DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
ARCHITECTURE DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 285 578 747 1610

NON-DRAFTED MATERIAL
3 X SCOPE OF WORK 15 15
4 X MTO 5 15 20
100 X SPECIFICATIONS 10 38 48
TEAM MANAGEMENT, IAP, MEETINGS AND COORDINATIONS 50 50
QUALITY/ABR REVIEW 35 35
2 X DVP/DCL PREPARATION, PROGRESS REPORT & UPDATES 27 27
CLIENT REVIEW/COORDINATION MEETINGS 30 30
COMMENTS REVIEW AND RESPONSES 15 10 25
0
SITE VISITS: (Team x Trips x Days x Hours/Day) 0
2 x 1 x 1 x 10 = 10 10 20

0 0 0 2 107 0 0 NON-DRAFTED DWGs - TOTAL MANHOURS 197 73 0 270

EXCEPTIONS / CLARIFICATIONS
1. AS BUILT IS EXCLUDED
2 DEMOLITION IS EXCLUDED

MAN-HOUR DISTRIBUTION CHECK LIST: Please Check all the following items are taken care or not. Yes No
NAME MHRs 1. ALL NEW DWGs COVERED P
ABDULLAH ALRASHED 2. ALL EXSISTING DWGs COVERED P
ABDULRAHMAN NAQI 3. FIELD VISIT & DWG. SEARCH P
HASSAN ALIBRAHIM 4. SUB CONTRACT COORDINATION P
HAMAD ALABDULKARIM 5. MATERIALS REQUISITIONS
NOUF ALANBAR 6. DATA SHEETS (N/A) P
7. CALCULATIONS P
8. MATERIAL TAKE OFFs P
9. ANY OTHER ITEMS P

Drawing Size New Qty Exist Qty New Eq "A" Ext .Eq "A" Total Eq "A"
A 67 67.0 0.0 67.0
B 0.0 0.0 0.0
C 0.0 0.0
D 2 0.5 0.0 0.5
E 107 8.9 0.0 8.9
TOTAL MHRS TOTAL Eq "A" SIZE DWG 76.4 0.0 76.4

TOTAL MAN-HOURS (ALL SHEETS) 482 651 747 1880


TOTAL Eqv. "A" SIZE DWG = 76.4 TOTAL AV. MHRS/ "A" SIZE DWG = 24.6

Page 1 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
ARCHITECTURE DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 285 578 747 1610
"A" "D" "E"
NEW REV. RDD
size
"B" size
size size 0.0 0.0 0.0 0

DRAFTED DRAWINGS

GENERAL
3 X COVER SHEET 3 7 10
1 X SYMBOLS AND ABBREVIATIONS 5 10 15

SUBSTATION
1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X BUILDING ELEVATIONS 5 10 10 25
1 X BUILDING SECTIONS 5 10 15 30
1 X WALL SECTIONS 5 10 15 30
1 X PRECAST PANELS ELEVATIONS AND DETAILS 5 10 15 30
2 X MISCELLANEOUS DETAILS 5 10 15 30
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25

PUMP SHELTER
1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X BUILDING ELEVATIONS 5 10 10 25
1 X BUILDING SECTIONS 5 10 15 30
1 X WALL SECTIONS 5 10 15 30
1 X PRECAST PANELS ELEVATIONS AND DETAILS 5 10 15 30
2 X MISCELLANEOUS DETAILS 5 10 15 30
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25

SAPMT SITE OFFICE


1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X BUILDING ELEVATIONS 5 10 10 25
1 X BUILDING SECTIONS 5 10 15 30
1 X WALL SECTIONS 5 10 15 30
1 X FIRNITURE LAYOUT 5 10 15 30
3 X MISCELLANEOUS DETAILS 5 10 15 30
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25
1 X ENLARGED BATHROOM DETAILS 5 10 10 25

Page 2 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
ARCHITECTURE DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 285 578 747 1610

