VIDHYADEEP INSTITUTE OF ENGINEERING AND TECHNOLOGY, ANITA, KIM

MID SEMESTER EXAMINATION APRIL,2018


Subject Code:2180611 Subject Name: Construction Management SEMESTER: VIII
Enrollment Number: _______________________
Instructions:-
1 Attempt all questions. Date: 06/04/2018
2 Make suitable assumptions wherever necessary. Time: 9:30 am to 10:45 am
3 Figures to the right indicate full marks. Total Marks: 30

A Attempt any 3 Question


Q:1 What is construction management? Discuss in detail various phases and function of 6
Construction Project.
Q:2 Discuss Ethical Conduct for Engineers. 6
Q:3 Explain with Example “Effect of Taxation & Inflation on Construction Project” 6
Q:4 Define Following: 1.) Critical Path 2.) Activity 3.) Organization 4.) Total Float 5.) WBS 6
6.) Job Layout
Q:5 Write
) down Rules for Preparation of Network. 6

----------------------------------------------------------------------------------------------------------------------------------------

VIDHYADEEP INSTITUTE OF ENGINEERING AND TECHNOLOGY, ANITA, KIM


MID SEMESTER EXAMINATION APRIL,2018
Subject Code: 2180611 Subject Name: Construction Management SEMESTER: VIII
Enrollment Number: _______________________
Instructions:-
1 Attempt all Questions. Date: 06/04/2018
2 Make suitable assumptions wherever necessary. Time: 9:30 am to 10:45 am
3 Figures to the right indicate full marks. Total Marks: 30

A Attempt any 3 question


Q:1 What is construction management? Discuss in detail various phases and function of 6
Construction Project.
Q:2 Discuss Ethical Conduct for Engineers. 6
Q:3 Explain with Example “Effect of Taxation & Inflation on Construction Project” 6
Q:4 Define Following: 1.) Critical Path 2.) Activity 3.) Organization 4.) Total Float 5.) WBS 6
6.) Job Layout
Q:5 Write
) down Rules for Preparation of Network. 6
B Attempt all questions. 12 marks
1 The data for the Project is given bellow. Prepare a network diagram and find out:
1. Total float 2. Free float 3. Independent Float
Activity A B C D E F G H I J K L
Duration 8 9 10 9 10 6 6 11 7 8 8 11
Presiding - - - A A B B C,F D,H D,H G, I E, J , K
Following D , E F , G H I, J L H K I , J K L L -

2 Activity A B C D E F G H
Duration 6 10 5 8 6 5 8 10
Logic :
1. A is the first and H is the last activity.
2. Activity B and C can be started simultaniously.
3. Activity D can only be started after the completion of activity B.
4. Activity G can not started untill Activity B is completed.
5. Activity E and F can be started after the completion of activites C and D.
6. Activity H can be strated after the completion of activity G and F.

Find Out : 1. Total Float 2. Free Float 3. Independent Float 4. Critical Path.

B Attempt all question 12 marks


1 The data for the Project is given bellow. Prepare a network diagram and find out:
1. Total float 2. Free float 3. Independent Float
Activity A B C D E F G H I J K L
Duration 8 9 10 9 10 6 6 11 7 8 8 11
Presiding - - - A A B B C,F D,H D,H G, I E, J , K
Following D , E F , G H I, J L H K I , J K L L -

2 Activity A B C D E F G H
Duration 6 10 5 8 6 5 8 10
Logic :
1. A is the first and H is the last activity.
2. Activity B and C can be started simultaniously.
3. Activity D can only be started after the completion of activity B.
4. Activity G can not started untill Activity B is completed.
5. Activity E and F can be started after the completion of activites C and D.
6. Activity H can be strated after the completion of activity G and F.

Find Out : 1. Total Float 2. Free Float 3. Independent Float 4. Critical Path.