Вы находитесь на странице: 1из 15

Feet

“ ”

80
“ ”

40
0
” ” ” ”


Feet
80
40
0
PROPOSED BLDG
FFE: 687.6
Feet
80
40
0
PROPOSED BLDG
FFE: 687.6
PROP

0 40 80
Feet
Feet
80 40 0
PROPOSED BLDG
FFE: 687.6
Feet
80
40
0
PROPOSED BLDG
FFE: 687.6
Feet
80
40
0
PROPOSED BLDG
FFE: 687.6
H-1
HYDROLOGY REPORT
Runoff (Q) and peak flow (q) values were calculated using the SCS Curve Number and
Rational methods, respectively. Runoff from pre- to post-development stayed the same at 4.52
inches. Peak flow decreased 0.4 cfs from 14.9 cfs pre-development flow to 14.5 cfs post-
development flow. Hydrology characteristics for pre- and post-development are listed below as
well as runoff and peak flow values (tables 1-4).
Pre-Development

Table 1. Pre-development site descriptions with contributing areas, runoff coefficients, and
Manning’s Roughness Coefficients (n).
Surface description Area C n
(ac)
impervious (roof)
0.50 0.90 0.011
impervious (asphalt parking lot
and concrete sidewalk) 1.23 0.90 0.011
grass (short, design purposes) 0.77 0.25 0.150
Total/Weighted Values 2.50 0.70 0.054

Table 2. Hydrology characteristics for pre-development with total runoff (Q) and the peak
discharge (q).
P2 weighted n, L S weighted C, Tc [1] i[2] Q[3] q[4]
nw Cw
(in) (ft) (ft/ft) (min) (in hr-1) (in) (cfs)
4.16 0.054 300 0.067 0.70 5.6 8.5 4.52 14.9

0.007(𝑛𝑛𝑛𝑛)0.8
[1] 𝑇𝑇𝑐𝑐 = , where P2 is for 2-yr 24 hr design storm
(𝑃𝑃2)0.5 𝑆𝑆 0.4
[2] i value interpolated for 15-yr storm at Tc
1000 2
�𝑃𝑃−0.2� −10��
𝐶𝐶𝐶𝐶𝑤𝑤
[3] 𝑄𝑄 = 1000 , where P is for 15-yr 24 hr design storm
𝑃𝑃+0.8� −10�
𝐶𝐶𝐶𝐶𝑤𝑤
[4] 𝑞𝑞 = 𝐶𝐶𝑤𝑤 𝑖𝑖𝑖𝑖, where A is the total area from Table 1
H-2
Post-Development

Table 3. Post-development site descriptions with contributing areas, runoff coefficients, and
Manning’s Roughness Coefficients (n).
Surface description Area C n
(ac)
impervious (asphalt) 0.90 0.90 0.011
impervious (concrete sidewalk) 0.23 0.90 0.011
grass (good condition) 0.85 0.20 0.150
impervious (roof) 0.50 0.90 0.011
bioswale 0.02 0.20 0.150
Total/Weighted Values 2.50 0.66 0.059

Table 4. Hydrology characteristics for post-development with total runoff (Q) and the peak
discharge (q).
P2 weighted n, L S weighted C, Tc [1] i[2] Q[3] q[4]
nw Cw
(in) (ft) (ft/ft) (min) (in hr-1) (in) (cfs)
4.16 0.059 300 0.063 0.66 6.2 8.2 4.52 14.5

0.007(𝑛𝑛𝑛𝑛)0.8
[1] 𝑇𝑇𝑐𝑐 = , where P2 is for 2-yr 24 hr design storm
(𝑃𝑃2)0.5 𝑆𝑆 0.4
[2] i value interpolated for 15-yr storm at Tc
1000 2
�𝑃𝑃−0.2� −10��
𝐶𝐶𝐶𝐶𝑤𝑤
[3] 𝑄𝑄 = 1000 , where P is for 15-yr 24 hr design storm
𝑃𝑃+0.8� −10�
𝐶𝐶𝐶𝐶𝑤𝑤
[4] 𝑞𝑞 = 𝐶𝐶𝑤𝑤 𝑖𝑖𝑖𝑖, where A is the total area from Table 1

Stormwater Conveyance, Treatment, and Detention


The stormwater management design has been designed in order to treat and clean the first
inch of rainfall and detain 50% of the 15-yr design storm runoff. Five main drainage sub-basins
were created and peak flows and volumes were calculated using the Hydraflow Hydrographs
program.
H-3

Table 5. Sub-basin characteristics.


