Академический Документы
Профессиональный Документы
Культура Документы
1
1. Medium voltage synchronous switching: introduction
Between the years 1745 and 1746, a new breakthrough Abbé Nollet, Professor of Physics at the Collège de Navarre
revolutionized the physics of electricity. In order to study the in Paris, updated his demos to a further extent by discharging
electrification of water, scientist Andreas Cunaeus, who lived a battery of Leyden jars through a human chain. But it
in Leiden, Holland, placed the liquid in a small glass jar with was Benjamin Franklin's
a long metal spike through its stopper, which was connected experiments that showed
to the terminal of an electrostatic machine. As he held how the water could be
the jar in his hand, the unsuspecting scientist touched the eliminated and that the
spike and received a shock that was much more powerful shape of the glass jar was
than those usually obtained from the electrostatic machine. unimportant. His device
In January 1746, Pieter van Musschenbroek informed the simply consisted of a piece
Academy of Paris about the phenomenon, which was given of glass between two metal
the name of Leyden jar. This bottle full of water was actually plates, called armatures.
the first capacitor in history.
2
The concepts of capacitance and capacitor were actually
introduced during the same period by Alessandro Volta, who
can be considered the father of modern electrostatics. An
example of Volta's condenser is illustrated in the figure below.
Fig. 4: Volta's condenser Fig. 5: ABB SIKAP: a compact solution for MV capacitor
banks
After the victory of alternating current over direct current in Since loads fluctuate, capacitor bank switching-in and off
the so-called War of Currents in the late 19th century, when operations are frequent, and occur at least daily. Although
there was a rapid expansion of AC electricity transmission the capacitive current is normally of a small entity compared
and distribution networks, researchers began to address the to the rated current of the circuit-breaker, capacitor bank
problem of reducing the amount of reactive power circulating switching still creates even considerable transients, which are
around the lines so as to reduce the consequent losses. considered to be one of the possible causes of faults in the
Nowadays, increased efficiency and reduced consumption are capacitors themselves and, more generally, in installations.
strongly encouraged while there is a pressing demand from Pre-switching of resistors or inductors, fixed inductors and
governments and public opinion for reduced environmental surge arresters are among the possible countermeasures
impact. So much so, reactive power (basically of the inductive adopted. However, besides taking up space and being
type) compensation by local installation of capacitor banks often unable to ensure that the phenomenon is completely
is becoming increasingly widespread. In addition, use of eliminated, these solutions lead to losses and additional
power factor correction capacitors provides tangible benefits costs.
for consumers since they avoid the fines that would be due Synchronous switching is a further solution, developed in
should the power factor of their installations be below the recent times. In this case, circuit opening and closing takes
contractually established threshold. place in sync with voltage oscillation so that capacitor bank
Capacitor banks with even high power ratings can be installed switching-in and off occurs at zero volts. Compared to the
in the primary substations of public utility companies or traditional methods, this solution possesses the undoubted
even on individual users (typically motors) in the consumers' advantage of theoretically eliminating the problem at its origin.
factories. The best way to obtain this result is to operate the poles of
the switching apparatus individually and independently.
3
1. Introduction
When it comes to the costs and dimensions of the circuit- As can be seen, the most frequent application has
breakers and capacitor switches, this solution was initially progressively become capacitor bank switching, which
used at high voltage but recently, thanks to use of electronics already accounted for almost 70% of the applications in
in the apparatus and particulatly compact actuators, the 2001. The reason for this success is that concrete savings are
principle can now be employed at medium voltage. obtained through the elimination of pre-insertion resistors and
inductors, fixed inductors and surge arresters. In addition,
maintenance costs are reduced thanks to the longer electrical
life of the switching devices while last but not least, there is
less likelihood of faults in the installations.
In medium voltage installations, the circuit-breakers
and capacitor switches normally consist of three poles
mechanically connected to each other by a single operating
mechanism with preloaded springs or by a single magnetic
actuator. By contrast, synchronous switching must be
performed individually by each pole with respect to its
reference voltage, thus an operating mechanism or actuator
must be available for each pole. Synchronism is achieved by
a control unit so that the switching takes place in the point
of the voltage wave that avoids transients caused by arc
restrikes, i.e. when voltage crosses through zero.
Clearly the success of synchronized switching does not solely
depend on the characteristics of the apparatus, but also on
those of the electrical installation. This means that the cause-
and-effect relationship between switching and the consequent
behavior of the electrical installation must be defined and
Figure 6: synchronous circuit-breaker in a 420 V substation
understood. Vice versa, the characteristics of the electrical
installation before switching (e.g. presence of harmonics) may
According to an investigation conducted by CIGRE, use of influence the synchronization process.
synchronous apparatus has rapidly increased since the first In addition, the design characteristics of the apparatus must
experiments in 1990 owing to the good performance achieved all be constantly monitored to prevent wear or malfunctioning
in practical situations. As far back as 2001, there were already from interfering with the switching operation, e.g. speed of the
some 2400 HV synchronous apparatuses and their number contacts, state of the voltage sensors, actuators and of the
was forecast to reach 6700 units in 2009 thanks to reliability control unit itself.
improvements due to use of advanced sensors and modern
digital technologies.
Installation (Units)
Line
1%
Transformer
4000 14%
Reactor
Line 18%
3000 1%
Reactor
23%
1000
0
1989 1991 1993 1995 1998 2001 2004 2006
4
2. Capacitor bank switching
2.1 Switching-in capacitor banks If the capacitors are equal to each other and thus L=L1=L2
and C=C1=C2, the formulas are simpler and become:
Capacitor bank switching is often affected by overvoltages
and transient overcurrents.
The worst case occurs if a capacitor bank is switched-in
when other banks are already connected (so-called back-to-
back switching). This is because the amplitude and frequency
of the inrush current can be very high. In the case of n capacitors already connected:
Busbars
Thus, for Ls >> L1 there is: Lastly, by replacing the capacitance with the relative
capacitive current:
5
2. Capacitor bank switching
The simplified formulas are outlined in the table below: The capacitance and current of the capacitor bank are:
ƒ i (Hz)
6
Fig. 10: inrush current for switching-in a capacitor bank
7
2. Capacitor bank switching
The results obtained by applying the formula are: In this case, the inrush current exceeds the values
recommended by IEC 62271 for capacitive current switching
by the circuit-breaker and contactor (20 kAp short-time peak
current at 4250 Hz frequency for the circuit-breaker and 8 kPa
short-time peak current at 2500 Hz frequency for the
contactors).
