RESEARCH ON

UNDERSTANDING INTERIM &


FINAL INSPECTION FOR
CONSTRUCTION PROJECTS

Prepared by:

AR RIDHA RAZAK
28/6/16
INTRODUCTION

 Construction has a major impact on public safety


 Construction are becoming more complex
 Construction defects can be very expensive to repair

`Awell functioning building control regulatory system is


an important component of modern society.’
TYPICAL DEVELOPMENT PROCESS

1 2 3 4

Certificate of
Submission Issuance of Site/Final Completion
of Plans Approvals Inspections and
Compliance

• Multiple agencies
(IWK, TNB, DOSH,
MCMC, SYABAS,
BOMBA, Local
authorities, JKR,
JPS)
Certificate Completion and Compliance flow chart
Complying - UBBL 25A & SDBA 70 (20-27)

Submit Approval: UBBL SEC 3


PSP SDBA SEC 70 (4)

OSC

Obtain Building Plan approval


PSP
Sec 22: Form B
Sec 25: Monitor form G1-21
Construction Supervise site : UBBL SEC 5
Submit Form B : UBBL Sec 22

Obtain approval from Clearance/Confirmation


Professional, Contractor authorities according to
By relevant
or Tradesmen stage completion where
applicable Technical agencies
certify for completion of
stage G1-21
Sign F form when all document
PSP complete attach with relevant document

CCC complete

Original copy Arch keep LAM/LJM PBT


to client 1 copy 1 copy 1 copy
WHICH ONE NEED CLEARANCE LETTER?

TNB
SYABAS
IWK
BOMBA
DOSH
JKR
JPS
PBT?
UNDERSTANDING EXTERNAL AGENCIES SITE INSPECTION
PROSES PERAKUAN BERPERINGKAT
JENIS BORANG KOMPONEN INSPECTION Clearance letter PROFESIONAL
G1 Kerja-Kerja Tanah PBT NA (SP)
G2 Pemancangan Tanah NA NOT REQUIRED (PSP)
G3 Tapak PBT NOT REQUIRED (SP)
G4 Struktur PBT NOT REQUIRED (SP)
G5 Perpaipan Air Dalaman SYABAS NOT REQUIRED (SP)
G6 Perpaipan Sanitari Dalaman IWK? NOT REQUIRED (SP)
G7 Elektrikal Dalaman TNB NOT REQUIRED (SP)
G8 Menentang Kebakaran (Pasif) BOMBA YES IF APPLICABLE (PSP)
G9 Menentang Kebakaran (Aktif) BOMBA YES IF APPLICABLE (SP)
G10 Pengudaraan Mekanikal PBT NOT REQUIRED (SP)
G11 Pemasangan Lif/Eskalator DOSH NOT REQUIRED (SP)
G12 Bangunan PBT? NOT REQUIRED (PSP)
G13 Sistem Bekalan Air Luaran SYABAS YES (SP)
G14 Retikulasi Pembentungan IWK YES (SP)
G15 Loji Rawatan Pembentungan IWK YES (SP)
G16 Sistem Bekalan Elektrik Luaran TNB YES (SP)
G17 Jalan dan Parit PBT YES (SP)
G18 Lampu Jalan PBT NOT REQUIRED (SP)
G19 Parit Luaran Utama JKR YES IF APPLICABLE (SP)
G20 Telekomunikasi TELCO NOT REQUIRED (SP)
G21 Landskap PBT NOT REQUIRED / (Arkitek / Arkitek
Lanskap)
OSC 3.0
PERINGKAT PEMBINAAN
PROJEK BERSKALA BESAR/ KECIL
Penumpuan kepada hanya 6 proses utama
F1 : FASA 1 F2 : FASA 2 F3 : FASA 3
PRA PEMBINAAN PEMBINAAN SIAP PEMBINAAN

