Академический Документы
Профессиональный Документы
Культура Документы
OW NER.
2. CONCRETE COMPRESSIVE STRENGTH SHALL CONFORM WITH
REQUIREMENTS OF 70-TMSS-03 REV.0 AND SHALL HAVE
MINIMUM COMPRESSIVE STRENGTH OF 38Mpa FOR SEVERE
UNFACTORED
EFFECTIVE REBAR LIST FOR PEDESTAL REBAR LIST FOR FOOTING BARS FOUNDATION DATA EXPOSURE SOIL AND 28Mpa FOR MODERATE EXPOSURE SOIL
FOUNDATION LOADS CONDITION.
TS
SOIL PARAMETERS
OF I
LONGITUDINAL BARS (BAR B) TIES (BAR A) TOP BARS BOTTOM BARS FOOTING PEDESTAL [kgf] 3. YIELD STRENGTH OF DEFORMED STEEL REINFORCEMENT,
DESIGN
fy = 420 MPa.
TOWER NO. OVERALL CALCULATION#
BEARING UNIT NOS. NOS. DEPTH 4. THE MINIMUM CONCRETE COVER TO REINFORCEMENT STEEL
NOS. NOS. CUTTING CUTTING SIZE H
CONSENT
C2 C3 SIZE L x B DEPTH DEPTH SHALL BE 75mm.
CAPACITY WEIGHT SIZE A1 B1 LENGTH SIZE LENGTH a1 REQ’D IN C1 C3 REQ’D IN "OL" Pu Pd
(DEG) REQ’D REQ’D SIZE LENGTH (LTB) SIZE LENGTH (LBB) (a x a)
2 3
EACH DIR. EACH DIR. "Fd" "h" PHX PHY 5. PROVIDE (2) TWO LAYERS OF 150 MICRON THICK POLYETHYLENE
kN/m kN/m
SHEET UNDER 75mm THICK LEAN CONCRETE AS PER SEC
STANDARD TCS-Q-113.03 SEC: 7.3.7.
S1, S3, 1A, 1B & 1C 30.0 350 17.044 {25 40 5226 300 5526 {12 2900 22 650 {20 29 4600 425 5450 {20 29 4600 425 5450 4800 x 4800 800 800 x 800 3700 5250 294582 349575 74512 82028 06-P-916F-PA-HA-DE-R0
6. TOP SURFACE OF CONCRETE SHALL BE CROWNED AND GIVEN
TTEN
A SMOOTH STEEL TROWEL FINISH.
THE W RI
MATERIALS AND COMPACTION SHALL BE CARRIED OUT TO
ACHIEVE A MIN. 95% OF STANDARD PROCTOR DENSITY IN
LAYERS NOT MORE THAN 200mm THICK.
| OF FOUNDATION
8. ALL EXPOSED CONCRETE SURFACES SHALL BE DRY &
CLEANED AT THE TIME OF APPLICATION AND IT SHALL BE
STUB ANGLE COATED WITH POLYURETHANE WATER PROOFING MEMBRANE.
THOUT
SEE NOTE #10 9. ALL CONCRETE SURFACES BELOW GRADE LEVEL SHALL BE
| OF FOOTING COATED WITH A MINIMUM OF (2) COATS OF COAL TAR EPOXY.
PUNCH MARK
WI
| OF PEDESTAL 10. FOR STUB & STUB SETTING DETAILS AND TOWER GROUNDING
FOR CONCRETE LEVEL
DETAILS SEE REFERENCE DRAWINGS.
DOCUMENT
11. TOWER SHALL NOT BE ERECTED/INSTALLED UNTIL AT LEAST
a
PUNCH MARK COATING HAS REACHED 28 DAYS STRENGTH AS PER CLAUSE 4.3 OF
C
S
(SEE NOTE #8) TCS-P-122.06, REV.01.
THI
FOR CONCRETE LEVEL
C 13. CONSTRUCTION JOINT IF REQUIRED, SHALL BE PROVIDED AT
450
1.5 - 2% 300mm BELOW THE STUB ANGLE. BEFORE APPLICATION OF
1.5 - 2%
FROM
TOP OF SLOPE NEXT CONCRETE POURING APPROVED BONDING AGENT SHALL
1
SLOPE
0
BE USEDAS PER 11.3.1 OF TCS-P-122.05, REV.1.
.7
a STRUCTURE PAD
4
14. EXPOSED FOUNDATIONS SHALL BE CURED IN MOIST CONDITION
5
300
SEE NOTE#15
NED
10
2
NATURAL
00
FOR 21 DAYS FOLLOWING CLAUSE 8.3.5 OF TCS-Q-133.03, REV.0.
