Академический Документы
Профессиональный Документы
Культура Документы
NOV, 2018
TABLE OF CONTENTS
1.0 INTRODUCTION......................................................................................................................................................1
4.1 B OREHOLES.................................................................................................................................................................................................. 11
4.2 S TANDARD PENETRATION TESTS (SPT).......................................................................................................11-12
4.3 DISTURBED SAMPLING IN BOREHOLES .......................................................................................................................................... 12
4.4 UNDISTURBED S AMPLING IN BOREHOLES.................................................................................................................................... 12
4.5 LABORATORY TESTING..................................................................................................................................................... ……….12-13
11.30 RECOMMENDATIONS……………………………………………………………………………………26
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
ANNEXURES
1.0 INTRODUCTION
The concessionaire, M/s SHYAM INDUS POWER SOLUTIONS PVT. LTD. have
entrusted the work of sub soil investigation to M/s Space Engineer’s Consortium (P) Ltd
under Ref .No: SHYAM/PGCIL/WO-SS02/J&K/21.M/s SECL carried out the
investigations, field tests, sampling and laboratory testing under the instructions of main
contractor. SECL carried out the field - work during November 2018.
Field identification tests and in situ strength tests as well as laboratory tests on soil
samples were carried out. All the fieldwork and laboratory tests were conducted as per the
standard specifications and instructions of client. This report is based on the data collected
during the fieldwork and laboratory testing on collected soil samples.
P age |1
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Based on nature of the project, soil borings under the structures were planned to: obtain
soil samples, both representative and undisturbed (wherever possible) for classification
tests and other laboratory tests for determining engineering properties; conduct Standard
Penetration test in the boreholes;
2.2.1 All field, laboratory work and presentation of boring records have been done in
accordance with relevant Indian Standard Specifications.
2.2.2 Bore holes of specified depth, to be carried out by shell and auger.
2.2.3 The diameter of the bore holes shall be minimum 150mm for auger boring.
Undisturbed samples shall be of 100mm diameter and 450mm long to be collected at
specified interval and at every significant change in strata. The depth at which ground
water level is struck shall be recorded in each bore hole and record of water levels to be
maintained in all the bare holes till the completion of field work.
2.2.5 Laboratory tests shall be carried out on disturbed and undisturbed samples of soil
as follows:
Atterberg limits to determine index properties.
Mechanical analysis.
Unconfined compression and direct shear test to determine cohesion and angle of
internal friction.
Sp e c if ic g ra v ity .
Consolidation test to determine settlement characteristics.
P age |2
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
2.2.8 Plate Load Test: For the determination of Safe bearing capacity at foundation level at
specified locations as per IS 1888.
2.2.9 Trial pits including excavation of test pit, dressing pit, taking samples and visual
geological observations.
3 Void ratio
4 Coefficient of consolidation
6 CBR test
7 Specific Gravity
8 Atterberg Limits
P age |3
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
3.1 Location
Nowshera is the notified area in the municipal committee of Srinagar, in the Indian
administered state of Jammu and Kashmir. It is located about 9.9 km towards
North from the commercial center of Kashmir and is at an average altitude of
1,592 m (5,223 ft) above sea level, located on at 34.129977°N 74.805308°E. The
area is bounded by Soura towards North, Zadibal towards South, Lal
Bazar towards East and Zanimar towards West. Most of the residential places are
quite old fashioned and date back to the time when people at the first place settled
here similar to one's in Downtown Srinagar.
3.2 Climate
The climate found in the zone of the Middle Mountains and the valleys is of a particular
type. Altitude determines the degree of coolness and elevation the form of precipitation
and summer temperature. Winter is cold and of long duration. When the monsoons are
strong, rain is caused. In higher mountains round the valley of Kashmir, winter is very
cold and there is snow-fall. Summer is very short and milder. The climate in the Valley of
Kashmir has its own peculiarities. Winter is very cold. It lasts from November to March.
During these months strong winds bring snow and rain from the Mediterranean
depressions. Spring begins after 15th of March when rain falls heavily. It causes
landslides. But for sowing crops this rain is extremely useful. Rainfall in July and August
is as high as 70% and with summer temperature, it causes discomfort. The lakes and
waterways make the atmosphere damp and oppressive. The entire valley is covered with
a haze that hides the surrounding mountains from view. The seasons are marked with
sudden change and the year is divided into six seasons of two months each.
P age |4
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
From December 24 to March 8 temperature is often below zero. Strong winds blow from
south and southeast. It snows during winter and there are thick black clouds in the sky.
Annual rainfall of the valley recorded is about 720mm. The highest temperature reliably
recorded is 38.3 °C (100.9 °F) and the lowest is −20.0 °C (−4.0 °F). January is the coldest
month.
3.3.1 The sequence of un-consolidated clay, and conglomerate, with lignite of PLIOCENE to
quarternary age in the Kashmir valley, overlying the pre-cambrian to Mesozoic basement
rocks and overlain, in turn, by the more recent river alluvia is defined lithostrati
graphically as the Karewa group. The soft, un-consolidated sand – clay – conglomerate
rocks of Karewa group characterize the Kashmir valley and occupy nearly half of the
Kashmir valley floor. The karewa deposits represent a sequence of fluvial, lacustrine and
Aeolian sediments that were deposited initially in the framework of a large lake which
once covered the whole of Kashmir valley floor and that the karewa succession is
invariably topped by subaerial brown silts that were generated later when the draining out
/ desiccation of the lake had set in.
