 9:00 4-Dec-18 17:30 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily


4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:30 4-Dec-18 13:00 Daily

4-Dec-18 9:30 4-Dec-18 18:00 Daily

4-Dec-18 8:45 4-Dec-18 9:00 Daily

4-Dec-18 10:00 4-Dec-18 17:00 Daily

4-Dec-18 10:00 4-Dec-18 18:00 Daily

4-Dec-18 10:00 4-Dec-18 18:00 Daily

4-Dec-18 10:00 4-Dec-18 18:00 Daily

4-Dec-18 14:00 4-Dec-18 17:30 Daily

4-Dec-18 18:00 4-Dec-18 18:15 Daily

4-Dec-18 8:00 4-Dec-18 17:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 11:00 4-Dec-18 17:00 Daily

4-Dec-18 8:00 5-Dec-18 18:00 continous

4-Dec-18 9:00 5-Dec-18 18:00 Cont.

4-Dec-18 9:00 5-Dec-18 18:00 Daily

4-Dec-18 9:00 5-Dec-18 17:00 Continue

Continuou
4-Dec-18 8:00 6-Dec-18 18:00 s

4-Dec-18 9:00 4-Dec-18 12:00 Daily

4-Dec-18 12:00 4-Dec-18 15:00 Daily


4-Dec-18 9:00 4-Dec-18 18:00 Daily

CONTINUO
3-Dec-18 6:00 8-Dec-18 18:00 US

4-Dec-18 9:00 4-Dec-18 18:00 Daily

deferred
Continuou
28-Nov-18 9:00 15-Dec-18 18:00 s
Continuou
1-Dec-18 8:00 10-Dec-18 17:00 s

1-Dec-18 8:00 15-Dec-18 18:00 Continous

Continuou
3-Dec-18 7:30 4-Dec-18 17:30 s
Continuou
3-Dec-18 9:00 4-Dec-18 17:00 s

3-Dec-18 9:00 4-Dec-18 18:00 Cont.

3-Dec-18 8:00 5-Dec-18 18:00 Daily

3-Dec-18 9:00 5-Dec-18 18:00 Daily

3-Dec-18 10:00 6-Dec-18 18:00 Cont.

Continuou
3-Dec-18 7:30 7-Dec-18 17:30 s

3-Dec-18 9:00 4-Dec-18 18:00 Continous

3-Dec-18 9:00 4-Dec-18 18:00 Continous

3-Dec-18 9:00 5-Dec-18 18:00 DAILY

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 6:30 4-Dec-18 17:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 13:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 4-Dec-18 18:00 Daily

4-Dec-18 9:15 4-Dec-18 14:30 Daily


4-Dec-18 14:00 4-Dec-18 14:00 Daily

4-Dec-18 15:00 4-Dec-18 17:00 Daily

4-Dec-18 8:00 4-Dec-18 17:00 Daily

Continuou
4-Dec-18 9:00 6-Dec-18 18:00 s

4-Dec-18 11:00 4-Dec-18 13:00 DAILY

4-Dec-18 9:00 4-Dec-18 13:00 Daily

4-Dec-18 14:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 9:00 6-Dec-18 18:00 daily

Auto Reclosers: Appr


4-Dec-18 7:00 4-Dec-18 17:00 Daily

4-Dec-18 7:00 4-Dec-18 19:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 10:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 18:00 Daily

4-Dec-18 8:00 4-Dec-18 17:00 Daily


Reason For Outage Status

Approved
For Hardware tightening & replacement of faulty disc
insulators and for Annual Outage maintencne Approved
work/Diagnostic work of Sub Station Equipment etc
Quarterly Maintenance work & Reapir scissors of 400KV
P.G Isolator and Servicing and allignment of isolators Approved
work
For OPGW stringing works, Auto to Non Auto request Approved

New relay ABB make REL 670 Retrofitting & Approved


relay testing work

For Bay Annual Maintenance Approved

BAY AMP WORKS Approved

03 nos CB Replacement work and at GETCO hadarwa Approved


End

Overhauling of CGL make SF6 CB Pole column Approved

LE scheme for insulator string replacement & Cold Approved


washing of insulators
Replacement of 400 Kv CB and 3 No 400Kv CTs under Approved
PSDF Scheme. Line will remain charge through Tie CB

Overhauling of Line Reactor at Itarsi end. Approved

CSD commissioning at Parli(New) Approved

Maintenance work Approved

For preventive maintenance Approved

Maintenance of 400KV Bus Coupler Bay Bus -1 isolator Approved


and Sugen Unit 30 Bus-1 isolator..
Maintenance of 400KV Bus Coupler Bay Bus -1 isolator Approved
and Sugen Unit 30 Bus-1 isolator..

