Академический Документы
Профессиональный Документы
Культура Документы
A TECHNICAL REPORT
ON
SETTING OUT
PREPARED BY
CVE/2013/061
January 2019
ii
Ile-Ife,
Osun state.
Ile-Ife,
Osun state.
Dear Sir,
LETTER OF TRANSMITTAL
Please find attached, the setting out report written in fulfilment of CVE 502
Thank you.
Yours faithfully,
……………………………….
CVE/2013/061
iii
ACKNOWLEDEMENT
I thank the Almighty God, the Omniscient Spirit and the Author and Dispenser of
Knowledge and Wisdom. May His holy name be glorified for His grace and for His
I will like to appreciate the support, encouragement and prayers of my parents; Mr. and
Mrs. Balogun. May the good Lord continue to grant them sound health, protection and
prosperity.
Finally, I will like to thank Mr. R.B. Ajala for his efforts in impacting the needful
TABLE OF CONTENTS
LETTER OF TRANSMITTAL ii
ACKNOWLEDEMENT iii
TABLE OF CONTENTS iv
CHAPTER ONE 1
INTRODUCTION 1
LITERATURE REVIEW 3
CONCLUSION 26
REFERENCES 27
vi
LIST OF FIGURES
Figure 3.2: Gridline and Offset line for building setting out 25
vii
EXECUTIVE SUMMARY
Setting out is the establishment of the marks and lines to define the position and level
of the fundamental elements for the construction work in order that the work can
proceed with reference to them.
In this report, the material and equipment used and involved in setting out process are
explained. The principle as well as methods used for the various setting out are also
explained.
Methods discussed in this report include the builders’ square method, 3-4-5 method and
the theodolite method. Precautions taken in setting out method are also explained in
this report.
1
CHAPTER ONE
INTRODUCTION
In every country, construction is a major activity and setting out, therefore becomes an
a map or plan showing existing features of the ground. Setting out is the reverse
In order to begin excavation of trenches required for a building’s foundation, the builder
must know the positions and levels of building lines shown on the construction plans
on the ground. That is, the exact length, width, depth, and position of the foundation
trenches must be marked on the ground. This movement from the construction plan to
the actual site by transferring dimensions from the layout plan to the ground is called
setting out. It is probably the most critical step in the entire construction process.
Controlling dimensions and references on the plans will determine the positioning of
the building, and in particular its foundations. These include; overall length and width,
The controlling points of the structure can then be marked so that the construction team
is able to easily identify them. This usually consists of marking the building’s corners,
horizontal and vertical positions, using stakes, batter boards with string lines, drill
Main reasons for setting out are to allow for construction to be done within the legal
boundary, which is vital to ensure no boundary disputes later on and also to enable the
2
construction team to build exactly to plan as markers are physically laid out in front of
them.
(a) to define accurately the outline and width of the excavation and the centre line
(b) to ensure that the various element of the schemes is positioned correctly in all
CHAPTER TWO
LITERATURE REVIEW
Setting out is the translation of construction plans into physical points on the ground
that can be used as a basis for the actual construction. Construction surveying provides
not only the horizontal location of new structure, but also the vertical information
required. The setting out survey consists of locating and marking horizontal and vertical
sewers at manholes).
Stake out reference points and markers that will guide the construction of new
structures.
construction project to verify that the work authorized was completed to the
i. Pegs: The pegs have to be driven in 500 mm outside the final position of the
building. Pegs or stakes are used to mark out residential boundaries and indicate
points and positions of a site. They are usually made of wood (although some are
ii. Profile board: A sight rail placed on the pegs outside of an excavation, usually
iii. Measuring tape: A tape measure or measuring tape is a flexible ruler and used
iv. Lines (different colours): This is used for alignment and to guide while
v. 2 inches Nails: These are used to couple the peg and profile board together, and
are also used for noting points of excavation. Lines are also tied on it during
vi. Builders square: This is used to obtain a perfect 900 shape at corner joints.