This means that additional inductors in series must be used to
limit them. The limiting inductance value can be obtained by
applying the previous formulas in reverse, beginning with the
limits recommended by the Standards:
Fig. 12: inrush current for back-to-back switching-in of a second capacitor bank
8
where 1.3 is a coefficient suggested by the Standard allowing Installation of an inductor in series with a capacitor creates a
for +130% tolerance on the permissible frequency of the resonant circuit. So much so, it is advisable to check for the
inrush current under service conditions. presence of harmonics, normally of the high-order type, which
could energize the circuit and cause undesired overloading
Thus: of the inductor and capacitor. Once the capacitance of the
capacitor bank is known, the value of the inductance for a
determined order-n harmonic can be found so as to prevent
resonance:
i.e. at least 1.929 additional µH. Moreover, with this value, the
peak value would drop to 16.3 kA.
As to the positions of the limiting inductors in relation to
the switching device and capacitor, theoretically there is no One approach could be to set the inductor to harmonic values
difference to their limiting effect so long as they are installed that are much higher than those in the installation, e.g. above
on each phase and in series with the capacitors. the thirteenth harmonic. Particular attention should be paid if
In some case, inductors are also installed on the neutral there are inverters in the installation.
terminal of the capacitor. However, this is not the most widely The major disadvantage in using limiting inductors is certainly
used configuration. their cost: the initial outlay, the cost of mitigating the TRV if
When limiting inductors are installed for the purpose of limiting necessary, and the installation costs.
inrush current, the risk is of a fault occurring in such a way Inductors also cause additional losses due to their resistance.
that the inductor limits the fault current interrupted by the Lastly, one must also bear in mind that the voltage increase
circuit-breaker owing to the low capacitance of the circuit and due to large inductors being installed can lead to oversizing of
increases the TRV imposed by the contacts to an excessive the rated voltage of the capacitors as well as a variation in the
extent. In the examples shown in the figure, the TRV caused power they provide.
by the fault can often exceed the permissible limits of the
circuit-breaker, a phenomenon very similar to that of short line
interruption.
Circuit
Circuit breaker
breaker Transient limiting Transient limiting Circuit breaker
inductor (TLI) inductor (TLI)
Exmple with circuit breaker before TLI Exmple with circuit breaker after TLI
Circuit breaker
Translent limiting
inductor (LTI)
9
2. Capacitor bank switching
LS + ur –
2.2 Interruption of
capacitive loads
With reference to the next figure and + + +
Restriking
10
Recovery voltage (p.u.)
3.5
3.0
2.5
2.0
1.5
1.0
0.5
The initial trend of the TRV would lead to a peak of three 2.3 Further methods for reducing
times the grid supply voltage (dotted blue line). However,
when the last two poles interrupt a fourth of the cycle after switching transients
the first (90°), a discontinuity appears in the trend and the final There are several methods for reducing inrush current or TRV
peak drops to 2.5 times the peak supply voltage. in the switching device itself:
Standard IEC 62271-100 establishes two classes for circuit- – installation of limiting inductors so as to reduce the peak
breakers, depending on their behavior towards restriking: current and frequency of the inrush current;
– class C1 with a low probability of restriking during the – addition of pre-insertion resistors or reactors in the
interruption of capacitive currents; switching devices;
– class C2 with a very low probability of restriking during the – capacitor switching in the incremental mode;
interruption of capacitive currents; – use of surge arresters (metal oxide varistors – MOVs);
The standard also describes the tests to which the circuit- – use of sycnrhonous switching devices in both closing and
breaker must be subjected, depending on the type of opening phases;
capacitive load envisaged (especially when overhead lines L
and cables C are powered-up), and for capacitor banks B. The effectiveness of these methods depends on the
Thus there will be a total of six test cycles: LC1, LC2, CC1, characteristics of the electrical installation, thus the most
CC2, BC1 and BC2. The tests can be combined so as to appropriate choice must be made after detailed research into
cover the three types of load, by declaring a single value. the behaviour in transient conditions. Each of these methods
The type tests for class C2 are conducted after pre- has different advantages and disadvantages as to reductions
conditioning, which includes short-circuit current interruptions in overvoltage, costs, installation requirements, maintenance
followed by a certain number of capacitive current and reliability. Use of limiting inductors is described in chapter
interruptions. Pre-conditioning is not required for class C1 2.1.
tests, and there are fewer capacitive current interruptions than
class C2.
11
2. Capacitor bank switching
2.3.1 Pre-insertion resistors or reactors As already explained for the limiting inductor, the pre-
Pre-insertion resistors or reactors are a very effective way for insertion inductor also reduces the inrush current as well
reducing switch-in transients. They are connected before the as contributing towards limiting transient overvoltages. This
capacitor bank is energized and then short-circuited after the effect depends on the system's inductance value and is
transient has been damped, obviously giving rise to a second effective for values that are the same or higher than this latter.
transient. The resistor and inductor must be sized on the A high resistance also helps by increasing the damping effect
basis of the switch-in transient values of the capacitor banks on voltage wave oscillation.
and the successive bypass transient. When this solution is adopted, it is obviously necessary to
calculate the peak current and frequency of the oscillation
both before and after pre-insertion, as described in chap. 2.1.
12
3,0
2,5
Upl = LIPL
2,0
Ups = SIPL
Normal voltage peak in p.u.
1,5
Ur x
Uc x
1,0
0,5
25° C 140° C
0,0
1x10-5 1x10-4 1x10-3 1x10-2 1x10-1 1x100 1x101 1x102 1x103 1x104 1x105
Current (A)
– The power absorbed determines the type of arrester with – the connection to the surge arrester must be as short as
200 to 1000 A peak currents for multiple re-ignitions, or possible and must have the same earth as the apparatus
those of 10 kA or more for lightning impulses; that must be protected. In the example in figure 20
– position the arrester as near as possible to the apparatus below (taken from the Standard) there are three cases of
that must be protected; protection of a transformer T where case 3 guarantees
– the best protection is obtained by connecting the arresters excellent protection since there is only one earth and
between adjacent phases and between all the phases and connection b is short and less than connection a.
earth;
b b a a
a
b
T T T
C C C
1 2 3
Fig. 20: position of a surge arrester to protect a transformer
13
2. Capacitor bank switching
The energy associated with re-striking due to capacitor This means that there will be no problems from an energy
bank switching must be assessed with the greatest care. aspect if an ABB MWD surge arrester is installed, since its
Although rare, restriking can be a challeging task, especially energy has been tested in accordance with Standard IEC
for surge arresters installed near the capacitor banks. In 60099-4 and is 5.5 kJ/kV.
actual fact, surge arresters installed even further away,
including low voltage ones, can be affected in the case of Surge arresters can be installed in different positions
multiple restriking events. The energy that affects the surge depending on the switching device and limiting inductor.
arrester depends on the capacitance of the capacitor bank These positions are listed below:
owing to the charge stored in the bank itself. The effect of a) on the supply side of the switching device;
this is to increase overvoltage oscillation amplitude the instant b) on the supply side of the limiting inductor;
restriking occurs. Annex G.2, standard IEEE Std C62.22- c) between the limiting inductor and capacitor;
2009 “IEEE Guide for the Application of Metal-Oxide Surge d) at the ends of the limiting inductor.