Mula Akhir
P1 P2 P3 P4 P5 P6

Pra Pertimbang Notis Pemeriksaan Pemeriksaan Pendepositan


Rundingan an kepada Mula Kerja Interim Akhir CCC
Pelan-pelan Peringkat I & dan
Cadangan Peringkat II Borang-
Pemajuan Borang G
Untuk projek
berskala besar
sahaja

Proses 1 Proses 2 Proses 3 Proses 4 Proses 5 Proses 6


PROSES 1 : PRA RUNDINGAN

AGENSI MEMBERI MAKLUMAT Agensi Teknikal


tetapkan dalam
• Pelan susunatur 1.2 tempoh 14 hari
• Anggaran Permintaan PBAN
Bekalan Air
• Tetapkan Tapping point &
tekanan air

• Pelan susunatur
• Anggaran Beban Elektrik 1.3
Awalan & Muktamad
TNB
• Tetapkan keperluan TNB
1.1 1.6
PEMOHON PEMOHON

• Mendapatkan
• Terima Maklumat Tapping Point
maklumat teknikal
1.4 & Tekanan Air
SKMM • Terima Maklumat Keperluan TNB
• Tetapkan tapping point (manhole • Terima senarai maklumat Tapping
terdekat) setiap NFP Point, Surat Pengesahan tiada
• Pelan susunatur • Surat Pengesahan tiada halangan halangan gelombang mikro (jika
gelombang mikro & kes ‘reroute’ berkaitan), dan Anggaran Kes
jika berkaitan dari setiap NFP
Pemberian Servis setiap NFP dari
• Anggaran kes pemberian servis
SKMM.
setiap NFP
• Terima maklumat jenis
permohonan perihal tanah dari
1.5 PTG/PTD
• Pelan susunatur
• Carian Rasmi
PTG/PTD • Maklumat sah 3 bulan dari tarikh
• Salinan Geran • Tetap jenis-jenis makluman
permohonan perihal tanah
yang berkaitan
PROSES 2 : PERTIMBANGAN KEPADA PELAN-PELAN CADANGAN PEMAJUAN

2.1

PEMOHON
Pemohon kemuka AGENSI MEMPERAKUKAN
permohonan
2.3 2.11
secara satu OSC
persatu atau
Pentadbir Tanah Negeri
Sediakan surat
secara serentak •124A, 204D, Lain-lain
2.8 pengendosan pelan
OSC kepada Agensi
2.4
Jabatan Perancang PBT Memperaku
• Pelan KM
• Pelan Nama Jalan
2.2 • Pelan Nama Taman 2.12 OSC
OSC • Pelan Lanskap 2.9 Sediakan surat
MESY JK
pemakluman
2.5 OSC keputusan kepada
Jabatan Bangunan PBT 2.15 OSC
• Pelan Bangunan Pemohon
Kumpulkan surat-
• Permit Papan Adang surat Kelulusan
• Permit Roro bin Permit dan Pelan-
2.10 2.13 OSC
Tidak Lengkap? pelan yang telah
2.6
Jabatan Kejuruteraan PBT OSC Sediakan
• Permintaan Pemakluman keatas diendos dan serah
Tambahan • Pelan Struktur kepada Pemohon
permohonan yang
Dokumen / • Pelan Kerja Tanah
lulus kepada
Maklumat • Pelan Jalan Parit dan Lampu Jalan
Mesyuarat Majlis Perlu
Garis Merah menunjukan susur pembahagian Ulasan

• Permit Korek Jalan pindaan
Semak Penuh
kelengkapan • Pelan Laluan Utiliti dan
dokumen kemuka
2.14 ke OSC
• Kemukakan OSC
Lengkap Pemakluman Lengkap ?
AGENSI MENGULAS Kelulusan KM
Bersyarat Untuk 2.16
2.7 Selesaikan Hal-Hal
KELULUSAN
• JPS • SKMM Tanah kepada PTN
• JBPM • PTN/PTG KPD
• TNB • JMG PEMOHON
• IWK • PBAN
• JPBD • JKR
• JAS
PROSES 3 : NOTIFIKASI (PERMULAAN KERJA BINAAN)

