QUESTION 1

1.1 Delivery invoice (1)


1.2 Storekeeper/store clerk (1)
1.3 Buying department (1)
1.4 Fine and theft (1)
1.5 Care (1)
1.6 Works (1)
1.7 Moisture (1)
1.8 Are toxic (1)
1.9 Fragile (1)
1.10 Damage/theft (1)
[10]
QUESTION 2
General site meeting to be held at place at time. (1)
1. Welcome – introduction (1)
2. Apologies for absence (1)
3. Attendance register (1)
4. Minutes (1)
5. Matters arising from minutes (1)
6. Main business (1)
6.1 General problem areas
6.2 Variations
6.3 Progress
6.4 Sub-contractor
6.5 Nominated sub-contractor
6.6 Local authorities
7. General (1)
8. Date for next meeting (1)
9. Closing (1)
[10]

QUESTION 3

DHET Exam Centre # 0899992801


City & Guilds Centre Gauteng # 848506
QCTO Accreditation # WC NATED/ 15/0190
City & Guilds Centre Western Cape # 848506A
QCTO Accreditation # Gauteng NATED/ 14/0067
ISO 9001:2008 Certification # FS 639700
DHET Distance Learning Exam Centre # 1199995013
3.1 (5)

3.2 A = ½ × 5[ (30 + 20) + 2 ( 33 +30 + 38 + 30 + 18 + 11 + 18 ) ] (2)


= ½ × 5[ (50) + (178 ) ]
= ½ × 5[ 50 + 356 ]
= 5 × 406
= 1015m
3.3 A = 1/3 × 5 [(30 + 20) + 2 (30 + 30 + 11) + 4 (33 + 38 + 18 + 18)] (2)
= 1/3 × 5[(50 ) + 2 (71) + 4 107)]
= 1/3 × 5[50 + 142 + 428]
= 5 × 620
= 1 033,33 m
3.4 (1)
[10]

QUESTION 4
4.1 The time period between the early start or finish of one activity and (2)
the early start or finish of another in the sequential chain is called lag.

DHET Exam Centre # 0899992801


City & Guilds Centre Gauteng # 848506
QCTO Accreditation # WC NATED/ 15/0190
City & Guilds Centre Western Cape # 848506A
QCTO Accreditation # Gauteng NATED/ 14/0067
ISO 9001:2008 Certification # FS 639700
DHET Distance Learning Exam Centre # 1199995013
4.2 Backward pass begin at the client's end date where the forward pass (2)
end

4.3 Forward pass through network, we work from left to right beginning at (2)
the client's start date.
4.4 Fast tracking a project means that activity that are normally done in (2)
series are done in parallel.

4.5 The time differential between the schedule completion date and the (2)
required date to meet critical path is referred to as the slack time
[10]

QUESTION 5
5.1 CONTRACT DOCUMENTS (10)
 Drawings
 Specifications
 Bills of quantities
 Principal building agreement
 (Conditions of contract/ schedule of conditions)
Drawings
 is the basis of the contract and communicates the overall form
and intentions of the architect
Specifications
 supplement drawings by specifying description that cannot
accurately be presented on the drawing
Bills of quantities
 extraction of material & labour of drawings and specifications
Principal Building Agreement
 Explains and refers to above documents, how to be used.

5.2 Written information/guidance, binding for both parties (2)

DHET Exam Centre # 0899992801


City & Guilds Centre Gauteng # 848506
QCTO Accreditation # WC NATED/ 15/0190
City & Guilds Centre Western Cape # 848506A
QCTO Accreditation # Gauteng NATED/ 14/0067
ISO 9001:2008 Certification # FS 639700
DHET Distance Learning Exam Centre # 1199995013
5.3 (10)

[20]

QUESTION 6
6.1 LIABILITY INSURANCE (2)
The responsibility to ensure the building and people shifts immediately
with handing over back from the contractor to the employer.
6.2 LATENT DEFECTS LIABILITY (2)
Some error can only be detected after a certain time, e.g. a leaking
roof. A clause keeps the contractor a while responsible (5 years after
commencement of the work) after handing over to repair it.
6.3 PATENT DEFECTS LIABILITY PERIOD (2)
The period after practical completion (after handing over) where in the
contract has to repair all defects.
6.4 RELEASE OF CONSTRUCTION GUARANTEE (2)
When all defects re repaired, the guarantee with the contractor lapses
6.5 PENALTY FOR NON-COMPLETION (2)
An amount of money which the contractor has to pay a day to the
employer in case he cannot hand over the work within the tender
period
[10]

DHET Exam Centre # 0899992801


City & Guilds Centre Gauteng # 848506
QCTO Accreditation # WC NATED/ 15/0190
City & Guilds Centre Western Cape # 848506A
QCTO Accreditation # Gauteng NATED/ 14/0067
ISO 9001:2008 Certification # FS 639700
DHET Distance Learning Exam Centre # 1199995013