Arresters for Alternating-Current Systems”, provides a method
for calculating the energy dissipated by the surge arrester in The benefits and disadvantages of each installation, which
this situation. Supposing that the transient overvoltage due must be preceded by research for the purpose of coordinating
to circuit-breaker restriking during the opening operation of a the insulation of the system, are outlined in the next table:
capacitor bank reaches 3 p.u. and that the discharge voltage
of a typical surge arrester installed on the bank or in its
immediate vicinity is about 2 p.u., the suggestion provided by
the Standard is to estimate the energy discharged by a surge
arrester as depending on the size of the capacitor bank, as
described below:
14
Position Layout Benefits Disadvantages
a) On supply side of switching Protects switching device, Protects capacitor bank to a
device Switching Limiting when open, from lightning and lesser because of voltage rise
device inductor (LTI) switching; across inductor.
Protects limiting inductor
from fast front surges (e.g.
lightning).
Capacitor
Surge arrester bank
b) On supply side of limiting Protects limiting inductor from Protects capacitor bank to
Switching Limiting
inductor device inductor (LTI) fast front surges. a lesser extent because of
voltage rise across inductor.
Capacitor
Surge arrester bank
15
2. Capacitor bank switching
16
To capacitor
Lastly, ABB proposes an innovative solution comprising a
To supply source bank switch able to combine the advantages of conventional switch
To monitoring device
with those of the power electronics. The synchronous switch
is the first switch to feature air-insulated diode technology and
to be designed for switching capacitor banks in particular.
The basic principle is to resolve the problem of accurate
identification of zero voltage or current, by connecting or
disconnecting the diodes in advance of the main contacts so
that the current begins to flow or is interrupted in a natural
way. Thanks to this operating mode, the apparatus is able
to ensure that overvoltages and overcurrents are absent,
thanks to the absence of pre-ignitions and re-striking. As in
all synchronous apparatuses, the operations are performed
independently on all three poles. A controller receives the
signals from the sensors and deals with the operations and
diagnostic functions. Since the current flows by means of the
switch contacts once the closing operation has terminated,
the device does not need a dedicated cooling system. This
makes it extremely compact. So much so, it can even be
installed in a normal MV panel.
The main advantages of this device, which will be described
in detail in the next chapter, are:
– improved grid reliability thanks to the sophisticated
Fig. 22: static circuit-breaker circuit diagnostics system, which monitors the intrinsic operation
of the device and reduces outages in the installation to the
minimum;
– no impact on the installation components owing to
These apparatuses can deal with an extremely high number transient overvoltage or overcurrent generated by capacitor
of operations and function at a remarkably high switching switching;
speed. The electronic components ensure stability and – low environmental impact, since the switch is insulated with
accurate operating times, exceeding the limits described dried air, unlike other oil- or gas-insulated devices. Thanks
for conventional circuit-breakers. This makes these devices to its small size, the device occupies less surface space
theoretically ideal for synchronous switching. However, they (reduced footprint).
do pose the very well known problem for power electronics,
of losses due to the internal resistance of the components. There are many, very interesting applications for this device.
Cooling at continuous current is a serious problem, which has Its natural application is for switching capacitor banks, but
been resolved by using sometimes complex cooling systems, any other application that can benefit from synchronized
with solutions similar to those adopted for transformers with operation can be developed thanks to the flexibility of the
insulating oil, radiators and forced ventilation. This sort of electronic controller.
cooling system obviously increases the size of the apparatus
to a considerable degree and often makes it difficult to install.
More importantly, devices with thyristors have difficulty in
withstanding the overvoltages from the system and must
be protected by surge arresters on the feeder, which must
also be equipped with some sort of disconnector (fuse
disconnector or plug-in circuit-breaker) to guarantee galvanic
insulation.
17
2. Capacitor bank switching
These apparatuses are classified by Standard IEC 62271- 100, since the test conditions defined by this standard are
103 High-voltage switchgear and controlgear – Part 103: more demanding than IEC 62271-103. These tests are
Switches for rated voltages above 1 kV up to and including comparable to those required by Standard IEEE C37.09a. The
52 kV, as “special purpose switches” for switching capacitor tests performed on DS1 are listed in the table below.
banks in class C2. The tests for switching capacitive currents
were conducted in accordance with Standard IEC 62271-
18
DS1 has been designed to combine high precision mechanics - feeder module (2);
with power electronics. With reference to the figure below, the - actuating capacitor (3);
architecture of this device includes the following components: - servomotors (4).
- poles (6);
- electronic control unit (1);
6 6 6 3
4 4
1
3 4 1 2 4 4
19
2. Capacitor bank switching
The electronic control unit (1) is built into the device and With reference to the next figure, before the capacitor bank
pre-calibrated in the factory. It is formed by three modules, is energized, the apparatus is in situation a), with the switch
each of which controls its own servomotor (4). The control open and the bank isolated from the grid. After this, as shown
unit also contains a feeder module (2), which supplies the in b), the moving contact connects the diodes and the bank is
three previous modules and charges the actuation capacitor naturally supplied at voltage zero. Lastly, as shown in c), after
(3). The purpose of the capacitor is to ensure the motors a quarter of a cycle, the moving contact closes the switch and
receive power even in the absence of the auxiliary supply. allows current to flow without losses.
This architecture allows the three poles to be operated
independently, depending on the application required. The
control unit also provides diagnostic functions.
a) b) c)
Current
Current
Current
(ms)
0 10 20 30 40 0 10 20 30 40 0 10 20 30 40
20
Thus the apparatus is able to supply the capacitor bank at the The energy dissipated in the arcing chamber is also reduced
correct instant thereby minimizing transients caused by the to the minimum, thereby allowing a large number of electrical
switching operation. operations to be performed.
