A1D
Rework Production order WIP
In process
Business Process Procedure
________________________________________________________________________
IMC Dash Solution By KPIT 1 of 17
A1D- Rework Production order WIP In process
________________________________________________________________________
IMC Dash Solution By KPIT 2 of 17
A1D- Rework Production order WIP In process
Contents / Index
1. Purpose.......................................................................................................4
2. Prerequisite.................................................................................................5
Master Data.................................................................................................5
Required Primary Steps.................................................................................5
3. Process Steps...............................................................................................6
Process Flow Diagram....................................................................................6
Process Overview Table.................................................................................7
4. Scenario: Long Term Planning Capacity Evaluation...........................................8
A1D.10 Confirmation of Operation – Rework Occurred.......................................8
A1D.20 Check for Rework Production Order in Order Report.............................10
A1D.30 Release Rework Order......................................................................10
A1D.40 Extra Components for rework order is updated in Order........................11
A1D.50 Issue Goods to Rework Order............................................................11
A1D.60 Confirm Rework Order......................................................................12
A1D.70 Technically complete Order...............................................................13
A1D.80 Confirm remaining operations in Main Order........................................14
A1D.90 Goods Receipt.................................................................................15
A1D.100 Settlement of Main and Rework Order..............................................16
________________________________________________________________________
IMC Dash Solution By KPIT 3 of 17
A1D- Rework Production order WIP In process
1. Purpose
While processing production operations for particular product, defect can be
identified which can be reworked to correct. As this rework is only for operation, this
activity can be treated as Operation Rework – Work In Progress.
When an event of operation rework is occurred, user needs to set the rework status
active while confirming the operation. This will create rework production order
without reference to material automatically by system.
Any extra material needed for rework is consumed to rework order and cost will be
debited to Rework Order.
This production order will be finally settled on to Main Production Order. So after
confirmation of Main order and settlement of main order, Rework cost can be seen
separately.
The quantity which can not be reworked will be scrapped and charged to Cost center.
________________________________________________________________________
IMC Dash Solution By KPIT 4 of 17
A1D- Rework Production order WIP In process
2. Prerequisite
Master Data
You have to Enter Master data to execute this scenario.
Following Master data to be maintain or ensure while going through all Business
Process Procedure of this scenario.
Material Master
BOM
Routing
Rework Work Center
Standard Trigger Point
Rework operation Set
________________________________________________________________________
IMC Dash Solution By KPIT 5 of 17
A1D- Rework Production order WIP In process
3. Process Steps
Process Flow Diagram
________________________________________________________________________
IMC Dash Solution By KPIT 6 of 17
A1D- Rework Production order WIP In process
________________________________________________________________________
IMC Dash Solution By KPIT 7 of 17
A1D- Rework Production order WIP In process
Prerequisite
Rework Reference Operation set is created.
Trigger Point is created
In Routing Master or in Production Order, trigger points are assigned
to all operations where rework can occur.
Main order is created and released.
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Confirmation > Enter > For Operation > Time
Ticket
Transaction Code CO11N
Business Role Production Supervisor
Enter
Result
Rework Order is generated for rework quantity entered. Main order’s
operation is saved.
________________________________________________________________________
IMC Dash Solution By KPIT 9 of 17
A1D- Rework Production order WIP In process
Prerequisite
Rework Order is created in the system
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Information System > Order Information
System
Transaction Code COOIS
Business Role Production planner
Execute .
In the Order report, Superior Order column shows your main Order
and Order column shows your Rework Order.
Result
Rework Order is checked.
Prerequisite
Rework Order is created in system
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Order > Change
________________________________________________________________________
IMC Dash Solution By KPIT 10 of 17
A1D- Rework Production order WIP In process
Transaction Code CO02
Business Role Production Planner
Result
Rework Order is released
Prerequisite
Rework Order is created.
Need for Extra components for rework
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Order > Change
Transaction Code CO02
Business Role Production Planner
Save .
Result
Prerequisite
________________________________________________________________________
IMC Dash Solution By KPIT 11 of 17
A1D- Rework Production order WIP In process
All components required for Production Order are in Inventory with
required quantity
Procedure
Easy Access Path Logistics > Materials Management > inventory
management > goods movement > goods issue
Transaction Code MB1A
Business Role Store Executive
Result
Goods required for Production Order are issued.
Prerequisite
All components required for operation needs to be issued.
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Confirmation > Enter > For Operation > Time
Ticket
Transaction Code CO11N
Business Role Production Supervisor
________________________________________________________________________
IMC Dash Solution By KPIT 12 of 17
A1D- Rework Production order WIP In process
On the Initial screen, make following entries
Result
All operations in Rework Production Order are confirmed.
________________________________________________________________________
IMC Dash Solution By KPIT 13 of 17
A1D- Rework Production order WIP In process
After completing confirmation of all operations in rework order, user
needs to give status to order as it is Technically Complete so that all
cost incurred on to Rework Order can be settled to main Order.
Prerequisite
All Operations in Rework Orders are confirmed
________________________________________________________________________
IMC Dash Solution By KPIT 14 of 17
A1D- Rework Production order WIP In process
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Order > Change
Transaction Code CO02
Business Role Production Planner
Save .
Result
System Updates TECO status to Rework Order
Prerequisite
All components required for operation needs to be issued.
Rework Order is completed if full confirmation is to be carried out.
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Confirmation > Enter > For Operation > Time
Ticket
Transaction Code CO11N
Business Role Production Supervisor
On the Initial screen, make following entries
Result
All operations in Main Production Order are confirmed.
Prerequisite
All operations in Production Order are confirmed
Procedure
Easy Access Path Logistics > Production > Shop Floor Control >
Goods Movements > Goods Receipts
Transaction Code MB31
Business Role Production Engineer
________________________________________________________________________
IMC Dash Solution By KPIT 16 of 17
A1D- Rework Production order WIP In process
Enter
Result
Finished Material is updated in Stock.
Please refer to D1L- Period End Closing Scenario for further details
________________________________________________________________________
IMC Dash Solution By KPIT 17 of 17