3.3.2 The major lithological constituents of karewa group are plastic, gray to bluish – gray
clay, light – gray sandy clay, fine to coarse, green to purple sand, conglomerate, lignite
and lignitic clay in the lower part (i.e. Hirpur formation), fine to coarse greenish sand,
gray and ochre sandy clay, ochre and cream coloured marl and marklekor and gravel in
the middle part (i.e. Nagum formation) and brown silt in the upper part (i.e. Dilpur
formation).
P age |5
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
P age |6
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
P Methawain
L Member
I
O Rambiara
C Member
HIRPUR FORMATION
N
E Dubjan Member
P age |7
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
3.4 Seismicity
The state of Jammu & Kashmir is the western most extension of the Himalayan
mountain range in India. Here it comprises of the Pir Panjal, Zanskar, Karakoram and
Ladakh ranges. The boundary of the Punjab plain and the mountains forms the
Himalayan Frontal Thrust (HFF), which in this area is the Murree Thrust. The Main
Boundary Thrust (MBT) underlies the Pir Panjal Range and is known as the Pir Panjal
Thrust in the region. The Zanskar ranges which are part of the Great Himalayan range
are underlain by the Zanskar Thrust. The Kashmir Valley lies between the Pir Panjal and
the Zanskar thrusts, making it very vulnerable to earthquakes. Other northern parts of
Jammu & Kashmir are heavily faulted. Along the Zanskar and the Ladakh ranges runs a
NW-SE trending strike-slip fault, the longest in the Jammu & Kashmir area. Apart from
the routine small tremors moderate to large earthquakes have hit nearly all parts of the
state. However, it must be stated that proximity to faults does not necessarily translate
into a higher hazard as compared to areas located further away, as damage from
earthquakes depends on numerous factors such as subsurface geology as well as
adherence to the building codes.
The map of Jammu and Kashmir earthquake epicentres (Figure 3.4) shows earthquakes
from January 2006 to August 2013 with magnitudes of 2.0 and more on the Richter scale
(Table 1). Events of magnitude 4.0 or more are capable of causing damage to buildings.
Jammu and Kashmir lies within a broad NW-SE trending belt of epicentres. The largest
events recorded in this zone were of Richter magnitude 7.6, the epicentre of which was
in North Kashmir. Small earthquakes occur at a continuous rate in this region as a result
of which the entire region is marked as very high damage risk zone V (MSK IX or more)
and high damage risk zone IV (MSK-VIII).
P age |8
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Figure 3.4 Map showing earthquakes occurred in Jammu and Kashmir region
from January2006 to August 2013 (Figure modified after Patil, 2012).
The area under study and its surroundings are seismically active falls in Seismic Zone V
and the tectonic elements of the area are considered capable of generating an earthquake
of magnitude of 7.5. Seismic map of srinagar district is given in figure 3.5
P age |9
p
!
p
!
p
!
74°30'E 75°0'E 75°30'E
p
! 4.6(1968)
p
!
SRINAGAR DISTRICT
4.4(1979)
p
! (JAMMU & KASHMIR)
p
!
NA Earthquake Hazard Zoning Map
4.2(1992)
p
! p
!
(showing faults, thrusts and
earthquakes of magnitude ≥4)
0 5 10 15 20 25 Km
p
! KUPWARA
Total No. of Houses : 2,62,239
4.6(1979) Population : 12,36,829INDUS SUTURE ZONE
p
!
34°30'N
p
! 34°30'N
4.3(1990)
p
!
BANDIPORE 4.6(2010)
p
!
p
! KARGIL
4.8(1981)
p
!
4.6(1985)
p
!
GANDERBAL
BARAMULA
7(1885)
0
!"
4.3(2008) SRINAGAR
p
!
7.5(1552)
34°0'N
0
! 4.2(2008)
7(1803)6.5(1885)
7.3(1784)
0̀
0
!
¶ 7.7(1778)
7.5(1735)
p
! 5.3(1963) 7.5(1662) 34°0'N
(
!
4.6(1985)
BADGAM p
!
PULWAMA
4(2004)
p
!
4.6(2010)
p
!
4.5(1983)
PUNCH p
!
ANANTNAG
4.4(2001)
(
!
SHUPIYAN p
!
4.7(1967)
p
!
p
! 4.0 - 4.9
5(1967)
(
! KISHTWAR
5.5(1967) (
! 5.0 - 5.9
(
!
¶
` 6.0 - 6.9
p
!
4.9(1967)
0
! 4.3(2003)
7.0 - 7.9
4.4(2001) p
!
33°30'N
KULGAM p
!
" District Headquarter
7.3(1884)7(1863)
Fault
( 0
!( Neotectonic Thrust
33°30'N
LT
KISHTWAR FAU
4.9(2005)
p
! ( Thrust
$$$ """
Suture
4.9(1981)
Strike slip
p Fault
!
(
!
5(1993)
RAJOURI 4.5(1976)
p
! State Boundary
4.1(2000)
p
!
4(2006) 4.7(1989)
MBT p
! p
! p
!
District Boundary 5.3(1990)
REASI RAMBAN 4.8(1967) 4.5(1981) (
!
p
! p
!
Subdivision Boundary
4(2002) (
!
p
!