Similarly, the capacitor bank is opened without causing any Accurate control over the electrical and mechanical quantities
disturbance in the grid. Figure 26 shows the switch initially was required in order to achieve this result.
in the closed position, with the bank connected to the The diagnostic function provided by the control unit includes:
grid (a). After this, in (b), the moving contact connects the – continuous control of the synchronization signal; accuracy
diodes, which begin to conduct. Half a cycle afterwards, the as to the presence of system voltage, frequency and
diodes shut off the passage of current at zero and are finally harmonic distortion. The control unit regulates trip time for
disconnected with the main contacts (c) open. ±1.4 Hz frequency variations so as to ensure a high level of
synchronization;
a) b) c)
Current
Current
Current
21
2. Capacitor bank switching
– regular monitoring of the state of the cinematic chain, in The following are available at the DS1 terminal box:
the closed position, by means of tiny movements to check – opening and closing command;
torque, speed and position every 24 h. This procedure – interlock input;
is important for checking the state of the actuation chain – the open and closed state;
before the command is imparted for the purpose of – the diagnostic output: ready and alarm (if the switch is
ensuring a maximum level of reliability for the operation; unable to operate);
– complete control of movements immediately after the – the self-test output of the control unit.
operation has terminated, so as to check the position, There is a further function that allows switch reclosing to be
speed and torque of the servomotors and inform the user inhibited until the capacitors have completely discharged. To
about the way in which the operation had been performed; achieve this, the closing command is inhibited for 5 minutes
– continuous monitoring of the servomotors by means of the after opening and the not-ready signal is activated. This delay
state of the wiring and windings, so as to ensure complete can be adjusted to suit different standards.
functionality; From the installation aspect, the most widely used solution is
– regular inspection of the state of the capacitor by means to install fuses on the load side and supply side of the switch
of the voltage, so as to check that the capacitor is always so as to protect the capacitor bank if faults occur. A circuit-
loaded and thus able to supply the servomotors with power breaker is also positioned on the supply side of the capacitor
when necessary; banks to open the circuit if the fuses trip, in the case of
– continuous monitoring of the state of the actual control unit unbalanced loads or, if it is the plug-in type, to isolate the
by means of self-monitoring functions. line for maintenance. This function is performed by a feeder
Further diagnostic functions concern the poles, e.g. disconnector in the case of fixed circuit-breakers.
monitoring of the internal pressure of the dried air by the
pressure switch to ensure the insulation level is maintained,
and monitoring of the apparatus operating mode.
Fuse
Circuit-breaker
Switching
device
Reactor
22
DS1 has been designed to support a sufficient short-time
current to allow the fuses that protect the capacitor bank to
trip. To prevent inappropriate closing, it can also be easily
interlocked with the circuit-breaker on the supply side and
with the feeder disconnector and earthing switch.
Regarding capacitive load switching, DS1 has been tested
in accordance with Standard IEC 62271-100, which requires
more stringent tests than IEEE 37.09a or IEC 62271-103.
In conclusion, synchronous capacitor switch DS1 offers the
following advantages:
– it is eco-friendly, since it uses dried air for insulation;
– at its rated current value, it does not need cooling systems
such as radiators or fans;
– limiting reactors for the inrush currents are not required
since it eliminates the closing transients of the capacitor
banks;
– surge arresters for protection against overvoltage are not
required since, if supply-side circuit-breaker switches only
in case of short-circuit, it eliminates the opening transients
of the capacitor banks;
– it is extremely compact and interchangeable with MV
circuit-breakers, thus easy to integrate into existing
installations.
23
3. Comparison among different switching technologies
for capacitor banks
As described in the previous chapter, there are various ways switching operations and assess the efficacy of the solutions
to reduce the value of the overvoltages generated when applied.
capacitor banks are switched-in and off. The various different The following circuit can be used for this purpose, where Zs is
solutions can be compared by using simulation software so the grid impedance and Zc the impedance of the connections:
as to check the maximum overvoltage generated during the
devices.
If no voltage damping system is used,
the overvoltage reaches its maximum
value of 1.8 p.u. when the first capacitor
is energized, while the inrush current
Putting into service
reaches its maximum value when the Putting into service
of second bank
of first bank
second bank is energized back-to-back (back-to-back)
at 13.6 kA.
Time [ms]
Voltage [kV]
Time [ms]
24
A limiting inductor can be included so as to reduce the inrush this particular case, is f=4.5∙60=270 Hz.
current. This also changes the resonance frequency. The The value of the limiting inductor can therefore be calculated
inductance value must be chosen so as to avoid the third and in the following way:
fifth harmonic, i.e. normally a frequency of f=4.5∙f0 which, in
Time [ms]
Voltage [kV]
Time [ms]
25
3. Comparison among different switching technologies for
capacitor banks
Note how there is a substantial reduction in inrush current, the moment in which the resistor is short-circuited after a few
which has a peak value of approx. 2 kA, and a beneficial milliseconds, to prevent unnecessary losses. Let's assume
effect on the peak value of the overvoltage, which is 1.64 p.u. that a 6 Ohm resistor is included in the circuit:
We'll now examine the case where a pre-insertion resistor is
included. Consider that a voltage transient will be generated
Time [ms]
Voltage [kV]
Time [ms]
26
The graphs show that there has been a remarkable when the resistor is disconnected. The overvoltage peak is also
improvement in the inrush current value, which reduces to reduced to 1.8 p.u.
about 1.5 kA even though an additional 4.5 kA peak is caused Now let's see how the circuit behaves if the switching device
is a synchronized vacuum circuit-breaker. We'll consider
1-millisecond uncertainty in contact closing after current zero,
RDDS characteristic of circuit-breaker normally delayed to avoid pre-striking phenomena. At 6.9 kV
Uncertainty and 60 Hz, this equals a voltage value of 3.6 kV:
Absolute value
of voltage Here, a 60 µH limiting inductance is introduced so as to
remedy the problem; thus the circuit becomes:
Maximum pre-striking
voltage
Fig. 34: uncertain closing of the contacts of a synchronous circuit-breaker Fig. 35: simulation of circuit with synchronous circuit-breaker
Simulation is as follows:
Current [kA]
Time [ms]
Voltage [kV]
Time [ms]
27
3. Comparison among different switching technologies for
capacitor banks
Time [ms]
Voltage [kV]
Time [ms]
28
4. Impact of overvoltage on the components
of an electrical installation
Even though they are very brief, overvoltages due to transient over a period of 10 years, between 1980 and 1990, which
phenomena can have significant impact and shorten the showed a failure rate of almost 6%, the majority of which
electrical life of the electrical components in an electrical due to insulation problems [9]. 541 faulty capacitors were
installation if they occur frequently. The factors that affect the analyzed and the causes were identified and classified for 536
life of the components to the greatest degree are the inrush as can be seen in the next table [9], which gives data for four
currents and overvoltages deriving from capacitor switching- different manufacturers. They were all 150 kVA single-phase
in transients and the probability of prestrikes and restrikes in capacitors installed in 4.8 kV distribution systems.
the respective switching devices [2] [3] [4].