AGENSI TERIMA NOTIFIKASI

3.3 JABATAN
BANGUNAN
Terima Borang B, Jadual Kedua
UKBS 1984
3.2
3.1 OSC
PEMOHON 3.4
Edar notis dan dokumen
Deposit Notifikasi JABATAN KEJURUTERAAN
kepada agensi
Terima Borang B, UUK Kerja Tanah

Senarai semak deposit:


• Borang B, Jadual kedua UKBS 1984 3.5
• Borang B. UUK Kerja Tanah APP (IWK/MAJAARI)
• PDC 6, MSIG Vol II Terima PDC 6, MSIG
• Borang JKJ103, Seksyen 35 Akta Kilang dan Jentera VOL II
1967
• Jadual pelaksanaan projek
• Borang perakuan perunding bagi skop Pengairan dan 3.6 DOSH
Saliran JPS Terima JKJ 103
• Borang perakuan perunding bagi skop Pengurusan
Sisa Pepejal dalam bangunan .
• Pelan Bangunan untuk rekod PPSPPA 3.7
LAIN-LAIN AGENSI
• Senarai perunding-perunding projek yang berurusan
dengan PBT
Terima dokumen-dokumen yang
• Sijil tanah berkaitan
• Bayaran caruman infrastruktur (ISF) PBT cek/wang
pos/bank deraf
PROSES 4 : NOTIFIKASI PEMERIKSAAN INTERIM

AGENSI MEMERIKSA
4.3 5.4
PBAN
a. Pemeriksaan Interim
b. Sambungan Paip Utama

4.4 5.5
TNB
4.1 5.2 4.2 Pemeriksaan Interim
PEMOHON OSC
4.5
PBT / JKR
• Notifikasi  OSC menerima notifikasi Pemeriksaan Interim
Pemeriksaan pemeriksaan interim
Interim untuk yang menyatakan 4.6
projek berskala pemajuan telah DOSH
Pemeriksaan Interim
besar memenuhi kehendak
agensi peringkat interim
dan bersedia untuk 4.7
pemeriksaan oleh agensi APP (IWK/ MAJAARI)
Pemeriksaan Interim
 OSC edar notis kepada
TNB, BOMBA, PBAN,
4.8
IWK, DOSH dan JKR/PBT. BOMBA
Pemeriksaan Interim

*Bagi sebarang ketidakpatuhan,


agensi akan keluarkan notis
ketidakpatuhan kepada
pemohon
PROSES 5 : PEMERIKSAAN AKHIR DAN PENGELUARAN SURAT PENGESAHAN CCC

 Maklum keperluan
pemeriksaan akhir I
PEMERIKSAAN AKHIR PERINGKAT I
kepada PBAN,TNB,
PBT/JKR 5.3 NFP
 Maklum kepada NFP
•Penyambungan komunikasi *Agensi salinkan
buat sambungan
surat pengesahan
5.4 PBAN CCC kepada unit
a.Pengemukaan Laporan Pengujian dan OSC
Pentauliahan
5.1 b.Pemeriksaan Akhir
PEMOHON 5.2
c.Sambungan meter
• Kemuka OSC d. Pengeluaran Surat Pengesahan CCC (G13)
Permohonan
5.5 5.5 TNB
a. Pemeriksaan akhir
b.Sambungan elektrik
 Permohonan untuk c.Pengeluaran surat pengesahan CCC (G16) 5.10 5.11
PSP
pemeriksaan akhir I bagi OSC Terima surat
skop PBAN, TNB & 5.6 pengesahan CCC
PBT / JKR
PBT/JKR
a. Pemeriksaan akhir
b.Pengeluaran surat pengesahan CCC (G17)
 Permohonan
Sambungan komunikasi.