4.8(2009) p
!
p
! 5.1(2001)
© NDMA, Government of India, Copyright 2016. p
!
DODA (
! 4.8(1967)
The responsibility for the correctness of internal details rests with the publisher. p
!
4.5(1981)
The territorial waters of India extend into the sea to a distance of twelve nautical miles measured from the appropriate base line.
The external boundaries and coastlines of India agree with the Record/Master copy certified by Survey of India.
Zone V! : Very High Damage Risk Zone (MSK IX or more)
4.2(2006)
p p
!
JWALA p4.1(1978)
! 4.8(1973)
p
!
MUspellings
The of names in this map, have been taken from various sources.
KHI TH use of the map, permission is required from NDMA. For other purposes, acknowledgement is to be given. p
! p
For commercialRU ST UDHAMPUR 4.4(1973)
! p
!
(
!
74°30'E 75°0'E 75°30'E
NDMA - BMTPC Earthquake Hazard Zoning Map; Map is Based on digitised data of SOI; Sub-Division Boundary as per Census of India 2011; Seismic Zones! p of India
p
! Map p
!
IS: 1893 (Part I) - 2002,BIS; Earthquake Epicentre from IMD; Seismotectonic Atlas of India and its Environs, GSI; Houses/Population as per Census 2011. "(First
p Edition)"
! (
! p
!
Disclaimer: The maps are solely for thematic presentation.
p !
! p
JK – 54
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
The investigation was planned to obtain the subsurface stratification in the proposed
project site and collect soil samples for laboratory testing to determine the engineering
properties such as shear strength, along with basic engineering classification of the
subsurface stratum to arrive at the foundation design parameters.
4.1 Boreholes
For Geotechnical investigation work, boring rig was installed at the specified borehole
location. Stability of rig was ensured by making level ground. The boreholes were
progressed using a mechanical shell and auger, where caving of the borehole occurred,
150 mm diameter casing was used to keep the borehole stable as per IS specifications.
For location of these boreholes please refer site plan attached with this report.
When the number of blows exceeded 50 to penetrate the first or second 15 cms length of
the sampler, the SPT N is regarded as more than 100 as described in IS 2131 - 1981. The
test is terminated in such case and a record of penetration of the sampler under 50 blows
or more is made. SPT refusal is recorded when there is no penetration of the sampler at
any stage and also when a rebound of the sounding system is recorded.
SPT ‘N’ values are correlated with relative density of non-cohesive stratum and with
consistency of cohesive stratum. SPT values of respective boreholes are given in
Annexure I and II.
P a g e | 11
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Hard Above 32
Disturbed soil collected in the SPT sampler was preserved in polythene covers and
transported to the laboratory. One more polythene cover was provided to prevent the loss
of moisture during the transit period.
Undisturbed samples were collected using 100mm diameter and 450mm long MS tubes
provided with sampler head with ball check arrangement. Undisturbed samples were
not proved to be truly undisturbed in case of Non-plastic sandy soils or hard clay soil.
The laboratory testing was done on collected material as per relevant IS codes. The
laboratory-testing program consisted of testing the soil index and strength properties, as
well as the consolidation characteristics. The index tests were performed to determine the
soil moisture content, unit weight, specific gravity, gradation characteristics (gravel, sand
and fines content) and consistency limit. The strength tests were performed to determine
the shear parameters (cohesion, friction angle) of soil; the consolidation tests were
performed to find out the consolidation properties. The index tests were performed on
disturbed split-spoon soil samples or undisturbed samples, except the natural moisture
P a g e | 12
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
content and dry density tests, which were performed only on the undisturbed soil
samples. The strength tests consisted of the direct shear test. The consolidation
characteristics tests were preformed on a one-dimensional consolidometer. The strength
tests were performed on undisturbed soil samples.
The sub-soil strata for different structures planned at different locations given below
comprise of two types of layers (based on laboratory test result data). Description of each
layer along with various engineering parameters is as under based on field and laboratory
classification.
Stratum 2 Silty Sand(SM) /Silt of low plasticity (ML) / Silt with fine Sand(SM-ML).
P a g e | 13
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Classification as Observed
B.H. No. Thickness (m)
per IS 1498 SPT,‘N’ value
4 10.0-15.0 SM/ML/SM-ML R
DESIGN PARAMETERS
DESIGN ‘N’
DEPTH (m) SOIL TYPE ϒsubmerged
VALUE Cu, T/m2 φ°
(T/m3)
BH 1
0.00-10.0 CI/ML/MI 24 0.91 2.4 15
BH 2
0.00-10.0 MI/ML 19 0.89 1.8 14
BH 3
0.00-8.5 ML-MI/MI 17 0.90 1.0 15
BH 4
0.00-10.0 MI/CI/ML 21 0.92 2.0 11
BH5
CI/ML-MI/MI/CL-
0.00-10.0 16 0.93 1.7 17
ML/ML
Water table was encountered between 9.50 m to 10.5 m depth below the existing ground
level / bed level. The ground water table is expected to fluctuate depending upon the
P a g e | 14
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
climatic factor, drainage conditions and other factors. Water table is considered at bed
level for all design purposes.
Soil resistivity testing is the process of determining the conductivity of the soil. The
resulting soil resistivity is expressed in ohm-meter. Soil resistivity is a function of soil
moisture and the concentrations of ionic soluble salts and is considered to be most
comprehensive indicator of a soil’s corrosivity.