(a)
(b)
(d)
(c)
Figure 2.1: Equipment (a) peg (b) measuring tape (c) nail (d) builders square
6
Setting out is done on the principle of whole to part. According to this principle the
largest possible rectangle of the building is found and set out. The rectangle is further
partitioned into small parts (internal rooms). It’s very important to ensure that the main
The level is obtained by use of a clear hose pipe filled with water. Ensuring that the
pegs are positioned at the same horizontal level is very important as it eliminates
arithmetic errors, which could arise when getting your diagonals, to establish if the
The main rectangle is set using the pegs that are in horizontal level. The diagonals of
the main rectangle are checked to determine its accuracy. Accurately set up main
rectangle is then subdivided to obtain the consisting gridlines. These are obtained by
the using structural drawings, Theodolite and steel tape. Nylon threads are stretched
between the pegs to obtain the gridlines when necessary. For this division of the internal
wall to take place, profiles must be in place on the ground. Profiles consist of pegs,
driven into the ground, with cross pieces of timber attached to them. Wooden pegs atop
by a wire nail are driven to establish the grid lines of the building. Usually apart from
the pegs depicting the main grid lines, pegs which show the 500mm off sets are also
established during the setting out process to facilitate the construction that follows.
Although profile boards are temporary, they contain a lot of important information on
distance, with the points clearly marked on them showing the position of the walls and
width of trench. These can be marked on the profile board using nails, and later
It is very important for the profile to be placed firmly on the ground, and at a safe
distance from the excavation area, so that they can be used when setting the wall on top
of the ground slab. Also, these pegs are driven at places such that they won’t be
disturbed by field work etc. Usually they are driven with a distance of 1.5 meter from
The first task in setting out a building is to establish a baseline from which the whole
of the building can be set out. The building position of this line must be marked on the
site, so that it can be properly re-established at any given point in time. The building
line is frequently determined by the highway authority or officials, and in urban areas.
It is often eight metres from the back of the public foot path. If other buildings have
been erected at the area the building line can be determined from these existing
buildings.
After the base line has been established, marked and checked properly, the main lines
of the buildings can be set out, each corner being marked with stout peg. A check is
then made of the setting out lines for right angles and correct lengths. The method of
establishing of the right angle is what the setting out sets out to establish in addition to
i. Find the distance of the site building to the building line on working drawings.
ii. Place a peg in the ground at corner A and hammer a nail into the top of the peg.
iii. Repeat these steps to place a peg in the ground for corner B.
8
iv. Tie the string between pegs A and B. Measure the distance between A and B (check
that the distance on the ground is the same on the drawing) by measuring.
vi. Measure the diagonals A-D and B-C (the two diagonals should be equal)
vii. Use the builder's square to check that the corners are at right angles. Figure 2.2
To set out right angles in the field, a measuring tape, two ranging poles, pegs and three
persons are required. The first person holds together, between thumb and finger, the
zero mark and the 12 meters mark of the tape. The second person holds between thumb
and finger the 3 meters mark of the tape and the third person holds the 8 meters mark.
When all sides of the tape are stretched, a triangle with lengths of 3 m, 4 m and 5 m is
formed (as shown in figure 3.1), and the angle near person 1 is a right angle. Instead of
(a) A theodolite or total station is set up over a control point which has known co-
ordinates.
(b) The instrument is then pointed at another control point in order to orientate the
(c) The distances and bearings from that control point to those points which require
(d) A control point which is located near to the structure to be set out will ensure
maximum accuracy.
(e) If a total station is used the co-ordinates are entered into the software and the prism
target will allow the bearing and distance to be located for each point.
(f) If a conventional theodolite is used the co-ordinates of the control point are
compared with those of each point to be set out. This will require whole circle
(g) The procedure is then to simply turn to the required bearing and measure the
Figure 2.4 shows a labelled theodolite and Figure 2.5 illustrates setting out using the
theodolite.