 Permohonan Maklum keperluan


pemeriksaan akhir
pemeriksaan akhir II II kepada JBPM, PEMERIKSAAN AKHIR PERINGKAT II
bagi skop JPBM, DOSH, DOSH, APP
APP (IWK/MAJAARI) (IWK/MAJAARI)
5.7 JBPM
a. Pemeriksaan akhir
b.Pengeluaran surat pengesahan CCC (G8,G9)

5.8 DOSH
a. Pemeriksaan akhir
b.Pengeluaran surat pengesahan CCC (G11)
*Agensi salinkan
5.9 APP (IWK/ MAJAARI) surat pengesahan
CCC kepada unit
a. Pemeriksaan akhir OSC
b.Pengeluaran surat pengesahan CCC
(G14,G15)
PROSES 6 : DEPOSIT CCC

6.3
JABATAN
BANGUNAN
6.2
6.1 Rekod dan fail CCC &
PEMOHON OSC
Borang G1 – G21
Deposit 2 Salinan CCC & Terima dan edar
Borang G dalam tempoh 14 CCC (Salinan)
hari selepas CCC dikeluarkan Borang G1 – G21 (Salinan)
6.4

LAM/LJM
Rekod dan fail CCC & Borang G1 – G21
INSPECTIONS DURING
CONSTRCUTION
FINAL INSPECTION

For a typical development, final inspections and


letters of clearance are required from various
agencies as follows:

Government Utility providers


Local authority TNB
Bomba IWK
DOSH Water Authority eg. SYABAS
JKR MCMC/Telcos
JPS
PENINSULAR MALAYSIA SUMMARY DEVELOPMENT PERMIT PROCESS

CONSTRUCTION PERMIT PROCESS


Collation of information Submission to OSC for • FORM B Certify Interim Final Inspection I Deposit CCC to
from technical agencies propose development • PDC 6, FORM Inspection PBAN, TNB & PBT/JKR LA, Developer ,
Water, Electric, MSIG Vol II G1-G21 TNB, BOMBA, Permohonan Sambungan LAM
Telecomunications, Land KM / BP/ Structure/ • Borang By PBAN, IWK, komunikasi.
Engineering/ Earthwork/ JKJ103, stages DOSH dan FORM F
Infrastructure/ Landscape JKR/PBT. Final Inspection II JPBM, FORM G1-G21
FORM A : Submission • Sijil tanah
DOSH, APP (IWK/MAJAARI) CLEARANCE
BP/ Structure • etc LETTER

PRE CONSIDERATION COMMENCEMENT INTERIM FINAL


FOR DEVELOPMENT INSPECTION INSPECTION DEPOSIT CCC DLP
CONSULTATION OF WORK
CONSTRUCTION PERIOD

Apply Developer Third Schedule: Progress Billing


HOUSING license & Open
Accounts Delivery of Vacant All schedule
DEVELOPMENT Possession
PERMIT Apply Advertising DLP 24
Permit to Schedule G & I - Months
PROCESS commence sales Within 24 Month

Schedule H & J –
Schedule G Schedule H Schedule I Schedule J Within 36 Month
Individual Strata Individual Title Strata
Title Title Title
Built then sell
Stage billing Stage 10:90 Built then sell
billing 10:90

Super structure
stage

STRATA TITLES Submit Sifus to Obtain Permit


And
Submit Propose Establish
PTG & Submit Strata Plan to
PROCESS Schedule Parcel to commence
JUPEM at G12
Submit to Land VP & issuance MC
sale Office Strata Title SMA 2013
COB for stratified and obtain CPSP
sales After BP
GENERAL OVERVIEW OF INSPECTION

CONSIDERATION
FOR INTERIM FINAL DEPOSIT END
COMMENCEMENT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

CLEARANCE RELATED G
LETTER FORM

BOMBA BOMBA YES G8, G9

DBKL PBT YES G12

IWK IWK IWK LOC G14, G15

SYABAS SYABAS SYABAS QT G13

DOSH DOSH YES NA

TNB TNB TNB YES G16

TELCO TELCO NA NA

LOC- Letter of Clearance


QT- Quality Test
BOMBA
BOMBA INSPECTIONS

 Application for Inspection


• UBBL fire Checklist
• Forms C1, C2 and C3 to be signed and attached with
Bomba certificates for specified items;
• Certification of sprinkler systems (Borang A) by
Mechanical Engineer;
• Certification of fixed active fire fighting and alarm systems
(Borang B) by Mechanical Engineer;
• Copy of receipt (H13) for portable fire extinguishers;
SENARAI SEMAK PEMERIKSAAN
PEMOHONAN PEMERIKSAAN DAN
UJIAN SERTA BAYARAN
BOMBA INSPECTIONS