Soil resistivity testing is the single most critical factor in electrical grounding design. This
is true when discussing simple electrical design, to dedicated low-resistance grounding
systems. Electrical resistivity is the measurement of the specific resistance of a given
material.
Field soil resistivity measurements are most often conducted using the Wenner four-pin
method and a soil resistance meter. The Wenner method requires the use of four metal
probes or electrodes, driven into the ground along a straight line, equidistant from each
other. Soil resistivity is a simple function derived from the voltage drop between the
center pair of pins, with current flowing between the two outside pins. The specifications
for the equipment and other accessories required for performing electrical resistivity test,
the test procedure and reporting of filed observations confirm to IS: 3043.
This method depends on differences in the electrical resistance of different soil (and rock)
types. The flow of current through a soil is mainly due to electrolytic action and therefore
depends on the concentration of dissolved salts in the pores. The mineral particles of soil
are poor conductors of current. The resistivity of soil, therefore, decreases as both water
content and concentration of salts increase.
Based upon resistivity data observed during testing following table gives the average
value of resistivity in Ohm-meter:
P a g e | 15
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Resistivity in Ohm-meter of SW
Resistivity in Ohm-meter of NE
Resistivity in Ohm-meter of SE
Resistivity in Ohm-meter of W
Resistivity in Ohm-meter of N
Resistivity in Ohm-meter of E
Resistivity in Ohm-meter of S
direction
direction
direction
direction
direction
direction
direction
direction
S. No
Field observation of the test are Annexured in Annexure IV and graphical representation is
shown in Figure 6.1
Figure 6.1
P a g e | 16
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
The California Bearing Ratio test, or CBR test, is a laboratory (or in-situ) testing method
to estimate the bearing value and the mechanical strength of highway sub-bases and
subgrades.
The primary purpose of the California Bearing Ratio test is to determine the bearing
capacity and the mechanical strength of road sub-bases and subgrades. In this test in the
laboratory, the sample is prepared at Proctor's maximum dry density or any other density
at which the test is required or undisturbed samples.
A plunger of a standard area is then pushed into the soil at a fixed rate of penetration, and
the force required to maintain that rate is measured. The CBR value is then defined as the
ratio of the measured force to that required for similar penetration into a standard sample
of crushed California limestone rock:
CBR=(F/Fs)x100%
where F is the measured force and Fs is the force required for similar penetration into a
standard sample. Higher values of CBR indicate harder surface of material. Typical
values of CBR rating for different materials are
2.5 1370 70
5 2055 105
P a g e | 17
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
CBR tests were conducted on undisturbed test sample in unsoaked condition and results
of these tests are given below:
Condition of sample at test Unsoaked/Undisturbed
Water content(%) 18
Density (g/cc) 1.83
Depth of sample(m) 0.5
P a g e | 18
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
8.1 Plate load test is a field test, which is performed to determine the ultimate bearing
capacity of soil and the probable settlement under a given load. This test is very popular
for selection and design of shallow foundation
8.2.1 For conducting the test, provisions and requirements laid in IS: 1888-1982 were adhered
to.
8.2.2 A 3.0m x 3.0m test pit was dug upto the proposed test level. The bottom of the pit was
cleaned of all loose soil and properly levelled. Proper care was taken to restrain sliding of
soil from sides of the test pit. A 450mm x 450mm x 25mm steel plate was used for the
test. The plate was placed over a fine 5mm thick sand layer filled in a depression equal in
size to the test plate and properly levelled. The plate was centred with the sand layer
below and underside of reaction girder above with the help of a plumb bob and
horizontally levelled by spirit level to ensure proper load transfer. Reaction loading was
provided by sand bags placed over steel plates resting on cross girders/channel sections
over the main reaction girder.
8.2.3 A 100-ton hydraulic jack with separate ram and pump assembly connected by a pressure
hose was placed centrally over the test plate. A loading column was inserted in between
the jack and the reaction beam. The pumping unit was placed well outside the test pit.
8.2.4 Four dial gauges with 50mm travel and 0.01mm accuracy were used for recording
settlements. The dial gauges were placed at four corners of the plate and connected to a
firmly anchored datum beam by means of magnetic arms.
8.3.1 A seating pressure of 0.1 kg/cm2 was applied before application of test pressure
increments and maintained for ten minutes after which the pressure was released and dial
gauges set to zero position.
P a g e | 19
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
8.3.2 Pressure increments were applied by means of the hydraulic jack in increments of 9.88,
19.76, 29.64, 39.52, 49.4, 59.28 and 69.16 t/m2 . For each pressure increment, settlements
were recorded at time intervals of 1, 2.25, 4, 6.25, 9, 16 and 25 minutes and thereafter at
hourly interval. The settlement records for each pressure increment are given in TABLE-I
(PLT-1) and TABLE-II (PLT-2) in Annexure V.
8.4.1 Pressure increments were applied upto a maximum intensity of 69.16 t/m2 and total
cumulative settlement recorded for the test at location of PLT-2 was 10.02mm. For each
pressure increment, major portion of the settlement occurred immediately upon
application of a particular load after which the rate of settlement decreased with increased
time interval.