CONTRACTOR SITE OFFICE


1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X BUILDING ELEVATIONS 5 10 10 25
1 X BUILDING SECTIONS 5 10 15 30
1 X WALL SECTIONS 5 10 15 30
1 X FIRNITURE LAYOUT 5 10 15 30
2 X MISCELLANEOUS DETAILS 5 10 15 30
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25
1 X ENLARGED BATHROOM DETAILS 5 10 10 25

REPEATER SHELTER FOR COMM. AT KM 128


1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X BUILDING ELEVATIONS 5 10 10 25
1 X BUILDING SECTIONS 5 10 15 30
1 X WALL SECTIONS 5 10 15 30
1 X PRECAST PANELS ELEVATIONS AND DETAILS 5 10 15 30
2 X MISCELLANEOUS DETAILS 5 10 15 30
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25

EQUIPMENT ROOM AT BLDG #C4400


1 X LIFE SAFETY CODE ANALYSIS 5 10 15 30
1 X FLOOR PLAN 5 10 15 30
1 X ROOF & REFLECTED CEILING PLAN 5 10 10 25
1 X DOORS AND FINISHES SCHEDULE 5 10 10 25
1 X BUILDING SIGNAGE FLOOR PLAN AND DETAILS 5 10 10 25

67 DRAFTED DWGs - TOTAL MANHOURS 285 578 747 1610

Page 3 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
HVAC DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 105 150 255 510

NON-DRAFTED MATERIAL
3 X SCOPE OF WORK 10 10
4 X MTO 15 15
100 X SPECIFICATIONS 38 38
TEAM MANAGEMENT, IAP, MEETINGS AND COORDINATIONS 10 10
QUALITY/ABR REVIEW 20 20
2 X DVP/DCL PREPARATION, PROGRESS REPORT & UPDATES 10 10
CLIENT REVIEW/COORDINATION MEETINGS 30 30
COMMENTS REVIEW AND RESPONSES 20 20
X HVAC CALCULATIONS 30 30
SITE VISITS: (Team x Trips x Days x Hours/Day) 0
2 x 1 x 1 x 10 = 10 10 20

0 0 0 2 107 0 0 NON-DRAFTED DWGs - TOTAL MANHOURS 193 10 0 203

EXCEPTIONS / CLARIFICATIONS
1. AS BUILT IS EXCLUDED
2 DEMOLITION IS EXCLUDED

MAN-HOUR DISTRIBUTION CHECK LIST: Please Check all the following items are taken care or not. Yes No
NAME MHRs 1. ALL NEW DWGs COVERED P
MOHAMMAD ALI KHAN 2. ALL EXSISTING DWGs COVERED P
IRFAN TAND 3. FIELD VISIT & DWG. SEARCH P
SAMIVULLAH 4. SUB CONTRACT COORDINATION P
5. MATERIALS REQUISITIONS
6. DATA SHEETS (N/A) P
7. CALCULATIONS P
8. MATERIAL TAKE OFFs P
9. ANY OTHER ITEMS P

Drawing Size New Qty Exist Qty New Eq "A" Ext .Eq "A" Total Eq "A"
A 22 22.0 0.0 22.0
B 0.0 0.0 0.0
C 0.0 0.0
D 2 0.5 0.0 0.5
E 107 8.9 0.0 8.9
TOTAL MHRS TOTAL Eq "A" SIZE DWG 31.4 0.0 31.4

TOTAL MAN-HOURS (ALL SHEETS) 298 160 255 713


TOTAL Eqv. "A" SIZE DWG = 31.4 TOTAL AV. MHRS/ "A" SIZE DWG = 22.7

Page 4 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
HVAC DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 105 150 255 510
"A" "D" "E"
NEW REV. RDD
size
"B" size
size size 0.0 0.0 0.0 0

DRAFTED DRAWINGS

GENERAL
1 X SYMBOLS AND ABBREVIATIONS 5 10 15

SUBSTATION
1 X HVAC FLOOR PLAN 10 10 15 35
1 X HVAC ROOF PLAN 5 5 10 20
1 X HVAC SCHEDULE 5 5 10 20
1 X SECTIONS 5 5 10 20
2 X MISCELLANEOUS DETAILS 5 5 10 20