Repeated overvoltages can trigger off partial discharge
which, as is known, cause the insulation in electrical devices
to age and progressively deteriorate until it actually tears and Manufacturer N° Main Oil leaks Insulators
leads to failure. insulation
unit unit % unit % unit %
A 325 306 94.15 10 3.08 9 2.77
B 150 137 91.33 11 7.33 2 1.34
C 38 36 94.74 1 2.63 1 2.63
D 23 17 73.91 5 21.74 1 4.35
Total 536 496 92.54 27 5.04 13 2.42
29
4. Impact of overvoltage on the components
of an electrical installation
In addition, it turns out that the faults are statistically concentrated in the individual banks, since all the
capacitors belonging to the bank are simultaneously affected by the same overvoltage [9]:
Meaning that 37% of the faulty units belong to the category of two failures per bank and 21% of the faulty units to
the category of three faults per bank.
Tripping of the internal fuses that protect the capacitors allows faults in the individual units to be eliminated and the
bank to continue to function, but does not solve the problem in general.
Insulators
Elements
Fuses
Discharge resistors
Internal fuses
Supporting bracket
Elements
Discharge
resistors
Metal enclosure
As illustrated previously, one of the phenomena that negatively Internal partial discharge forms in solid dielectrics owing
and sometimes significantly influences the electrical life of to cavities, called vacuoles, in the dielectric containing gas
capacitors is partial discharge. This phenomenon consists that forms or is already present at the origin owing to a
of electrical discharge in a portion of the dielectric between poor quality production process, or during service owing to
two conductors. This discharge is due to electrical stress mechanical, thermal or electrical stress. Partial discharge can
concentrated inside or on the surface of the dielectric itself. also appear in fluid insulating media owing to the formation of
The discharge is normally of the pulsed type and lasts around gaseous bubbles due to thermal or electrical stress.
1 µs.
30
Fig. 39: effect of partial discharge on solid and liquid insulating media [20]
[21]
In any case, partial discharges lead to slow and progressive inception voltage (called PDIV) and the extinction voltage
deterioration of the dielectric, which is irreversible in the case (called PDEV) becomes 10 to 30% lower than the inception
of solid dielectric and which can finally lead to a discharge voltage. Partial discharge is at low power. It deteriorates the
that destroys it. dielectric slowly and neither affects nor is it measurable during
With respect to the surrounding dielectric, vacuoles are the insulation tests of devices.
characterized by a lower dielectric constant ε and by a In modern capacitors with polypropylene film, vacuoles are
higher electric field, thus discharge can easily generate not present initially thanks to the quality of the production
inside it. The physical state of the vacuole changes and process. They can form successively throughout the years of
successive discharges can occur at lower voltage values and service owing to overvoltage. Gaseous formations can also
progressively deteriorate the material. Once initiated, partial occur in areas of higher electrical stress, typically at the edges
discharge can also continue at lower voltage values than the of the aluminum conductive foil, even when the dielectric
impregnating product has also been chosen to minimize the
partial discharges themselves.
Cold-welded
electrode
on anode
Cold-welded
on cathode
31
4. Impact of overvoltage on the components
of an electrical installation
Normally, the most critical situation is due to the switching-in Where LH is the reference life due to the sole electric field
transient, since the switching overvoltages are followed by a EH, and n is the voltage endurance coefficient (VEC), which
period of operation and therefore allow partial discharges to can be obtained from the accelerated ageing tests to which
come into play. the capacitors are subjected. Note that for E, EH and LH
The PDEV value is extremely important since partial discharge constants, the lifetime of the materials increases as the VEC
ceases below that value and the impregnating insulating fluid value increases.
can re-establish itself. The case of a capacitor with n=11.5 is illustrated in the graph
The edge of the conductive foil is one of the most critical below by way of example:
points since the magnetic field is stronger and it is here that
partial discharge concentrates more frequently.
Aluminum foil
Life (h)
Polypropylene film
32
If we now use αi to indicate the fraction of time during which The upper limit of the integral is infinite in the aforementioned
the known overvoltage is applied, calculated as the ratio equation since it corresponds to the probability of having a
between time ti and total lifetime Ltot, estimated considering the failure equal to 1. For practical purposes one can consider,
for Vp, an upper limit of Vp-lim, such that the contribution to
superimposing effect, thus , we can write that: the equation provided by the integration between Vp-lim and
and the infinite is negligible. An acceptable limit is 99.9% of the
probability density function, which we'll call Vp99.9%.
and then rewrite the Miner's rule as: Now, assuming that a voltage pulse with amplitude Vp applied
for an interval of dt(Vp) and probability density f(Vp) obtains
lifetime L(Vp) and that A.C. voltage is constantly applied
throughout the total lifetime of the insulation Ltot (thus tac=Ltot),
using equations (4) and (8) the result is:
from which Ltot is obtained:
33
4. Impact of overvoltage on the components
of an electrical installation
The time-to-failure of the insulating material, or its lifetime, definition, αt represents time-to-failure at 63.2% probability,
follows a stochastic law. Different failure times are observed one can expect a notable diminution of αt as the electric
in identical capacitors subjected to the same stress owing to field increases, in accordance with the inverse power model.
the different consistency of the insulating materials, different The relation between αt and electric field E can therefore be
production processes employed, imperfect quality control, written in the following way:
environmental conditions, etc. Failure time can therefore
be associated with a failure probability by means of an
appropriate probability distribution function. Assuming that
lifetime distribution for electrical insulations subjected to
electrical stress can be represented by the two parameters of Where EH is the maximum Ej and αtH is the 63.2-th percentile
a Weibull distribution, the cumulative distribution function that of time-to-failure below EH.
provides failure probability at time t is therefore [10]:
If we now consider the overvoltages, we can replace αt in the
equation (12) with the complete lifetime model (11), thereby
obtaining the following function of the probability distribution
model:
Parameters βt and αt can be estimated by performing an Thus, reliability for the capacitors becomes:
accelerated lifetime test at different stress values Ej, with
j=1,…,m (≥3). ni samples are tested for each Ej to obtain
time-to-failure tFi. Assuming that the time-to-failure complies
with Weibull distribution, parameters βt and αt are estimated
for each sample using the linear regression method or the
maximum probability estimation method [10]. Laboratory
tests show a modest variation in βt as the level of electric
stress varies. This value can therefore be considered as
a constant. On the contrary, αt has been found to vary
significantly depending on the electric field applied. Since, by
34
After having developed the theory, the reliability of the capacitors can be calculated by means of the following parameters [19]:
tac≈tp [h] EHac [kV/mm] EHp [kV/mm] nac np βt ƒ 0 [Hz] Rated voltage of Thickness
(peak-peak) (peak-peak) capacitor elements [kV] of dielectric
[µm]
0,0004 500∙2∙√2 840∙2∙√2 11.5 5.5 0.65 50 1.5 15 + 15
The thickness of the dielectric was chosen by considering the the overvoltages due to capacitor switching-in (from 1 to 3
rated voltage of the elements so as to obtain the typical A.C. p.u.) (since these are the most harmful ones from the partial
electric field of a power capacitor (50 kV/mm), as considered discharge aspect as the capacitor continues to be energized),
in literature [6] [13]. as well as the overvoltages due to circuit-breaker re-striking
Dielectric strength EHac was chosen considering that values during the opening operation (which can lead to higher values,
up to 600 kV/mm are declared for the new biaxially oriented although with lower probability):
polypropylene film (BOPP) [15]. However, values between 200
kV/mm and 300 kV/mm are indicated for less recent film [13].
