TREN DE ACTIVIDADES E N E R O F E B R E R O M A R Z O

EDIFICIO 1 - CONDOMINIO ALEGRA SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6


L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D
Actividad Día Und
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11

CASCO DE MUROS Y TECHOS


MUROS
Acero en Placas 1 kg 1549.17 1549.17 1549.17 1549.17 1549.17 1549.17 1549.17 1549.17 1549.17
Encofrado en Placas m2 640.67
2
Concreto de Placas m3 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86 46.86
TECHOS
Encofrado de Techos m2 309.83
3
Acero en Techos kg 1342.62 1342.62 1342.62 1342.62 1342.62 1342.62 1342.62 1342.62 1342.62
Concreto en Techos 4 m3 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62 26.62

ºº