The Certificate of Completion and Compliance (CCC)


forms are to be supported by Forms G8 and G9
• Form G8: Certification by architect for passive fire
systems;
• Form G9 : Certification by engineer for active fire
systems;
FORM G8 & G9
SURAT PELEPASAN
CARTA ALIRAN PEMERIKSAAN BOMBA
1. BORANG SENARAI SEMAK
PEMERIKSAAN DAN
KEPERLUAN
2. BORANG PEMOHONAN
PEMERIKSAAN DAN UJIAN
SERTA BAYARAN
BOMBA INSPECTIONS

CONSIDERATION
FOR INTERIM FINAL DEPOSIT END
COMMENCEMENT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

MAIN
INSPECTION
CHECKLIST

SUBMIT SURAT
PERAKUAN BY
ARCH. FORM G8
BY
SUBMIT ARCHTECT
FORMS C1, C2
SUBMIT & C3 FOR FIRE ISSUANCE
BUILDING SURAT OF CCC BY
NOTIFICATION DOORS AND
PEMBAYARAN INSPECTION SOKONGAN ARCHITECT
FOR EQUIPMENT
BY BOMBA BY BOMBA
INSPECTION
TO OSC
SUBMIT FORM G9
SURAT BY M&E
PERAKUAN BY ENGR.
M&E ENGR.

SUBMIT
BORANG A
FOR
SPRINKLER
SYSTEM

SUBMIT
BORANG B
FOR OTHER
ACTIVE FIRE
SYSTEMS
TIDAK SOKONG FOR
REINSPECTION
LOCAL AUTHORITY
LOCAL AUTHORITY

Final inspection and Letter of Clearance required


(where applicable) for :
Roads and drainage
Street lighting
Landscape
The inspections are normally carried out by the
Engineering section in the local authorities.
JKR/JPS

Final inspection and Letter of Clearance


required from JKR for roads where it
affects and/or impacts on JKR roads

Clearance required from JPS to ensure


that the site complies with MASMA
requirements.
FINAL INSPECTION DBKL

CONSTRUCTION PERIOD
CONSIDERATION
FOR END
COMMENCEMENT INTERIM FINAL DEPOSIT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

No Clearance FORM G12 BY


Building ?? letter required ARCHITECT

No Clearance FORM G18 BY


Street lighting
letter required M&E ENGINEER

PBT FORM G21 BY


Landscape No Clearance
LANDSCAPE
letter required
ARCHITECT

ISSUANCE
FORM G17 BY OF CCC BY
SUBMIT Road Drainage Clearance letter CIVIL STRUCUTRE ARCHITECT
NOTIFICATION ENGINEER
FOR
INSPECTION
TO OSC

Clearance letter
JKR ROAD

JPS FOR
JPS Clearance letter
MASMA
IWK
IWK INSPECTIONS

CONSTRUCTION PERIOD

INTERIM FINAL DEPOSIT END


CONSIDERATION COMMENCEMENT
INSPECTION INSPECTION CCC DLP
FOR DEVELOPMENT OF WORK

PDC 6
Notification of Commencement of
Handover
Sewerage Works/Septic Tank
PDC 7 Sign-Off
Works
Notice of Form
PDC 8
Intermediate
PDC 6-1 Notice of Final
Inspection of
Notification for Connection to Public Inspection Certificate of
Sewerage
Sewer compliance (
Works FORM G14
CoC) & G15 BY ISSUANCE OF
For upgrading of plant, require kick & Letter of CCC BY
C&S
of meeting before PDC 6. Completion ARCHITECT
ENGINEER
Technical (LOC)
Comments
by IWK

