OF BEARING INSTALLATION
0
STEP 1:-
Prepare block out / recess holes using template / PVC pipes and cast the bottom plinth according to
the required height and size by contractors.
STEP 2:-
Place the Bearing on the bottom plinth. Use shim plates to ensure bearing reaches the required height.
Place the hydraulic cylinder / temporary supports at specified or designated location (by others).
1
STEP 3:-
STEP 4:-
Tighten the bolts at the top attachment plate to required torque value.
2
STEP 5:-
Prepare formwork for grouting. Using approved grout material, grout the bottom anchor plate using
manual pouring method.
STEP 6:-
Remove the hydraulic cylinder / temporary support after the grout has achieved the required strength.