Sub-basin Area Cw Time of concentration, q Runoff Volume
Tc
(ac) (min) (cfs) (cuf)
1 0.2 0.72 5 1.3 377
2 0.49 0.66 5 2.8 847
3 0.17 0.9 5 1.3 401
4 0.34 0.86 5 2.6 766
5 0.5 0.9 5 3.9 1180
Total storm water drainage 11.9 3571

Water treatment and detention was achieved by designing both a dry pond and bioswale.
The dry pond was designed using Hydraflow Hydrographs (fig. 2). The bioswale was designed
using the following calculation design sheets obtained from the Louisville Metropolitan Sewer
District Design Manual (2009).

Figure 1. Sediment basin and dry pond characteristics, per Hydraflow Hydrographs program.
FINAL DESIGN PROJECT COST ANALYSIS
Item Category Items Quantity Unit Estimated Cost per Unit Total Estimated Cost

Connections (gas, sanitary sewer, water,


1 LS $6,875.00 $6,875
Utilities stormwater) - Tie to Existing

1 LS $2,800.00 $2,800
Utilities Electric Connection

1 LS $3,750.00 $3,750
Utilities Telecomm Connection

100 LF $23.00 $2,300


Utilities Underground Electrical (tie in to existing)

204 LF $15.55 $3,172


Utilities 6" Steel Water Main (tie in to existing)

204 LF $22.00 $4,488


Utilities 8" RCP casing for water main

135 LF $22.00 $2,970


Utilities 8" RCP Sanitary Sewer

1 EA $49.00 $49
Utilities Gas Valve

1 LS $150.00 $150
Utilities Water Valve

1 EA $1,200.00 $1,200
Utilities Concrete Pre-Cast Manhole w/ring & cover

3 EA $1,000.00 $3,000
Utilities Streetlights

550 LF $22.50 $12,375


Concrete and Paving 6' Sidewalk 2" thick w/ GAB

468 TON $75.00 $35,075


Concrete and Paving Asphalt (Parking Lot) Top Layer 2"

1170 TON $70.00 $81,871


Concrete and Paving Asphalt (Parking Lot) Bottom Layer 5"
Parking lot removal & disposal (w/ dumping
1 LS $29,000.00 $29,000
Concrete and Paving fees)

400 SY $5.45 $2,180


Concrete and Paving Sidewalk Removal/Demolition
Item Category Items Quantity Unit Estimated Cost per Unit Total Estimated Cost

4100 LF $26.00 $106,600


Concrete and Paving 6" Curb and Gutter, COA Std.
Parking lot painting (stalls, ADA stalls, stop bars,
1 LS $3,280.00 $3,280
Concrete and Paving crosswalks, arrows, stenciling)

1 LS $34,000.00 $34,000
Grading and Earthwork Grading, Complete (Cut and Fill)

14 EA $651.00 $9,114
Grading and Earthwork Tree Removal

11800 SF $0.55 $6,490


Grading and Earthwork Sod Grass
Erosion and Sediment
659 LF $12.45 $8,205
Control Type "A" Silt Fence, Installed
Erosion and Sediment
4 EA $300.00 $1,200
Control Inlet Sediment Traps
Erosion and Sediment
2 EA $1,500.00 $3,000
Control Construction Exit

126 LF $99.00 $12,474


Storm 36" RCP

53 LF $77.00 $4,081
Storm 33" RCP

126 LF $74.50 $9,387


Storm 30" RCP

78 LF $49.00 $3,822
Storm 24" RCP

113 LF $36.00 $4,068


Storm 18" RCP

51 LF $30.00 $1,530
Storm 15" RCP

60 LF $27.00 $1,620
Storm 12" RCP

1 EA $3,698.20 $3,698
Storm Fittings (10% of pipe cost)

1 EA $222.00 $222
Storm 48" Cylindrical Pipe Junction

1 EA $421.79 $422
Storm 72" Cylindrical Pipe Junction
Page 2 of 3
Item Category Items Quantity Unit Estimated Cost per Unit Total Estimated Cost

1 EA $305.56 $306
Storm Rectangular Junction Structure

4 EA $250.00 $1,000
Storm 48" Cylindrical Junction w/ Rectangular Frame

1 EA $1,200.00 $1,200
Storm Single Wing Curb Inlet (COA std)

3 EA $550.00 $1,650
Storm Drop Grate Inlets

1 EA $100.00 $100
Storm Dome Grate (Bioswale)

2 EA $150.00 $300
Storm Downspouts

1 EA $1,600.00 $1,600
Storm Double Wing Concrete Inlet (COA std)

3 EA $3,000.00 $9,000
Storm SPHW Concrete Rectangular Headwall

1 LS $8,500.00 $8,500
Storm Bioswale (Complete)

1 LS $4,000.00 $4,000
Storm Dry Pond (Complete)

$432,122.40
Total

Subtotal $432,122.40

O&P - Add 20% $44,020.20

Contingency - Add 10% $39,791.11

Eng. Design Fee - Add 15% $64,818.36

Total: $580,752.07

Page 3 of 3

Вам также может понравиться