8.4.2 The test data for PLT location 2 is presented in the form of settlement vs pressure
intensity plot drawn to arithmetical scale and shown in Figures A as annexured in
Annexure V
8.4.3 Based on the PLATE LOAD results, safe bearing capacity of 16 t/m² at PLT location 02
may be adopted for foundation design.
8.4.4 The plate load test 01 was carried out at specified location and it was found that this
location comprises of filled material. It was observed that there is a possibility of the
availability of some sort of bore well with approximate dia of 1.5m with unknown depth
as such the settlement was beyond reasonable limits. In presence of this it is
recommended to excavate the filled material upto the influence zone of footing and fill
the cavity with rubber soling in layers so that the density of soling should not be less than
2t/m3 to avoid the chances of settlement. For settlement record of this location i.e PLT 01,
table 01 may kindly be referred to.
P a g e | 20
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
i) Results of plate load tests reflect the strength and settlement characteristics of the
soil within the pressure bulbs which depend on the size of the loaded area which
in case of actual footing is much larger than the plate test. In the instant case, the
pressure bulb of intensity 0.2q would extend upto a depth equal to 1.5xBp (plate
width) =0.675m. As against this, pressure bulb of same pressure(0.2q) intensity
in a footing of width say 3.0m extends upto a depth of 1.5x3.0 = 4.5m as
illustrated below.
Plate
Footing q/ unit area
q/ unit area
Bf
Influence Bp 0.2q Influence
zone is zone is
1.5Bp 1.5Bf
0.2q
The plate load test does not therefore truly represent the actual conditions if the soil is
non-homogeneous and unisotropic to a large depth. The test is bound to give misleading
results particularly if a soft soil layer/stratum exists below 1.5 Bp.
ii) In case of plate load tests, the failure load except in case of general shear failure is
seldom well defined. An error of personal interpretation may be involved in other
types of failure.
iii) In case of saturated clays the ultimate bearing capacity is independent of the size
of the plate but for cohesionless soils it increases with the size of the plate. In
such soils consequently the safe bearing capacity in case of actual foundation may
be more than indicated by a plate load test.
P a g e | 21
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Trial pits are carried out in order to recover large bulk samples of sub-soil or and detailed
visual examination of the sub-strata. Test pit excavations can reveal a lot of visual
information about the shallow subsurface that soil boring/coring cannot, like
Five trail pits of 2mx2mx4m dimensions were dugged out at the site and visual
examination of these pits were carried out and the same are annexured in Annexure II
10.1. Computations have been made for an individual column footing of different sizes
founded at a depth of 2m and 3.0m below the existing ground surface level.
10.2 Influence zone depth considered is taken as 2.0xB (B = footing width) below the base of
the footing.
10.3 Computations made are as per IS: 6403-(1981) “Code of Practice for determination of
Bearing Capacity of Shallow Foundation”.
10.4 Sample calculations for safe allowable bearing pressure are enclosed at Annexure III. The
limiting settlement adopted is 40mm.
P a g e | 22
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH No 1 3mx3m 5mx5m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 1 6mx6m 8mx8m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 1 9mx9m
2m 13.29 5.98
3m 15.30 8.41
BH No 2 3mx3m 5mx5m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
P a g e | 23
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH No 2 6mx6m 8mx8m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 2 9mx9m
2m 11.48 4.65
3m 12.86 6.42
BH No 3 3mx3m 5mx5m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 3 6mx6m 8mx8m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
P a g e | 24
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH No 3 9mx9m
2m 9.95 4.18
3m 11.64 5.82
BH No 4 3mx3m 5mx5m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 4 6mx6m 8mx8m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
BH No 4 9mx9m
2m 11.18 4.44
3m 12.41 6.10
BH No 5 3mx3m 5mx5m
Depth Shear criteria (t/m2) Settlement Criteria (t/m2) Shear criteria (t/m2) Settlement Criteria (t/m2)
P a g e | 25
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
11.0 Recommendations
11.1 The sub strata at the location investigated is “fine grained” as per IS system of
classification and mainly comprises of clayey silt/silty clay of low to medium plasticity
upto 10.5m depth and silty sand from 10.5m to 15.0m depth .
11.2 Ground water table has been observed at average of 10.0m below existing ground surface
level
11.3 Allowable safe bearing pressure which is safe against shear failure and also against
settlement in excess of limiting settlement works out to 6.5 t/m² for isolated footing of
dimensions 3mx3m at a depth of 3.0m below existing ground surface level.
