ID Task Mode Task Name Duration Start Finish Predecessors rter 2nd Quarter 3rd Quarter 4th Quarter

Duration Start Finish Predecessors rter 2nd Quarter 3rd Quarter 4th Quarter 1st Quar
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 CHAMPIONS PROJECT 180 days Mar 19 '18 Dec 13 '18
2 DESIGN SIMS PROJECT 170 days Mar 19 '18 Nov 29 '18
3 Desain kapasitas main steam header (HP dan LP) existing untuk memastikan desain  6 days Mar 19 '18 Mar 26 '18
110 120% d i k it b il
4 Collect data dan survei lokasi 1 day Mar 19 '18 Mar 19 '18
5 Membuat desain dan reporting 3 days Mar 20 '18 Mar 22 '18 4
6 Publish meeting Project 1 day Mar 23 '18 Mar 23 '18 5
7 Finalisasi dan Filing Hard copy/google drive 1 day Mar 26 '18 Mar 26 '18 6
8 Desain steam header diameter (HP dan LP), Strainer dan Safety valve 8 days Mar 27 '18 Apr 6 '18
9 Collect data dan survei lokasi 1 day Mar 27 '18 Mar 27 '18 7
10 Membuat desain dan reporting 5 days Mar 28 '18 Apr 4 '18 9
11 Publish meeting Project 1 day Apr 5 '18 Apr 5 '18 10
12 Finalisasi dan Filing Hard copy/google drive 1 day Apr 6 '18 Apr 6 '18 11
13 Investigasi untuk ketersediaan drain leg dan air vent pada bagian ujung pipa untuk  12 days Apr 9 '18 Apr 24 '18
k l h f t
14 Collect data dan survei lokasi 1 wk Apr 9 '18 Apr 13 '18 12
15 Membuat desain dan reporting 5 days Apr 16 '18 Apr 20 '18 14
16 Publish meeting Project 1 day Apr 23 '18 Apr 23 '18 15
17 Finalisasi dan Filing Hard copy/google drive 1 day Apr 24 '18 Apr 24 '18 16
18 investigasi dan desain : Jalur distribusi steam yang sudah dilengkapi dengan line drain  10 days Apr 25 '18 May 9 '18
d t d t t b t i t (I ti )
19 Collect data dan survei lokasi 3 days Apr 25 '18 Apr 27 '18 17
20 Membuat desain dan reporting 5 days Apr 30 '18 May 7 '18 19
21 Publish meeting Project 1 day May 8 '18 May 8 '18 20
22 Finalisasi dan Filing Hard copy/google drive 1 day May 9 '18 May 9 '18 21
23 Investigasi dan Desain : moisture separator dan strainer untuk PRDS ke proses 10 days May 11 '18 May 24 '18
24 Collect data dan survei lokasi 3 days May 11 '18 May 15 '18 22
25 Membuat desain dan reporting 5 days May 16 '18 May 22 '18 24
26 Publish meeting Project 1 day May 23 '18 May 23 '18 25
27 Finalisasi dan Filing Hard copy/google drive 1 day May 24 '18 May 24 '18 26
28 Case study : safety measure di economizer boiler baru bagaimana caranya agar jika  10 days May 25 '18 Jun 11 '18
t t t d ht i fl d di i tid k
29 Collect data dan survei lokasi 3 days May 25 '18 May 30 '18 27
30 Membuat review desain dan reporting 5 days May 31 '18 Jun 7 '18 29
31 Publish meeting Project 1 day Jun 8 '18 Jun 8 '18 30
32 Finalisasi dan Filing Hard copy/google drive 1 day Jun 11 '18 Jun 11 '18 31
33 Review : Raw Water Quality Standard: SDI <3 Microbiology tidak lagi dimonitor Kedua  10 days Jun 12 '18 Jul 2 '18
h lt b td t k lif ti b bi f li di d d
34 Collect data dan survei lokasi (koordinasi dengan team QA) 3 days Jun 12 '18 Jun 21 '18 32
35 Membuat review desain dan reporting 5 days Jun 22 '18 Jun 28 '18 34
36 Publish meeting Project 1 day Jun 29 '18 Jun 29 '18 35
37 Finalisasi dan Filing Hard copy/google drive 1 day Jul 2 '18 Jul 2 '18 36
38 Case study : Tinjauan HACCP untuk menyelesaikan masalah kontaminasi bakteri di  10 days Jul 3 '18 Jul 16 '18
t t k
39 Collect data dan survei lokasi (koordinasi dengan team QA) 3 days Jul 3 '18 Jul 5 '18 37
