Вы находитесь на странице: 1из 5

ACI Concrete Field Testing Technician- Grade I

Study online at quizlet.com/_444cz

1. A 6 by 12 in [150 mm by 300 mm] cylinder mold can be 18. The concrete sample must be protected from
used for concrete containing aggregate with particles contamination and _____.: Rapid evaporation
not exceeding _____ in size, without the need for wet 19. Concrete samples from a truck mixer must be obtained
sieving the concrete.: 2 in. [50 mm] before any water or admixtures are added to the mixer
2. According to ASTM C1064, what is one reason to take the at the job site. True or False?: False
temperature of concrete?: Verify conformance to a specified 20. The container for obtaining the concrete sample used in
requirement for temperature of concrete this procedure can be a _____, _____, or _____.: Metal
3. After completing the strike-off procedure, what must be pan, wheelbarrow, flat, clean nonabsorbent mixing board
done before weighing the measure and sample?: Clean off 21. Cylinders made for the purpose of determining when a
any excess concrete structure may be put into service shall be removed from
4. After consolidation of the final layer, an excess of the mold __________.: At the time of the removal of
concrete ____ above the top of the measure is formwork
considered optimum.: 1/8 in. [3 mm] 22. Cylinders that are to be field cured are stored
5. After molding test specimens, you should wait two hours __________ and protected __________.: In or on the
before moving them to the location of initial storage. structure as near to the point of deposit of the concrete
True or False?: False; the specimens must be moved represented as possible; In as near as possible the same way as
immediately the formed work
6. After rodding each layer, what should be done to the 23. The diameter of the tamping rod used in the test method
measure before adding another layer of concrete?: Tap is _____.: 5/8 in. [16 mm]
the sides of the measure smartly 10 to 15 times with the mallet 24. The direct reading of the final liquid level in the neck of
7. After the final rodding, the sides of the slump mold the air meter, is estimated to teh nearest _____.: 0.25%
should should be tapped lightly with the tamping rod. 25. During transportation, test specimens must be
True or False?: False protected from damage due to _____, _____, and
8. After the temperature of the concrete is read, what is _____.: Jarring, freezing temperatures, moisture loss
required?: Reporting of temperature 26. Each layer should fill approximately _____ the volume
9. Air meter bowls used for this test must conform to ASTM of the mold.: One-third
_____ and be calibrated for volumee according to 27. Field Curing is the curing method used when test
ASTM _____.: C231, C29 specimens are to be used for __________.:
10. The approximate concrete depth (in verticle distance) Determination of whether the structure is capable of being put
after placing the first layer is _____, and the second into service; Comparison with standard cured specimens test
layer is _____.: 2 5/8 in. [70 mm], 6 1/8 in. [160 mm] results or with results from various in-place test methods;
11. ASTM Method gives standardized requirements for Adequacy of curing and protection of concrete in the Structure, or
_____, _____, _____, and _____, of test specimens.: Form or shoring removal time requirements
Making, curing, protecting, transporting 28. For a measure of 0.5 ft^3 [14 L], what is the required
12. At the end of the procedure, the air meter is _____.: number of strokes of the tamping rod for consolidation
Disassembled and its contents examined of each layer?: 25
13. The composite sample for a paving mixer must 29. For concrete with a slump of less than 1 in. [25 mm], the
represent a minimum of _____ different portions of test specimens must be consolidated by _____.:
the batch of concrete taken from the pile after Vibration
discharge.: 5 30. For cylinders with a diameter of 6 in. [150 mm] or
14. A composite sample of concrete is required even if the greater, the tamping rod must be a round, straight steel
only purpose for obtaining the sample is to determine rod with a diameter of _____.: 5/8 +- 1/16 in [16 mm +- 2
temperature. True of False?: False mm]
15. The composite samples from a truck mixer must be 31. For use in the slump test, the end or both ends of the
obtained from the _____ portion of the batch.: Middle tamping rod must be _____.: Rounded to a hemispherical
tip
16. Concrete mixtures with specified strengths of 6000 psi
32. The height of the slump mold is _____.: 12 in. [300 mm]
[40 MPa] or greater shall have an initial curing
temperature between __________.: 68 and 78 degrees F 33. How deep should the tamping rod penetrate into each
[20 and 26 C] layer?: Rod each layer throughout its depth; on the second and
17. The concrete sample must be obtained in accodance final layers, the rod should penetrate into the previous layer
with what ASTM method?: C172 approximately 1 in. [25 mm]
34. How long must the temperature measuring device 52. In rodding the sample, how deep should the rod
remain in the freshly mixed concrete?: At least 2 minutes penetrate each layer?: Rod bottom layer to full depth; rod
but not more than 5 minutes second and final layer penetrating the previous layer about 25