P a g e | 26
BH1 N-VALUE
1.0
33
2.0
3.0 24
4.0
18
5.0
6.0
20
7.0
27
8.0
9.0 41
10.0
60 LEGEND
11.0 CODE DESCRIPTION
SILTY CLAY
CLAYEY SILT
76 SILTY SAND
14.0 GRAVEL/COBBLE
CLAYEY SILT
1.0
8
2.0
3.0 12
4.0
13
5.0
6.0 17
7.0
R
8.0
9.0 47
10.0
18 LEGEND
11.0
CODE DESCRIPTION
SILTY CLAY
12.0 49 CLAYEY SILT
CLAYEY SILT
13.0
SANDY SILT
87 SILTY SAND
14.0
GRAVEL/COBBLE
CLAYEY SILT
15.0
SILTY CLAY
1.0
9
2.0
3.0 26
4.0
10
5.0
6.0
11
7.0
16
8.0
9.0 25
10.0
24 LEGEND
11.0 CODE DESCRIPTION
SILTY CLAY
12.0 R CLAYEY SILT
CLAYEY SILT
13.0 SANDY SILT
62 SILTY SAND
14.0 GRAVEL/COBBLE
CLAYEY SILT
15.0 SILTY CLAY
1.0
38
2.0
3.0 10
4.0
12
5.0
6.0 17
7.0
22
8.0
9.0 31
10.0
LEGEND
88
11.0 CODE DESCRIPTION
SILTY CLAY
SILTY SAND
R
14.0 GRAVEL/COBBLE
CLAYEY SILT
1.0
6
2.0
3.0 13
4.0
24
5.0
LEGEND
6.0 13 CODE DESCRIPTION
SILTY CLAY
20 CLAYEY SILT
SILTY SAND
9.0 29 GRAVEL/COBBLE
CLAYEY SILT
10.5 R
Shear Strength
SPT Test Results Grain Size Analysis
Depth in Meters below reference
Characteristics
Compression Index Cc
Level of Water Table
Moisture Content %
Nature of Sampling
Elevation in meters
Date of Sampling
Plastric Index %
bulk Density
Void ratio e0
qu(Kg/cm2)
N. Value (Corrected)
Dry Density
Penetration ( CM)
Depth in Meters
Cohension C
No. of Blows
Gravel%
Fines%
Sand%
No.
0 10 20 30of40Blows
50 60 70 80
0.0
Greyish clayey SPT observed
0.5 12/11/18 UDS 0.5-0.80 silt 8.2 10.5 81.3
SPT Corrected
Brownish Silty clay of 1.5
33 30 35 low Plasticity(CL)
1.5 12/11/18 SPT 1.5-1.95 0 5.6 94.4 34 23 11
plasticity
7.5 12/11/18 SPT 7.5-7.95 27 30 22 0 4.6 95.4 39 26 13 2.69
(MI)
9.0
9.0 12/11/18 SPT 9.0-9.45 41 30 28 0 3.8 96.2 40 27 13
10.0 12/11/18 UDS 10.0-10.30 1.86 1.57 18 0.61 0.13 16 0.89 0.12 10.5
Shear Strength
SPT Test Results Grain Size Analysis
Depth in Meters below reference
Characteristics
Compression Index Cc
Level of Water Table
Moisture Content %
Nature of Sampling
Elevation in meters
Date of Sampling
Plastric Index %
Void ratio e0
bulk Density
N. Value (Corrected)
qu(Kg/cm2)
Penetration ( CM)
Depth in Meters
Cohension C
No. of Blows
Gravel%
Fines%
Sand%
Dry Density
No. of Blows
0 20 40 60 80 100
(MI) 6.0
6.0 16/11/2018 SPT 6.0-6.45 17 30 17 0 4.9 95.1 38 25 13
7.0 16/11/2018 UDS 7.0-7.30 1.93 1.608 20 1.18 0.16 15 0.77 0.12
7.5
10.2 m
Gravel/
7.5 16/11/2018 SPT 7.5-7.95 R cobble
9.0
9.0 16/11/2018 SPT 9.0-9.45 47 30 32 Brownish Clayey
0 11.4 88.6 34 25 9 2.65
silt of low
Plasticity(ML)
10.0 16/11/2018 UDS 10.0-10.30 1.91 1.632 17 0.04 17 10.5
Shear Strength
SPT Test Results Grain Size Analysis
Depth in Meters below reference
Characteristics
Compression Index Cc
Level of Water Table
Moisture Content %
Nature of Sampling
Elevation in meters
Date of Sampling
Plastric Index %
bulk Density
Void ratio e0
qu(Kg/cm2)
N. Value (Corrected)
Penetration ( CM)
Depth in Meters
Cohension C
No. of Blows
Gravel%
Fines%
Sand%
Dry Density
No.30
0 10 20 of Blows
40 50 60 70
Greyish 0.0
SPT observed
0.5 14/11/2018 UDS 0.5-0.80 clayey silt 2.3 5.7 92.0
SPT Corrected
1.5
1.5 14/11/2018 SPT 1.5-1.95 9 30 14 0 4.2 95.8 35 25 10
7.0 14/11/2018 UDS 7.0-7.30 1.83 1.551 18 0.84 0.08 17 0.77 0.13
7.5
9.5 m
Shear Strength
SPT Test Results Grain Size Analysis
Depth in Meters below reference
Characteristics
Compression Index Cc
Level of Water Table
Moisture Content %
Nature of Sampling
Elevation in meters
Date of Sampling
Plastric Index %
Void ratio e0
bulk Density
N. Value (Corrected)
qu(Kg/cm2)
Penetration ( CM)
Depth in Meters
Cohension C
No. of Blows
Gravel%
Fines%
Sand%
Dry Density
No. of Blows
0 15 30 45 60 75 90 105
Greyish clayey
0.0
silt
SPT observed
0.5 13/11/2018 UDS 0.5-0.80 0 6.3 93.7
Brownish clayey silt of SPT Corrected
intermediate 1.5
1.5 13/11/2018 SPT 1.5-1.95 38 30 38 Plasticity(MI) 0 5.3 94.7 38 26 12
Brownish silty
3.0 13/11/2018 SPT 3.0-3.45 10 30 14 clay of 0 4.1 95.9 39 25 14 2.64
3.0
intermediate
Plasticity(CI)
4.0 13/11/2018 UDS 4.0-4.3 1.85 1.529 21 0.95 0.23 9 0.89 0.18