In this case, the high-range value was chosen to highlight the
impact of overvoltages on useful life even when the capacitors
have been manufacturered according to the best technology.
Regarding EHp, dielectric strength measured by means of the
rising-voltage test is always higher than EHac. Consequently,
Frequency
35
4. Impact of overvoltage on the components
of an electrical installation
1
only voltage D.C.
0,9
1 operation per day
0,8
2 operations per day
0,7
30 years
0,6
Reliability
0,5
0,4
0,3
0,2
0,1
0
1,0E+00 1,0E+02 1,0E+04 1,0E+06 1,0E+08 1,0E+10
Life (h)
The vertical line in the graph represents the thirty years phenomenon is progressive and not constant, and that this
lifetime normally required when capacitors are designed. In can impair reliability to an even greater extent.
the absence of overvoltages, reliability is 99% at thirty years As can be seen from the way the curves slope, compared to
(blue curve). the condition without overvoltages, deterioration of reliability
Reliability diminishes in the presence of switching after thirty years becomes extremely marked.
overvoltages. At a frequency of one switch a day, reliability Bear in mind that the result described is the outcome of a
drops to about 93% (black curve) and to 90% at a frequency theoretical study by researchers and specialists and that it
of two switches a day (red curve). This value gets worse should therefore be considered in qualitative terms for the
if switching occurs more frequently. With a frequency of 6 purpose of demonstrating how the reliability of capacitors
switches a day, reliability at thirty years drops to 85%. Lastly, depends on the phenomenon of overvoltages due to
consider that in reality, the trend of the partial discharge switching of the capacitors themselves.
36
4.1.1 The protection system associated with the capacitor Failure of one element will short-circuit the group associated
bank with that unit. This leads to an increase in the current that
The impact of the failure of a single capacitor depends on crosses the bank and an increase in the voltage on the
the construction characteristics of the bank. Some capacitor elements of the remaining groups. In this sort of construction,
banks are protected by external fuses while others are it is normally necessary to replace the affected bank as soon
protected by internal fuses. as the first failure is detected.
Capacitor banks without internal fuses consist of a set of Vice versa, when the capacitors have internal fuses, all the
groups of elementary single capacitors connected in parallel. elementary capacitors have a fuse in series. Thus the faulty
element is excluded without compromising the others in the
group to which it belongs.
capacitor
enclosure
capacitor
element
group of
capacitor elements
capacitor
enclosure
capacitor
element
group of
capacitor elements
37
4. Impact of overvoltage on the components
of an electrical installation
The bank can remain in service with reduced reactive power One of the functions used for protecting the capacitors
so long as the voltage on the remaining capacitors does is protection against phase unbalance. This protection is
not exceed the tolerance margin of +10% of the rated based on the quantity or on the variation of the current or
voltage envisaged by the manufacturer. Obviously, the more voltage due to an unbalanced neutral, which is the result of
elementary capacitors form the bank, the lower will be the a certain number of elementary capacitors or units having
impact, in percentage terms, on both the diminution of failed and which can be calculated on the basis of the bank
reactive power and on the increase in the voltage on the configuration and rating plate data.
remaining capacitors. In the very common case in which the capacitor banks are
The following formula gives the overvoltage Vpu on the managed with an isolated neutral, the layout for protecting a
remaining capacitors in the group in relation to the number n single bank is as follows:
of faulty capacitors:
Fig. 47: protection layout for a single bank with isolated neutral
38
The simplest way to detect unbalance in this case, is to In this situation, it is very simple to obtain compensated
measure the voltage on the neutral or zero sequence. In unbalance protection since the zero sequence component
normal conditions, the voltage is obviously zero, while any of the system affects the two banks in the same way, while a
variation on one of the phases causes a variation in the faulty elementary capacitor seems like an unbalance between
neutral current or zero sequence. Figure 47 a) illustrates the neutrals. The first diagram shows a current transformer
method, which consists in measuring the voltage between connected between the two neutrals and an overcurrent
the capacitor neutral and earth using a VT or resistive divider protection function. The second diagram uses a voltage
and an overvoltage protection function. This method is very transformer and an overvoltage protection function. The effect
simple, but its disadvantage is that it also measures grid of voltage unbalance in the system is eliminated in both cases
unbalance and the natural unbalance of the bank. A second but not that of natural bank unbalance due to the tolerances
method, shown in figure 47 b), consists in using three VT involving the presence of currents or voltages between the
and calculating the zero sequence voltage from the phase- neutrals, even in the absence of faults. Consequently, a
neutral voltages. Lastly, figure 47 c) illustrates a solution for natural unbalance compensating function must be adopted if
eliminating both grid unbalance and that of the bank. Grid a very sensitive protection is required.
unbalance is eliminated by measuring the zero sequence The error due to natural unbalance may make the protection
residual voltage, by connecting the secondaries of the insensitive or, vice versa, cause untimely trips. It is advisable
broken-delta VT, or by calculating it numerically from the to perform compensation by means of the relative protection
phase-earth voltages. The natural unbalance of the bank can function if the error nears 50% of the required alarm threshold.
be calculated by means of a compensation function included A so-called H configuration is often used in large capacitor
in all modern protections. banks, with a current transformer connected between the
The protection layouts for two capacitor banks are illustrated connections between banks, as shown in figure 49.
in figure 48.
Fig. 48: protection layout for two banks with isolated neutral
39
4. Impact of overvoltage on the components
of an electrical installation
No current flows in the absence of faulty elements, otherwise first trip threshold for banks with isolated neutral must be
a current begins to flow through the current transformers. 125% of the rated phase current, while the value of the upper
The advantage of this configuration is its insensitivity to grid threshold must be higher than the transient inrush current in
unbalance, but natural unbalance causes a current to flow any case, e.g. from three to four times the rated current of the
between the branches. This means that here again, a natural bank. Whether it is directional or not, in the case of an earth
unbalance compensating function must be used so as to fault in systems with isolated neutral, the protection must be
obtain a very fast and sensitive unbalance protection. This is as sensitive as possible. If the earth fault occurs inside the
why this configuration is so widely used for large capacitor bank, this will also cause an unbalance. Thus the unbalance
banks. protection is also a back-up protection for the earth fault
Overload protection is also used for capacitor banks. If the protection.
capacitors are subject to overvoltages for long periods, The unbalance protection may not be sensitive enough to
e.g. owing to a high harmonic content, this can cause the trip when certain faults occur inside large capacitor banks,
current that flows around the bank to increase and stress the e.g. faults between racks in certain H configurations. In this
individual elements. Since capacitors are particularly sensitive case, it may be necessary to add a back-up protection, i.e. an
to overvoltage, it is advisable to measure the voltage peak. negative sequence overcurrent protection.