35. How long should the air meter be inverted and mm (1 in.)
agitated?: No more than five seconds at a time, but must be 53. The initial quantity of water and alcohol added to the air
repeated for a minimum of 45 seconds to free concrete from the meter can be poured directly into the neck of the top
base section of the air meter. True or False?: False; the funnel
36. How many times does the rolling operation occur?: A must be used
minimum of 2, a minimum of 3 54. The interior surface of the slump mold is allowed to
37. How much time is allowed for lifting the slump mold?: 5 have minor irregularities. True or False?: False
+- 2 seconds 55. It is necessary to tap the sides of the bowl after each
38. How much time is allowed to conduct the slump test layer has been rodded. True or False?: True
from beginning to completion?: 2 1/2 minutes 56. A mallet weighing ____ must be used to tap the sides of
39. If less than 2.5 pints of alcohol are used, the air content the bowl after rodding each layer.: 1.25 +- 0.50 lb. (600 +-
is always indicated by the inal meter reading. True or 200 g)
False?: False, if the air content is more than 9%, the number of 57. The maximum allowable time between obtaining the
calibrated cups of water introduced into the meter to bring the first and final portions of a composite sample is _____
liquid level within the graduated range must be added minutes.: 15
40. If more than 2.5 pints of alcohol are used, the final 58. The maximum elapsed time allowed between obtaining
meter reading is always adjusted using _____.: A the final portion of the composite sample and beginning
correction factor the tests for slump, temperature, and air content is
41. If portions of undisturbed concrete are found in the air _____ minutes.: 5
meter at the end of the test, _____.: The test is invalid 59. The maximum size aggregate allowed for this test
42. If rodding is the method of consolidation being used, the method is _____.: 50 mm (2 in.)
measure must be filled in how many layers?: 3 60. The maximum size aggregate allowed in this test method
43. If the air content is greater than the 9% range of the is_____.: 1 1/2 in. (37.5 mm)
meter, _____.: Calibrated cups of water are added to ring the 61. A maximum temperature of freshly mixed concrete is
liquid level within the graduated range specified in ASTM C1064. True of False?: False
44. If the concrete contains aggregate larger than the 62. The measurement for slump is made from the top of the
maximum allowed for this test, the sample must be mold to what point of the concrete specimen?: The
_____.: Wet sieved over a 1 1/2 in. (37.5 mm) sieve displaced original center of the top surface of the specimen
45. If the concrete is to be consolidated by vibration, a 63. Measures other than air meter bowls used for this test
standard 4 by 8 in. [100 mm by 200 mm] cylinder mold must conform to ASTM _____.: C29
must be filled in _____ equal layers.: 2 64. The minimum frequency of an internal vibrator used in
46. If the concrete sample contains aggregate larger than this procedure is _____.: 9000 vibrations per minute [150
that allowed for this test, the sample must be _____.: Hz]
Wet sieved over a 1-in. (25-mm) sieve 65. The minimum size sample for making strength test
47. If the concrete sample is to be consolidated by rodding, specimens is _____.: 28 L (1ft^3)
the measure is filled in _____ layers.: 3 equal 66. The mold for making the slump test is in the shape of
48. If the concrete sample is to be consolidated by vibration, _____.: The frustum of a cone
the measure is filled in _____ layers.: 2 equal 67. The molding of strength test specimens shall begin
49. If vibration is the method of consolidation, the measure within _____ minutes after fabricating the composite
must be filled in _____ approximately equal layers.: 2 sample.: 15
50. If, after consolidation of the final layer, the concrete 68. The outside diameter or side dimension of the vibrating
level is 1/2 in. (13 mm) above the top of the measure, element must be at least _____ but not greater than
what should be done?: Remove a representative portion of the _____.: 0.75 in. [19 mm], 1.50 in. [38 mm]
excess concrete with a trowel or scoop 69. A plastic container can be used for the measure in this
51. In order for an initial meter reading to be valid, the method. True or False?: False, measure must be steel or
meter must not be leaking, the liquid level must stabilize another suitable metal
within 6 minutes, and the foam on the surface of the 70. Portions of a composite sample shall be thoroughly
liquid must not be greater than 2 full percent divisions. remixed bfore beginning tests on the sample. True of
True or False?: True False?: True
71. The pressure method of determining air content can be 90. The temperature measuring device shall be calibrated
used on concrete containing _____ _____ aggregate.: _____, or whenever there is a question of _____.:
Relatively Dense Annually, accuracy