40 Membuat review desain dan reporting 5 days Jul 6 '18 Jul 12 '18 39
41 Publish meeting Project 1 day Jul 13 '18 Jul 13 '18 40

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SIMS Champions Actio
Milestone Inactive Summary Start-only Critical
Date: Mar 13 '18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task Mode Task Name Duration Start Finish Predecessors rter 2nd Quarter 3rd Quarter 4th Quarter 1st Quar
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
42 Finalisasi dan Filing Hard copy/google drive 1 day Jul 16 '18 Jul 16 '18 41
43 Review : Main steam flowmeter tidak akurat, sehingga steam mass balance tidak  10 days Jul 17 '18 Jul 30 '18
k t
44 Collect data dan survei lokasi 3 days Jul 17 '18 Jul 19 '18 42
45 Membuat review desain dan reporting 5 days Jul 20 '18 Jul 26 '18 44
46 Publish meeting Project 1 day Jul 27 '18 Jul 27 '18 45
47 Finalisasi dan Filing Hard copy/google drive 1 day Jul 30 '18 Jul 30 '18 46
48 Condensate Return System: ‐Temperature kondensat tidak dimonitor ‐Conductivity  10 days Jul 31 '18 Aug 13 '18
d t b l di it ( j t b il b )
49 Collect data dan survei lokasi 3 days Jul 31 '18 Aug 2 '18 47
50 Membuat review desain dan reporting 5 days Aug 3 '18 Aug 9 '18 49
51 Publish meeting Project 1 day Aug 10 '18 Aug 10 '18 50
52 Finalisasi dan Filing Hard copy/google drive 1 day Aug 13 '18 Aug 13 '18 51
53 Review dan pembuatan SOP : pengecekan m dan p alkalinity di demineralization. 12 days Aug 14 '18 Aug 31 '18
54 Collect data dan survei lokasi 1 wk Aug 14 '18 Aug 21 '18 52
55 Membuat review desain dan reporting + SOP 5 days Aug 23 '18 Aug 29 '18 54
56 Publish meeting Project 1 day Aug 30 '18 Aug 30 '18 55
57 Finalisasi dan Filing Hard copy/google drive 1 day Aug 31 '18 Aug 31 '18 56
58 Review dan pembuatan SOP : pengecekan silica dan silicate di sistem RO 10 days Sep 3 '18 Sep 17 '18
59 Collect data dan survei lokasi 3 days Sep 3 '18 Sep 5 '18 57
60 Membuat review desain dan reporting + SOP 5 days Sep 6 '18 Sep 13 '18 59
61 Publish meeting Project 1 day Sep 14 '18 Sep 14 '18 60
62 Finalisasi dan Filing Hard copy/google drive 1 day Sep 17 '18 Sep 17 '18 61
63 Review dan Pembuatan SOP : pengecekan TDS di cooling tower 10 days Sep 18 '18 Oct 1 '18
64 Collect data dan survei lokasi 3 days Sep 18 '18 Sep 20 '18 62
65 Membuat review desain dan reporting + SOP 5 days Sep 21 '18 Sep 27 '18 64
66 Publish meeting Project 1 day Sep 28 '18 Sep 28 '18 65
67 Finalisasi dan Filing Hard copy/google drive 1 day Oct 1 '18 Oct 1 '18 66
68 Case study : Efficiency boiler tidak dapat konsisten di angka 80% Cycle of  10 days Oct 2 '18 Oct 15 '18
C t ti B il ih 20 A ti ih t d t b ik t k
69 Collect data dan survei lokasi 3 days Oct 2 '18 Oct 4 '18 67
70 Membuat review desain dan reporting 5 days Oct 5 '18 Oct 11 '18 69
71 Publish meeting Project 1 day Oct 12 '18 Oct 12 '18 70
72 Finalisasi dan Filing Hard copy/google drive 1 day Oct 15 '18 Oct 15 '18 71
73 Case study : Steam turbine thermal efficiency hanya 24% dari best practice 40%  10 days Oct 16 '18 Oct 29 '18
dik k t bi i H l i i bi diti d kl j ti d l b t k i k t
74 Collect data dan survei lokasi 3 days Oct 16 '18 Oct 18 '18 72
75 Membuat review desain dan reporting 5 days Oct 19 '18 Oct 25 '18 74
76 Publish meeting Project 1 day Oct 26 '18 Oct 26 '18 75
