1. Preliminaries particular
a. Project, Parties and consultants
Name, nature and location
General description of the works
Name and address of the Employer and consultants
b. Description of site
Boundaries of the site, means of access and position of the works
Existing drainage, water, gas and electrical services
Adjacent or abutting buildings
Facilities for visiting the site.
c. Drawings and other documents
List of drawing for bills of quantities
Address for drawing and others documents inspection.
2. Contract
a. Form, type and conditions of contract
Edition of standard CoC, Schedule of the clause headings, optional clauses applied
and any amendments to standard CoC.
Schedule of insertions or appendix to the CoC.
b. Contractor’s liability
Contractor’s liability for risk
I. 3rd party/Public liability Insurance,
II. Insurance of the Works,
III. Workmen’s compensations
c. Employer’s liability
The cost of insuring employer’s liability (if required to be included in the contract
sum) shall be given as a provisional sum.
Maintaining, adapting, clearing away and making good including any notices /permits and
fees for temporary building to statutory authorities if any shall be deem to be included with
the items.
1. Introduction
SMM menyediakan asas pengukuran yang seragam bagi kerja bangunan dan
melambangkan suatu aras amalan yang baik, Bagaimanapun maklumat yang lebih
terperinci (jika perlu) hendaklah diberikan untuk menentukan dengan lebih tepat
jenis dan takat kerja yang diperlukan.
2. Bills of Quantities
1. Senarai kuantiti perlu lengkap dan tepat mengambarkan kualiti dan kuantiti
kerja yang perlu dilaksanakan.
Kerja yang pasti perician kerjanya tetapi tidak dapat diukur, dinyatakan
sebagai Provisional (Kuantiti Sementara) atau sebagai Approximate
Quantities (Kuantiti Anggaran).