Академический Документы
Профессиональный Документы
Культура Документы
A Practical Approach to Modelling LNG Train Design for Minimizing Measurement & Allocation Uncertainty
www.daniel.com
The calculation process requires such information as: • Laboratory Analysis Uncertainties
• Calibration Procedures, frequency and tolerance
• Primary Measurement Element Uncertainties (Orifice, This information is used to calculate the individual Measurement
Turbine Meter, Coriolis, USM, Etc.) System Uncertainties and their consequent contribution to the
• Secondary Instrument Uncertainties (DP, Pressure, overall LNG Train Metering Allocation Uncertainty (calculated
Temperature, Densitometer, Flow Computer, etc.) separately by the MEM).
• Correction Algorithms, Process Simulation Typical Custody & Allocation Measurement Systems include:
Assumptions, etc. • Gas Pipeline Meters (Custody)
• Train Inlet Meters (TIM) (Allocation) identify any “high risk” metering
• Train Liquid Output Meters (Allocation) elements in the system and establish the overall Allocation
• Train Output Meters (Allocation) Uncertainties.
• Storage Tank Measurements (Stock/Allocation)
• Fuel Gas Meters (Allocation The results are typically presented as follows:
• Flare Gas Meters (Allocation)
• Gas Recycle Meters - where fitted (Allocation) • Measurement Uncertainty of each measurement point
• Tanker Loading Measurements (Custody) expressed as a percentage and in terms of product
• Measurement Uncertainty associated with the Plant
Using Figure 3 Output Data, the MEM user can enter the Balance expressed as a percentage and in terms of
estimated measurement uncertainty relating to the metering product
element Operating Condition, thus enabling the Model to • Measurement Uncertainty associated with the Plant
simulate most working conditions and reflect the additional Allocation expressed as a percentage and in terms of
uncertainty in Allocation for those conditions. This can be product
particularly helpful where the operator needs to be cognisant • Cost based Risk Analysis to contributing Fields and
of the effect that instrument malfunctions or other failures may Owners for various operating scenario’s
have on the final Allocation uncertainty for the system.
Thus, once the initial uncertainty analysis has been performed on
4 MEASUREMENT EXPOSURE MODEL (MEM) each metering system to establish the Allocation measurement
The Measurement Uncertainty Assessment forms an essential point Inputs, then the MEM analysis can be performed to asses
input to the MEM. In cases where the LNG Plant is not yet the sensitivity of these points on the Plant Balance & Allocation
designed, design estimates of measurement uncertainty can and the results documented.
be entered into the MEM such that the Design Engineers can
accurately assess their impact on the Plant Allocation. This Any trouble spots highlighted can be re-assessed in order to
aspect of the MEM is not to be underestimated, as it could save maximize the Plants performance. In this way, attention need
considerable Capital Expenditure on unnecessary design for only be focused on those elements that most affect the system
uncritical elements of the Plant Measurement System. In the and the reduced risk associated with the changes can be
identified by the model.
case of an existing LNG Plant, weaknesses in the
measurement systems
provided can be identified,
thus providing substantial
justification for change,
in terms of misplaced
Allocation Revenue.
As can be seen from the Mimic illustrated in Section 2.0, the Assumptions: Gas Price $ 5.00 per MMBtu,
whole Allocation Process depended on the Train Inlet Meters Discount Factor of 10%,
(TIM) to enable back allocation of all the Atlantic LNG Plant Capital Outlay = Loss production + Cost of project= $25.2MM
OUTPUT products to the Gas Delivery Points (GDP), it follows Project Life cycle 20 years.
that their measurement accuracy is of prime importance. The
MEM demonstrated the cost of the measurement uncertainty Of interest to note, is that once other projects are undertaken
to the Operators and their Partners by reference to a live Mimic which increases the 576 TBtu for the facility then this project
responding to reported Allocation data. financing can be further enhanced, therefore giving economic
benefits to perpetuity. Therefore it is imperative that on an LNG
5 MEASUREMENT PROJECTS JUSTIFICATION complex inlet measurement uncertainty be optimized.
The objectives of Capital expenditure plant projects can be
generally categorized into two main areas: 6 TRAIN INLET MEASUREMENT
As shown from the MEM an improvement in inlet measurement
• Maintaining and Sustaining Production (Reliability meant a significant reduction in LNG allocation product
Projects): Major upgrades and/or overhauls to plant uncertainty. The challenge for the project team would be
equipment aimed at improving the cost of operation to improve the Train inlet measurement to 1% or better thus
and for mitigating against equipment obsolescence. improving the allocation uncertainty by 2%. The project team
• Throughput and Yield Projects (Optimization chose to improve on the existing single path ultrasonic meters
Projects): Equipment enhancements and upgrades by replacing them with multi path ultrasonic meters. Since the
geared towards increasing the production capability of inlet measurement to the LNG train significantly impacted on the
the asset. apportioned LNG, it had to be as close as possible to custody
metering systems.