Maintenance work Approved

Faulty OTI replacement, Fire fighting painting work and Approved


scheduled AMP work.
For Installing B/U impedance relay and Yph unit Approved
Coservator low oil level rectification works

For line maintenance work Approved

For post monsoon maintenance / Testing work Approved

For Bay AMP Approved

For AMP work Approved


For AMP works. Approved

For AMP works Approved

AMP work at Wardha end Approved

For AMP works Approved

AMP works (CT C Tan ë, CRM & DEW POINT) Approved

Attending Hotspot observed during Thermovision Approved


scanning and other shutdown nature defects in line.

For AMP work Approved

For DO Signal testing Approved

AMP work Approved

For taking out 50MVAr Non-Switchable Line Reactor at Approved


Nagda end for AMP work

Annual Maintenance testing of CB and CT Approved

For Bay AMP works Approved

For AMP works of 702 Tie Bay Approved

For AMP works Approved

For DO Signal testing Approved

For taking 50MVAr Non-Switchable Line Reactor into Approved


service at Nagda end after AMP work
Routine maintainance and diagonastic testing such as
CT tandelta,CRM,IR values,isolater maintainance work Approved
and DCRM
Testing and maintenance of Breaker Approved

(409) Ektuni-I CB diagnostic testing Approved

For annual maintenance and testing of bay Approved


To facilitate Gantry & Equipment erection of under
construction 765KV Bus Reactor bank#3 at Approved
Dharamjaigarh PS & Other ckt A/R in Non-auto mode
required.
AMP for liquidation of defects at 42 Nos of defetcs Approved
Spacer opened

For post monsoon maintenance / Testing work Approved

Relay retrofitting at Kasor & Line Maintenance work Approved

Under
For online SEM meter calibration at Korba NTPC end review
Under
For online SEM meter calibration at Korba NTPC end review
Installation and Testing of Impedance Relay and AMP Approved
Works
REFIXING OF LINE SPACERS AND JUMPER SPACERS OF Approved
LINE-2
Hotline maintenance of Bus B, inside the DBPL Approved
switchyard

deferred
For Pole-3 Stand alone Commissioning works. During
Pole -3 power flow testing Pole 1 cannot be run, so Pole Deferred
1 shutdown
1) is required
Dismentling on continuous
of conductor at loc. No.basis.
1103 to 1106 2)
Tower erection at loc. No. 1104 to 1105 3) Dismentling Deferred
of Tower exsting Loc.No.1104 4) Stringing of conductor
at Loc.No. 1103 to 1106
Line Reactor overhauling works Deferred

ANNUAL BAY MAINTENANCE Deferred

Annual Maintenance Programme. Deferred

ICT AMP, 765kv and 400kv Bay AMP works Deferred

Off line washing job for Bus B Gantry insulators, 4B2 Deferred
isolator and EMVT of Bus.

For Replacement of Bushing Deferred

For ABB CB operating Mechanism Overhauling work & Deferred


Bay AMP work.

ANNUAL MAINTENANCE & ATTENDING OIL LEAKAGE Deferred

HEAT EXCHANGER REPLACEMENT & Software Deferred


Upgradation

Software Upgradation Deferred

PM & equipment testing works Deferred

Line Maintenance work Deferred

Switch Yard Equipment Painting Job Deferred

Breaker DCRM and Bay Maintenance work Deferred

Erection of Bus Duct structure for New bays Deferred

Bay equipment and line maintenance work Deferred

FOR AMP WORK Deferred


Shut down nature defect (for attencd spacer cum
damper open, copper bond missing, socket clavis nut Deferred
missing)
Outage of ICT-2 for installation, testing and Deferred
commissioning of Backup Impedance Relay at Itarsi SS.

online retrofitting of PLCC ch-1 Deferred


Installation & commissioning of new B/U impdance Deferred
relay
Line outage will be required for end to end testing of Deferred
PLCC after retrofitting.

