Project: Standard Two-Storey School Building (12-Classrooms)

Location: Various DPWH Proposed Projects


Subject: Bill of Materials

SEQUENCE ACTIVITY DURATION START FINISH

PHASE I. PRE-CONSTRUCTION / PREPARATION

1 Site Clearing 2 4-3-17 4-4-17

2 Site Surveying 2 4-5-17 4-6-17

3 Soil Testing 1 4-7-17 4-7-17

4 Site Plan Design 3 4-8-17 4-10-17

5 Survey and Stake out footprints 1 4-11-17 4-11-17

Total 9

PHASE II. CONSTRUCTION AND OPERATION


Excavation/Leveling
1 4 4-12-17 4-15-17
/Compaction

2 Filling and Backfilling 3 4-16-17 4-18-17

3 Footing 2 4-19-17 4-20-17

4 Placing of steel reinforcement 3 4-21-17 4-23-17

5 Formworks Installation 3 4-24-17 4-26-17

Foundation Leveling/Rebar
6 3 4-27-17 4-29-17
Installation

7 Concreting and Curing 6 4-30-17 5-5-17

8 Column Rebar Installation 4 5-6-17 5-9-17

Scaffolding and Formworks


9 4 5-10-17 5-13-17
Installation

10 Concreting and Curing 6 5-14-17 5-19-17

2nd Floor Beam and Slab Rebar


11 4 5-20-17 5-23-17
Installation

Scaffolding and Formworks


12 6 5-24-17 5-29-17
Installation
13 Concreting and Curing 6 5-30-17 6-4-17

2nd Floor Column Rebar


14 4 6-5-17 6-8-17
Installation

Scaffolding and Formworks


15 6 6-9-17 6-14-17
Installation

16 Concreting and Curing 5 6-15-17 6-19-17

17 2nd Floor Stairs Rebar Installation 4 6-20-17 6-23-17

Scaffolding and Formworks


18 1 6-24-17 6-24-17
Installation

19 Concreting and Curing 6 6-25-17 6-30-17

2nd Floor Roof Beam Rebar


20 4 7-1-17 7-3-17
Installation

Scaffolding and Formworks


21 1 7-4-17 7-4-17
Installation

22 Concreting and Curing 5 7-5-17 7-9-17

23 Walls 2 7-10-17 7-11-17

Total 92
PHASE III. WOODWORKS

1 Placing of Door frames 1 7-12-17 7-12-17

Forming fascia boards, cabinets/


2 1 7-13-17 7-13-17
closed shelves

3 Forming purlins, ceiling joist 2 7-14-17 7-15-17

4 Making Boards 1 7-16-17 7-16-17

Total 5

PHASE IV. PAINTING WORKS

1 Coating on Paint walls 2 7-17-17 7-18-17

Total 2

PHASE V. PLUMBING WORKS

1 Installing pipes and fittings 3 7-19-17 7-21-17

Total 3
PHASE VI. ELECTRICAL WORKS

Installing wirings, breakers and


1 2 7-22-17 7-23-17
switches

Total 2

PHASE VII. ROOFING AND TINSMITHING

1 Roofing 3 7-24-17 7-26-17

2 Installation of roof gutters 1 7-27-17 7-27-17

Installation of roof and fascia


3 1 7-28-17 7-28-17
board

4 Placing of purlins on roof 2 7-29-17 7-30-17

Total 7

Project Duration : 4 months

Project Start : April 3, 2017

Project Completion : July 30, 2017