LC3-KKIA

Method Statement for Formworks,


Rebar, and Cast-in-Situ concrete
(Pouring, embedment’s, curing), rev. D
SSEM reply to AECOM Comments

SN AECOM COMMENTS SEEM REPLY REMARKS


1 Page 4 – Equipment: Add “Concrete Truck Included. Please see clause 5
Mixer” on the Equipment List.
2 Page 7, Formworks:
a Arrange sequence of works from Noted and modified. Please see clause
preparation of formworks, installation and 9.2
removal.
b Indicate the design of formworks for critical Noted and incorporated.
concrete construction shall be submitted for
review
c Include and specify materials type to be Noted and incorporated.
used for forms including accessories
d Include formworks tolerances specified and Noted and incorporated.
mentioned in ACI 117
e Include provision of 20mm chamfer on all Noted and incorporated.
exposed edges of concrete structure
f Indicate that form tying device will not be Noted and incorporated.
embedded in the concrete
3 Page 9, Steel Reinforcement:
a Include and specify reinforcing steel types Noted and included. Please see clause
and accessories 9.3
b Indicate minimum steel cover as per ACI 318 Noted and incorporated.
section 7.7
c Include spacing of ties at intersections Noted and incorporated.
d Specify that the detail of reinforcement will Noted and incorporated.
be in accordance with ACI SP-66 or
equivalent
4 Page 9, Anchor Bolt and Embedded Item
a Include and specify types of anchor bolts, Noted and included. Please see clause
embedded items and accessories 9.4
5 Page 10, Concrete Pouring
a Check spelling of “Concrete” Noted and modified. Please see clause
9.6
b Include Civil QC Inspector to check the truck Noted and incorporated.
delivery note to establish that the correct
type of concrete has been delivered
c Mention involvement of third party Noted and incorporated.
technician to include its duty and
responsibility
d Include location where concrete samples Noted and incorporated.
are to be taken

Page 1 of 2
e Sampling of concrete shall be using a Noted and modified.
cylinder not a cube
f Frequency of concrete cylinder sampling Noted and modified.
shall be every 110 cubic meter or fraction
thereof per day and every type of concrete
g Indicate minimum and maximum concrete Noted and incorporated.
slump and temperature
h Indicate that concrete shall be used within Noted and incorporated.
90 minutes after water has been added at
the plant. Tampering of mix by adding water
will not be allowed
i Indicate maximum layer thickness of placed Noted and incorporated.
concrete
j Indicate maximum drop of concrete Noted and incorporated.
k Indicate that use of bagger mixer is not Noted and incorporated.
allowed
5 Page 11, Stripping of formworks
a Indicate duration of form removal as per ACI Noted and incorporated. Please see
347 clause 9.8
6 Include section for surface preparation and Noted and incorporated. Please see
moisture test prior to bitumen coat clause 9.9
application