Tighening of earthwire & conductor Deferred

Annual Maintenance Deferred

Attending the Hotspot in Y-phase of WAVE trap & B- Deferred


phase line jumper

For Busbar Protection Testing Deferred

For Busbar Protection Testing Deferred

For Carrying PID Work deferred

for schedule maintenance, jumper tightness and


damper scaper installation Deferred

Auto Reclosers: Approved


PID work Approved

ONLINE OPGW WORK( LINE A/R DISABLEMENT Approved


REQUIRED)
ONLINE OPGW WORK( LINE A/R DISABLEMENT Approved
REQUIRED)
ONLINE OPGW WORK( LINE A/R DISABLEMENT Approved
REQUIRED)

PID work from location no.33 (LILO Point) to PGCIL End Approved

PID testing work. Approved

Online PID testing work Approved

For PID work Approved


WRLDC Reliability Consent System Agency WRLDC Remark
Shall be facilitated after revival of A'bad-Pune-1 w/o LR.
Chandrapur-Padghe Pole-1, All lines from 500kV Pune GIS,
Pune PG, Kharghar, Lonikhand,Lonikhand-II, Kalwa and
Padghe shall be available. In case of contingency load MSETCL MSETCL
management shall be done by SLDC. Maharashtra to review
outages in their internal system.
OK MSETCL MSETCL

OK POWERGRID SRTS-I
System
All other lines at SSP /Dhule (depend on voltage conditions) to SSP/getco/M ownership to be
be inservice with Ar enabled. SLDC Maharashtra / SSP to be GSECL
H mentioned
informed clearly.
Line to be in service with tie bay TRNEPL TRNEPL

both elements to be in service with respective main bays.


NLDC consent required POWERGRID WR-II
All otehr lines at KAPS /Haldarwa to be inservice with AR
enabled. no other element shall be effected. KAPS/sldc POWERGRID WR-II
Gujarat to be informed.
Line to be inservice with TBC bay MSETCL MSETCL
All other lines at RGPPL to be inservice with AR enabled. No
otehr element shall be effecetd. care to be taken. RGPPL to be MSETCL MSETCL
informed.
Line to be inservice with Tie bay MPPTCL MPPTCL

If volatge less than 415kV POWERGRID WR-II

ICT-2 to be inservice with complete dia. NLDC consent WRTS-I WRTS-I


required
All other lines at Wnakbori/Soja to be in service with
complete dia at both ends with AR enabled. No other element GETCO GETCO
shall be effected. care to be taken
ckt-2,3 to be inservice with AR enabled. RTAMC WR1 to be
informed. No other element shall be effected. care to be CSPTCL CSPTCL
taken.
All elements to be inservice with bus-2. Contingency tripping
of Bus-2 while doing work on Bus-1 leads to tripping of all TPL-SUGEN TPL-SUGEN
connected elements. No other s/d to be allowed at adjacent
All elements to be inservice with bus-2.
stations by sldc Gujarat. care to be takenContingency tripping element name
of Bus-2 while doing work on Bus-1 leads to tripping of all TPL-SUGEN TPL-SUGEN not clear, station
connected elements. No other s/d to be allowed at adjacent name missing
stations by sldc Gujarat. care to be taken
All other lines at bhilad/TAPS to be in service with AR enabled. GETCO GETCO
No other element shall be effected. care to be taken
if voltage less than 415kV. No other element shall be effected. POWERGRID WR-II
care to be taken.
ICT-1 to be in service with complete dia. no other element WRTS-I WRTS-I
shall be effected. care to be taken.
all other lines at gwalior/morena/malanpur to be in service
with AR enabled. No other element shall be effected. care to MPPTCL MPPTCL
be taken. load to be managed by sldc MP. RTAMC WR2 to be
informed.
All other lines at Bina/BHOPAL to be in service with complete
dia at both ends with AR enabled. No other element shall be MPPTCL MPPTCL
effected. care to be taken
OK, no other element shall be effected. care to be taken. POWERGRID WR-II

OK, no other element shall be effected. care to be taken. WRTS-I WRTS-I


if voltage less than 775kV. No other element shall be effected. WRTS-I WRTS-I
care to be taken. NLDC consent required.
ICT-2 to be inservice with complete dia. No other element WRTS-I WRTS-I
shall be effected. care to be taken.
ICT to be inservice with main bay. no other element shall be WRTS-I WRTS-I
effected. care to be taken. NLDC consent required.
ICT-2 to be inservice with complete dia. No other element WRTS-I WRTS-I
shall be effected. care to be taken. NLDC consent required
Line to be inservice with main bay. No other element shall be WRTS-I WRTS-I
effected. care to be taken.
Shall be facilitated after revival of ckt-2 w/o LR. All other lines
at dehgam / nagda to be inservice with complete dia at both POWERGRID WR-II
ends with AR enabled. No other element shall be effected.
care to be taken. SLDC MP / Gujarat to be informed.
BR to be inservice with tie bay depend on voltage conditions POWERGRID WR-II
permitted
BR to be inservice with tie bay depend on voltage conditions BDTCL BDTCL
permitted

