Академический Документы
Профессиональный Документы
Культура Документы
Yilma Goshime(Msc)
Target Group:-4th Year Bsc Information System Students
Haramaya Universty,Ethiopia
Information System
Project Managment
Project vs research
Projects and operations differ primarily in that operations are ongoing and
repetitive, while projects are temporary and unique.
The purpose of a project is to attain its objective and then terminate.
Conversely, the objective of an ongoing operation is to sustain the business.
Is tere similarities?
Both are:-
Performed by people
Constrained by limited resources
Planned, executed, and controlled.
one more?
The level of uncertainty is highest and, hence, risk of failing to achieve the
objectives is greatest at the start of the project.
The certainty of completion generally gets progressively better as the project
continues.
Cost and staffing levels are low at the start, peak during the intermediate
phases, and drop rapidly as the project draws to a conclusion.
Is there differences between PDLC and SDLC?
PDLC
it is a process that is responsible for bringing to market a new product and
generally includes the business units.
It is, therefore, the process of developing a product.
SDLC
is used for developing particular software products.
is primarily aimed at solving a specific software problem that may arise.
That is, it points to specific steps within the PDLC.
We may also say that SDLC is a subset of PDLC. Such steps are the
responsibility of a technical department within an organization.
Note:-If the project that we develop is specific one we may follow just SDLC
phases. because designing a system also consider as a project.
Chapter Two
Introduction
Objectives
functions of the project
Performance Issues
Management and Technical Constraints
Project Estimates
We may use Historical Data
Estimation Techniques Used
Effort, Time, and Cost Estimates
Schedule
Work Breakdown Structure
Gantt Chart Representation
Project Resources
People
Hardware and Software
Staff Organization
Team Structure
Management Reporting
Miscellaneous Plans
Quality Assurance Plan:-which is performed based on the
standard.Standards are the key to effective quality management.
Configuration Management Plan:- encompasses the disciplines and
techniques of initiating, evaluating and controlling change to products
during and after the process.
System Testing Plan
Delivery, Installation, and Maintenance Plan
To estimate various project parameters like project size, cost, effort, and
duration by using various estimation techniques.
It makes proper planning and scheduling of organizational resources.
Empirical Estimation
Expert Judgment
Delphi cost estimation
Expert Judgment
Here an expert guess about problem size after analyzing the problem.
Usually expert estimates the cost of modules of each subsystem to get the
overall estimation of system.
Problem:-There may be personal bias and interference.
Estimation Steps:-
1 Determine size of the product(KLOC).
2 From the size estimate, determine the effort needed.
3 From the effort estimate, determine project duration, and cost.
Step-1 and 2 :- after identifying tasks the project manager break down this
large task into smaller activities by using a work breakdown structure.
Includes the processes required to ensure that the project includes all the
work required to complete the project successfully.
primarily concerned with defining and controlling what is and is not included
in the project.
It has its own processes,such as:-
1 Scope Planning:-Creating a project scope management plan that
deliverables.
5 Scope Control:-controlling changes to the project scope.
Those processes interact with each other and with processes in the other
Knowledge Areas as well.
Each process can involve effort from one or more persons or groups of
persons, based on the needs of the project.
In the project context, the term scope can refer to:-
1 Product scope:-The features and functions that characterize a product,
Scope Planning/Input...
1 Enterprise Environmental Factors:- Such as the organization culture,
infrastructure, tools, human resources, personnel policies and marketplace
conditions that could affect how project scope is managed.
2 Organizational Process Assets:The formal and informal policies, procedures
and guidelines that could impact how the project scope is managed.(e.g
Historical information about previous projects)
3 Project Charter:-Formal document which authorizes a project or a project
phase.
4 Preliminary Project Scope Statement:-Intial project scope statement
document that provides a high level scope narrative.
5 Project Management Plan:-Formal document whch is necessary to define,
prepare, integrate, and coordinate all subsidiary plans.(by PMP teams)
Scope Defination/Input
1 Organizational Process Assets
2 Project Charter
3 Preliminary Project Scope Statement
4 Project Scope Management Plan:-Which was the out put of scope planning
5 Approved Change Requests:-Can cause a change to project scope, project
quality, estimated costs or project schedule.
Create WBS/Input
Organizational Process Assets
Project Scope Statement:-just out put of scope defination
Project Scope Management Plan:-out put of scope defination
Approved Change Requests
Scope Verification/Input
Project Scope Statement:-out put of WBS
WBS Dictionary:-out put of WBS
Project Scope Management Plan:-out put of WBS
Deliverables:-Those that have been fully or partially completed Project
Execution process
Scope Control/Input
Project scope statement:-Associated with WBS and WBS dictionary which
defines the project scope baseline and product scope.
Work Breakdown Structure
WBS Dictionary
Project Scope Management Plan
Performance Reports:- Provide information on project work performance,
such as interim deliverables that have been completed.
Approved Change Requests
Work Performance Information:-Give us information about the performance
of the work
Like Project scope managment those processes interact with each other and
with processes in the other Knowledge Areas as well.
The process can involve effort from one or more persons or groups of
persons based on the needs of the project.
Activity Defination/Input
Enterprise Environmental Factors:-Can be availability of project management
information systems and scheduling software tools.
Organizational Process Assets:-Contain the existing formal and informal
activity planning-related policies and procedures that are considered in
developing the activity definitions.
Project Scope Statement:-B/c deliverables, constraints, and assumptions
necessary for activity defination.
Work Breakdown Structure:-Also primary input for activity defination
WBS Dictionary
Project Management Plan:-Contains the schedule management plan so,it
gives guidance about development of activity defination.
Activity Sequencing/Input
Project Scope Statement:-Includes product characteristics that often can
affect activity sequencing
Activity List
Activity Attributes
Milestone List
Approved Change Requests
Cost estimating/Input
Enterprise Environmental Factors:-Cost Estimating process
considers:Marketplace conditions(What products, services)and Commercial
databases(Resource cost rate information
Organizational Process Assets:-Existing formal and informal cost
estimating-related policies and procedures are considered in developing the
cost management plan
Project Scope Statement:-Describes the business need, justification,
requirements and current boundaries for the project.
Work Breakdown Structure:- Provides the relationship among all the
components of the project and the project deliverables
WBS Dictionary:- Also give information about deliverables
Project Management Plan:-Provides the overall plan for executing,
monitoring and controlling the project and that provide direction for cost
management planning and control.
Yilma Goshime(Msc.) (Haramaya
Information
Universty,Ethiopia
System Project
) managment 96 / 101
Project Cost managment...