INSPECTION PROCEDURES FOR SEWERAGE WORKS (IWK)


ACTION BY
NO. FORM USED DESCRIPTION REMARKS
Contractor Consultant IWK Developer
Notification of Commencement of Sewerage
1 PDC 6   - - Consultant to Notify
Works/Septic Tank Works

2 PDC 6-1 Notification for Connection to Public Sewer - - - Consultant to Notify
Notice of Intermediate Inspection of Sewerage
3 PDC 7 -  - - Consultant to Notify
Works
4 - Technical Comments    - IWK to Issue
5 PDC 8 Notice of Final Inspection   -  Consultant to Notify
6 - Confirmation of Completion of Work - -  - IWK to Issue
Declaration by Competent Person Who Supervised
7 PDC 9 -  -  Consultant to Declare
the Septic Tank Works
8 - Handover Sign-Off Form -    IWK to Issue
SYABAS
SYABAS INSPECTION
CONSTRUCTION PERIOD
CONSIDERATION
FOR COMMENCEMENT INTERIM FINAL DEPOSIT END
DEVELOPMENT OF WORK INSPECTION INSPECTION CCC DLP

QT1 – 6th Schedule QT4(a) QT7 QT11- TENTH


HYDROSTATIC SCHEDULE
APPLICATION FOR PRESSURE TEST & NOTIFICATION FOR
TEST AND LEAKAGE TEST SUBMISSION OF BANK ACCEPTANCE OF
INSPECTION OF REPORT GUARANTEE OVER HANDING OVER OF
EXTERNAL PIPELINE DEFECT LIABILITY EXTERNAL WATER
EXTERNAL WATER RETICULATION
PERIOD (EXTERNAL
RETICULATION QT4(b) RETICULATION WATER SYSTEM / SUPPLY
SYSTEM / SUPPLY HYDROSTATIC SUPPLY SYSTEM / MAIN* FROM A
MAIN* PRESSURE TEST SUPPLY MAINS*) DEVELOPER
REPORT
EXTERNAL PIPELINE &
MAIN PIPE COMPLETE QT8
QT2
WITH FERRULE AND FORM G13 BY M&E
COMMUNICATION PIPE SUPPORT LETTER ENGINEER
RESPONSE ON FROM DISTRICT O&M
APPLICATION FOR DEPT FOR TAPPING
TEST AND INSPECTION WORKS
OF EXTERNAL WATER QT5
RETICULATION ISSUANCE OF CCC
SYSTEM / SUPPLY WATER TIGHTNESS BY ARCHITECT
MAIN* TEST REPORT FOR QT9 – 11th Schedule
RESERVOIR/ SUCTION
CISTERN CERTIFICATE OF
DISINFECTION
QT3
QT6(a)
FINAL JOINT
MATERIAL QT10- Ninth Schedule
INSPECTION REPORT
INSPECTION REPORTS
(EXTERNAL PIPELINE)
APPLICATION FOR
QT6(b) HANDING OVER OF
FINAL JOINT EXTERNAL WATER
INSPECTION REPORT RETICULATION
(RESERVOIR/ SUCTION SYSTEM / SUPPLY
CISTERN/ PUMP MAIN* TO A WATER
HOUSE) DISTRIBUTION
LICENSEE/ SERVICE
LICENSEE

QT- Quality Test


DOSH
DOSH INTERIM/ FINAL INSPECTION

CONSTRUCTION PERIOD
CONSIDERATION
FOR END
COMMENCEMENT INTERIM FINAL DEPOSIT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

FORM G11
PAYMENT FOR BY M&E ISSUANCE OF
INSPECTION & ENGINEER CCC BY
ISSUE PMA & ARCHITECT
TAK LENGKAP/ MAKLUMAT NO. BY JKKP COMPETEN
TAMBAHAN
T PERSON