ICT to be inservice with TBC bay POWERGRID WR-II


All other lines at dehgam / nagda to be inservice with
complete dia at both ends with AR enabled. No other element POWERGRID WR-II
shall be effected. care to be taken. SLDC MP / Gujarat to be
informed.
Both elements to be in service with respective main bays. No POWERGRID WR-II
other element shall be effected, care to be taken.
Line to be inservice with tie bay. No other element shall be WRTS-I WRTS-I
effected. care to be taken.
Both elements to be in service with respective main bays. No
other element shall be effected, care to be taken. NLDC WRTS-I WRTS-I
consent required
if voltage less than 415kV. No other element shall be effected. POWERGRID WR-II
care to be taken.

ICT to be in service with tie bay BDTCL BDTCL


All other lines at dehgam / nagda to be inservice with
complete dia at both ends with AR enabled. No other element POWERGRID WR-II
shall be effected. care to be taken. SLDC MP / Gujarat to be
informed.
Line to be in service with tie bay MSETCL MSETCL

Line to be in service with tie bay ATIL ATIL

Line to be in service with tie bay MSETCL MSETCL


All other lines at kawas/Vav to be inservice with AR enabled.
No other element shall be effected, care to be taken. SLDC PGCIL NTPC
Gujarat / RTAMC Wr2 to be informed.
All other WR-ER lines to be inservice with complete dia at
both ends with AR enabled. No other element shall be WRTS-I WRTS-I
effecetd, care to be taken. NLDC consent required
All other lines at Seoni / Bina to be inservice with complete
dia at both ends with AR enabled. No other element shall be WRTS-II-2 WRTS-I
effected. care to be taken. NLDC consent required.
ICt-1 to be in service with complete dia. no other element
shall be effected. care to be taken. RTAMC WR2 to be MPPTCL MPPTCL
informed. Load to be managed by SLDC MP
All other lines at kasor/ Gpec to be in service with complete
dia at both ends with AR enabled. No other element shall be GETCO GETCO
effected. care to be taken.
Confirm Meter NO NTPC WR 1

Confirm Meter NO NTPC WR 1


Ict-2,3 to be inservice with complete dia. No other element WRTS-I WRTS-I
shall be effected. SLDC Goa to be informed.
Line-1 to be inservice with complete dia. No other element GCEL GCEL
shall be effected.care to be taken. RTAMC Wr1 to be informed.

OK, no other element shall be effected. care to be taken. DBPL DBPL

In view of approved s/d on 765kV Gwalior-Satna ( Sensitivty of WR-1 WR-1


Champa-KKR HVDC outage on Satna-0rai is 7%)

readiness not received MSETCL MSETCL

deferred from site POWERGRID WR-II


Line to be
readiness not received WRTS-1 NTPC inservice with
TBC bay w/o LR
In view of approved s/d on Bhatapara Bus-2 CSPTCL CSPTCL
With consent
deferred from site WRTS-I WRTS-I from
Maharashtra
readiness not received TPL - DGEN TPL - DGEN

deferred from site POWERGRID WR-II

reschedulled to 5th Dec by site POWERGRID WR-II


Line to be
readiness not received NTPC NTPC inservice with
TBC bay w/o LR
deferred from site POWERGRID WR-II

