Академический Документы
Профессиональный Документы
Культура Документы
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 1/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Performing
Performing power
power factor
factor test
test on
on dry-type
dry-type transformer
transformer during
during commissioning
commissioning (photo
(photo credit:
credit:
sgb-smit.com)
sgb-smit.com)
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 2/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Figure
Figure 11 –– Insulation
Insulation System
System Equivalent
Equivalent Circuit
Circuit and
and Power
Power Factor
Factor Vector
Vector Diagram
Diagram
Watts = E × IT × Cosine Ө
Power factor = Cosine Ө = Watts / (E × IT)
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 3/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Other test names synonymous with the power factor test are
dielectric loss angle, dissipation factor test, tan delta or
doble test.
1. The unit must be de-energized and isolated from the power system
including the neutral connection from ground.
2. Transformer enclosure must be properly grounded and applicable to
when testing spare units.
3. All terminal of each winding are short-circuited together including the
neutral terminals. This will minimize the effect of winding inductance
during testing.
4. Load tap changer (LTC) should be set of neutral if it has arrester-type
elements that are not effectively short circuited in the neutral position.
The power factor test typically applies a test voltage less than the stress
working levels of the equipment. Refer to Table 1.
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 4/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
The required tests are noted in Table 2 and its connection is shown in
Figure 2 and Figure 3. The difference between the high voltage winding
tests and the low voltage winding tests are the placement of the test leads
and the test voltage levels. Test 3 and test 8 of Table 2 should generate
the same value as they both measure the same capacitance between the
windings.
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 5/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Test number Test mode Energized winding Ground Guard UST Measure
1 GST High Low – – CH+CHL
2 GST High – Low – CH
3 UST High – – Low CHL
4 Calculate Test 1 minus Test 2 CHL
5 GST Low High – – CL+CHL
6 GST Low – High – CL
7 UST Low – – High CHL
8 Calculate Test 5 minus Test 6 CHL
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 6/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Figure
Figure 22 –– Power
Power Factor
Factor High
High Voltage
Voltage Winding
Winding Test
Test Connection
Connection
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 7/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
8. Confirm capacitance value from GST test minus Guard test equal
UST test
Figure
Figure 33 –– Power
Power Factor
Factor Low
Low Voltage
Voltage Winding
Winding Test
Test Connection
Connection
Caution //
Always ground to the previously energized terminal with a
grounding stick before making any connection changes to
bleed off any electrical charge that may be present. Leave
the grounding connected until connection changes is completed
and before the start of the next test.
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 8/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 9/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 10/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 11/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 12/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
Edvard Csanyi
Electrical engineer, programmer and founder of EEP. Highly specialized for
design of LV/MV switchgears and LV high power busbar trunking (<6300A)
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 13/14
12/25/2018 Performing power factor test on dry-type transformer during commissioning | EEP
https://electrical-engineering-portal.com/dry-type-transformer-power-factor-test 14/14