PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 04/04/2017 &
Item Description:NON-STD. STRINGER DETAILS – (NSTD-1) Date : 05/04/2017

Paint Spec 19260008-PRC-ME-GNR-


Ref.DWG/Documents 192-60-001-DRW-ME-CD3-2005 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal
Surface DFT
Item / part No. Result
preparation Avg(in
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 04/04/2017 04/04/2017 05/04/2017 04/05/2017 ACC
11.00 AM 03.50 PM 9.30 AM 02.35
*** Refer attached annexure PM
for DFT ***
NSTD1 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME Mr.K.SIVA KUMAR P.JAGADEESH KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD3-2005 NON-STD. STRINGER DETAILS – (NSTD-1)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
NSTD1 69 64 65 68 64 66 178 175 176 177 174 176 54 58

Ardee Engineering TUV-SUD


S – (NSTD-1)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
56 52 54 54.8

KPCL
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 04/04/2017 &
Item Description:NON-STD. STRINGER DETAILS – (NSTD-4) Date : 05/04/2017

Paint Spec 19260008-PRC-ME-GNR-


Ref.DWG/Documents 192-60-001-DRW-ME-CD3-2006 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal
Surface DFT
Item / part No. Result
preparation Avg(in
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 04/04/2017 04/04/2017 05/04/2017 04/05/2017 ACC
11.00 AM 03.50 PM 9.30 AM 02.35
*** Refer attached annexure PM
for DFT ***
NSTD4 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME Mr.K.SIVA KUMAR P.JAGADEESH KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD3-2006 NON-STD. STRINGER DETAILS – (NSTD-4)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
NSTD4 66 64 62 63 64 63.8 179 175 174 175 170 174.6 55 58

Ardee Engineering TUV-SUD


S – (NSTD-4)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
57 52 54 55.2

KPCL
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Inspection 04/04/2017 &
Item Description:NON-STD. STRINGER DETAILS – (NSTD-2,3) Date : 05/04/2017

Paint Spec 19260008-PRC-ME-GNR-


Ref.DWG/Documents 192-60-001-DRW-ME-CD3-2007 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal
Surface DFT
Item / part No. Result
preparation Avg(in
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 04/04/2017 04/04/2017 05/04/2017 04/05/2017 ACC
11.00 AM 03.50 PM 9.30 AM 02.35
*** Refer attached annexure PM
for DFT ***
NSTD2,3 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME Mr.K.SIVA KUMAR P.JAGADEESH KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD3-2007 NON-STD. STRINGER DETAILS – (NSTD-2,3)


PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
NSTD2,3 63 62 65 60 60 62 170 174 174 172 173 172.6 58 54

Ardee Engineering TUV-SUD


S – (NSTD-2,3)
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
57 56 55 56

KPCL
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:TAIL END ASSEMBLY & DETAILS FOR CD3 & Inspection 04/04/2017 &
GCD3 Date : 05/04/2017

Paint Spec 19260008-PRC-ME-GNR-


Ref.DWG/Documents 192-60-001-DRW-ME-CD3-2008 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal
Surface DFT
Item / part No. Result
preparation Avg(in
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 04/04/2017 04/04/2017 05/04/2017 04/05/2017 ACC
11.00 AM 03.50 PM 9.30 AM 02.35
*** Refer attached annexure PM
for DFT ***
TAIL FRAME -CD3 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME Mr.K.SIVA KUMAR P.JAGADEESH KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD3-2008 TAIL END ASSEMBLY & DETAILS FOR CD3 & GCD3
PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
TAIL FRAME 69 65 64 65 66 65.8 174 177 176 179 170 175.2 55 58

Ardee Engineering TUV-SUD


AILS FOR CD3 & GCD3
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.
56 59 54 56.4

KPCL
PAINTING INSPECTION REPORT

PROJECT WAGON LOADING STATION PHASE -I


Manufacturer ARDEE ENGINEERING COMPANY Report No :
Item Description:HEAD PULLEY FRAME ASSB. DETAILS FOR CD3 Inspection 04/04/2017 &
& GCD3 Date : 05/04/2017

Paint Spec 19260008-PRC-ME-GNR-


Ref.DWG/Documents 192-60-001-DRW-ME-CD3-2008 No: 0002-Rev 0

Used Measuring and test Equipment Ref.(if applicable) : DFT Meter SL NO:150

PAINT DETAILS
PRIMER COAT INTERMEDIATE COAT FINAL COAT
Manufacturer HEMPEL HEMPEL HEMPEL
Description Hempardur avent guard Mastic grey Hempathane
PIGMENT:076113064 BASE :077024315 BASE :77091962
Batch No
BINDER :'076071510 HARD :076102884 HARD :77081656
OBSERVATIONS
Temperature 38 deg C Relative Humidity ~ 67-80 %

DFT Toatal
Surface DFT
Item / part No. Result
preparation Avg(in
Primer Coat Intermediate final Coat microns)
Coat
Date / Time 04/04/2017 04/04/2017 05/04/2017 04/05/2017 ACC
11.00 AM 03.50 PM 9.30 AM 02.35
*** Refer attached annexure PM
for DFT ***
HEAD FRAME -CD3 SA 2 1/2 readings ***

REMARKS:

PREPARED BY WITNESSED BY VERIFIED BY


ORGANIZATIONS
ARDEE ENGINEERING TUV-SUD KPCL
NAME Mr.K.SIVA KUMAR P.JAGADEESH KUMAR

SIGNATURE

DATE
WAGON LOADING STATION PHASE-I

ANNEXURE OF PAINTING REPORT No:AEC/PIR/

DRAWING Nos 192-60-001-DRW-ME-CD3-2009 HEAD PULLEY FRAME ASSB. DETAILS FOR CD3 & GC
PART Nos: PRIMER(HEMPADUR AVANTGUARD)-60 Min INTERMEDIATE(MASTIC GREY)-170 Min FINAL(HEMPATHANE)
SPOTS 1 2 3 4 5 Avg. 1 2 3 4 5 Avg. 1 2
HEAD FRAME-
CD3 63 65 62 64 60 62.8 175 174 176 177 174 175.2 52 50

Ardee Engineering TUV-SUD


DETAILS FOR CD3 & GCD3
FINAL(HEMPATHANE)-50 Min
3 4 5 Avg.

50 51 53 51.2

KPCL