72. The pressure method of determining air content cannot 91. The temperature measuring device shall have a capacity
be used on concrete containing the following types of of measuring temperature of freshly mixed concrete to
aggregates, _____, _____, _____.: Lightweight, air- +- _____ degrees F [+- _____ C] throughout a range of
cooled blast furnace slag, or aggregates of high porosity _____.: 1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
73. Prior to lifting the mold, concrete must be removed from 92. The temperature of concrete is reported to the nearest
_____.: The area surrounding the base of the mold _____ degrees F [_____ C]: 1 degree F [0.5 C]
74. The sample of concrete for use in making the slump test 93. The temperature of concrete may be measured in a wall
must be obained in accordance with ASTM Standard form. True of False: True
_____.: C172, Standard Practice for Sampling Freshly Mixed 94. The temperature of concrete may be measured in a
Concrete wheelbarrow. True or False?: True
75. The sample of concrete used for temperature 95. This method covers sampling from four types of
determination must be rodded 25 times. True or False?: mixtures which are _____, _____, _____, and _____.:
False Stationary mixers, paving mixers, revolving drum mixers, and
76. The sample of concrete used for this test is to be open top mixers
obtained in accordance with what ASTM Standard?: 96. Transportation time shall not exceed _____.: 4h
C172
97. Up to 48 hours after molding, test specimens that are to
77. The sample of concrete used in molding test specimens
be standard cured shall be stored in a temperature
must be obtained in accordance with what ASTM range between _____ to _____.: 60 and 70 degrees F [16
Standard?: C172 and 27 C]
78. The sample of concrete used in this test method must be 98. Upon completion of initial curing, the test specimens
obtained in accordance with what ASTM Standard?: may be left in their molds and sealed in plastic bags.
C172 True or False?: False; specimens are to be demoled and placed
79. Sampling by this method is required when tests are to be in water storage tanks or moist rooms with free water at a
made to determine _____ with specification temperature of 73.5 +- 3.5 degrees F [23.0 +- 2.0 C]
requirements.: Compliance 99. Upon final filling of the air meter with water, what part
80. The sensor of the temperature measuring device shall be of the liquid level should be adjusted to teh zero mark on
submerged a minimum of _____ in. [_____mm] into the meter?: Bottom of the meniscus
the freshly mixed concrete.: 3 in. [75 mm] 100. Vibration of the concrete sample is not allowed when
81. The slump mold is filled in _____ layers.: 3 the slump of concrete exceeds _____.: 75 mm (3 in.)
82. The slump mold should be in a dry condition before 101. The volumetric method of determining air content of
beginning the test. True or False?: False concrete can be used on concrete containing what types
83. The slump of the concrete is measured and reported to of aggregate?: All types of aggregate
the nearest _____.: 1/4 in. [5 mm] 102. What are the required characteristics of the tamping
84. The slump test is applicable to plastic concrete with a rod used in this test method?: Round, straight steel rod,
maximum size aggregate of _____.: 1.5 in. [37.5 mm] with a 16 mm [5/8 in.] +- 2 mm [1/16 in.] diameter, length at
least 100 mm [4 in.] greater than the depth of the measuring
85. Specimens shall not be transported until _____ after
bowl, but not greater than 600 mm [24 in.] in overall length,
final set.: 8h
with the tamping end rounded to a hemispherical tip of the same
86. Standard Curing is the curing method used when test diameter as the rod.
specimens are to be used for _________.: Acceptance 103. What are the requirements for the strike-off bar used
testing for specified strength, checking the adequacy of mixture
in this test method?: Flat, straight steel bar at least 1/8 by 3/4
proportions for strength, quality control
by 12 in. [3 by 20 by 300 mm] or a 4.4 flat, straight high-density
87. The supporting surface on which specimens are stored polyethylene bar, or other plastic of equal or greater abrasion
shall be level within _____.: 1/4 in. per ft. [20 mm per m] resistance, at least 1/4 by 3/4 by 23 in [6 by 30 by 300 mm].
88. The surface on which the slump mold will be placed 104. What are the requirements for the tamping rod used in
must be _____.: Flat, level, moist, nonabsorbent, and free of the test method?: Round, straight 5/8 [16 mm] +- 1/16 in. [2
vibration mm] diameter rod at least 5 in. [300 mm] greater in length than
89. The temperature and moisture environment for field the depth of the bowl being used, with the tamping end rounded
cured cylinders must be __________.: The same as the to a hemispherical tip of the same diameter, made of steel, high-
structural work density polyethylene, or other plastic of equal or greater abrasion
resistance.
