Вы находитесь на странице: 1из 1

00 01

WA-401413 MK238 Q 4400005604


NOTES
REV. NO. SHEET NO. DRAWING NUMBER PLANT NO. INDEX JOB ORDER NO. CONTRACT NO.
1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE
NOTED.

OW NER.
2. CONCRETE COMPRESSIVE STRENGTH SHALL CONFORM WITH
REQUIREMENTS OF 70-TMSS-03 REV.0 AND SHALL HAVE
MINIMUM COMPRESSIVE STRENGTH OF 38Mpa FOR SEVERE
UNFACTORED
EFFECTIVE REBAR LIST FOR PEDESTAL REBAR LIST FOR FOOTING BARS FOUNDATION DATA EXPOSURE SOIL AND 28Mpa FOR MODERATE EXPOSURE SOIL
FOUNDATION LOADS CONDITION.

TS
SOIL PARAMETERS

OF I
LONGITUDINAL BARS (BAR B) TIES (BAR A) TOP BARS BOTTOM BARS FOOTING PEDESTAL [kgf] 3. YIELD STRENGTH OF DEFORMED STEEL REINFORCEMENT,
DESIGN
fy = 420 MPa.
TOWER NO. OVERALL CALCULATION#
BEARING UNIT NOS. NOS. DEPTH 4. THE MINIMUM CONCRETE COVER TO REINFORCEMENT STEEL
NOS. NOS. CUTTING CUTTING SIZE H

CONSENT
C2 C3 SIZE L x B DEPTH DEPTH SHALL BE 75mm.
CAPACITY WEIGHT SIZE A1 B1 LENGTH SIZE LENGTH a1 REQ’D IN C1 C3 REQ’D IN "OL" Pu Pd
(DEG) REQ’D REQ’D SIZE LENGTH (LTB) SIZE LENGTH (LBB) (a x a)
2 3
EACH DIR. EACH DIR. "Fd" "h" PHX PHY 5. PROVIDE (2) TWO LAYERS OF 150 MICRON THICK POLYETHYLENE
kN/m kN/m
SHEET UNDER 75mm THICK LEAN CONCRETE AS PER SEC
STANDARD TCS-Q-113.03 SEC: 7.3.7.
S1, S3, 1A, 1B & 1C 30.0 350 17.044 {25 40 5226 300 5526 {12 2900 22 650 {20 29 4600 425 5450 {20 29 4600 425 5450 4800 x 4800 800 800 x 800 3700 5250 294582 349575 74512 82028 06-P-916F-PA-HA-DE-R0
6. TOP SURFACE OF CONCRETE SHALL BE CROWNED AND GIVEN

TTEN
A SMOOTH STEEL TROWEL FINISH.

7. BACKFILLING SHALL BE DONE WITH APPROVED BACKFILLING

THE W RI
MATERIALS AND COMPACTION SHALL BE CARRIED OUT TO
ACHIEVE A MIN. 95% OF STANDARD PROCTOR DENSITY IN
LAYERS NOT MORE THAN 200mm THICK.
| OF FOUNDATION
8. ALL EXPOSED CONCRETE SURFACES SHALL BE DRY &
CLEANED AT THE TIME OF APPLICATION AND IT SHALL BE
STUB ANGLE COATED WITH POLYURETHANE WATER PROOFING MEMBRANE.

THOUT
SEE NOTE #10 9. ALL CONCRETE SURFACES BELOW GRADE LEVEL SHALL BE
| OF FOOTING COATED WITH A MINIMUM OF (2) COATS OF COAL TAR EPOXY.
PUNCH MARK

WI
| OF PEDESTAL 10. FOR STUB & STUB SETTING DETAILS AND TOWER GROUNDING
FOR CONCRETE LEVEL
DETAILS SEE REFERENCE DRAWINGS.

DOCUMENT
11. TOWER SHALL NOT BE ERECTED/INSTALLED UNTIL AT LEAST
a

| OF FOUNDATION CHAMFERED STUB ANGLE


(25x25) 150x150x15H 10 DAYS AFTER POURING THE CONCRETE FOUNDATIONS AS PER
CLAUSE 4.3 OF TCS-P-122.06, REV.01.

ELASTOMERIC PU 12. NO LOAD TO BE APPLIED TO TOWER UNTIL THE CONCRETE

PUNCH MARK COATING HAS REACHED 28 DAYS STRENGTH AS PER CLAUSE 4.3 OF
C

S
(SEE NOTE #8) TCS-P-122.06, REV.01.

THI
FOR CONCRETE LEVEL
C 13. CONSTRUCTION JOINT IF REQUIRED, SHALL BE PROVIDED AT

450
1.5 - 2% 300mm BELOW THE STUB ANGLE. BEFORE APPLICATION OF
1.5 - 2%

FROM
TOP OF SLOPE NEXT CONCRETE POURING APPROVED BONDING AGENT SHALL

1
SLOPE

0
BE USEDAS PER 11.3.1 OF TCS-P-122.05, REV.1.

.7
a STRUCTURE PAD

4
14. EXPOSED FOUNDATIONS SHALL BE CURED IN MOIST CONDITION

5
300
SEE NOTE#15

NED
10

2
NATURAL

00
FOR 21 DAYS FOLLOWING CLAUSE 8.3.5 OF TCS-Q-133.03, REV.0.

.4
SECTION C-C

1000.
GROUND LEVEL

S OBTAI
12
15. STUB ANGLES SHALL BE CONNECTED BY (7#5 OR 7#7, AS

500

10
)
APPLICABLE) COPPER CLAD GROUNDING CONDUCTOR THROUGH

TYP.
500
COMPRESSION CONNECTOR AND REBARS EXOTHERMALLY WELDED

(
AT LEAST TWO (2) LOCATIONS ON EACH TOWER LEG AS PER
2 COATS (MIN.)

I
| OF FOOTING CLAUSE 6.3 OF TCS-Q-122.10, REV.0.
EPOXY COATING

PART
(SEE NOTE #9) 16. DE-SHUTTERING AND REMOVAL OF TEMPLATES SHALL BE CARRIED
15
8. OUT AFTER (72 HOURS) 3 DAYS OF CONCRETE CURING FOLLOWING
8000 13
3 CLAUSE 10.3 OF TCS-P-122.03, REV.0.
(TYP.) 158.133

N
I
TWO COATS OF
17. EXCAVATION MUST BE CLOSELY MONITORED TO MAKE SURE
COAL TAR EPOXY

FULL OR
PEDESTAL THE SOIL/ROCK PARAMETERS USED IN THIS DESIGN ARE IN
AGREEMENT WITH THE ACTUAL SITE CONDITION. IF THERE ARE
ANY DIFFERENCES, DESIGN OFFICE SHALL BE INFORMED FOR
TIES @ 200mm
RECTIFICATION AND REDESIGN IF NEEDED.
OL

18. THE REINFORCEMENT DETAILS SHOWN IN THE DRAWING AND THE


LONGITUDINAL BARS

N
I
SCALES ARE REPRESENTATIVE ONLY. THE ACTUAL DIMENSION

A1

ON
AND NUMBER OF BAR SHALL BE OBTAINED FROM THE SCHEDULE
h

REPRODUCTI
A A SHOWN IN THE TABLE.
SELECTED
EXCAVATI0N
BACKFILL
a

LINE
B

| OF FOOTING SEE NOTE #7


75mm COVER
REFERENCE DRAWINGS
(TYP)
ANGLE AS PER DRAWING TITLE DRAWING NO.

THE TOWER LEG


DRAWING CONTROL SHEET WE-401392

NO
CONSTRUCTION SLOPE ANGLE
a
JOINT PROJECT TECHNICAL SPECIFICATIONS PTS-14WO141

TWO COATS OF STUB AND CLEAT DRAWING WA-400863


B1
COAL TAR EPOXY TOP BARS

d SA
100 (TYP.) STUB SETTING TEMPLATE DRAWING WA-400863
(BOTH WAYS)
ALL SIDES

onalGri
TOWER / MONOPOLE GROUNDING DETAILS WA-400863
WA-294555
LONGITUDINAL BARS
Fd

ONG
ON PEDESTAL

0 L

OF Nati
L

349
905
STUB ANGLE

..
L + 200
75

0x35
LEAN CONCRETE BOTTOM BARS 250x250x35H
B1 B1 PUNCH MARK FOR
SEE NOTE-5 (BOTH WAYS)

0x25

ARE THE SOLE PROPERTY


100 L 100 CONCRETE LEVEL
P L A N

L25
51
REBAR CHAIRS (IF REQUIRE)
SECTION A-A

11
2
512

461
VARIES

EARTHING CLAMP

| OF FOOTING | OF STRUCTURE G.L/TSP G.L/TSP


| OF FOOTING &
PEDESTAL AT BASE PUNCH MARK FOR AS-BUILT BY DATE

GROUND LEVEL a1

N
HEREI
3413
BOTTOM BARS

LENGTH)
TIES

NED
75mm CLEAR COVER

MBEDDED
00 13/11/17 AZ ISSUED FOR APPROVAL FNK

CONTAI
TYP. ALL AROUND

REV. DATE BY CHKD. CERT. APPD.


DESCRIPTION
ES

| OF STRUCTURE NO.

(
}

2050
} /2

} /2

CLEAT
VARI

PEDESTAL
BARS
BARS

2400
C1 DRAWING COMPLETION CERTIFICATE (DCC):
200x200x20H

ON
B

NFORMATI
| OF FOOTING & TOP BARS
BOTTOM
a
TOP

| OF T/L | O PEDESTAL AT BASE


F T ADDITIONAL
/L
TIES @ 400MM

C3

THE I
| OF FOOTING a AZ/TE MNK
DRAWN BY CHECKED BY SCALE: N.T.S

10/04/2015 _________
BOTTOM BARS DATE STARTED DATE COMPLETED

AND
OPR’G. DEPT. ENG. DEPT.
C2
TOP BARS

THIS DRAWING IS NOT TO BE USED FOR CERTIFIED

NG
FOUNDATION PLAN (TYP) CONSTRUCTION OR FOR ORDERING

DRAW I
MATERIAL UNTIL CERTIFIED AND DATED BY DATE

L
FOOTING BARS
CONSTRUCTION OF 110 kV D/C OHTL FOR

S
THI
TYPICAL STUB AND CLEAT ANGLE FOR ’HA-DE’ WALLI AL AHAD-2 S/S WITH NETWORK
REINFORCEMENT DETAILS MAKKA SAUDI ARABIA
(FOR DETAILS SEE STUB ANGLE REF. DWG.)
CONTRACT NO. JOB ORDER NO. INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO.

4400005604 Q MK238 WA-401413 01 00


NG-A (2012/01)

DMS VECTOR NGA00

Вам также может понравиться