Вы находитесь на странице: 1из 6

Page 1 of6

"DEAD" CIRCUITS ARE NOT ALWAYS DEAD

Giuseppe Parise (Fellow IEEE) Erling Hesla (L. S. M. IEEE)


Electrical Engineering Dept. Hesla & Associates
"Sapienza" University Camano Island, Washington USA
parise@ieee.org e.hesla@ieee.org

Abstract. Some work activities in electrical electric shock and/or the effects of short circuits and
installations are sensitive to unexpected sources, arcing. Dead working is obviously the preferred basic
especially when working on conductors to be broken procedure. Making certain that a circuit is 'dead' can
or joined or on overhead lines. Generally there is involve more than simply opening a switch. In dead
uncertainty about existence, gravity level, risk or working, de-energizing is only one part of creating an
seriousness of exposure to the unexpected sources. electrically safe work condition.
The possibility of unexpected electrical energy, the What, exactly, is the meaning of 'de-energized'?
need for additional protective measures and its The term 'de-energized' can be found in several IEC
resolution frequently are decisions made under and IEEE Standards and documents where it is
pressure in the field, entrusted to the person defined as "free from any electrical connection to a
performing the work. source of potential difference and from electric
The authors submit that methods to detect charge; not having a potential different from that of
unexpected energy sources, together with guidelines the earth." [3]. Determining whether or not there may
for addressing such situations, can and should be be an additional energy sources and if so, the nature
developed for incorporation into safety procedures. of the source and the best approach to removing it,
The authors also indicate approaches to system can be a difficult and uncertain process involving
design that can reduce exposure to unexpected power extensive analysis of the system.
sources. A practical approach is to find out the presence
and magnitude of currents on the working circuits,
Index terms - Safety procedures, Employee such as grounding conductors and overhead lines, by
Workplaces, Maintenance & Operation, Risk detection tests or measurements in the field that
assessment, Overhead Lines Safety verify the effectiveness of the protective measures. In
case the measures should prove to be insufficient, the
tests will identify:
INTRODUCTION - the need to disconnect all additional interfering
sources of energy to comply fully with the basic first
Circuits may be energized from many sources in requirement of dead work
addition to the obvious one of a metallic connection - or alternatively, the need to adopt live working
through a switch or breaker. Examples of less procedures such as working with insulating glove or
obvious energy sources include capacitors, transfer with bare hands, as suggested by EN 50110-1 and the
switches, UPS, batteries, mechanical sources equivalent by NFPA 70E.
(rotating motors), electrostatic coupling, magnetic For the sake of brevity, this paper focuses on
coupling, and others. Creating an electrically safe situations where the source of unexpected energy is
condition at the work location is mandatory for the an adjacent power line. The reader will have little
duration of the work itself, including safety from difficulty in applying the same line of reasoning to
unexpected power sources. other sources of unexpected energy.
European Standard EN 50110-1, Operation on
electrical installations [1], divides the work into three ACTIVITIES SENSITIVE To UNEXPECTED SOURCES
different procedures: 1- dead working (the European
definition of de-energized work); 2- live working; Some activities are sensitive to unexpected
and 3- working in the vicinity of live parts, very sources and in these cases, depending on the
similar to NFPA 70E [2]. These procedures are electrical energy available, these sources can cause
founded on the use of protective measures against injury or death. EN 50110-1 highlights, as sensitive

978-1-4244-9500-9/11/$26.00 © 2011 IEEE


Page 2 of6

to unexpected sources, work where the actIvIty potential between conductors and ground to a safe
requires conductors to be broken or joined. These level; or by equipotential bonding at the work
operations request a direct contact of workers with location in order to avoid the possibility of workers
bare conductors and not by insulated devices. inserting themselves as conductors in an induction
Under these circumstances there is a risk that loop.
potential differences will appear on the installation, For the problem related to induction, NFPA 70E
in which case suitable measures such as bonding [2], sub clause 2-1.1.3 (f) recommends: where the
and/or grounding must be taken at the work location possibility of induced voltages (Figure I) or where
before the conductors are broken or joined as line stored electrical energy exists, ground the phase
conductors or grounding conductors in HV/MV/LV conductors or circuit parts before touching them.
systems. A hazard is presumed to exist if the induced
These conductors are grounded or short circuited by voltage is 50 volts (rms) or more that is sufficient to
proper or mobile equipment that avoid the risk of cause the threshold current of perception (1 rnA)
electric shock for direct contact when potential through the body resistance of a person (0.5 kQ) not
differences will surge. protected from injury due to involuntary reactions
Unexpected power sources can appear on dead or de­ from electric shock [5].
energized lines. Depending on the electrical energy
available, these voltages can cause injury or death. Ground-leakage currents and ground fault
These unexpected sources are generally: [1], [2], [4]: currents.
- induced voltages and capacitive recharging A risk of potential differences could appear on
- ground-leakage currents and ground fault grounding conductors that are to be broken or joined.
currents A special case can be considered the grounding
- accidental contact with other circuits and conductors in a data center, because of the grounded­
penetrating an "unknown" space. leakage currents that are as higher than multiple
Unexpected power sources can appear particularly servers are connected to the same power source.
when working on component disconnections and on For this paper we assume that for bare overhead
overhead lines ( Figure I). lines and bare conductors, grounding and short­
circuiting will be carried out on all sides of the work
location on all conductors entering this location. Note
that this grounding creates closed loops that make
possible circulating currents in the working circuits,
derived by ground faults or by induction. Ground
fault currents generally have a short duration since a
protective device clears the circuit. The steady
induced currents could be dangerous because they
may introduce overvoltages in conductors being
disconnected.