105. What is the approximate volume of the measuring cup 124. When consolidating a flexural strength test specimen
used to add water to the air meter, in relation to teh by rodding, rod one stroke for each _____ of top
volume of the air meter bowl?: 1.00% +- 0.04% surface area.: 2 in.^2 [14 cm^2]
106. What is the minimum allowable capacity of the 125. When consolidating the concrete by vibration, how
measuring bowl used in this test method?: 6 L (0.20 ft^3) many times should the vibrator be inserted into each
107. What is the minimum thickness for a glass or acrylic layer?: Three (3)
strike-off plate?: 1/2 in. [12 mm] 126. When filling the bowl of the air meter, the concrete
108. What is the minimum thickness of a metal strike-off must be placed in _____ layers of equal depth.: 2
plate?: 1/4 in. [6 mm] 127. When internal vibration is used to consolidate a
109. What is the required minimum frequency of the standard flexural strength test specimen, the technician
vibrator used in this test method?: 7000 vibrations per should insert the bibrator at intervals not exceeding
minute _____ along the center line of the beam.: 6 in. [150 mm]
110. What is the required shape of the tamping end of the 128. When large amounts of alcohol are used, the direct
rod?: Rounded to a hemispherical tip reading will tend to indicate a _____ air content.:
Higher
111. What is the specified number of roddings for each
129. When raising the slump mold, it should not be rotated
layer?: 25
or twisted, True or False?: True
112. What is the specified number of strokes required when
130. When rodding a standard 6 by 12 in [150 mm by 300
rodding each layer of concrete?: 25
mm] cylinder, each layer must be rodded _____ times.:
113. What is the specified size of the mallet required for this
25
test method when the measuring bowl has the capacity
131. When rodding each upper layer of concrete in a
of 14 L [0.5 ft^3] or less?: 0.60 +- 0.25 kg [1.25 +- 0.50 lb.]
cylinder, the tamping rod should penetrate into the
114. What is the specified weight of the mallet used on
underlying layer by about _____.: 1 in. [25 mm]
measures that are 0.5 ft^3 [14 L] or smaller?: 1.25 +- 0.50
132. When rodding the bottom layer, the tamping rod must
lb. [600 +- 200 g]
be _____ to uniformly distribute the strokes.: Slightly
115. What method of consolidation must be used when the
inclined
slump is greater than 3 in. [75 mm]?: Rodding
133. When rodding the concrete sample, what is the
116. What method of consolidation must be used when the
specified number of strokes required for each layer?: 25
slump is less than 1 in. (25 mm]?: Vibration
134. When rodding the middle and the top layers, the
117. What must be done if the concrete drops below the top
tamping rod should penetrate into the layer below
of the slump mold while the top layer is being rodded?:
approximately _____.: 1 in. [25 mm]
Add additional concrete to keep an excess of concrete above the
135. When sampling from a revolving drum truck mixer,
top of the mold at all times
concrete must be sampled at a minimum of _____
118. What must be done if there is a slight deficiency in the
regularly spaced intervals during discharge of the
quantity of concrete in the measure of consolidation of
middle portion of this batch.: 2
final layer?: Add a quantity of representative concrete before
136. When sampling from a stationary mixer, the batch
strike off
must be sampled at _____ or more regularly spaced
119. What must be done if there is an excessive amount of
intervals during discharge of the middle portion of the
concrete in measure following consolidation of the final
batch: 2
layer?: Remove a representative quantity of concrete with the
137. When strenght specimens are to be made, what three
scoop or trowel before the strike off
other tests must be made?: Slump, air content, temperature
120. What must be done to the concrete surrounding the
138. When the concrete contains aggregate larger than
temperature measuring device after the device is
submerged in the fresh concrete.: Gently press the concrete allowed for the slump test, the large aggregate must be
around the temperature measuring device at the surface of the _____.: Removed by wet sieving the sample over 1.5 in. [37.5
concrete mm] sieve
121. What must be done to the sample container prior to 139. When the concrete contains aggregate larger than that
sampling the concrete?: Dampen (with water) permitted for a particular test method, the sample of
concrete must be _____ _____ before making the test.:
122. What tools may be used to strike off the top surface of
Wet sieved
the concrete following consolidation of the final layer?:
140. When using an internal vibrator to consolidate a 6 by 12
A strike-off bar; a metal, glass, or acrylic plate
in. [150 mm by 300 mm] compressive strength test
123. What type of alcohol and concentration must be used in
specimen, the vibrator must be inserted at _____
this test method?: Isopropyl, 70% by volume (65% by weight)
different points for each layer.: 2
141. Why is the isopropyl alcohol added to the meter?: To dispel any foam that may be on the surface of the water