However, it is also possible to use an overload protection A further protection function must be included to prevent the
based on filtered current measurement, which is certainly banks from reconnecting immediately after a disconnection,
more economical (figure 50). i.e. before the discharge time has terminated, thus in medium
voltage within 5 minutes ((ANSI/NFPA 70) or within 10
There must obviously also be a protection against short- minutes (IEC 60871-1). This is normally achieved by using
circuits between the phases and towards neutral and earth. an appropriately delayed undervoltage or minimum current
In this case, an overcurrent protection with two thresholds is function to prevent the circuit-breaker or switch from reclosing
normally employed, in which the higher threshold is used for before the discharge has terminated. If a specific apparatus
short-circuits between the terminals of the banks and circuit- has been installed to switch the bank in addition to the circuit-
breaker while the lower threshold is used for faults between breaker (such as DS1), this function must be performed on the
banks, where greater sensitivity is required. In order to avoid load side of the switching apparatus. DS1 inhibits reclosing
untimely trips, the overcurrent thresholds must take account after the bank has opened for an adjustable time so as to
of the inrush currents. Typically, the minimum value of the account for the discharge time (5 min by default).
Overload protection
Special filter
5
0
Ic
Ic Protection
-5
Amplitude [dB]
-10
-15
-20
-25
Uc
-30
-35
0 100 200 300 400 500 600
Frequency [Hz]
40
Lastly, it is also advisable to install an overvoltage protection
function to prevent the banks from being subjected to
abnormal overvoltage long enough for them to be damaged.
When the banks open, the overvoltage in their vicinity is
also limited, thereby reducing the stress to which the other
components of the installation are subjected. The voltage is
normally measured from the busbar on the supply side of the
circuit-breaker. The function must be coordinated with that
of the overcurrent and can therefore also act as a back-up
protection.
41
4. Impact of overvoltage on the components
of an electrical installation
4.2 Impact of capacitor switch-in In the case of low voltage motors, the standards (e.g. IEEE
141-1993) recommend the maximum capacitor size (C1 in
transients on the other components figure 54) coupled to a certain motor if permanent connection
in an electrical system is required. If a larger size capacitor is required, provide for
separate switching (C3 in figure 54) by means of a dedicated
Capacitors are frequently used in industrial installations for switching device.
power factor correction in the presence of large motors Irrespective of whether medium voltage or low voltage
that operate with a power factor at full load starting from is used, this latter configuration still poses the problem
0.60. Certain precautions must be taken when sizing these of overvoltage caused by capacitor switching, since the
capacitors, especially to prevent overvoltage due to self- consequent transient overvoltages or multiple zero crossings
energizing of motors disconnected from the network and can cause the protections of the variable speed starting
still turning, when the capacitors are permanently connected systems of the motors to trip. In certain types of drive with
to them. The presence of capacitors also prolongs residual the first conversion stage formed by simple rectifier diodes,
voltage damping after opening, thereby increasing the risk of the overvoltage that reaches the terminals comes from the DC
restarting during this transitory period, during which the actual connection (figure 55).
motors and other equipment could sustain damage.
power supply grid To protect the capacitor and the electronic components of
the inverter stage, the DC connection of the drive is normally
protected against overvoltage. This protection functions by
disconnecting the drive when the overvoltage exceeds a
C4 certain threshold, generally little more than 110% of the rated
DC voltage.
This situation may get worse in the case of medium voltage
capacitor switching (C4 in figure 54) when other low voltage
capacitors are present (C1, C2, C3 in figure 54), thus on the
load side of the MV/LV transformer. So-called secondary
resonance may occur in this case, where overvoltage caused
by medium voltage capacitor switching may cause much
higher overvoltage in the low voltage secondary circuit if the
distribution switchgear resonance frequency of the capacitors is near to the natural
resonance of the switched medium voltage capacitor. In this
case, the initial MV overvoltage creates LV overvoltage as in
the relation:
C1
C3
M
loads
C2 C2
Fig. 54: example of a circuit with several power factor correction points
Where ƒ c is the oscillation frequency that couples with
frequency ƒm of switching oscillation, Ls and Cs are inductance
and capacitance in the secondary circuit, Lm and Cm are
inductance and capacitance in the MV circuit. The lower the
ƒ c/ƒ m ratio, the greater the amplitude of the consequent LV
transient, which can even reach 5 p.u.
42
Drive
DC connection
Rectifier Inverter
Motor
Voltage [V] and current [A] on the DC connection
overvoltage ( 2 p.u.)
Voltage on DC
connection
overcurrent
Current on DC
connection
t [ms]
Fig. 55: diagram of a motor driver and example of the effect on the DC connection of a capacitor switching operation
t [ms]
43
4. Impact of overvoltage on the components
of an electrical installation
These overvoltages can therefore cause faults and trip the This phenomenon can be amplified by resonance phenomena
protection relays and fuses on the low voltage side as well as even when the capacitors are not switched-in together with
tripping the motor drive protections. the transformer. This is because the no-load switching-in
current of the transformers has a certain harmonic content.
Since the motor must obviously remain in service and One of the harmonics, typically of the lower order, may
production downtimes must be avoided, chokes are installed resonate with the capacitors, causing prolunged overvoltage
in series with each drive. Typical values range from 3 to 5% with a high harmonic content that may last for many cycles.
of the drive power expressed in kVA and are sufficient to
reduce the overvoltage on the DC bus to below tripping level.
Although it is simple, this solution clearly requires a large
Step B
number of reactances to be installed in relation to the number
of motors in the installation.
Once again, the alternative solution is to eliminate the
switching overvoltages of MV capacitors by using a
synchronous capacitor switch. In the previous example, where
Voltage [p.u.]
44
5. Economic benefits obtained by using the diode-based
synchronous capacitor switch
45
5. Economic benefits obtained by using the diode-based
synchronous capacitor switch
We'll consider that the cost of the banks equals Ccon for both The replacement costs must also be considered. In the first
configurations. case, the normal life of a circuit-breaker is 10,000 operations.