Accidental contact with other circuits and


Figure 1 Unexpected sources can happen in dead penetrating an "unknown" space.
working on overhead lines Where it is reasonable to anticipate that the
conductors or circuit parts being de-energized could
Induced voltages.
contact other exposed energized conductors or circuit
EN 50110-1, [1] sub clause 6.1.1 warns: conductors
parts, apply ground connecting devices rated for the
or conductive parts in the proximity of live
available fault duty.
conductors may be electrically influenced; that is, the
In order to control the electrical hazards in the
live conductor may induce a voltage in the adjacent
vicinity of live parts protection may be provided by
conductor. In addition to the requirements for dead
either screens, barriers, enclosure or insulating
working or working in the vicinity of live parts,
covering [I] (Figure 2)..
specific precautions must be taken when working on
This covering is a rigid or flexible cover made of
electrical systems influenced by induction
insulating material used to cover live parts and/or
(particularly for work on overhead lines) either by
adjacent parts in order to prevent accidental contact .
grounding at adequate intervals in order to reduce the

978-1-4244-9500-9/11/$26.00 © 2011 IEEE


Page 30f6

IMPACT OF ARCHITECTURE ON INTEGRITY OF


ELECTRICAL INSTALLATIONS

Statistics show that many electrical accidents and


fatalities involve work near overhead electric lines
(see 10.5.1 [4]). Many times, due to the need to
maintain service continuity, lines are kept energized
while work is being performed near them. Frequently
situations are such that de-energizing all sources of
induction is not possible because of the impact on
other electrical services. Commonly the working
zone sources are de-energized, while adjacent lines or
Figure 2 The insulating covering is a rigid or flexible other exposed energized conductors or circuit parts
cover made of insulating material used to cover live remain energized to guarantee service continuity.
adjacent parts in order to prevent accidental contact. Given the growing demand for greater safety and
"A task that is encountered often, not only by service continuity, situations that require de­
electrical personnel, but by many employees in energizing essential critical components (such as
different crafts, is to penetrate a wall, drill into a transmission lines) must become rare.
floor, or excavate the earth, or otherwise penetrate High availability and integrity requirements for all
into a space containing unknown things. Many loads or for parts of loads have to be satisfied by
shocks, injuries and quite a few deaths have resulted means of a system architecture that overcomes fault
from doing such tasks without doing a thorough job conditions by adopting more independent power
of investigating what might possibly be in that space. sources and by introducing adequate components and
These unknown areas might contain other circuits or modeling suitable for the configuration of the
electric lines." (see 10.5.5 Penetrating Into distribution system.
"Unknown" Space [4]). Usually these situations are The level of complexity of an electrical system
recognized. will increase for overcoming contingency conditions,
Generally, however, there is uncertainty about the such as the loss of a generator, a transmission line, or
existence and gravity level of exposure to unexpected a transformer. This complex configuration allows
sources. preventive and curative maintenance to be carried out
Design configuration (discussed later in this on all of the electrical distribution system upstream
paper) is outside the realm of the operator; hence the without interrupting globally the power supply.
operator is obliged to work with the circuit as it Design of HVIMVILV supply substations could
exists. Mathematical models for predicting voltages incorporate configurations of independent sub­
and currents are very arduous considering the systems that avoid interferences or inductive
numerous parameters that are difficult to define, coupling with other systems, thereby meeting
particularly for transient phenomena, and in any case
such models are not appropriate for use in the field
by an operator.
Nevertheless, when one suspects that non­
negligible energy will appear or be imposed,
additional measures are desirable to provide an extra
margin of safety assurance, such as safety grounds or
equipotential grounding, to minimize the possibility
of accidental energization from unexpected sources.
Operators in the field require adequate and efficient
suggested field tests to verify the presence or absence
of unexpected sources in each specific case, for
without such information it is difficult to set firm
criteria for additional measures.
Figure 3 A very compact HV component.

