Sulut-3 Coal Fired Steam Power Plant Project (2x50MW)

ID Name Duration Start Finish


2019
2018 2019 2020 2021
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Critical: Yes 1066d Thu 5/10/18 Fri 4/9/21 Critical: Yes
46 plant basic design 68 days Sun 9/9/18 Thu 11/15/18
953 soil investigation(onshore) 142 days Thu 5/10/18 Fri 9/28/18
1018 Foundation excavation 13 days Sat 5/4/19 Thu 5/16/19
1025 Foundation excavation 13 days Wed 7/3/19 Mon 7/15/19
1039 Foundation excavation 13 days Wed 7/3/19 Mon 7/15/19
1040 Cushion concrete pouring 7 days Tue 7/16/19 Mon 7/22/19
1041 Foundation concrete pouring 90 days Tue 7/23/19 Sun 10/20/19
1043 Backfill 10 days Mon 10/21/19 Wed 10/30/19
1304 unit 2 boiler steel structure erecion 110 days Sat 11/30/19 Wed 3/18/20
1305 unit 2 boiler steel heating surface 120 days Thu 3/19/20 Thu 7/16/20
1307 unit 2 boiler hydrostatic test 25 days Fri 7/17/20 Mon 8/10/20
1308 unit 2 boiler refratory 30 days Tue 8/11/20 Wed 9/9/20
1309 unit 2 dry-off over and acid cleaning 10 days Thu 9/10/20 Sat 9/19/20
1310 unit 2 subsystem trial operation 19 days Sun 9/20/20 Thu 10/8/20
1311 unit 2 Boiler first light up, oven 20 days Fri 10/9/20 Wed 10/28/20
1312 unit 2 Boiler steam blowing 20 days Thu 10/29/20 Tue 11/17/20
1313 unit 2 System restore 20 days Wed 11/18/20 Mon 12/7/20
1314 unit 2 Initial synchronization 33 days Tue 12/8/20 Sat 1/9/21
1384 unit 2 Pass the reliable run 90 days Sun 1/10/21 Fri 4/9/21
1385 unit 2 Commercial operation date (Plant COD)0 days Fri 4/9/21 Fri 4/9/21 4/9