PUMP SHELTER
1 X HVAC FLOOR PLAN 5 5 10 20
1 X HVAC SCHEDULE 5 5 10 20
1 X MISCELLANEOUS DETAILS 5 5 10 20

SAPMT SITE OFFICE


1 X HVAC FLOOR PLAN 5 10 15 30
1 X HVAC SCHEDULE 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

CONTRACTOR SITE OFFICE


1 X HVAC FLOOR PLAN 5 10 15 30
1 X HVAC SCHEDULE 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

REPEATER SHELTER FOR COMM. AT KM 128


1 X HVAC FLOOR PLAN 5 10 15 30
1 X HVAC SCHEDULE 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

EQUIPMENT ROOM AT BLDG #C4400


1 X HVAC FLOOR PLAN 5 10 15 30
1 X HVAC SCHEDULE 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

22 DRAFTED DWGs - TOTAL MANHOURS 105 150 255 510

Page 5 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
FIRE PROTECTION DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 65 90 155 310

NON-DRAFTED MATERIAL
3 X SCOPE OF WORK 10 10
4 X MTO 10 10
100 X SPECIFICATIONS 20 20
TEAM MANAGEMENT, IAP, MEETINGS AND COORDINATIONS 10 10
QUALITY/ABR REVIEW 20 20
2 X DVP/DCL PREPARATION, PROGRESS REPORT & UPDATES 10 10
CLIENT REVIEW/COORDINATION MEETINGS 10 10
COMMENTS REVIEW AND RESPONSES 20 20
X CALCULATIONS 20 20
SITE VISITS: (Team x Trips x Days x Hours/Day) 0
2 x 1 x 1 x 10 = 10 10 20

0 0 0 2 107 0 0 NON-DRAFTED DWGs - TOTAL MANHOURS 140 10 0 150

EXCEPTIONS / CLARIFICATIONS
1. AS BUILT IS EXCLUDED
2 DEMOLITION IS EXCLUDED

MAN-HOUR DISTRIBUTION CHECK LIST: Please Check all the following items are taken care or not. Yes No
NAME MHRs 1. ALL NEW DWGs COVERED P
MOHAMMAD KHALEEL 2. ALL EXSISTING DWGs COVERED P
ABHILASH 3. FIELD VISIT & DWG. SEARCH P
SAMIVULLAH 4. SUB CONTRACT COORDINATION P
5. MATERIALS REQUISITIONS
6. DATA SHEETS (N/A) P
7. CALCULATIONS P
8. MATERIAL TAKE OFFs P
9. ANY OTHER ITEMS P

Drawing Size New Qty Exist Qty New Eq "A" Ext .Eq "A" Total Eq "A"
A 14 14.0 0.0 14.0
B 0.0 0.0 0.0
C 0.0 0.0
D 2 0.5 0.0 0.5
E 107 8.9 0.0 8.9
TOTAL MHRS TOTAL Eq "A" SIZE DWG 23.4 0.0 23.4

TOTAL MAN-HOURS (ALL SHEETS) 205 100 155 460


TOTAL Eqv. "A" SIZE DWG = 23.4 TOTAL AV. MHRS/ "A" SIZE DWG = 19.6

Page 6 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: REPLACE THREE SUBSTATIONS AT RIYADH ORIGINATOR: AAR DATE: 04-Feb-16 REV. NO.:
REFINERY - BI-10-00778
FIRE PROTECTION DETAIL DESIGN DEPT MGR.: JT DATE: 04-Feb-16 A
DRAWING CLASSIFICATIONS MAN-HOURS
DELIVERABLES
No. of Drawings Eng'g Design CADD Total

Existing
New
"A" "B" "C" "D"
size size size size
"E" size DRAFTED DRAWINGS 65 90 155 310
"A" "D" "E"
NEW REV. RDD
size
"B" size
size size 0.0 0.0 0.0 0