978-1-4244-9500-9/11/$26.00 © 2011 IEEE


Page 4 of6

requirements for worker safety and service exposure these systems often have due to their length
continuity. and location.
The new generation of very compact HVIMV/LV Many industrial facilities and utilities require
components doesn't have to cause an higher temporary personal protective grounding as measures
induction among adjacent equipment and systems in essential for all aerial power line works and not
stations (Figure 3) and transmission lines. simply as additional protection in relation to the risk
The compact execution of components has to assessment of each specific work (see 10.4.3
contribute to reduce the electrical interferences and to Temporary personal protective grounding [4]).
increase the ergonomic safe distances than to reduce Additional requirements can be applied
the total space size of the sub stations. effectively not only to the personal protective
equipment and to passive protection (like additional
This paragraph touches on significant design temporary grounding and equipotential bonding at
considerations that apply prior to installation, but are the work location) but also to active protection
not usually suitable for existing installations. against energy from unexpected sources by de­
energizing all sources of induction, disconnecting by
ADDITIONAL REQUIREMENTS OF MAXIMAL CAUTION isolated devices the paths for current circulation, or
by adopting live working procedures. Frequently in
A key element in the success of any safety practice, however, situations are such that de­
program is employee awareness that no violation of energizing all sources of induction is not possible
the program is acceptable, implying that the program because of the impact on other electrical services.
addresses all situations that can be foreseen within Standard IEEE C2-NESC [6], part 4 Sec.422
reason. Generally, the program highlights minimum Overhead line operating procedures, sub clause C 5
safety measures that are realistic for several Installing and removing wires or cables, recommends
situations. To be effective, a program for safe "Employees working on or in the vicinity of
working practices should be written in specific, equipment or lines exposed to voltages higher than
rather than general, terms. Ultimately the degree of those guarded against by the safety appliances
caution or safety that is required will be a decision provided shall take steps to be assured that the
made in the field, entrusted to the wisdom and equipment or lines on which the employees are
scrupulousness of the person performing the work working are free from dangerous leakage or
who will base decisions on safety instructions and on induction or have been effectively grounded". Before
perceptions of conditions in the field. starting work, the canonical requirements (''the five
Without clearly defined safety procedures for safety rules" of EN 50110-1 or the equivalent "six
such situations, resorting to additional requirements safety rules" of the NFPA70E) ensure that the
based on intuition or "guesses" can obviate the electrical installation at the work location is
validity of the program. It is not reasonable for the meticulously de-energized and secure for the
person performing the work to be saddled with duration of the work ([1],[2],[5],[6]). In other words,
decisions involving additional protection that are after the work zone has been identified it is not
based on judgments that have subjective and variable sufficient to disconnect completely and to secure
threshold values. Additional requirements determined against re-connection; the rules require verification
in the course of the work may be irrelevant or that the installation is actually de-energized.
inappropriate, unwittingly imposing exaggerated Absence of objective tests to verify the levels of
requirements of maximal caution or worse still, unexpected sources of energy and the adequacy of
jeopardizing the entire safety procedure. Operators related additional protection measures expose the
are not incompetent; nevertheless it is well known worker to risk of electrocution [8]. Specific
that very many workers involved in accidents were instructions on how to determine and cope with
skilled, experienced, and mature. unexpected sources should be part of the safety
Without question, carefully defined safety instructions given to the worker.
requirements for unexpected sources of energy must The shortcoming today is that standard procedures
become a mandatory part of safety procedures. don't recommend conventional tests to assess the
Additional requirements for maximum caution exposure and to improve decision-making regarding
usually are established for aerial power line work on additional measures for the safety program.
power systems over 1kV because of the increased