With measurement projects both of the objectives can be
achieved. Ultrasonic meters (USM) were selected as the preferred flow
measurement technology for the following reasons:
As shown in the MEM, the single biggest measurement
point is the inlet measurement to each of the LNG trains. In 1. Endorsed by various regulatory bodies, standards and
general, although measurement projects may not generally codes for custody measurement, e.g. AGA Report 9, UK
increase production it is the perception of the production that Department of Trade & Industry’s Petroleum Measurement
is being addressed. This perception translates into financial Guidelines and the Norwegian Petroleum Directorate.
exposure risk for all parties. As can be seen from the MEM an 2. High accuracy can be achieved in the field when properly
improvement in the train inlet measurement uncertainty from 5% installed and maintained.
to 1% translates to an improvement in Allocation Uncertainty of 3. High turndown ratios available for individual meters.
2% or in other words a financial exposure benefit of 2% to the 4. Minimum pressure drop.
shareholders. 5. Strong diagnostic built in capability.
6. Low maintenance as compared to other technologies e.g.
Therefore, using traditional techniques for project justifications Orifice or Turbine meters.
such as NPV, Pay Pack and IRR measurement projects may be
justified on this basis. However, the USM can be susceptible to noise generated by
control valves. This noise, typically referred to as white noise
As in the case of the Train Inlet Measurement Upgrade project affects the performance of the meter. Also, the level of noise
assuming that a 4% reduction in measurement uncertainty can generated by a control valve is a function of the flow-rate,
be practically achieved then this project should be evaluated differential pressure drop, pressure and valve trim characteristics.
in relation to other initiatives competing for financial resources.
For example, assuming that three days of downtime on a facility
are required for the measurement upgrade and the total cost of 7 USM NOISE REDUCTION STRATEGIES
the project is 1.2 million USD, for an LNG complex with annual Most control valve manufacturers achieve their low noise levels
production target of 576 TBtu this gives an NPV (financial risk) by pushing their audible (20Hz-20kHz) emissions out of the
of 444 million USD and a payback in less than 1 year with a audible range and into a range (20-200kHz) which typically
profitability index of 17. affect USM detection signals. This was illustrated during our
DANIEL MEASUREMENT AND CONTROL WHITE PAPER page 6
flow calibration of the meters where a control valve similar to The newly purchased 24” 4 path USM were calibrated at the
one used at the inlet of the facility was installed to determine following points as recommended by AGA Report 9. qmin,
the extent of noise generated, and to see how the meter tuning 0.10qmax, 0.25qmex, 0.40qmax, 0.70qmax, and qmax, together
(noise reduction techniques) would impact the performance. with two additional points. The meter’s performance was
• Signal Stacking
• Digital Filtering
• Correlation
Techniques
• Statistical
Methods
The above picture (Fig. 7) shows the valve and meter being
Figure 9 - Noise as seen by the USM (Noise distorts the USM detection waveform)
With Stacking Applied only, the USM was still unable to register
a good reading.
A Practical Approach to Modelling LNG Train Design for
page 9
Minimizing Measurement & Allocation Uncertainty
(Calibration Results)
Figure 12 – USM Calibration with Flow Standard and Control valve
The illustration above (Fig.12) shows the improvement of the next step was to execute the installation and commissioning of the
USM Calibration against the Flow Standard Meter Bank when meters. The meters were shipped and stored until an opportune
the control valve was throttled at various differential pressures. time for installation. Having the control valve available at CEESI
proved invaluable, since the noise characteristics generated
9 PERFORMANCE OF USM VS CUSTODY ORIFICE by this particular valve were analyzed and this significantly
MEASUREMENT SYSTEM minimized the commissioning time. Furthermore this addressed
After the flow calibration of the ultrasonic meters at CEESI the the concern as to whether the valve and meter in close proximity
DANIEL MEASUREMENT AND CONTROL WHITE PAPER page 10
could fulfil plant flow regulation and product allocation. It must 3. Vapour recovery measurement will aid in the traceability of
be noted however, that in some of the installations, further LNG production per train.
noise tuning (custom data filtering) was required. This was
readily observed on installations where the pressure drop was 11 MAINTENANCE OF MEASUREMENT AND ALLO-
significantly greater than that tested at the facility. CATION UNCERTAINTY
Figure 13 - The performance of the ultrasonic meters and the custody metering system on the facility
The diagram shows that percentage deviation between the With the inlet measurement being so critical to the allocation
USM and the orifice measurement system is of 0.16%-0.6% of LNG and NGL on a multi train complex, this point of
with the USM reading marginally higher than the orifice measurement must be effectively maintained. Our experience
measurement. to date has shown that the USM probes must be kept clean for
good meter performance.