4.5
4.5 13/11/2018 SPT 4.5-4.95 12 30 18 0 3.7 96.3 37 25 12 2.66
Brownish
clayey silt of 6.0
6.0 13/11/2018 SPT 6.0-6.45 17 30 17 0 5.8 94.2 38 25 13 2.64
intermediate
plasticity
7.0 13/11/2018 UDS 7.0-7.30 1.84 1.559 18 0.76 0.17 12 0.85 0.14 7.5
(MI)
9.5 m
Shear Strength
SPT Test Results Grain Size Analysis
Depth in Meters below reference
Characteristics
Compression Index Cc
Level of Water Table
Moisture Content %
Nature of Sampling
Elevation in meters
Date of Sampling
Plastric Index %
Void ratio e0
bulk Density
N. Value (Corrected)
qu(Kg/cm2)
Penetration ( CM)
Depth in Meters
Cohension C
No. of Blows
Gravel%
Fines%
Sand%
Dry Density
No. of Blows
0 10 20 30 40
0.0
0.5 25/10/18 UDS 0.5-0.80 Greyish Silty 0 8.5 91.5 SPT observed
clay of
SPT Corrected
1.5 25/10/18 SPT 1.5-1.95 6 30 9 intermediate 14 6.7 79.3 36 23 13 1.5
Plasticity(CI)
intermediate 6.0
7.0 26/10/18 UDS 7.0-7.30 plasticity(MI) 1.97 1.728 14 1.23 0.11 18 0.87 0.10
Brownish silty clay of
low to intermediate
7.5 26/10/18 SPT 7.5-7.95 20 30 18 plasticity(CL-CI) 0 5.5 94.5 35 24 11 2.65 7.5
Annexure-II
RECORD OF BORING
Project : Soil Investigation at Substation at Khanyar in Kashmir
Bored for : Shyam Indus Power Solution Pvt Ltd
Site : Khanyar
Depth of Boring : 4.0m Trial Pit No. : 1
Laboratory
Ground
Soil
Water Sample
Depth (m) Description Of Strata Classificatio Legend Remarks
Level Type
n
(m)
IS System
1 2 3 4 5 6 7
Disturbed
++++NIL
2.0 with small proportion of
pebbles MI
3.0
Brownish Clayey silt MI
4.0
P a g e | 37
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure-II
RECORD OF BORING
Project : Soil Investigation at Substation at Khanyar in Kashmir
Bored for : Shyam Indus Power Solution Pvt Ltd
Site : Khanyar
Depth of Boring : 4.0m Trial pit No. : 2
Laboratory
Ground
Soil
Water Sample
Depth (m) Description Of Strata Classificatio Legend Remarks
Level Type
n
(m)
IS System
1 2 3 4 5 6 7
Greyish Clayey silt
1.5 with broken pieces ML
of earthen pots
Disturbed
2.0
Brownish clayey silt
NIL
with small
3.0 proportion tending
ML
to negligible of
soling debris and
4.0 pebbles
P a g e | 38
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure-II
RECORD OF BORING
Project : Soil Investigation at Substation at Khanyar in Kashmir
Bored for : Shyam Indus Power Solution Pvt Ltd
Site : Khanyar
Depth of Boring : 4.0m Trial pit No. : 3
Laboratory
Ground
Soil
Water Sample
Depth (m) Description Of Strata Classificatio Legend Remarks
Level Type
n
(m)
IS System
1 2 3 4 5 6 7
Greyish clayey silt CI
with clay pots ,
1.5 soling debris& rock
piece
Brownish silt with
Disturbed
2.0
colour patches
NIL
CI
3.0
Brownish clayey
silt with pebbles
ML-MI
and white patches
4.0
P a g e | 39
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure-II
RECORD OF BORING
Project : Soil Investigation at Substation at Khanyar in Kashmir
Bored for : Shyam Indus Power Solution Pvt Ltd
Site : Khanyar
Depth of Boring : 4.0m Trial pit No. : 4
Laboratory
Ground
Soil
Water Sample
Depth (m) Description Of Strata Classificatio Legend Remarks
Level Type
n
(m)
IS System
1 2 3 4 5 6 7
Greyish clayey silt
with earthen pot
1.5 pieces and stone
MI
soling pieces
Disturbed
2.0
NIL
Brownish clayey
silt with gravel ,
3.0 pebbles & small CI
proportion of
soling pieces
4.0
P a g e | 40
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure-II
RECORD OF BORING
Project : Soil Investigation at Substation at Khanyar in Kashmir
Bored for : Shyam Indus Power Solution Pvt Ltd
Site : Khanyar
Depth of Boring : 4.0m Trial pit No. : 5
Laboratory
Ground
Soil
Water Sample
Depth (m) Description Of Strata Classificatio Legend Remarks
Level Type
n
(m)
IS System
1 2 3 4 5 6 7
Greyish clayey silt MI
1.5 with earthen pot
pieces
Disturbed
2.0
NIL
Brownish clayey
3.0 silt with variable
proportion of
pebbles
4.0
P a g e | 41
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH1
Depth of dn = 3m, dn size = 3m x 3m
I.z = 6m
Shear Criteria
Cav = 0.24kg/cm2`