978-1-4244-9500-9/11/$26.00 © 2011 IEEE


Page 5 of6

RECOMMENDATION In case the measures should prove to be


insufficient, it would stress the need to disconnect
The authors strongly recommend that industrial also all the sources of induction, complying fully
users, utilities, standards organizations, and all with the basic first requirement of dead work.
involved in electric works collaborate to set concrete In other way, it would stress the need to adopt live
guiding criteria at the standard level for tests to detect working procedures, like insulating glove working or
unexpected sources, initially for the steady ones and bare hand working, methods suggested by EN 50110-
subsequently for transient sources. The following 1 or equivalent by NFPA 70E.
outline is offered as a starting point. A motto says it is safer to work live and to know
Conventional detecting tests of appropriate it than work dead but believe it.
simplicity are needed to discover the presence and
magnitude of currents on the working circuits, like CONCLUSIONS
conductor junctions, overhead lines, grounding
conductors. Standard criteria and tests for unexpected energy
An easy method of checking current draw with sources will help and support the person performing
any electrical set-up is to adopt an amp clamp. The the work by defining detection steps of appropriate
jaws of the clamp are spring loaded so that they can simplicity together with additional safety measures.
be clamped around a cable. It is non-invasive because This integrative rule could be added to the canonical
it is not necessary to plug anything in to the line requirements of dead work as the final one in order
(Figure 4). It will be safe in any case because it has to of execution.
be operated at the end of the execution of the Documented and certified records in the cases of
canonical procedure that ensure the electrical sensitive works will enforce conscious decision­
installation at the work location is de-energized. making regarding choice of additional protective
measures.

REFERENCES

[1] European Standard EN 50110 (-1,-2): 1996-12


"Operation of electrical installations" CENELEC.
[2] NFPA 70E, Standard for Electrical Safety
Requirements for Employee Workplaces, 2004
Edition
[3] 100-1996 IEEE Standard Dictionary of Electrical
and Electronics Terms.
[4] 902-1998 IEEE Guide for Maintenance,
Operation and Safety of Industrial and
Commercial Power Systems (IEEE Yellow
Book).
Figure 4 Detecting test of the presence and
[5] OSHA 1910.269 Instruction CPL 2-1.38,
magnitude of currents on the working component
Enforcement of the Electric Power Generation,
Additional actions could be: Transmission and Distribution Standard
- to apply the equipotential bonding at the work [6] ANSI/IEEE C2-National Electrical Safety Code
location by insulated devices in order to avoid (NESC)
induction loops, [7] G. Parise, W. Moylan, P. E. Sutherland:
- and/or to disconnect temporarily and opportunely Electrical safety for employee workplaces in
some grounding and short circuiting device or Europe and in USA IEEE Transactions on Vol.
equipment, in order to open the current loop. 41 n. 4 , July-August 2005 Pages:l091-1098
Repeating the detection tests it must to be verified [8] G. Parise, E. Hesla "Dead work is vulnerable to
the absence of current on the working circuit that is unexpected power sources", 2010 IEEE/I&CPS
the effectiveness of the protective measures of the Tech.Conf., Tallhassee, Florida, USA, May 9-13
bonding and of the grounding disconnection [9] G. Parise, R.E. Nabours, B. McClung "Relevance
respectively. of competence in risk reduction for electrical

978-1-4244-9500-9/11/$26.00 © 2011 IEEE


Page 6 of6

safety" Transactions IEEE/IAS Vol. 44 n.6 globalization. He is professional engineer in several


November December 2008 Page(s): 1892 - 1895 States and has served as an expert witness.

Giuseppe Parise (M'82-SM'03-


Fellow '10)) received his
Master's degree in Electrical
Engineering from the University
of Rome in 1972. He has been at
Department of Electrical
Engineering of the University of
Rome "La Sapienza" ever since
1973 and is currently a Full Professor of Electrical
Power Systems. He has authored about 200 papers
and two patents. Since 1983, he has been a member
of Superior Council of Ministry of Public Works. He
is active in IEEE/IAS (past Member at Large of
Executive Board), Chair of Electrical Power Systems
Sapienza University researchers, chair of Italy
Section Chapter IA34, member of subcommittees, in
CEI (Italian Electrical Commission), in AEIT
(Electrical Italian Association), he is past President
of AEIT Rome's Section and President of Rome's
Electrical Professional Engineering Voluntary
Committee. Since 1975 he has been a Registered
Professional Engineer; he has been designer of Power
Electrical Systems in Buildings Complexes like in
Roma Sapienza University City and Engineering
Faculty, Polyclinic Umberto I, Italian Parliament,
Campus Biomedical Research Center.

Erling Hesla (S'46; M'48; SM'62;


LSM'86) was born and educated in
Canada, graduating from the
University of British Columbia
('47) with the degree of Bachelor of
Applied Science (EE). He was
employed by Canadian General
Electric Company, Cobast Brazil,
and Scott Paper Company before moving into
consulting practice. He also founded a panel
manufacturing firm and a robotics control firm. He
holds three patents relating to hearing aid devices. He
has been active in AlEE and IEEE, for example:
Chair of the "Yellow Book" (902-1998), earlier as
Chair of a chapter of the "Red Book" (141-1983),
past Member-at-Large of the lAS Executive Board,
and past Chair of lAS Chapters
Technical&Professional Outreach Committee. He
received the RAB Larry K. Wilson Transnational
Award ('98) for innovative promotion of IEEE

978-1-4244-9500-9/11/$26.00 © 2011 IEEE

Вам также может понравиться