In the first case, with reference to chapter 4, capacitor At the rate of 730 operations a year, the apparatus will have
reliability can be calculated with reference to the red curve of to be replaced every 10000/730=13.7 years. Supposing that
figure 44 relating to two switches per day. In these conditions, the circuit-breaker replacement cost is CCB, the result is:
reliability is 94% after ten years or, vice versa, failure
probability is 6%. In a capacitor bank formed, for example, by
4 groups in series of 12 capacitors, this means that between
2 and 3 capacitors (figure 61) will fail and that the bank
will have to be replaced since the voltage on an individual
capacitor is: When it comes to maintenance costs and supposing that
maintenance must be performed after every 2,000 operations,
it is due every 2000/730=2.74 years. Supposing that there
will be a maintenance cost every two years of Cman per
intervention, the result will be:
thus higher than the limit value, which is 10% more than the
rated voltage.
P [kV] cosϕ=0,78
0,2 P
h [hours]
When this cost is annualized, the result is:
8 12 14 18 24
Fig. 62: example of a load diagram for an installation that needs power-
factor correction
46
Considering a cost per time-slot B = 0.13 €/kWh, the yearly Now let us attempt to analyze the costs in the second case,
losses per three-phase bank will be: i.e. using a DS1.
In the absence of overvoltages, the failure probability for
switching overvoltage becomes negligible, thus Ccon2=0
When it comes to replacement costs, the normal life of a DS1
is 50,000 operations. At the rate of 730 operations a year,
the apparatus will have to be replaced every 50000/730=68
Another problem in the first case concerns tripping of the years. Thus Csost2=0 since the design life of a capacitor bank
protections in the variable frequency starters that control the is 30 years.
motors in industrial installations or, at any rate, untimely trips of As to maintenance costs, DS1 is maintenance-free so
the protection relay or fuses as a consequence of overvoltage. maintenance costs can be considered nil:
In the first case, this involves an additional cost for possible
loss of production Cpp1.
The total annual cost in the case of the circuit-breaker will Since limiting inductors are not required, the cost of the
therefore be: relative losses is nil, thus:
The total annual cost in the case of DS1 will therefore be:
47
6. Conclusions
Frequent switching of capacitors for power-factor correction [7] E. Sebillotte et al. “ac Degradation of Impregnated
in MV power grids can generate switching overvoltages Polypropylene Films”, IEEE Transactions on Electrical
and overcurrents able to progressively deteriorate the Insulation Vol. 27 No. 3, June 1992
state of the components in the actual installation. Certain [8] C. W. Reed, S. W. Chichanowski. “The Fundamentals of
statistical studies have shown that these same capacitors Aging in HV Polymer-film Capacitors”, IEEE Transactions
may be affected by this deterioration process over time, with on Dielectrics and Electrical Insulation Vol. 1 No. 5,
progressive loss of life until complete breakdown occurs in the October 1994
bank. [9] A. S. Farag et al. “Failure Analysis of composite Dielectric
Although there are tried-and-tested techniques that allow of Power Capacitors in Distribution Systems”, IEEE
these transients to be reduced, they are unable to fully resolve Transactions on Dielectrics and Electrical Insulation Vol. 5
the problem. No. 4, August 1998
On the other hand, the new and innovative diode-based [10] G. C. Montanari, D. Fabiani and F. Ciani, “Partial
capacitor switch technology provides an efficient solution to discharge and aging of AC cable systems under
the problem by reducing both inrush currents and switching repetitive voltage transient supply”, IEEE 34th Electrical
overvoltages to negligible levels. Insulation Conference (EIC), 19-22 June, 2016, Montreal,
The main economic benefit provided by this solution is Quebec.
obviously due to the lower level of stress to which the [11] M. A. Miner. "Cumulative Damage in Fatigue". Joumal of
electrical installation is subjected and, thus, by the ensuing Applied Mechanics, pp. Al59-AI 63, September 1945
enhanced continuity of service and lower maintenance and [12] G. Passarelli. “Modelli Affidabilistico-Diagnostici per i
replacement costs. Componenti delle Reti Elettriche”, Dottorato di Ricerca in
Ingegneria Elettrotecnica, Università di Bologna, 2008
[13] Y. Yoshida et al., “Evolution of Power Capacitor as a
Result of New Material Development”, International
Bibliography Conference on Large High Voltage Electric Systems, 27 -
04, August - September, 1980, Paris, France.
[1] S. W. Cichanowski, G. R. Newcomb, “Power [14] T. Umemura, K. Akiyama. “Accelerated life testing of
Capacitors”, IEEE Electrical/Electronic Insululation power capacitor dielectric systems”, IEEE Transactions
Conference Memo Report HF91-802, 1991. on Electrical Insulation Vol. EI-22 No.3, June 1987
[2] J. C. Das, “Transients in Electrical Systems - Analysis, [15] T. C. Mike Chung. “Functionalization of Polypropylene
recognition and Mitigation”, Milano, Mc Graw Hill, 2001 with High Dielectric Properties: Applications in Electric
[3] F. Pardini, “Apparecchi elettrici: teoria, costruzione, Energy Storage” in Green and Sustainable Chemistry,
applicazione 1”, Milano, Clup, 2001 2012, 29-37
[4] R. P. P. Smeets et al. “The Impact of Switching Capacitor [16] ABB S.p.A. SACE Dalmine. “DS1 - Diode based transient
Banks with Very High Inrush Current on Switchgear”, free capacitor switch”, Medium voltage products
Cigré session 2012 papers of study committee SC A3, catalogue, June 2015
2012 [17] ABB S.p.A. SACE Dalmine. “DS1 - Diode-based
[5] D. G. Shaw, S. W. Cichanowski and A. Yializis. “A transient-free capacitor switch - Key Technological
changing capacitor technology - failure mechanism Features”, Presentation of Medium Voltage Products,
and design innovation”, IEEE Transactions on Electrical June 2015
Insulation Vol. EI-16 No. 5, October 1981 [18] ABB S.p.A. SACE Dalmine. “Capacitor switching
[6] S. Cesari et al., “Evaluation of New Fluid Impregnated All comparison: the supremacy of diode technology”,
Film Power Capacitor Performance”, 12th International Presentation of Medium Voltage Products, June 2015
Conference on Conduction and Breakdown in Dielectric [19] E. Ragaini, F. Viaro, G. C. Montanari, C. A. Mastromauro.
Liquids, 15-19 July 1996, Roma, Italy “Reduction of Capacitor Aging by the use of Transient-
free Diode-based Synchronous Switch” IEEE EEEIC17
and I&CPS Europe Conference, June 2017
48
49
Contacts
ABB S.p.A. The data and illustrations are not binding. We reserve the
1VCP000629 - Rev - en - 2017.06 - (Technical Application Manual No. 23 Medium voltage synchronous capacitor switching) (gs)
right to make changes without notice in the course of
ABB SACE Division technical and product development.
Medium Voltage Products
© Copyright 2017 ABB. All rights reserved.
Via Friuli, 4
I-24044 Dalmine
Tel.: +39 035 6952 111
Fax: +39 035 6952 874
e-mail: info.mv@it.abb.com
www.abb.com