av = 15 0
' = tan-1 (0.67 tan) = 10.170
N'c = 8.43, N'q = 2.51 , N' = 1.26
Sc = 1.3, Sq = 1.2 S = 0.8
N = tan2 (/4 + '/2) = 1.42
dc = 1 + 0.2 x D/B N = 1.00
dq = d = 1.0
w' = 1.0
q'd = 2/3 x 2.4x8.43x1.3x1.0x1+5.88x(2.51-1)x1.2x1.0x1
+ ½ x 3 x 1.96x 0.8 x 1.0x1.0x1.0
= 31.24t/m²
F.O.S = 2.5
qd net = 12.49t/m2
qd cross = 18.38 t/m2
Settlement Criteria
Cc = 0.14 H = 6m e 0 = 0.86
S = Cc x H x 1000 (Po + P)
1 + eo Po
Po = (3 + 3) x 0.96 = 5.76
P = 0.336 x 18.38= 6.17
S = 0.14 x 6000 log (5.76+6.17) = 142.90 mm
1.86 5.76
Rf = 0.8, Df = 0.74
Scorrected = 142.90x 0.8 x 0.74 = 84.59mm
Safe b/c = 40 x 18.38 = 8.69 t/m2
84.59
Page 42
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure IV
E1 to North East 2.71 0.73 0.16 0.08 34.0376 22.922 10.048 7.536
E1 to North West 2.32 0.81 0.27 0.12 29.1392 25.434 16.956 11.304
E1 to South East 1.82 0.57 0.19 0.10 22.8592 17.898 11.932 9.42
E1 to South West 1.83 0.54 0.18 0.07 22.9848 16.956 11.304 6.594
P a g e | 43
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Annexure V
Table-I
P a g e | 44
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
P a g e | 45
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Table-2
Plate Load Test : 02 Site : Khanyar Sub Station
Test Depth : 3.0m
P a g e | 46
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
P a g e | 47
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
P a g e | 48
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
0 47.25 0
P a g e | 49
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Figure A
P a g e | 50
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
Project : Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of
Jammu & Kashmir.
BH1
109
107
105
103
101
PERC ENT FINER BY WEIGHT
99
97 0.5m
95 1.5m
93
3.0m
91
89 4.5m
87 6m
85 7.5m
83
9m
81
79
77
75
0.01 0.1 1 10
PARTICLE DIA, mm
P a g e | 51
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
120.0
100.0
PERC ENT FINER BY WEIGHT
80.0
60.0 10.5m
13.5m
40.0 15m
20.0
0.0
0.050 0.500 5.000
PARTICLE DIA, mm
BH
Soil Description Depth(m) Gravel(%) Sand(%) Fines(%)
No.
10.5 2.2
Silty Sand SM 83.9 13.9
13.5 0
BH1 Clayey Silt ML 13.4 86.6
15 0
Silt with fine Sand SM-ML 41.7 58.3
P a g e | 52
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH2
105
100
95
PERC ENT FINER BY WEIGHT
90
0.5m
85
1.5m
80 3.0m
4.5m
75
6.0m
70 9.0m
65
60
0.01 0.1 1 10
PARTICLE DIA, mm
P a g e | 53
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
120.0
100.0
PERC ENT FINER BY WEIGHT
80.0
10.5m
60.0
12m
13.5m
40.0
15m
20.0
0.0
0.050 0.500 5.000
PARTICLE DIA, mm
Silty Sand SM 12 0 63 37
BH 2
Silt with fine Sand 35.3 64.7
13.5 0
SM-ML
P a g e | 54
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH3
110
105
PERC ENT FINER BY WEIGHT
100
0.5m
1.5m
95
3.0m
4.5m
90
6.0m
7.5m
85
80
0.01 0.1 1 10
PARTICLE DIA, mm
P a g e | 55
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
120.0
100.0
PERC ENT FINER BY WEIGHT
80.0
9m
60.0
10.5m
12m
40.0
13.5m
20.0
0.0
0.050 0.500 5.000
PARTICLE DIA, mm
BH 3
Silty Sand SM 12 0 79.3 20.7
P a g e | 56
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH4
110
105
PERC ENT FINER BY WEIGHT
0.5m
100
1.5m
3.0m
95 4.5m
6.0m
7.5m
90 9m
85
0.01 0.1 1 10
PARTICLE DIA, mm
P a g e | 57
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
120.0
100.0
PERC ENT FINER BY WEIGHT
80.0
10.5m
60.0
12m
13.5m
40.0
15
20.0
0.0
0.050 0.500 5.000
PARTICLE DIA, mm
Silty Sand SM 12 0 72 28
BH 4
Silty with fine sand
13.5 0 23.4 76.6
SM-ML
P a g e | 58
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
BH5
110
105
100
PERC ENT FINER BY WEIGHT
0.5m
95
1.5m
3.0m
90
4.5m
6.0m
85
7.5m
80
75
0.01 0.1 1 10
PARTICLE DIA, mm
P a g e | 59
SPACE ENGINEERS CONSORTIUM (P) LIMITED
Geotechnical Investigation for proposed 132/33kV GIS Substation at Khanyar in the state of Jammu & Kashmir.
110.0
105.0
100.0
PERC ENT FINER BY WEIGHT
95.0
9m
90.0
10.5m
85.0
80.0
75.0
0.050 0.500 5.000
PARTICLE DIA, mm
P a g e | 60