77 Finalisasi dan Filing Hard copy/google drive 1 day Oct 29 '18 Oct 29 '18 76
78 Case study : Reverse Osmosis Permeate Recovery masih dibawah 80%. Lakukan analisa 12 days Oct 30 '18 Nov 14 '18
i d t il d h k t h d it h i 80%
79 Collect data dan survei lokasi 1 wk Oct 30 '18 Nov 5 '18 77
80 Membuat review desain dan reporting 5 days Nov 6 '18 Nov 12 '18 79
81 Publish meeting Project 1 day Nov 13 '18 Nov 13 '18 80
82 Finalisasi dan Filing Hard copy/google drive 1 day Nov 14 '18 Nov 14 '18 81

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SIMS Champions Actio
Milestone Inactive Summary Start-only Critical
Date: Mar 13 '18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
ID Task Mode Task Name Duration Start Finish Predecessors rter 2nd Quarter 3rd Quarter 4th Quarter 1st Quar
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
83 Case Study: Cycle of Concentration Cooling Tower turbin & wwtp belum pernah  10 days Nov 15 '18 Nov 29 '18
di it d tid k id B t P ti t d d 35 L k k li i
84 Collect data dan survei lokasi 3 days Nov 15 '18 Nov 19 '18 82
85 Membuat review desain dan reporting 5 days Nov 21 '18 Nov 27 '18 84
86 Publish meeting Project 1 day Nov 28 '18 Nov 28 '18 85
87 Finalisasi dan Filing Hard copy/google drive 1 day Nov 29 '18 Nov 29 '18 86
88 INSTALL / ERECTION SIMS PROJECT 157 days Apr 2 '18 Nov 23 '18
89 Install : Penambahan sampling facility (plus cooler) untuk sample kualitas steam. Hal  50 days Apr 2 '18 Jun 21 '18
i i ti t k it k lit t d hk k d bl d
90 Pembuatan PR/PQ team project 2 days Apr 2 '18 Apr 3 '18
91 Pencarian Vendor oleh Purchasing 3 days Apr 4 '18 Apr 6 '18 90
92 Collect data dan survei lokasi oleh vendor 3 days Apr 9 '18 Apr 11 '18 91
93 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 5 days Apr 12 '18 Apr 18 '18 92
94 Tender 1 wk Apr 19 '18 Apr 25 '18 93
95 Negotion oleh purcahing 4 days Apr 26 '18 May 2 '18 94
96 PO for execution 1 wk May 3 '18 May 9 '18 95
97 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 1 mon May 11 '18 Jun 11 '18 96
98 Closing project 3 days Jun 12 '18 Jun 21 '18 97
99 Install Hidrant water spraying system di area coal handling 70 days Apr 9 '18 Jul 26 '18
100 Pembuatan PR/PQ team project 2 days Apr 9 '18 Apr 10 '18 90FS+3 days
101 Pencarian Vendor oleh Purchasing 3 days Apr 11 '18 Apr 13 '18 100
102 Collect data dan survei lokasi oleh vendor 3 days Apr 16 '18 Apr 18 '18 101
103 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 5 days Apr 19 '18 Apr 25 '18 102
104 Tender 1 wk Apr 26 '18 May 3 '18 103
105 Negotion oleh purcahing 4 days May 4 '18 May 9 '18 104
106 PO for execution 1 wk May 11 '18 May 17 '18 105
107 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 2 mons May 18 '18 Jul 23 '18 106
108 Closing project 3 days Jul 24 '18 Jul 26 '18 107
109 Install flow meter pada Jalur steam ke deaerator 92 days Apr 16 '18 Sep 5 '18
110 Pembuatan PR/PQ team project 2 days Apr 16 '18 Apr 17 '18 100FS+3 days
111 Pencarian Vendor oleh Purchasing 1 wk Apr 18 '18 Apr 24 '18 110
112 Collect data dan survei lokasi oleh vendor 3 days Apr 25 '18 Apr 27 '18 111
113 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 5 days Apr 30 '18 May 7 '18 112
114 Tender 1 wk May 8 '18 May 15 '18 113
115 Negotion oleh purcahing 4 days May 16 '18 May 21 '18 114