DRAFTED DRAWINGS

GENERAL
1 X SYMBOLS AND ABBREVIATIONS 5 10 15

SUBSTATION
1 X FIRE PROTECTION LAYOUT 10 10 15 35
2 X MISCELLANEOUS DETAILS 5 5 10 20

PUMP SHELTER
1 X FIRE PROTECTION LAYOUT 5 5 10 20
1 X MISCELLANEOUS DETAILS 5 5 10 20

SAPMT SITE OFFICE


1 X FIRE PROTECTION LAYOUT 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

CONTRACTOR SITE OFFICE


1 X FIRE PROTECTION LAYOUT 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

REPEATER SHELTER FOR COMM. AT KM 128


1 X FIRE PROTECTION LAYOUT 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

EQUIPMENT ROOM AT BLDG #C4400


1 X FIRE PROTECTION LAYOUT 5 10 15 30
1 X MISCELLANEOUS DETAILS 5 5 10 20

14 DRAFTED DWGs - TOTAL MANHOURS 65 90 155 310

Page 7 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: DETAILED DESIGN ORIGINATOR: FMI DATE: ### REV. NO.:

CSA EWO-2011-025 SECURITY MANAGEMENT BUILDING DEPT MGR.: FMI DATE: ### 01
DRAWING CLASSIFICATIONS MAN-HOURS
TOTAL NO. OF NEW DW
DELIVERABLES
No. of Drawings Eng'g Design CADD Total ###

Existing
New
"A" "B" "C" "D" "E"
size size size size size DRAFTED DRAWINGS

TOTAL MAN-HOURS (FROM OTHER SHEETS) 256 512 512 1280


NO. OF NEW DRAWIN
NON-DRAFTED DRAWINGS A
0 ###
30 X SCOPE OF WORK 30 30 ###
80 X SPECIFICATIONS 80 80 ###
160 X STRUCTURAL CALCULATIONS 160 160 ###
100 X MATERIAL TAKE OFFs 120 120 ###
CSA TEAM MANAGEMENT AND MEETINGS 100 100 ###
QUALITY 30 0 30 ###
0
MATERIAL REQUISITIONS: 0 ###
NONE 0 0 ###
0 0 ###

SITE VISITS: (Team x Trips x Days x Hours/Day) 0 ###


1 x 2 x 3 x 10 = 30 30 60 ###

SUBCONTRACTS:
NONE 0
0
0 ###
0 ###
370 NON-DRAFTED DWGs - TOTAL MANHOURS 430 150 0 580

EXCEPTIONS / CLARIFICATIONS
1. GEOTECHNICAL INESTIGATION & TOPOGRAPHIC SURVEY ARE NOT INCLUDED IN JZ SOW
2. AS BUILT IS EXCLUDED FROM JZ SOW
3. PARKING SHADE IS EXCLUDED FROM JZ SOW

MAN-HOUR DISTRIBUTION CHECK LIST: Please Check all the following items are taken care or not. Yes No
NAME MHRs 1. ALL NEW DWGs COVERED P
MUHAMMAD AMIR RIZA 2. ALL EXSISTING DWGs COVERED P
PROSPERO L. BORJA 3. FIELD VISIT & DWG. SEARCH P
AUDI D. DASALLA 4. SUB CONTRACT (SOW AND COST) P
5. MATERIALS REQUISITIONS P
6. DATA SHEETS (N/A) P
7. CALCULATIONS P
8. MATERIAL TAKE OFFs P
9. ANY OTHER ITEMS P

Drawing Size New Qty Exist Qty New Eq "A" Ext .Eq "A" Total Eq "A" ###
A 42 0 42.0 0.0 42.0 ###
B 6 0 3.0 0.0 3.0 ###
C 0 0 0.0 0.0 0.0
D 0 0 0.0 0.0 0.0
E 370 0 30.8 0.0 30.8
TOTAL MHRS 0 TOTAL Eq "A" SIZE DWG 75.8 0.0 75.8

TOTAL MAN-HOURS (ALL SHEETS) 686 662 512NO. OF


1860
NEW DRAWIN

Page 8 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: DETAILED DESIGN ORIGINATOR: FMI DATE: ### REV. NO.:

CSA EWO-2011-025 SECURITY MANAGEMENT BUILDING DEPT MGR.: FMI DATE: ### 01
DRAWING CLASSIFICATIONS MAN-HOURS
TOTAL NO. OF NEW DW
DELIVERABLES
No. of Drawings Eng'g Design CADD Total ###

