TOILET
SUPERVISOR RUANG
ROOM UPS
KONSTRUKSI
SATELLITE OFFICE AREA
PEMBUATAN SALURAN AIR PERAPIHAN VALVE CHAMBER PEMASANGAN JOINT SEALENT RIGID
DI SISI SELATAN SO BUILDING AREA SO BUILDING AREA SO BUILDING (ON PROGRESS)
KONSTRUKSI
AREA CARGO : BLOCK OUT & WELDING FLANGE PIPE 6 INCH
PEMANCANGAN CSP DI VC 35 :
SEMENTARA WAKTU DITUNDA KARENA TITIK VC 35 JUGA VC 36
DEKAT DENGAN AREA PEMASANGAN TIANG LISTRIK OLEH ADHI
KARYA
PETA PROGRESS AREA CARGO)
288 287 286 285 284 283 282 281 280 279 278 277 276 275 274 273
Stringging 26 Pipa
Stringging 12 20”
Pipa 20”
Pengelasan = 22 / 24 joint
Pengelasan = 2 /10 joint Area VC 34 :
HSS = 22 / 24 joint • pengecoran dinding VC 34
= 159,39 m3 (100 %)
KETERANGAN :
1. Limestone: PROGRESS CARGO,
• AREA CARGO, PIPA 6” :
2. Basecourse : - Lowering = 16 / 16 line - Basecourse = 16 /16 line
- Urugan Pasir = 16 /16 line - CTBC = 16 / 16 line
3. CTBC :
4. Backfill Tanah :
Page 10
AREA AVSEC / PUMPING
KONSTRUKSI
TEST PIT AREA MICROTUNNELING 2 GALIAN LUBANG ENTRY PIT PERSIAPAN BESI UNTUK PEMASANGAN
CROSSING REL KAI MICROTUNNELING 2 TURAP MICROTUNNELING 2
- 8 Pipa
- 6 joint
- 6 HSS
Area Auger
Boring
Page 12
AREA DPPU KONSTRUKSI
INSTALASI SPOOL & FLANGE
PENGELASAN SPOOL PENGELASAN SPOOL PENGELASAN SPOOL
& FLANGE & FLANGE & FLANGE
KETERANGAN :
1. Pipeline 20” =
2. Backfill Pipa 20”
=
KETERANGAN :
1. Pipeline 20” =
2. Backfill Pipa 20”
=
3. Stripping tanah
=
- 10 Pipa
- 8 joint
- 8 HSS
AREA PIPE
- 4 Pipa BRIDGE - Stringging Pipa = 22 pipa
- 2 joint - Pengelasan = 20 / 20 joint
- 2 HSS - HSS = 20 / 20 joint
- BACKFILL = 22 / 22 PIPA
PETA PROGRESS AREA MASJID GMF
AREA VC 32
PEMASANGAN BESI
AREA VC 32 PEMBESIAN TAHAP 3 VC 32
PEMINGGANG
PROGRESS AREA VC 32 :
• Pemasangan Bekisting VC 32 = 22 / 66 m2 (BARU TAHAP 1)
• Pengecoran Dinding VC 32 (tebal = 35 cm) = 7,7 / 23,1 m3 (BARU TAHAP 1)
• Pembesian TAHAP 2 dari 3 CLOSED
PETA PROGRESS AREA GMF
PIPELINE 20” DI AREA BEKAS HDD BORING 1
GALIAN SSP
di VC 32 (CLOSED)
ENTRY PIT
PILOT BORING (310 M = 1 LINE) PILOT BORING (310 M = 1 LINE) PILOT BORING (310 M = 1 LINE
EXIT PIT
PIPA STOCKYARD DI AREA PROGRESS HDD BORING 2 :
EXIT PIT 1 EXIT PIT 2 EXIT PIT HDD BORING 2 1 line = 310 m
2 line = 620 m
• LINE 1 = SUDAH TAHAP REAMING 12
• LINE 2 = TAHAP PILOT BORING 310 m
• Bobokan Aspal untuk persiapan Exit
Pit = 2 titik (CLOSED)
• Tranfer Pipa 20” ke Area Exit Pit HDD
Boring 2 = 65 pipa (CLOSED)
KONSTRUKSI
ELECTRICAL
KETERANGAN :
TARIKAN KABEL NEW OFFICE 1. Test Pit Total SUDH 104 titik
2. Penyambungan Pipa HDPE 2” = 9/12 titik
(ON PROGRESS)
3. Tarikan Kabel New Office = 30 / 39 titik
4. 1 LAMPU SUDAH DI TES PENYALAAN
5. PEMASANGAN STOP KONTAK
PEMASANGAN STOP KONTAK NEW OFFICE LAMPU GUARD POST NEW OFFICE LAMPU BAGIAN DALAM NEW OFFICE
KONSTRUKSI
AREA SEMANGGI UTARA
HDD BORING
PERSIAPAN HDD BORING PERSIAPAN HDD BORING
@SEMANGGI SELATAN @SEMANGGI SELATAN
VC 36 VC 35 VC 34
Ket :
OPEN CUT =
Auger Boring =
HDD Boring =
Valve Chamber = VC 33
VC 28
VC 31 VC 29
VC 32
VC 30
Page 28
LAYOUT PROGRESS PIPA & VALVE CHAMBER AREA M1M2 &
CARGO INTERNATIONAL
PEMANCANGAN
VC 35
Ket :
OPEN CUT =
HDD Boring =
PEMANCANGAN
VC 33
PEMANCANGAN
VC 32
Page 29
TERIMA KASIH