COMPLY
SUBMIT
LIFT AND
APPLICATION
DOSH CHECK MACHINERAY 1ST SCHEDULE
FORM FOR
APPLICATION INSPECTION INSPECTION
JKKP
BY JKKP
INSPECTION

Don’t
Comply
TNB
TNB INTERIM/ FINAL INSPECTION

• TNB support for CCC will only be given after :


– Sub-station building handover process completed
and equipment installed.
– TNB underground cable installation completed.
– TNB feeder pillar installation completed.
– TNB meter panel installation and cable termination
completed.
• Inspection with TNB only during the process to
handover the sub-station building to TNB.
TNB INTERIM/ FINAL INSPECTION

• TNB Inspection comprises the below steps:


– Inspection for Cas Sambungan Pengguna (CSP) estimation.
Road condition to be at least first layer crusher run.
– Inspection for sub-station building handover. Road condition
to be at least second layer crusher run and properly
compacted. TNB will comment on installation of light fitting,
socket outlet, earthing bar, painting, signage, logo, door,
compound finishes, gate size etc.
– Inspection for house meter compartment. TNB will comment
on meter panel board, meter standing height from FFL, space
in compartment, door size, louver and glass panel size.
TNB INTERIM/ FINAL INSPECTION

CONSIDERATION
FOR INTERIM FINAL DEPOSIT END
COMMENCEMENT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

Inspection for Cas


Sambungan Pengguna
(CSP) estimation.
Site condition to be as soon
as earthwork start INTERNAL SUBSTATION
INSPECTION(
INSTALLATION)

Sub-station building
handover process
completed and equipment
Inspection for sub- installed.
station building
handover.
Road condition to be at
least second layer All comply,
APPLY TO
crusher run and properly TNB to FORM G16 ISSUANCE OF
TNB FOR
compacted. TNB will issue BY M&E CCC BY
HANDOVER
comment on installation clearance ENGINEER ARCHITECT
INSPECTION
of light fitting, socket letter
outlet, earthing bar,
painting, signage, logo, EXTERNAL INFRA
door, compound INSPECTION
finishes, gate size etc.
Inspection for TNB
Installation from
Substation to Customer
meter Comperment

-TNB underground cable


installation completed.
-TNB feeder pillar
installation completed.
-TNB meter panel
installation and cable
termination completed.
TELCO
TELCOS INSPECTION

 Telcos approval normally involves 2 inspections:


internal and external.
 Internal Inspection involves design inside
premise/house unit to first external manhole.
Usually design compliance and internal fiber cable
are tested to meet guidelines set by MCMC.
 Testing done randomly with Telco inspector by
selecting few houses or installation. Full test
report to be submitted by sub-contractor to Telco.
TELCOS INSPECTION

• External Inspection involved mandrel test for


underground ducting from manhole to manhole.
• Also done randomly and full test report to be
submitted to Telcos.
• Supporting letter then can be requested next day by
writing officially to Telco.
TELCOS INSPECTION

CONSIDERATION
FOR INTERIM FINAL DEPOSIT END
COMMENCEMENT
DEVELOPMENT INSPECTION INSPECTION CCC DLP
OF WORK

Internal Inspection
involves design
inside premise/house Testing done
Full test report
unit to first external randomly with
to be submitted
manhole. Usually Telco inspector
by sub-
design compliance by selecting
contractor to
and internal fiber few houses or
Telco.
cable are tested to installation.
meet guidelines set FORM G20 BY
APPLY TO by MCMC. M&E
TELCO FOR ENGINEER
INSPECTION Report/Supporti
ng letter /
External Inspection Also done Certificate/
involved mandrel test randomly and ISSUANCE OF
for underground full test report to then can be CCC BY
ducting from manhole be submitted to requested next ARCHITECT
to manhole. Telcos. day by writing
officially to
Telco.
CONCLUSION
By Ar QHWARIZMI
UNDERSTANDING INTERIM/
FINAL INSPECTION PROCESS
FOR TECHNICAL AGENCIES
FOR CONSTRUCTION
PROJECTS

Prepared by:

AR RIDHA RAZAK