Existing
New
"A" "B" "C" "D" "E"
size size size size size DRAFTED DRAWINGS

TOTAL Eqv. "A" SIZE DWG = 75.8 DEM-1, Rev. no. 3, April 15, 2009 by FMI TOTAL AV. MHRS/ "A" SIZE DWG = 24.5 A
0.0 0.0 0.0 0 ###
DRAFTED DRAWINGS ###
0.0 0.0 0.0 0 ###
GENERAL 0 0 0 0 ###
1 X GENERAL NOTES, ABBREVIATION AND LEGEND-CIVIL WORKS 4 8 8 20 ###
1 X GENERAL NOTES, ABBREVIATION AND LEGEND-STRUCTURAL WORKS 4 8 8 20 ###

SITE WORKS
2 X GENERAL NOTES, ABBREVIATION AND LEGEND 12 24 24 60 ###
1 X GRADING, PAVING & FENCING PLAN 6 12 12 30 ###
2 X GRADING AND PAVING DETAILS 12 24 24 60 ###
2 X SANITARY SEWER LAYOUTS 8 16 16 40 ###
2 X SWS MANHOLES PLAN SECTION & DETAILS 12 24 24 60 ###
2 X U/G POTABLE WATER TANK DETAILS 12 24 24 60 ###
2 X U/G FIRE WATER TANK DETAILS 12 24 24 60 ###
2 X SEPTIC TANK PLAN, SECTIONS & DETAILS 12 24 24 60 ###
1 X LIGHTING POLE FOUNDATION DETAILS 6 12 12 30 ###
2 X GUARDHOUSE DETAILS 12 24 24 60 ###
2 X MISCELLANEOUS SITE DETAILS 10 20 20 50 ###

ISD BUILDING (SECURITY MANAGEMENT BUILDING) 0 0 0 0 ###


1 X FOUNDATION LOCATION PLAN 6 12 12 30 ###
2 X FOOTING PLAN, SECTIONS & DETAILS 12 24 24 60 ###
1 X GRADE SLAB PLAN, SECTIONS & DETAILS 6 12 12 30 ###
2 X GRADE BEAMS SCHEDULE & DETAILS 12 24 24 60 ###
1 X COLUMNS SECTIONS & DETAILS 6 12 12 30 ###
1 X FIRST FLOOR FRAMING PLAN 6 12 12 30 ###
1 X FIRST FLOOR BEAMS SCHEDULE & DETAILS 6 12 12 30 ###
1 X ROOF FLOOR FRAMING PLAN 6 12 12 30 ###
1 X ROOF BEAMS SCHEDULE & DETAILS 6 12 12 30 ###
1 X STAIR PLAN, SECTIONS & DEATILS 6 12 12 30 ###
1 X ELEVATOR SHAFT PLAN, SECTIONS & DEATILS 6 12 12 30 ###
2 X WALLS SECTIONS AND DETAILS 12 24 24 60 ###
1 X HAVC UNITS PADS PLAN, SECTIONS & DETAILS 6 12 12 30 ###
2 X MISCELLANEOUS CONCRETE DETAILS 10 20 20 50 ###
2 X MISCELLANEOUS STEEL DETAILS 10 20 20 50 ###
6 X STEE BENDING DETAILS 18 36 36 90 ###

Page 9 of 10
DELIVERABLES AND ESTIMATED MAN-HOURS

DEPARTMENT PROJECT TITLE: DETAILED DESIGN ORIGINATOR: FMI DATE: ### REV. NO.:

CSA EWO-2011-025 SECURITY MANAGEMENT BUILDING DEPT MGR.: FMI DATE: ### 01
DRAWING CLASSIFICATIONS MAN-HOURS
TOTAL NO. OF NEW DW
DELIVERABLES
No. of Drawings Eng'g Design CADD Total ###

Existing
New
"A" "B" "C" "D" "E"
size size size size size DRAFTED DRAWINGS

0 0 0 0 ###