10
i. Site clearance
iii. Get the necessary materials ready (i.e. pegs, nails, rope or line, hammer, tape,
iv. Firstly, take note of the four corners where we have the proposed columns/pillars
v. Establishing the four corners in relation to the dimension of the building floor plan
by pegging it.
vi. After establishing these four corners insert nails at the centre- top of each peg and
vii. Taking just one side measure the setback from back of fence to the end of building
lines in that particular angle, then come to the front and measure the setback also
viii. After this go back to the rear or you may use the front as a point mark depending
on which setback is more important to you. Measure the setback from fence
establish this two points with pegs then put a rope to cross both pegs and make
them form a right angle or 90 degrees. To determine if your rope are at right angle
put a checker popularly called ‘square’ by bricklayers, this will direct you if you
need to shift the other rope that can be varied since one is already fixed to form a
base mark (i.e. the rope running through two pegs from the rear to the front either
ix. After establishing a right angle, do your measurement to correspond with what is
on plan and then use the square at the other end to now establish the other two
15
½ ft behind your building line i.e. where blocks will actually pass through.
x. After this, nails peg at 3m interval round under the rope marking your building
line, then nail tie rods (flat thin wood) on top round the entire area.
xi. Establish each room measurement by nails ( you require four nails at each
measurement, two to establish the two sides of block you are going to place
later on then the other two at both ends to serve as the points where you will
excavate ,the length of this is usually three times the width of the block you are
using that is if you are using a 9“ block then expect to excavate or dig a trench of
27” wide.
xii. From the plan details, the width of excavation to be done is also marked by line
with pegs at appropriate positions. However the excavation width is then marked
xiii. The digging or excavated depth depends on the type of foundation as recommended
xv. After casting of foundation, use the nails on your profile board to determine where
your blocks will follow Set blocks, 3-4 or more coaches/courses and partitions in
xvii. Casting your ground floor slab or oversite concrete or German floor.
16
CHAPTER THREE
The elementary aids and equipment used for setting out are the following:
3. Ranging rods
4. Boning rods
5. Triangle sets
6. Cross staff
7. Optical square
8. Gradient template
Some of these equipment used for setting out method are explained with dimensions
i. Pegs: Are used to mark the alignment and/or the levels of the road. Usually, they
are made of wood. These pegs should have a length of approximately 40 cm and a
of the peg yellow or white so that it stays well visible even after a period of several
months. The chainage of the road will be marked on the reference peg (chainage
ii. Tape measure: A great variety of tape measures exist. The most common length
of tape measure used for setting out is 30 meters. The tapes are made of steel or
linen. Although the former is stronger, the numbers become illegible after a period
of use.
iii. Ranging rods: Are sticks usually 2.5-3.0 meters long with a diameter of
approximately 2.5 cm. They are made of various materials (metal, hard plastic or
wood) and are usually provided with a pointed metal end. Painted alternatively red
and white they are clearly visible. The length of the red/white sections varies: 25
cm, 30 cm or 50 cm.
iv. Boning rods: These are T-shaped and of a uniform height. They can be easily
wide on another lath of approximately 150 cm long and 10 cm wide so that the end
result looks like a "T". A simple stand can be manufactured so that the setting out
v. Triangle sets: These can be manufactured from three wooden laths to show
a. to set out a right angle to a centre-line (which has to be done when cross-
b. to control or estimate the steepness of gradients (in this case a spirit level or
The plan used for the setting out is shown in Figure 3.1 and the method is as follows:
After the site has been cleared by removing loose or vegetable soil, the following
i. First identify a reference point or reference line or base line according to the site
layout plan. This is a point where you position the first peg (first corner of the
ii. Establish the point or line considering the permanent structures and the relevant
distances to structural parts from them as given in the drawings. One side of the
house should run parallel to the boundary of the plot or an existing building.
iii. After establishing the base line, the main rectangle is set up using the pegs and
theodolite. Steel tape must be used to measure long distances and it must be tightly
stretched when taking the readings. Wooden pegs atop by a wire nail are driven to
establish the grid lines of the building. These pegs are driven at places such that
they won’t be disturbed by field work etc. Usually they are driven with a distance
iv. From the plan (fig 1), the centre line of the walls are calculated. Then the centre
lines of the rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose
the corner points are a, b, c, d, e, f and g which are marked by pegs with nails on
top.
v. The setting of the corner point is checked according to diagonals ac, bd, cf and eg.