10 OTHER LNG TRAIN MEASUREMENT ISSUES
Although, the inlet measurement had the single largest impact The piping system should be designed such that there is no
on the LNG train there are other areas where measurement accumulation of liquid upstream of the USM. Additionally, if the
improvements can be made to the facility. However, these USM are in series with an orifice measurement system (custody),
must be done at the design stage thereby improving on the the similarity of the analytical data in the USM and the custody is
overall allocation process. These areas include: of great importance to the flow registration alignment. Operating
the orifice custody metering skids at higher differentials per
1. Fuel Measurement. Installing a good single point of stream also helps with the alignment of the readings registered
measurement for fuel enhances the quality of measurement by both systems.
that can be installed and simplifies the number of allocation
points. For example on a facility with 3 LNG trains, having 1 The USM should also be installed with double block and bleed
meter per train for the fuel can replace 10 or more metering isolation valves so that the meter probes can be easily accessed
points per train. This improvement reduces the cost of for maintenance. Effective isolation also facilitates the easy
operation and maintenance. removal of the meters for re-calibration exercises, typically
2. Marine Flare Measurement. There are a number of every six years.
practical challenges with installing good flare measurement
during plant operation (availability issues). Having marine Maintenance of secondary instrumentation, temperature and
flare measurement implies that losses can be applied to pressure transmitters must also be done at regular intervals.
individual shippers accordingly if agreed commercially.
A Practical Approach to Modelling LNG Train Design for
page 11
Minimizing Measurement & Allocation Uncertainty
12 CONCLUSION REFERENCES:
Maintenance of measurement uncertainty greatly affects the Allen Fagerlund et al, ‘Identification and Prediction of Piping
allocation of products on a multi train LNG facility. It is therefore System Noise,’ Noise Conference Oct 2005.
important that all plant measurement systems be optimized for
minimum uncertainty. Building of a MEM can help technical Bill Johansen & Joel Clancy, CEESI ‘Flow Calibrating Ultrasonic
personnel on the facility quickly diagnose mis-measurement Gas Meters’ International School of Hydrocarbon Measurement
issues and plan for future capital expenditure. Design engineers May 2003
would also benefit from using the MEM at the conceptual stage
of a project to plan out the specifications for the measurement Charles Derr, Daniel Measurement and Control ‘Energy
system. Measurement using Ultrasonic Meters & Gas Chromatography’
International School of Hydrocarbon Measurement May 2003
Train inlet measurement, which is of great concern to all parties,
must be properly designed, operated and maintained to ensure Gerrit Vermeiren and Sven Lataire, SGS ‘How Accurate is
equity in the allocation. This paper highlighted the issues on the Shipboard Custody Transfer Measurement system?’ LNG
inlet USM measurement and control valves. Although USM Journal July/August 2005
have gained custody appeal, their use must be planned and
coordinated with the flow/pressure regulation valve into the James E Gallagher, Savant Measurement Corporation, ‘Orifice
facility, since USM are susceptible to noise induced by valves. Flowmeters and the Estimated Uncertainties in Natural Gas
Service,’ International School of Hydrocarbon Measurement
May 2003
Ronald Roberts Kevin Warner and Klaus Zanker, Daniel Industries, Inc ‘Noise
Instrumentation & Controls Engineer II Reduction in Ultrasonic Gas Flow Measurement’ 4th International
Atlantic LNG Company of Trinidad & Tobago Symposium on Fluid Measurement June 1999.
Point Fortin Trinidad & Tobago
rroberts@atlanticlng.com Lars Farestvedt, FMC ‘Multipath Ultrasonic Flow Meters
for Gas Measurement’ International School of Hydrocarbon
Justin Walter Measurement May 2003
Senior Measurement Consultant
Metco Services Limited Ronald H. Dieck, ‘Measurement Uncertainty Methods and
Aberdeen, Scotland Applications’ ISA 4th Edition 2007
Justin.Walter@metco-uk.com
STANDARDS:
AGA Report No 9 Measurement of Gas by Multipath Ultrasonic
Meters (1998)
©2010 Daniel Measurement and Control, Inc. All Rights Reserved. Unauthorized duplication in whole or in part is prohibited. Printed in the USA.
DAN-TECHNOLOGIES-A-PRACTICAL-APPROACH-TO-MODELLING-LNG-TRAIN-DESIGN-FOR-MINIMIZING-MEASUREMENT-&-ALLOCATION-UNCERTAINTY