116 PO for execution 1 wk May 22 '18 May 28 '18 115
117 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 3 mons May 30 '18 Aug 31 '18 116
118 Closing project 3 days Sep 3 '18 Sep 5 '18 117
119 Install sampling cooler untuk sampling point inlet water ke feed water tank. 53 days Sep 6 '18 Nov 21 '18
120 Pembuatan PR/PQ team project 2 days Sep 6 '18 Sep 7 '18 118
121 Pencarian Vendor oleh Purchasing 1 wk Sep 10 '18 Sep 17 '18 120
122 Collect data dan survei lokasi oleh vendor 3 days Sep 18 '18 Sep 20 '18 121
123 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 5 days Sep 21 '18 Sep 27 '18 122

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SIMS Champions Actio
Milestone Inactive Summary Start-only Critical
Date: Mar 13 '18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 3
ID Task Mode Task Name Duration Start Finish Predecessors rter 2nd Quarter 3rd Quarter 4th Quarter 1st Quar
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
124 Tender 1 wk Sep 28 '18 Oct 4 '18 123
125 Negotion oleh purcahing 1 wk Oct 5 '18 Oct 11 '18 124
126 PO for execution 1 wk Oct 12 '18 Oct 18 '18 125
127 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 1 mon Oct 19 '18 Nov 15 '18 126
128 Closing project 3 days Nov 16 '18 Nov 21 '18 127
129 Install cooling tower water basin indicator untuk continuous monitoring 53 days Sep 10 '18 Nov 23 '18
130 Pembuatan PR/PQ team project 2 days Sep 10 '18 Sep 12 '18 120
131 Pencarian Vendor oleh Purchasing 1 wk Sep 13 '18 Sep 19 '18 130
132 Collect data dan survei lokasi oleh vendor 3 days Sep 20 '18 Sep 24 '18 131
133 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 5 days Sep 25 '18 Oct 1 '18 132
134 Tender 1 wk Oct 2 '18 Oct 8 '18 133
135 Negotion oleh purcahing 1 wk Oct 9 '18 Oct 15 '18 134
136 PO for execution 1 wk Oct 16 '18 Oct 22 '18 135
137 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 1 mon Oct 23 '18 Nov 19 '18 136
138 Closing project 3 days Nov 21 '18 Nov 23 '18 137
139 IMPROVEMENT PPU PROJECT 62 days Sep 18 '18 Dec 13 '18
140 Review, Desain & Install : Spraying water untuk mengurangi dampak debu area coal  25 days Sep 18 '18 Oct 22 '18
h dli (Si l d i )
141 Pembuatan PR/PQ team project 2 days Sep 18 '18 Sep 19 '18 130FS+3 days
142 Pencarian Vendor oleh Purchasing 2 days Sep 20 '18 Sep 21 '18 141
143 Collect data dan survei lokasi oleh vendor 1 day Sep 24 '18 Sep 24 '18 142
144 General proposal + Detail Engineering, desain report, detail price + BoQ diterima AF 3 days Sep 25 '18 Sep 27 '18 143
145 Negotion oleh purcahing 2 days Sep 28 '18 Oct 1 '18 144
146 PO for execution 1 wk Oct 2 '18 Oct 8 '18 145
147 Purchase + Fabricaton + Installation + Test Commissioning oleh vendor 2 wks Oct 9 '18 Oct 22 '18 146
148 Review dan desain : Magnet sparator sering sobek, dan sering kelolosan besi 10 days Nov 30 '18 Dec 13 '18
149 Collect data dan survei lokasi 3 days Nov 30 '18 Dec 4 '18 87
150 Membuat review desain dan reporting 5 days Dec 5 '18 Dec 11 '18 149
151 Publish meeting Project 1 day Dec 12 '18 Dec 12 '18 150
152 Finalisasi dan Filing Hard copy/google drive 1 day Dec 13 '18 Dec 13 '18 151

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SIMS Champions Actio
Milestone Inactive Summary Start-only Critical
Date: Mar 13 '18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 4

Вам также может понравиться