deferred from site POWERGRID WR-II

readiness not received RGPPL RGPPL

deferred from site GETCO GETCO

readiness not received NSPCL NSPCL

deferred from site GETCO GETCO

readiness not received OSTRO WR-II

deferred from site GETCO GETCO

deferred from site WRTS-I WRTS-I

In view of approved s/d on 765kV D'garh-Ranchi-2 WRTS-I WRTS-I

deferred from site POWERGRID WR-II

deferred from site POWERGRID WR-II


deferred from site POWERGRID WR-II

deferred from site POWERGRID WR-II

deferred from site MSETCL MSETCL

readiness not received PGCIL NTPC

readiness not received SRPC POWERGRID

in view of approved s/d on Chandrapur-Padghe HVDC Pole-2 WRTS-I WRTS-I

in view of approved s/d on Chandrapur-Padghe HVDC Pole-2 WRTS-I WRTS-I

In view of approved CP HVDC Pole-2 MSETCL MSETCL

GMR WAROR GMR


WRPC consent required A WARORA

ved
OK MSETCL MSETCL

OK POWERGRID NR-1

OK POWERGRID WR-II

OK POWERGRID WR-II

OK MSETCL MSETCL

OK MSETCL MSETCL

OK MSETCL MSETCL

OK MSETCL MSETCL
Sent Date WRLDC
Utility
NLDC Remark Readiness Approval
Readiness Timing Number

Ready 11/23/2018 12:35 140669

Ready 11/28/2018 15:24 140694

140696

ready 11/30/2018 17:05 140720

READY 11/30/2018 14:45 140721

R READY 11/30/2018 12:43 140722

C
Load managed READY 11/30/2018 12:50 140723
on 400KV
Talandge-2 & READY 11/30/2018 15:40 140724
load shifted on
LoadTBC on
managed
03.12.2018
on Dabhol- Ready 11/30/2018 15:44 140725
Nagothane-II
R READY 11/30/2018 15:31 140726

C READY 11/30/2018 12:42 140727

C Ready 12/1/2018 12:28

READY 12/1/2018 14:17 140730

R READY 12/1/2018 1:35 140731

R READY 12/1/2018 1:09 140732

R READY 12/1/2018 1:08 140733

ready 12/1/2018 15:25 140734

R READY 12/1/2018 11:09 140735

R Ready 12/1/2018 13:14 140736

R ready 12/1/2018 11:24 140737

R ready 12/1/2018 11:25 140738

R READY 12/1/2018 11:10 140739

R Ready 12/1/2018 12:32 140740


R Ready 12/1/2018 12:32 140741

R Ready 12/1/2018 12:37 140742

R Ready 12/1/2018 12:33 140743

R Ready 12/1/2018 13:06 140744

R READY 12/1/2018 12:34 140745

R READY 12/1/2018 11:10 140746

R READY 12/1/2018 11:11 140747

R READY 12/1/2018 14:02 140748

R READY 12/1/2018 11:12 140749

C READY 12/1/2018 11:12 140750

R READY 12/1/2018 11:12 140751

R Ready 12/1/2018 12:34 140752

R Ready 12/1/2018 12:34 140753

C READY 12/1/2018 11:12 140754

R READY 12/1/2018 14:24 140755

C READY 12/1/2018 11:13 140756


400KV PGCIL
Line will be
charged READY 12/1/2018 17:42 140757
through Tie CB
421.
ready 12/1/2018 10:23 140758

CB Diagnostic ready 12/1/2018 17:43 140759


testing work

Ready 12/1/2018 10:02 140760

C Ready 12/1/2018 12:35 140761

R Ready 12/1/2018 12:35 140762

R ready 12/1/2018 11:25 140763

READY 12/1/2018 14:18 140764

Ready 2/11/2018 20:53

Ready 2/11/2018 20:53


C Ready 11/30/2018 13:16

Ready 140766

Ready 11/30/2018 19:59

Ready 11/22/2018 14:52

Deferred 11/28/2018 12:37

R READY 11/30/2018 14:34

R deferred 11/30/2018 14:11

R DEFERRED 11/30/2018 12:54

R READY 11/30/2018 12:45

DEFERRED 11/30/2018 13:01

DEFERRED 11/30/2018 13:01

400 KV Asoj-
Chorania line DEFER DUE TO
KASOR GPEC 12/1/2018 14:17
no. 01 A/R will LINE OUTAGE
remain out

defer from site 12/1/2018 15:25

DEFER 12/1/2018 14:17

R Deferred 12/1/2018 12:33

R Ready 12/1/2018 12:33

R Deferred 12/1/2018 11:11

R Deferred 12/1/2018 11:12


C Deferred 12/1/2018 12:55

R Deferred 12/1/2018 11:13


Tighening of
earthwire & Deferred 12/1/2018 17:43
conductor

Ready 12/1/2018 10:36

Ready 12/1/2018 10:36

Ready 43435.741979

ready 11/27/2018 9:49

Ready 43435.742153

Ready 43435.370058

Ready 43435.370116

Ready 43435.742326

Ready 43435.742593

Ready 43435.742743

Ready 43435.74294

Вам также может понравиться