19
the centre lines are extended and the centre points are marked about 2m away from
vii. Thus, the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre
line are shown clearly by stretching thread or rope. The centre points fixed 2m away
viii. From the plan details, the width of excavation to be done is also marked by thread
ix. The excavation width is then marked by lime or by with furrow with spade.
x. If the plan is much too complicated and follows a zigzag pattern, then the centre
3.3 Precautions
To prevent errors, the following are the different types of control that should be carried
out to prevent any errors during setting out building plan on ground:
On site control
Checks
To successfully set out the building, it is necessary to complete office works with great
accuracy. The drawing should be the latest version and if there are any changes in the
drawing, it should be checked whether it influences the work in the field or not.
It is required to examine and explore the quality of information, for example, the
dimensions should be checked and confirmed with structural dimensions to make sure
that it is realistic.
person who check the first computation may follow procedures and does not notice
errors. If a program is used to do calculations and solving problems, the user should
know the program well and have information that the software does work. The user
need to understand the results adequately otherwise unacceptable errors could occur.
22
It is required to check both primary baseline and bench marks to make sure that they
are accurate. Approximate setting out might be used for excavation but such work with
such quality cannot be accepted for concrete work which requires considerable
accuracy. It is advised to continuously check concrete benchmark station since they can
be damaged by excavations.
Also, it should be guaranteed that correct stations are used during working and this can
stations.
After accurate calculations at office are finished and good control is obtained at
staff to carry out the work and get the required accuracy.
It is recommended to do cross checks to specify any errors that have been made. For
example, when a rectangular shape is set out, diagonals should be computed prior to
Cross checks need to be used for completed works to examine their accuracy and find
out errors in the work if any exist. It is advised to begin setting out from the major
control lines and then proceed to other parts of the building to prevent accumulative
errors.
Also, it is recommended to establish secondary control points from the main control
point instead of using other secondary control points to set a new one. This is because
23
any error in one secondary control point would be repeated for other points and might
increase.
For example, one houses is set out, it is preferable to set each house from the main
control point rather than from another house since errors would cause considerable
issues. In this case, there might not be enough space for the last house to be set.
Use of common sense at the end of the works is the last check that should not be avoided
because great mistakes can be noticed and considerable cost could be saved.
It is recommended to use mark setting out using proper means to make it easy to
understand. The setting out would not serve any purpose if it cannot be understood by
user. The information provided on setting out should be adequate and the provision of
too much information needs to be avoided. It is advised to ask the person that will use
the setting out and find out what he wants about the work.
It is possible to use marks and expiations along the lines and on the wall unless it is a
finished surface. Regarding offsets, they should be sensible and proper dimensions shall
be used such as 1000mm. It may be required to explain the setting out by the individual
who carried out the work for a person who is going to use the setting out.
It is required to offset gridline from actual position to a new sight of line to keep the
account for size of columns and formworks. Figure 3.2 shows gridlines used for setting
out.
24
Errors in out of square taping would be insignificant if the offset is kept small to a
practical limit. In summary, no matter how offsets are established, it should not cause
errors at construction site. Regarding change in offsets, the variation should be obvious
Figure 3.2: Gridline and Offset line for building setting out
26
CHAPTER FOUR
CONCLUSION
Setting out must be done correctly before excavation starts because getting it wrong
could turn out to be expensive. Major responsibilities of setting out works lies with the
contractor as he is entitled to call upon the resident engineering to check that the setting
out is correct- although this does not prevent the contractor from being held responsible
for wall error which, even so, escape the notice of the resident engineer and the staff.
Setting out can be carried out on a virgin ground and as well on a german floor after the
casting had been done. But the most important thing to take note of is that is must be in
REFERENCES
How to Set Out a Building Plan on Ground with Procedure? – The Constructor
(2018). Retrieved from The Constructor - Civil Engineering Home
<https://theconstuctor.org/tips/setting-out-a-plan-on-ground/5897/>
Setting Out of Buildings – Archbaheez Blogspot (2016). Retrieved from Archbaheez
Blogspot : <https://archbaheez.blogspot.com/2016/09/setting-out-of-
buildings_21.html?m=1>
What is Setting Out/Stake out? – Civil Simplified (2016). Retrieved from Civil
Simplified – Civil Engineering Workshops and Projects:
<https://www.civilsimplified.com/resources/what-is-setting-out-stake-out>