.4
SECTION C-C
1000.
GROUND LEVEL
S OBTAI
12
15. STUB ANGLES SHALL BE CONNECTED BY (7#5 OR 7#7, AS
500
10
)
APPLICABLE) COPPER CLAD GROUNDING CONDUCTOR THROUGH
TYP.
500
COMPRESSION CONNECTOR AND REBARS EXOTHERMALLY WELDED
(
AT LEAST TWO (2) LOCATIONS ON EACH TOWER LEG AS PER
2 COATS (MIN.)
I
| OF FOOTING CLAUSE 6.3 OF TCS-Q-122.10, REV.0.
EPOXY COATING
PART
(SEE NOTE #9) 16. DE-SHUTTERING AND REMOVAL OF TEMPLATES SHALL BE CARRIED
15
8. OUT AFTER (72 HOURS) 3 DAYS OF CONCRETE CURING FOLLOWING
8000 13
3 CLAUSE 10.3 OF TCS-P-122.03, REV.0.
(TYP.) 158.133
N
I
TWO COATS OF
17. EXCAVATION MUST BE CLOSELY MONITORED TO MAKE SURE
COAL TAR EPOXY
FULL OR
PEDESTAL THE SOIL/ROCK PARAMETERS USED IN THIS DESIGN ARE IN
AGREEMENT WITH THE ACTUAL SITE CONDITION. IF THERE ARE
ANY DIFFERENCES, DESIGN OFFICE SHALL BE INFORMED FOR
TIES @ 200mm
RECTIFICATION AND REDESIGN IF NEEDED.
OL
N
I
SCALES ARE REPRESENTATIVE ONLY. THE ACTUAL DIMENSION
A1
ON
AND NUMBER OF BAR SHALL BE OBTAINED FROM THE SCHEDULE
h
REPRODUCTI
A A SHOWN IN THE TABLE.
SELECTED
EXCAVATI0N
BACKFILL
a
LINE
B
NO
CONSTRUCTION SLOPE ANGLE
a
JOINT PROJECT TECHNICAL SPECIFICATIONS PTS-14WO141
d SA
100 (TYP.) STUB SETTING TEMPLATE DRAWING WA-400863
(BOTH WAYS)
ALL SIDES
onalGri
TOWER / MONOPOLE GROUNDING DETAILS WA-400863
WA-294555
LONGITUDINAL BARS
Fd
ONG
ON PEDESTAL
0 L
OF Nati
L
349
905
STUB ANGLE
..
L + 200
75
0x35
LEAN CONCRETE BOTTOM BARS 250x250x35H
B1 B1 PUNCH MARK FOR
SEE NOTE-5 (BOTH WAYS)
0x25
L25
51
REBAR CHAIRS (IF REQUIRE)
SECTION A-A
11
2
512
461
VARIES
EARTHING CLAMP
GROUND LEVEL a1
N
HEREI
3413
BOTTOM BARS
LENGTH)
TIES
NED
75mm CLEAR COVER
MBEDDED
00 13/11/17 AZ ISSUED FOR APPROVAL FNK
CONTAI
TYP. ALL AROUND
| OF STRUCTURE NO.
(
}
2050
} /2
} /2
CLEAT
VARI
PEDESTAL
BARS
BARS
2400
C1 DRAWING COMPLETION CERTIFICATE (DCC):
200x200x20H
ON
B
NFORMATI
| OF FOOTING & TOP BARS
BOTTOM
a
TOP
C3
THE I
| OF FOOTING a AZ/TE MNK
DRAWN BY CHECKED BY SCALE: N.T.S
10/04/2015 _________
BOTTOM BARS DATE STARTED DATE COMPLETED
AND
OPR’G. DEPT. ENG. DEPT.
C2
TOP BARS
NG
FOUNDATION PLAN (TYP) CONSTRUCTION OR FOR ORDERING
DRAW I
MATERIAL UNTIL CERTIFIED AND DATED BY DATE
L
FOOTING BARS
CONSTRUCTION OF 110 kV D/C OHTL FOR
S
THI
TYPICAL STUB AND CLEAT ANGLE FOR ’HA-DE’ WALLI AL AHAD-2 S/S WITH NETWORK
REINFORCEMENT DETAILS MAKKA SAUDI ARABIA
(FOR DETAILS SEE STUB ANGLE REF. DWG.)
CONTRACT NO. JOB ORDER NO. INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO.