Вы находитесь на странице: 1из 28

<< Back

n°155
MV public distribution
networks throughout
the world

Christian Puret

A graduate Engineer from the


E.N.S.E.R.G. (Institut National
Polytechnique de Grenoble) and the
I.A.E. in Paris, he joined Merlin Gerin
in 1977.
His first assignment gave him
expertise in the field of
programmable logic controllers.
He was then put in charge of
customer training for the
Merlin Gerin Group.
In 1986, he rejoined the Medium
Voltage Division in which he now
holds a position involving strategic
marketing. He is in charge of
integration of developments in
protection systems and telecontrol
in MV equipment, and more
specifically in those destined for
public distribution networks.

E/CT 155 first published March 1992


glossary
Configuration : an operation, in both Cut-out type fuse : MV striker-type Sectionaliser : MV switch equipped
digital protection and telecontrol fuse, that performs the two functions of with a fault passage counter, it is
systems, that involves assigning, via protection and isolation. Isolation installed downstream of a MV
either a built-in or a loaded software occurs when the fuse melts by ejection overhead feeder protected by a
package, a standard piece of of the striker which in turn automatically recloser. Its automatic control counts
equipment to a specific application. triggers switch-over of the fuse the number of fault current passages
The latter operation, loading a software cartridge. (corresponding to the number of times
package, is carried out using a tool : the recloser is activated), and when a
Fault passage indicator : a device
the configurator, normally a personal preset number has been reached it
fitted to MV networks that indicates,
computer PC. This allows for example: opens the circuit breaker. Selectivity
fault passage either locally or at a
■ definition of functions that the can thus be obtained by installing
distance. In order to improve quality of
equipment will perform, several sectionalisers in series on a
service, the operating company makes
■ devising of connections with the MV feeder, the last sectionaliser
every effort to reduce the interruption in (which is furthest from the recloser)
environment,
supply to that part of the network in opening on the second instance of
■ creation of mimic diagrams and
which the fault exists. To achieve this current fault, the preceding
labelling of alarms for users.
they must know which portion of the sectionaliser opening on the third
Draw-out (part of an assembly) network is affected by the fault. With occasion and so on. This device is
(IEC 50 - chapter 441, NF C 01- 441) : this aim, the operating company installs used in North-American type
withdrawable part of an assembly that, fault passage indicators. Analysis of the distribution networks.
whilst remaining mechanically attached information provided enables the faulty
to the assembly, can be moved to the area to be closed off, followed by
position or one of the positions that reconfiguration of the network (typical
gives an insulating distance or a metal remote control application)
separation between open contacts.
This insulating distance or metal Prediction : a new science with the
separation always intervenes in the objective of event prediction, it is based
main circuit. It may or may not also on reasoning and scientific deduction.
intervene in auxiliary circuits. Recloser : MV circuit breaker
Fixed (fixed device), incorporating a multishot autoclosing
(IEC dictionary of electricity) : relay, installed on an overhead MV
a device that is designed to be feeder and coordinated with protection
mounted on a fixed support and devices (fuses) placed on the feeder
intended to be connected to external (upstream and downstream). It is used
circuits using fixed electrical in North-American type distribution
conductors. networks.

Cahier Technique Merlin Gerin n° 155 / p. 2


MV public distribution networks In a country, the Transmission and
Public Distribution networks ensure the
throughout the world transfer of electrical energy from points
of production to consumer units.
The points of production are power
stations that generate electrical energy
from various primary energy sources
(nuclear, hydro-electric, coal....)
The points of consumption in
MV - Medium Voltage -, are
table of contents substations, from which the energy is
delivered to customers (subscribers).
This takes place via the “MV
1. Different types of electrical The transmission and p. 4 distribution system “wich is the object of
networks interconnection network this “Cahier Technique“ report.
The subtransmission network p. 5 In this “Cahier Technique“ report, after
The MV network p. 5 having described the various types of
The LV network p. 6 distribution networks and the
distributor’s role, the reader who is not
Type of electric current p. 6
familiar with MV will find details on:
Network planning p. 6 ■ topologies of MV networks,
2. The distributor Reason of existence p. 7 ■ substations,
His role p. 7 ■ protection and telecontrol devices.

His development p. 8 Comment: In this “Cahier Technique“


3. MV network topologies Criteria in choosing a topology p. 10 report, the term MV applies to any
voltage from a few kV to 40 kV.
Items that depend on p. 10
the chosen topology
Various MV network layouts p. 10
Neutral earthing layouts p. 12
Protection system p. 13
Telecontrol system p. 14
4. MV Public distribution Substations on MV networks p. 15
Other MV installations p. 16
MV switchgear p. 16
French and p. 18
North-American layouts
5. Protection and control MV protection device technology p. 20
of MV networks Electromagnetic compatibility p. 21
MV control applications p. 21
MV telecontrol architectures p. 23
Communications networks p. 24
6. Conclusion p. 25
Appendix 1: some MV product standards p. 26
Appendix 2: various selectivity techniques p. 26
Appendix 3: EDF architecture and Merlin Gerin equipment p. 27
Appendix 4: references p. 28

Cahier Technique Merlin Gerin n° 155 / p. 3


1. different types of electrical networks

Producing electrical current in power corresponding voltage levels can be the transmission and
stations is not enough in itself, it must different from country to country.
also be brought to the end-user. However, in general the number of
interconnection network
In order to link production and voltage levels is limited to three; indeed The geographical distance between
consumption, which in turn can be in 1983 the IEC publication 38 production sites and consumer centres,
translated into financial benefit, a formulated recommendations for the irregularity of consumption and the
country’s electrical structure is voltage levels for 50 and 60 Hz impossibility of storing electrical energy
generally broken down into several networks. create the need for an electrical
levels that correspond to different types However, in order to gain better network that is capable of directing and
of electrical networks. (see fig. 1). understanding of this split, the following transmitting it across large distances.
It should be noted that there is no paragraphs present each grid with: These lines can stretch across
standard structure that exists ■ its object, thousands of kilometers , for
worldwide, and that the split into ■ its voltage level, example in the French network there
several networks with their ■ its structure. exists 20 000 km.

fig. 1: illustrated layout of an electrical network showing that electricity is produced, carried and distributed at various voltage levels.

Cahier Technique Merlin Gerin n° 155 / p. 4


The object of this network is threefold: the subtransmission the MV network
■ a "transmission" function with the aim
of carrying electricity from producing
network This level of a country’s electrical
The object of this network is essentially structure will be covered in more detail
power stations to the main consumer
to carry electricity from the transmission in the chapters that follow. Thus, here
zones;
network to the main consumer centres. we only give a few distinguishing
■ a "national interconnection" function
features.
that manages the product distribution These consumer centres are:
by relating the production to the ■ either from the public sector with The object of this network is to carry
geographical and time-dependant access to the MV network, electricity from the subtransmission
nature of demand; ■ or from the private sector with access network to points of medium
■ an "international interconnection" to high-consumption customer (greater consumption (greater than 250 KVA
function - that manages energy flux than = 10 MVA) supplied directly in France).
between countries dependant on with HV. In any country the number of These consumer points are:
programmed exchanges or as back-up. such consumers is very small (e.g. 600 ■ either in the public sector, with
In general only very few customers with in France). They are essentially access to MV/LV public distribution
a high consumption are connected to industries such as iron and steel, substations,
these networks. cement, chemicals, rail transport,.... ■ or in the private sector, with access to

The structure of these networks is delivery substations for medium


These networks are essentially of
generally of overhead type (sometimes consumption users. The number of
overhead type structure.
underground near urban areas). In this these customers (e.g. 160 000 in
The voltages are normally between 225 France) is only a small proportion of the
respect environmental concerns (care
and 400 kV, and sometimes 800 kV total number of customers supplied
for the environment and protection of
(e.g.: 765 kV in South Africa). Use of directly with LV. They are essentially
certain natural sites) are often raised in
such high voltages is tied in with cost from the tertiary sector, such as
opposition to the construction of lines.
saving objectives. Indeed for a given hospitals, administrative buildings,
As a result it is more and more difficult
power, the line losses by Joule effect small industries,...
and expensive for subtransmission
are inversely proportional to the square
networks to reach high population The structure is of overhead or
of the voltage:
density areas. underground type.
p = k/U2, with
U= network voltage, Voltage in these networks is between Voltage in these networks ranges from
k = constant - dependant on the line. 25 kV and 275 kV. a few to 40 kV (see fig. 2).
In addition the transmitted power The protection systems are of the same Operation of these networks, can be
values are such that using low voltages kind as those for transmission carried out manually or, more
would require totally unrealistic cable networks, the control centres being frequently, by remote control from fixed/
cross-sections. Use of high voltages is regional. mobile control centres. However, in
thus imposed in spite of the drawbacks order to account of specific needs for
involved in higher equipment insulation
costs, the easiest solution being the
use of overhead lines. % 100
5 2 5 5
In any case, the choice of transmission
90
voltage is above all a technico-economic
one, dependant on the power to be 80
transmitted and the distances to be
covered. 70
60
70 80
The safety aspect is fundamental for 60
these networks. Indeed any fault at this 50
level leads to important supply failures 95 95
for all consumer units. In 1965 in the 40
United States, 30 million people were
30
without electricity for 12 hours due to
such a fault. 20
35 25 10
These networks’ protection systems 10
must be very high-performance. As for 10
3
their operation on a national level, this
Belgium France Great Britain Italy Japan
is the task of a control centre from
which the electrical energy is
permanently monitored and managed. < 12 kV 12 < U < 17 kV 17 < U < 24 kV > 24 kV
fig. 2: proportion of various voltage levels within national MV networks as a function of the
lengths of lines of each country.

Cahier Technique Merlin Gerin n° 155 / p. 5


control of MV networks, these control type of electric current network planning
centres are different to those used on
Energy transmission on these various The installation and evolution of the
transmission and subtransmission grid.
networks is accomplished using electric structure of an electrical supply network
The number and the geographical
current. for a country corresponds to planning
dispersion of remote control units, the
Direct current or HVDC (high voltage operations.
management of several simultaneous
control centres, the number and level of direct current) links are used for For transmission and subtransmission,
qualifications of the operators all exchanges between countries these operations are generally
require appropriate solutions: exclusively on a transmission network centralised, since:
ergonomics and user-friendly type work level. The choice of this technique ■ the decisions leading to a
stations, control assistance tools, enables optimization of the use of modification in the structure of such
control centre configuration tools, and transmission cables, particularly by networks, for example the introduction
management of the various cancelling the "skin" effect. Such of a new MV/LV substation, requires to
transmission devices that are used. intercontinental and even continental take into account numerous technical
links exist, for example a link between and economical parameters;
Italy and Sardinia via Corsica (300 MW/ ■ the number of these parameters
the LV network 200 kV). involved and their possible interactions
The object of this network is to carry In other cases, particularly public MV means that help from computerized
electricity from the MV network to networks, links are through alternating tools is required, such as use of a data-
points of low consumption (less than current. Indeed, in these networks, the base and of expert systems.
250 KVA in France) in the public sector use of direct current would not be For MV and LV networks, the planning
with access to LV customers. profitable: is, however, often decentralized.
It represents the final level in an ■ losses reduced on short networks
electrical structure. (less than 100 km),
This network enables supply to a very ■ equipment made more expensive
large number of consumers (26 million (requirement of numerous direct/
in France) corresponding to the alternating converters).
domestic sector. In addition, alternating current is very
Its structure, whether overhead or well adapted to voltage changes
underground is often influenced by the (transformers) in the course of its
environment. transmission as electrical energy.
Voltages in these networks are With very few exceptions (Saudi
between 100 and 440 V. Arabia), and outside of the American
continent where 60 hertz is used
Such networks are often operated
throughout, the current frequency
manually.
is 50 hertz.
Of particular note is the case of Japan
where half of the country is on 60 hertz,
and the other half on 50 hertz.

Cahier Technique Merlin Gerin n° 155 / p. 6


2. the distributor

reason of existance: The role of the MV distributor is not transmission and distribution; it
clear-cut: it often covers LV - Low manages around 80% of the electricity
to supply electricity Voltage - distribution and in some distributed in Italy.
The electrical energy distributors exist cases he is also in charge of ■ in France the situation is similar with
to supply electrical energy to transmission, for example: the E.D.F.
consumers taking into account several
■ in Japan, nine regional private
objectives such as:
companies are each responsible for the
■ continuity and quality of service,
production, transmission and
■ safety of people and goods, transformers
distribution for their area, = 5% MV switchgear
■ flexibility and ease of operation,
■ in Germany around a thousand = 5%
■ commercial competitiveness.
companies are involved in the
distribution of electricity. Around 1/3
his role have their own production facilities.
If electricity supply is satisfactory in ■ in Great Britain production is the
industrialized countries, the degree of responsibility of two companies (NP -
electrification still remains variable in National Power - and PG - Power Gen).
certain other countries. The NGC (National Grid Company) are
Varying objectives depending on the in charge of transmission, and the
degree of electrification... regional distribution is looked after by
For countries that are not 100% around twelve Regional Electricity
electrified, the priority objective remains Companies. This structure is a result of lines
a privatisation bill for British distributors + poles
the improvement of this degree of + total installation
electrification. To this end, investment voted in 1990.
= 90%
is mostly in construction of networks ■ in Italy a law founded the E.N.E.L. in
and installations (see fig. 3). 1962. This is a public service fig. 3: break-down of costs of MV overhead
However, the investment capabilities, responsible for the production, lines.
sometimes reduced, can lead to
solutions based on simplification of the
networks’ structure to the detriment of
the system performance. In the same Net consumption / country Net consumption / inhabitant
way, sometimes a lack of availability TWh KWh
and competence of the operators can 3000 30000
lead to over-simplified operation.
2355
Varying situations in industrialized
countries 11760
In countries that are 100% electrified, 1000 10000
there are considerable differences in 595
uses of electrical energy: 5320
5200 4900
■ national electrical energy 3190
300 294 3000
consumptions show great differences 2790
(see fig. 4). These differences are due 1860 183
to the size of country, to its economic 108
growth (GNP) and to the weight of the 100 1000
industrial sector (example 40% of the
French consumption).
■ per capita consumption can vary by a 27
30 300
factor of 10 between certain countries 19
(see fig. 4). These differences are
mostly due to the pricing policy of
distributors, but also to climatic
Portugal Denmark Spain Italy France Japan United states
conditions.
fig. 4: net consumption per country and per inhabitant.

Cahier Technique Merlin Gerin n° 155 / p. 7


These examples would thus appear to his development: supply of A permanent fault implies an
show that the number of parties interruption lasting between several
involved, particularly in MV distribution,
high quality energy minutes to several hours ; it requires
can vary considerably from country to Increasingly, the energy distributor is human intervention.
country (see fig. 5). required to supply a high quality
Overhead networks, that are naturally
electricity product. In order to do this
In the case of MV distribution the considerably more exposed than
he must:
distributor generally has complete underground grid, require specific
■ reduce the number and the length of
responsibility for the network, from the solutions to problems encountered
interruptions in supply to his customers,
HV/MV substation to the MV/LV such as:
■ minimise the consequences of them,
transformer substation. In addition the ■ tree branches falling on overhead
■ avoid disruptions such as voltage and
distributor’s job now includes a lines;
frequency fluctations (see fig. 6).
commercial aspect with respect to the ■ birds landing on the line or its
sale of "electricity" as a product in the supports;
form of a kWh. He must thus ■ faults due to lightning, wind, frost,
continually improve the quality of the parameters nominal tolerances snow;
product to satisfy the demands of his values ■ vandalism.
various customers, and remain Frequency (50 Hz) ± 1Hz As a consequence, the type of failures
competitive in relation to other sources MV Voltage (12 to 24 kV) ± 7% encountered differ between overhead
of energy. This objective leads LV Voltage (230 or 400V) and underground networks:
distributors to consider several price overhead ± 10% ■ on overhead networks, the faults are
levels dependant on the quality of kWh underground ± 5% mostly momentary (80 to 90%) and
being sold. one-phased (75%) since they are often
Equally, the electrical network fig. 6: examples of a distributors "quality" due for example to storms, to a line
represents an important investment for constraints (EDF France). fallen to the ground or to shorting
the distributor. He has to make this across an insulator.
investment as profitable as possible ■ on underground networks, the faults
The type of faults depend on the
and it is for this reason that it is are mostly permanent (100%) and
type of network
increasingly frequent that distributors’ multi-phased (90%) since they are very
requirements include the idea of energy For customers, the consequences of often the result of severing a cable.
management. such phenomena depend above all on
the type of fault. A need for information
Lastly, distributors play an important The importance of understanding the
social and political role, a role which A fault can be:
incidents occuring on the network
■ momentary or permanent in duration;
can have a bearing on his choices, or increasingly justifies a need for
■ one-phase or three-phase dependant
at least on their priorities, as in the information that distributors satisfy by
following two examples: on the type of its cause.
using statistical studies.
■ supplying new customers may A momentary fault often means a brief
This analytical work aims to:
require extension of the network, interruption of the order of several
■ classify and code the incidents,
■ the price per kWh may be limited in 100 ms, essentially related to the ■ determine their origins and causes,
line with government economic policy. operating time of a recloser. ■ statistically calculate their frequencies,
■ search for correlations,
■ study the comparative performances
of the various topologies,
■ analyse the results according to
country number of distributors the most important operating methods and installed
total distributing 80% equipment involved.
of national
These statistics provide a tool for
consumption
helping distributors in the design,
Germany 600 20 R . W . E. operation and maintenance of public
Saudi arabia 5 5 S.C.E.C.O. networks.
Spain 200 6 Hydro Electrica In addition, in order to be able to decide
France 200 1 E.D.F. on the best solutions, the quality of
service must be able to be quantified
Great Britain 15 10 Regional Electricities Cie
and measured, and no longer just be
Italy 150 1 E.N.E.L. approached in a subjective manner.
Japan 9 9 Tokyo Electric Power Co In order to achieve this, new tools have
been designed (based on mathematical
models), particularly including the idea
fig. 5: electrical energy distributors in several countries. of "undistributed energy". Notably, to
measure the cost of low quality in

Cahier Technique Merlin Gerin n° 155 / p. 8


MV networks, the E.D.F. use the Advances in protection and telecontrol control centres:
formula: equipment with digital technology ■ there still exists control centres in
A*N*N*P + B*N*P*T, with (microprocessor) and expansion of which:
N = number of permanent breaks per communication networks, offer the ■ the status of various networks is
feeder, perspective of innovative solutions in indicated by manually displaced
P = average power per feeder in kW, terms of event prediction (see symbols on large charts several meters
T = average length of interruption per glossary). square in area,
failure, ■ and the instructions relating to
Lastly, the practice of live-line repair
A and B = economic value coefficients operations are hand written in log-
work and remote control of the
(in 1990, for the EDF in France books;
networks are also points that favour
A = 6 FF/ kW and B = 13.5 FF/ kWh). ■ in new centres all these operations
increased quality of service, by
However, measurement of the quality are performed on computer terminals,
reducing the number of interruptions
of service can require inclusion of even with:
and their duration.
■ all information available on screens in
more parameters. The complexity of
Of course, all of these developments real time (network layouts,
the calculations and simulations to be
require that the workforces should geographical description),
carried out, justifies the development of
software tools that are increasingly adapt quickly, following the example of ■ events logged automatically (data

powerful to help with the decision. the current changes in work practices in logging).
To measure the reliability of energy
supply to a residential LV customer,
distributors prefer to use the criteria of %
"degree of unavailability": this is the number of
LV customers 1986 1995
total annual time during which an
average customer has his supply 60
interrupted due to a fault on the
electrical network (HV, MV or LV).
50
Lastly, it is important to note that for a
LV customer, numerous incidents are
due to the MV network (60% according 40
to an EDF study) (see fig. 7).
Networks, equipment and operators, 30
are all evolving
It should not be forgotten that a
20
network’s performance depends above
all on its topology. However, throughout
the world, present networks are simply 10
the result of years of laying of
structures one on top of the other as
needs have increased. In addition a 0
0 1 2 3 4 5 >5 hours
network ages and is constantly in need
duration of interruption
of maintenance and renovation work to
retain its performance level and to fig. 7: degree of unavailability of electrical energy on one LV network (EDF - France).
avoid incidents, the sources of
"undistributed energy".
To answer these needs, the
manufacturers thus propose
"maintenance-free" or reduced
maintenance equipment; equipment for
which maintenance, modification and
addition type operations do not
adversely effect the continuity of
service.
In addition, energy distributors are not
willing to undertake preventive
maintenance, particularly device
monitoring by recording and analysing
incidents that occur on the network
(use of "disturbance recorders" and
time-stampers).

Cahier Technique Merlin Gerin n° 155 / p. 9


3. MV network topologies

The topology of an electrical network is items that depend on the ■ the choice of an overhead or
defined here as all of the principles underground distribution system has a
involved in carrying electrical energy in
chosen topology big influence on the installation costs
public distribution (layout, protection, The choice of a topology fixes the main and the quality of service (e.g.: costs of
operation). design elements of a distribution a trench / vulnerability to momentary
system, such as: faults...). For MV, in industrialized
In practice for a distributor, defining a
■ the rated power and the maximum countries, this choice can be broken
topology means fixing a certain number
value of earthing currents, e.g. for MV, down into three cases:
of physical factors, whilst taking
the EDF limits the value of these ■ highly populated urban area with an
account of criteria dependant on
currents to 300 A at 20 kV overhead underground distribution system,
objectives aimed for and technical
and to 1000 A underground; ■ highly populated suburban area with
constraints. Since these factors are
■ the rated voltages, e.g.:for MV Japan underground or part-underground part-
closely interrelated, choice of a certain
supplies at 6.6 kV, Great Britain at 11 overhead distribution system;
topology is always the result of
and 33 kV and France mostly at 20 kV; ■ scarcely populated rural area with
technico-economic compromises.
■ voltage surge ratings and
Here, the graphical representation of a overhead distribution.
coordination of isolation as well as
topology will be by simplified single-line protection systems against atmospheric However it should be noted that
layouts. voltages surges; historically, due to high initial costs,
■ the earthing connection layouts, as numerous urban areas have overhead
well as the number of distributed wires, distribution systems, as in Japan and
criteria in choosing a ■ the maximum feeder lengths (tens of the United States.
topology kilometers at MV);
The choice of a topology depends on ■ the type of distribution: overhead or
meeting objectives: underground (see fig. 8);
various MV network layouts
■ to ensure the safety of people and ■ the type of operation: manual, The choice of layout is important to a
goods, automatic, remote controlled. country: particularly for MV networks
■ to attain a pre-defined level of quality since they are of great length. Thus, for
It is important to note that:
of service, example, the total MV structure in
■ the choice of short circuit current has
■ to produce the desired profitability. France is around 570 000 km long, that
repercussions on the rating of the
of Italy being 300 000 km long and that
However, it must also meet certain equipment used in the network;
of Belgium being 55 000 km long.
requirements: ■ the choice of voltage rating(s) is
■ to correspond to the housing density always a compromise between the Several topologies exist:
and/or to consumption, known as the installation and operating costs of the ■ lattice type, closed loop topology,
load density, it plays an ever increasing network; ■ simplified lattice type, open loop
role. Calculated in units of MVA/km2, ■ the choice of insulation rating of topology,
this density enables the expression of equipment is generally in line with ■ open loop topology,
various geographical zones in terms of international and/ or national standards; ■ radial topology.
load concentration. Certain distributors
distinguish two types of consumption
zones by defining:
0 25 50 75 100%
■ low load density zone:
Germany
< 1 MVA/km2,
■ high load density zone: Canada
> 5 MVA/km2.
United States
■ to account for the geographical
spread, terrain and construction Denmark
problems,
Great Britain
■ to satisfy environmental constraints,
particularly climatic (maximum and Netherlands
minimum temperatures, frequency of
storms, snow, wind, etc.) and respect underground overhead
for surroundings.
fig. 8: proportion of lengths of overhead (lines) and underground (cables) on MV networks, for
several countries.

Cahier Technique Merlin Gerin n° 155 / p. 10


Other topologies are also used, for This layout is particularly used for MV unit on this structure can be supplied
example the double shunt found on distribution in rural areas. Indeed, it via two possible electrical paths, whilst
French MV networks. enables easy and low-cost supply to only one of those paths is activated at
Although none of them are "standard" low load density (≈ 10 kVA) consumer any one time, back-up is provided by
in MV, distributors lean towards two units with a wide geographical the possibility of using the other loop. In
base topologies: radial and open loop. dispersion (≈ 100 km2). such a layout, there is always an open
Each of these two topologies will thus Very often a radial layout is used with point in the loop, which leads to a
be covered in more detail and defined an overhead type distribution system. similar operation to two antenna
in terms of: layouts.
Its strengths and weaknesses are
■ its operating principle, The typical line layout is, of course, a
summarized in the table in figure 10.
■ its typical line layout, loop on which are connected consumer
■ its typical application, Open loop layout units (see fig. 9) which can be public
■ its strengths and weaknesses. Its operating principle uses two lines of distribution substations MV/LV, and/ or
supply. This means that any consumer delivery substations for a MV customer.
Radial layout
This layout can also be called
antenna-type.
Its operating principle is based on using technology strengths weaknesses
a single supply line. This means that all radial ■ simplicity ■ quality of service
consumer units in such a structure only ■ operation
have one possible electrical feed path. ■ installation costs.

It is of arborescent type (cf. fig. 9). open loop ■ simplicity ■ operation with more

This arborescence originates from ■ quality of service frequent switching


■ installation costs
supply points, that are MV/MV or
HV/MV distribution substations. fig. 10: comparative table of the two base MV network layouts.

HV/ MV
substations
HV/ MV transformers

radial layout open loop layout


supply path for all substations except n°1

MV/ LV
transformer
supply path for
substation n°1

MV/ LV substation n°1


transformer MV/ LV MV/ LV
transformer transformer
open point

fig. 9: the two basic layouts of a MV distribution network, radial (or antenna) and open loop (or artery break).

Cahier Technique Merlin Gerin n° 155 / p. 11


Each point (between 15 and 25 points The five neutral earthing layouts The differences between the five
per loop) is connected to the loop by used in MV throughout the world categories
two MV switches. All these switches Here again, no one standard neutral It has been previously stated that the
are closed , except for one of them that earthing layout exists. However, it is choice of neutral earthing layout
forms the opening in the loop and possible to bring together all the influences the performance of the
defines the feed path for each various cases met around the world network and the design of its protection
consumer unit. This opening can be into five categories (see fig. 12): system. Indeed, the main differences
displaced within the loop, particularly ■ direct distributed neutral earthing, between the five categories lie in the
during reconfiguration operations ■ direct non-distributed neutral earthing, behaviour of the network in an earth
following a fault. ■ neutral earthing via an impedance, fault situation.
Very often this layout is used in ■ neutral earthing via a designated
These differences translate in real
association with an underground type circuit, terms to the degree:
distribution system. ■ neutral insulated from earth. ■ of ease of detection of these faults,
It is typically used in highly populated As has already been said, none of the ■ of security achieved for people,
urban areas, and its strengths and categories is dominant throughout the ■ of impact on the requirements of
weaknesses are detailled in the table, world: some solutions are specific to electrotechnical equipment.
figure 10. some countries, and several categories The distributed neutral earthing layout
can be found within one single country, that allows single phase distribution
Double shunt layout or even within the network of one single
This rather uncommon layout is mostly should, however, be considered
electricity distributor. seperately. This possibility can be
used by the EDF in the Paris region, it
But in the end, the choice of a MV considered in certain countries on the
is shown in figure 11.
neutral earthing layout is always the basis of its reduced installation costs.
The operating principle is the following: result of a compromise between However, the more complex protection
■ the MV network is doubled up, installation and operating costs. devices require stricter maintenance.
containing two circuits A and B, both
normally live,
■ every MV/LV substation
■ is connected to both MV cables ("A"
and "B"), but it is only actually live to HV/ MV HV/ MV
one of the cables (MV switch closed on substation substation
cable "A"),
■ is equipped with a simple local
automatic control device,
■ on failure of cable "A", the automatic
control detects the lack of voltage in the
cable, checks the presence of voltage
in cable "B" and commands the closing
of one MV switch and the opening of
the other MV switch.
circuit "A"
neutral earthing layouts circuit "B"
The choice of neutral earthing layouts
(or neutral MV systems) defines
amongst other things the voltage surge
ratings and earth fault currents that
could be found on a network. It must be U
noted that these two parameters are 1
inlet A
contradictory, in view of the fact that
0
obtaining a low fault current level leads
to a high voltage surge and vice versa. inlet B 1
These values thus pose electrical 0
constraints that the electrotechnical tf tf
equipment must be capable of network 1
withstanding. However, in choosing the supplied 0
by... A B A
connecting layout, we simultaneously
select the possible solutions for
t f = 5 or 25 s t
protection of the electrical network and
influence the operating methods. fig. 11: double shunt distribution layout, used by EDF - France. In the inset, automatic control
sequence of Merlin Gerin permutator, conforming to EDF - France specifications.

Cahier Technique Merlin Gerin n° 155 / p. 12


Independantly of this particular case,
the table in figure 13, a summary of the
strengths and weaknesses of these
method
categories, shows why no one of these
categories is predominantly used
throughout the world.

protection system neutral neutral neutral neutral neutral


The electrical structure of a country distributed earthed earthed via earthed via insulated
with numerous directly and an impedance a designated from earth
corresponds to a group of electrical earthing points undistributed circuit
networks. country
Australia ■
An electrical network can itself be Canada ■
broken down into areas. Spain ■ ■ ■ ■
Each of these areas is generally France ■
protected by a circuit breaker in Japan ■
conjunction with detector devices Germany ■
(measurement sensor: current or
voltage transformer...), protection and
fig. 12: various MV neutral earthing layouts, and their applications throughout
control devices (protection relays), and
the world.
trip devices (actuators).
All these elements together make up a
chain of protection (see fig. 14) that
ensures isolation of the faulty part of
neutral earthing method strengths weaknesses
the network in the event of a fault.
Its role is to ensure safety by protecting direct earthing authorises one-phase ■ requires numerous high quality
and distributed and three-phase earthing points (safety)
against insulation faults between
distribution ■ requires a complex protection
phases or between phase and earth, system
and against prolonged overloading. The ■ leads to high values of earth
chain of protection must especially fault currents
reduce the consequences of a short direct to earth eases detection of leads to high values of earth
circuit, such as the risks of fire, and undistributed earthing faults fault currents
explosion of mechanical damage,... insulated limits earth fault leads to surge overvoltage
The network’s protection system is currents
made up of all of these chains of designated favours auto-extinction requires complex
protection, integrating their installation of earth protection systems
with the organization of the operation fault currents
between them. This protection system impedant
organization, including the trip times of (compared with neutral limits earth fault requires more complex
the associated circuit breakers, defines direct to earth) currents protection systems
the maximum duration of a current fault (compared with neutral reduces surge leads to higher earth fault
in the different parts of the electrical insulated from earth) overvoltage currents
network.
The effectiveness of a protection fig. 13: a summary of strengths and weaknesses of the five MV neutral earthing methods.
system depends on several criteria:
reliability, selectivity, rapidity,
sensitivity, adaptability.
Reliability measurement protection breaker
actuator
This criterion describes the level of sensor unit device
quality concerning safety of people and
property, particularly in terms of
dangers of electrocution by increased
earth potential. Although a protection
device is rarely activated, when there is
a fault it must act effectively, throughout electrical network
its many years of service. This criterion
directly influences the network fig. 14: MV chain of protection, and photograph of a SF set (Merlin Gerin), an example of
performance, thus, for example, any complete integration.

Cahier Technique Merlin Gerin n° 155 / p. 13


interruption in supply must be "justified" between HV/MV and MV/MV
since it entrains a loss of operation for substations and biased differential for
the customer ... and the distributor. HV/MV transformers. Lastly, distance
Sensitivity selectivity technique is mostly used by
This criterion also has a bearing in German distributors.
terms of security and costs: it describes
the ability to detect weak fault currents telecontrol system
without being sensitive to transitory
Under the one term of telecontrol are
phenomena due to the network
(operations) or to surrounding grouped all of the elements tied in with
operation of the network.
electromagnetic effects, thus before
there is any risk to people or property, A telecontrol system defines all of these
and that without tripping prematurely. elements and their relative operational
organization. In this way the telecontrol
Selectivity
system must enable the operator (the
This criterion has a particular bearing
distributor) to account for 3 situations
on costs of operation, since it indicates
■ normal operation,
to what degree it is possible to maintain
■ the instance of a fault,
the network operation whilst one part of
■ maintenance operations (live and
it is not working as it should do. In
dead).
practice, this leads to shutting off the
faulty element, and only the faulty Lastly, the operating tools installed in
element (see appendix 2: different this system are going to make a
selectivity techniques). considerable contribution to the quality
of service that is obtained.
Rapidity
This criterion, as in the preceding case, These tools range from the push-button
has an effect on costs: it enables control of a MV device up to the MV
reduction of the damage due to network control centre, from the
electrical arcs and short circuit currents, ammeter on a MV cubicle up to a
it particularly reduces the risk of fire automatic remote reading of the load
and the costs of repair work. curve for a MV feeder, etc...
Adaptability
This criterion particularly interests the
distributor and indicates the degree of
evolution that is possible (possibilities
and ease) for the protection system
with regards to modifications to the
network topology.
Of all these criteria, selectivity is the
one that leads to the most varied
solutions from country to country. They
depend on two initial choices made by
the energy distributors:
■ of which neutral earthing layout is
used, from which we define notably the
protection systems against earthing
faults (see previous section).
■ and that of which selectivity principle
will be used, of which the most
commonly used, called ampere-
chronometric selectivity, is based on
the association of the fault current
rating (amperemetric selectivity) and a
value of the tripping delay time
(chronometric selectivity). However,
several different techniques can exist
within the same network, in South
Africa for example E.S.C.O.M. uses
within one network, ampere-
chronometric selectivity, pilot wire

Cahier Technique Merlin Gerin n° 155 / p. 14


4. MV public distribution

This chapter is a reminder of the main The MV/LV substation in a public performs the transfer from MV
substations installed on MV networks, distribution system (≈ 10 kV) to LV (≈ 100 V).
and the main technologies used in MV Positioned between the MV network The typical layout of this substation is
equipment. It is concluded by two and the LV network, this installation of course a lot more simple than the
layouts showing their applications in
real terms.
HV/MV
substation HV incomers
substations on MV
networks
A substation or installation is a physical
entity defined by its position and its HV/MV transformers
function within electrical networks.
The role of a substation is essentially to
perform the transition between two MV bus section
voltage levels and/ or to supply the end circuit breaker
user.
The HV/MV substation in a public
distribution system
This installation is present in any of a
country’s electrical structures; it is overhead and/or underground MV feeders
positioned between the
subtransmission network and the MV MV/MV
network. substation MV incomers
Its function is to ensure transition from
HV (≈ 100 kV) to MV (≈ 10 kV).
Its typical layout (see fig. 15) involves
two HV inputs, two transformers HV/
MV, and 10 to 20 MV feeders. These
feeders supply overhead lines and/ or
underground cables. overhead and/or underground MV feeders

The MV/MV substation in a public MV/LV


distribution system substation
This installation performs two functions:
■ to ensure the demultiplication of MV
feeders downstream of HV/MV
substations (see fig. 15). In this case,
the substation does not include a
transformer. It is made up of 2 MV MV incomers MV/LV transformer LV feeders
inputs and 8 to 12 MV feeders. This protection
type of substation is used in several
countries like Spain, Belgium, South delivery
Africa. substation for
■ to transfer between two MV voltage a MV customer
levels. Such MV/MV substations do
contain transformers. They are
necessary in countries that use two
successive voltage levels in their MV
networks, for instance in Great Britain
MV general MV protection private MV private LV
where the MV network is broken down incomers and metering system feeders feeders
into two levels 11 kV and 33 kV. Their
typical layout ressembles that of the
fig. 15: various layout types for substations used on public distribution networks
HV/MV substation.

Cahier Technique Merlin Gerin n° 155 / p. 15


previous installations. In particular, the However, if the user is supplied with Amongst all the various types of
most common MV device used is the MV, a standard layout may be devices, two are particularly used in MV
switch and no longer the circuit proposed (see fig. 15). Installation of switchgear, the circuit breaker and the
breaker. such a substation is, however, evidently switch. They are virtually always
These substations are made up of four dependant on the distributor’s combined with other devices (protection
parts: agreement since they may have their and telecontrol units, sensor
■ MV equipment for connection to the own specific requirements (metering, measurement units,...) that make up
upstream network, operating conditions,...) their associated equipment.
■ the MV/LV distribution transformer, ■ MV circuit breaker
■ the LV feeder board as connection to Its main function is protection, but also
the downstream network (in LV), other MV installations performs a control function and,
■ and inceasingly frequently a pre- Outside of the substations already depending on its type of installation, a
fabricated outer enclosure (in metal or described, other MV installations exist switching function (draw-out, glossary).
increasingly frequently in concrete) to that are mainly positioned on overhead MV circuit breakers are nearly always
enclose the previous elements. networks. Often single function, they mounted in a MV cubicle.
are used ■ MV switch
The delivery substation for a HV or
■ either as protection, as in the case of Its main function is command, but also
MV customer
fuses and reclosers (glossary). often performs a role of switching. In
These installations perform the transfer addition, it is combined with MV fuses
■ or for operation, as in the case of
from public distribution to private to ensure protection of MV/LV
remote control switches.
distribution. They enable connection: transformers (30% of all MV switches
The MV remote control switch is part of
■ to the HV subtransmission network
network remote control systems. It used).
for a high-consumption customer
allows rapid reconfiguration operations MV cubicles have metal enclosures that
(≈ MVA) via a HV/MV substation,
without the operator having to travel. meet specifications laid down in the
■ to the MV network of a medium-
consumption customer (≈ 100 kVA) via publication IEC 298 that differentiates
four types of switchgear, each type
a MV/LV substation. MV switchgear (see appendix 1) corresponding to a level of protection
The choice of the connecting voltage to MV switchgear enables the three against fault propagation within a
the public distribution network for a following basic functions to be cubicle.
customer depends essentially on: performed: This protection system involves
■ the quality of the LV network, ■ isolation, which consists of isolating a
partitioning of the cubicle into three
particularly its power capacity (electrical part of the network in order to work on it basic compartments (see fig. 17):
capacity); in complete safety, ■ the switchgear compartment
■ the distributors policy, particularly on ■ control, that consists of opening or containing the device (MV circuit
the rates offered, since for the closing a circuit under its normal breaker, MV switch,...),
customer this defines the cost saving operating conditions, ■ the MV busbars for electrical
advantages of electrical energy, ■ protection, that consists of isolating connections between several MV
compared with other sources of part of a network with a fault in it. cubicles grouped together on a board,
energy: oil, gas,...
It essentially takes three forms: ■ MV cable connections compartment,
In practice, it is the power subscribed to ■ separate devices (see fig. 16) often with space for measurement
by the customer that determines (directly fixed on a wall and protected sensors.
whether he is connected to LV or MV, from access by a door),
with very different values from country Often a fourth compartment completes
■ metal enclosures (or MV cubicles) this assembly, it being the control
to country. Thus, in France a customer containing these devices,
is supplied MV from 250 kVA whereas compartment (or LV box) containing
■ MV boards that are made up of protection and control units.
in Italy this threshold is nearer several several cubicles.
tens of kVA. On the other hand in the In addition to this classification the
United States where a customer can be The use of separate devices is distinction should be noted between
supplied LV up to 2500 kVA. For users increasingly rare; only several countries Fixed and Draw-out (see glossary) that
supplied with HV, the layout of the such as Turkey or Belgium, still use this apply to the MV device and cubicle.
substation is specifically designed. technology. This distinction, that depends on the

MV devices isolator switch circuit breaker switch isolator draw-out fuse


function circuit breaker
isolating ■ ■ ■
command ■ ■ ■ ■
protection ■ ■ ■

fig. 16: various functions of MV devices that are used in public distribution(contactors are essentially used in industry).

Cahier Technique Merlin Gerin n° 155 / p. 16


connection and measurement
measurement transformer substation public public public HV/MV MV/LV
switchgear HV/MV MV/MV MV/LV customer customer
control
separate device S S

switchgear bloc CB or S S CB CB or S
circuit
breaker compartmented CB or S S CB CB or S

incomer
feeder metal clad CB CB CB

busbars GIS CB CB

RMU S S
fig. 17: various compartments of a MV
cubicle, surrounded with a metal enclosure,
S = with switch CB = with circuit breaker
and their main elements.
fig. 18: main MV switchgear applications.

ease of operation (as a function of time


taken to change a device), is only
indirectly involved in the idea of MV air oil SF6 vacuum
network safety.
MV switch ■ ■ ■ ■ ■
IEC 298 defines the following four types
of switchgear for MV cubicles:
■ "BLOC" switchgear divided to a MV ■ ■ ■ ■ ■ ■
greater or lesser extent into circuit breaker
compartments;
■ "COMPARTIMENTED" switchgear, of
which only the outer enclosure is fig. 19: MV device breaking techniques, their relative importance and the development of
obliged to be metal, has the three their use.
compartments separated with metal or
insulated partitions;
■ "METAL CLAD" switchgear also has
distinct compartments, but of which the
partitions are obliged to be metal;
■ "GIS" switchgear (Gas Insulated
Switchgear) that is hermetically sealed
and within which the compartments no
longer play an important safety role.
The GIS is essentially made up of
circuit breakers.
This technology is also applied to
switches within a RMU (ring Main Unit).
It provides the three standard functions
to be performed of a MV/LV substation
that is connected to an open loop
network (two connecting switches to
the network plus a tee-off fuse switch or
a circuit breaker as protection of the
MV/LV transformer).
The table in figure 18 shows the
switchgear that is most often used as a
function of the type of substation,
whereas the table in figure 19 shows
the current importance and trends of
various MV breaking techniques.

Cahier Technique Merlin Gerin n° 155 / p. 17


French and This sort of design reduces the costs of reclosers, sectionalisers, see glossary).
lines, the losses and the surges due to However, in certain cases, the
North-American layouts faults. However, it requires a very high protection is limited to cut-out type
With these two typical examples it is quality of neutral earthing. fuses (see glossary), the financial
aimed to show in real terms the various In order to obtain a satisfactory degree investment is thus restricted, but to the
elements that have been set out in this of personal safety, it is necessary to detriment of performance and safety
chapter and to highlight the diversity of include numerous MV devices (fuses, (risk of fire).
solutions that exist across the world.
Needless to say, other layouts exist,
even in these two countries.
The overhead single-line layout used
by the EDF (France) (see fig. 20)
This layout applies the following HV/MV substation
principles: HV/MV transformer
■ at the HV/MV substation, neutral
earthing is via an impedance limiting
the phase-earth shorting current to
300 A at 20 kV,
■ three-phase MV lines, undistributed
neutral,
■ radial layout (antenna type).
three-phase
This concept enables detection at MV circuit breaker with
feeder level of any earthing faults automatic reclosing
without any other MV protection device
downstream of this substation.
The result is protection and control
systems that are easy to design, to
operate and to modify.
overhead MV distribution,
Personal safety is guaranteed.
three-phase neutral undistributed
However, the quality of service that is
obtained is only average due to the fact
that each MV feeder, at the HV/MV
substation, is controlled by one single
protection device: when the protection MCOS : manually
device is tripped, the whole network h MCOS controlled three-phase
branc overhead switch
downstream of this MV feeder is cut off.
Solutions exist to make up for this weak
point. These days they are based on
the use of additional equipment such as
MCOS MV/LV
remote controlled switches, in the MCOS
RCOS : remote-
future reclosing circuit breakers will be controlled three-phase
used in the network. RCOS
overhead switch
The overhead single-line layout
found in North-America (see fig. 21) MV/LV
This design is sometimes seen in
rid

countries influenced by North-America


in g

(e.g. Tunisia). It is based on the MCOS


ma

following principles:
■ maximum MV distribution, by MV/LV
reducing the length of LV feeders in
order to reduce losses; MV/LV
■ MV neutral distribution with regular MV/LV
earthing (e.g. every 300 meters); transformer
■ three-phase MV lines on main
RCOS
structure, with three-phase, two-phase
or one-phase shunting for the MV/LV
connections.
fig. 20: overhead MV distribution layout (EDF - France).

Cahier Technique Merlin Gerin n° 155 / p. 18


The design of the protection and concerning grid of EDF-type layouts: countries spread over a large area and
control systems is complex in terms of ■ highly trained staff are required with a low load density (e.g.: United
the selectivity between the different (switchgear maintenance, protection States and Canada in rural areas).
protection devices. device setting,...),
In addition the operation and ■ considerable stocks of spare parts
maintenance of such networks is must be held (different rated fuses,...).
more difficult than for that This solution is especially justified in

HV/MV
substation
HV/MV transformer

circuit breaker
(3 independant single phases
or 1 three-phase)

MV overhead distribution neutral conductor


main grid : three phases and neutral,
two fuses as branch protection
branch : one, two or three phase with neutral
(2 phases + neutral)

recloser : overhead multiple


branch reclosing circuit breaker
(3 single-phased or 1 three-phased)

MV/LV transformer
(see inset below)

MV/LV Nb
sectionaliser
MV/LV

North-American MV/LV
transformer substation

Nb MV/LV MV
grid
in
ma

Nb MV/LV
LV LV

fig. 21: North-American overhead MV distribution layout (each phase shown).

Cahier Technique Merlin Gerin n° 155 / p. 19


5. protection and control of MV networks

The advent of digital technologies Lastly in the 1980”s, digital technology


based on microprocessors has greatly has, due to the processing power of
modified solutions used in design of microprocessors, enabled data
protection and control systems. This processing units to be produced that
chapter presents the latest can:
developments and future prospects for ■ generally back-up various protection
these increasingly complex functions devices,
that are operated on MV networks. It ■ replace the cubicle’s relays
also shows the importance of a new (automatic control),
subject, that being electromagnetic ■ provide electrical parameter
compatibility (EMC). measurements to the operator.
These versatile devices are:
■ flexible (protection selection is simply
MV protection device
programmed),
technology ■ parameter-adjustable (wide choice of
The role of a protection device, or MV settings),
relay (see appendix 1), is: ■ reliable (equipped with self-
■ to continually monitor various monitoring or watch-dog devices and
parameters for part of the network (line, self-testing),
cable or transformer), ■ cost saving (their cabling and
■ to act in the case of a fault, installation time are reduced).
■ and increasingly frequently to In addition, due to their powerful
transmit information for operation of the algorithms and their digital fig. 22: SEPAM, protection and control unit
network. communication, they enable the and its three Rogowski coil current sensors
To this end it analyses the electrical performance of additional functions (Merlin Gerin).
values that are supplied to it by such as logical selectivity.
measurement device sensors, and Using this ability to communicate, a
gives operating commands to the complete network control system is
switching circuits. now possible (similar to technical
Having been limited to electromagnetic management of an industrial plant).
technology, MV protection devices are In terms of sensors, and in particular
today undergoing fundamental those of current, there is an increasing
development with the use of trend towards wide measurement band
microprocessors. sensors in place of current transformers
Thus, the equipment available today is (1 or 5 A). This sort of sensor, that
based on three technologies: works on the Rogowski principle (air
electromagnetic, analog and digital. cored coil), is the type currently on
The oldest is electromagnetic offer. It offers distributors optimised
technology, the relays are simple and solutions (reduction of variables and
specialised (current, voltage, frequency ease of choice) and greatly improved
control) but are not very accurate, their performance (greater linearity of the
settings are liable to change with time. response curve) over traditional current
The more recent electrical analog transformers.
technology (transistor) has improved
precision and reliability.

Cahier Technique Merlin Gerin n° 155 / p. 20


electromagnetic MV control applications networks. The number and
geographical dispersion of the points of
compatibility (EMC) Towards centralized operation remote control, the simultaneous
The electromagnetic compatibility Remote control is the grouping of all management of several different control
(EMC) is defined as the ability of a that is necessary to control remotly MV centres, the number and
device, a piece of equipment or a network into one or several points (see level of qualifications of the operators
system to function in a satisfactory fig. 23). These points are fixed or requires adapted solutions:
manner in its electromagnetic mobile (taken in a vehicle) control ■ ergonomics and user-friendliness of
environment, without affecting this stations. They are also called, the work stations,
environment; this environment possibly dependant on distributors, control ■ control assistance tools,
containing other more or less sensitive centres, dispatching or SCADA ■ control centre configuration tools
devices. (supervisory control and data (glossary),
In order to develop its new products, acquisition). ■ management of the various
taking account of the development of To account for the specific needs of transmission systems used.
digital techniques and the necessary MV network control, these control In practice remote control covers the
cohabitation of MV equipment (high centres are different from those used functions of remote-data transmission,
values of voltage and current, on transmission and subtransmission remote supervision, telemetering and
particularly when being switched) and
electronic protection and control
devices (low voltage level and high
sensitivity to electromagnetic radiation),
Merlin Gerin has had to increase the
scope of and then develop applications
in the field of electromagnetic
radio waves fixed control
compatibility (EMC). In addition, in mobile
telephone network
remote-control centre
order to satisfy the distributors’
requirements (operational safety), it has unit
been necessary to carry out more
stringent tests than those defined in
recent standards that are currently valid
(see appendix 1) that define the
acceptable interference level.
■ Thus, for measurement devices,
the IEC 801-3 standard details
tests across a frequency range of radio
27 MHz - 500 MHz and three levels link
(1, 3,10 V/m) whereas test conditions in
Merlin Gerin laboratories are
considerably more severe: the range of telephone network
frequencies covered is from 10 kHz to (specialized line)
1 GHz; in addition, from 27 MHz to
telephone
1 GHz, devices can be tested in fields
network
of up to 30 V/m. (also see Merlin Gerin
"Cahier Technique" n°149)
■ And for MV equipment, certain tests
are carried out under real conditions on
complete boards (MV switchgear and
protection devices).
However, although electromagnetic
compatibility (EMC) is taken into
account in all development and
manufacturing phases of equipment, in
order to ensure perfectly operational
equipment, it must also be considered
during on site cabling and installation HV/ MV substation MV/ LV substation overhead MV device
phases.

fig. 23: example of remote control of a MV network, with the various links required for
information exchange.

Cahier Technique Merlin Gerin n° 155 / p. 21


remote controling. These functions control of the network in real time, or for Remote controlling
can be divided into two groups its analysis at a later date. Remote opening and
dependant on the direction of All this information together with its closing of power
transmission between the operator and display mode, is defined at the design equipment is a basic example of
the network: stage of the telecontrol system. In remote controlling. The practical
■ remote supervision, of devices by the particular, the mimic diagram displays application is in the form of remotely
operator, are created as a function of the actual controled MV switches and circuit
■ remote controlling, by the operator of installation and the operators needs. In breakers. Other functions can be
the devices. addition they are displayed in real time. remote controlled: settings, automatic
Remote supervision The operator can then visualise: control,...
This in itself groups ■ the operational layouts (electrical There must be a maximum degree of
signals concerning network, substation, MV cubicle); certainty concerning remote control
the position of various MV equipment, ■ installation status (status of MV commands. This is obtained using a
their possible tripping on fault, devices,...); powerful communications network that
instantaneous or weighted ■ values of operational data (currents, allows access to information in real
measurements from various parts of voltages, powers,...); time. Thus a switching command for a
the electrical network, and any other ■ values of MV protection devices MV device is transmitted via a double
information indicating the up-to-date settings; remote control (TCD), and confirmed
status of the network. It enables for ■ details concerning alarms, with their by return of a double transmission
example, the automatic and chronology of occurence; signal (TSD).
continuous printing, in sequentiel ■ ... Remote control processes also
order, of all the events necessary to integrate requests for validation and
confirmation before execution of a
switching command.
Remote control
In MV distribution this is a cost saving
factor in terms of operation of the
network. Indeed, without having to
travel, the operator can continually
monitor and control the operation of his
network. As an example: following a
remote control fault it is possible to rapidly change the
network operating layout so as to
minimise the proportion of it that is cut

=
off, this being done by remote
consultation of fault position indicators
(see glossary) that are installed at
different points on the MV network,
followed by remote control of MV
switches. This results in a considerable
reduction in the amount of undistributed
remote supervision remote controlling energy, but also in network optimization
(information transmission) (command transmission) with possibilities of optimum
management of the load distribution.
The network loading can also be

+
analysed.
In particular, by logging the load curve
verification and optimization of energy
consumptions can be performed.
Finally, to increase efficiency, the
operator can have rapid access to the
■ remote data transmission ■ remote control of most relevant information via an
■ telemetering network's MV devices automatic pre-processing method such
■ remote adjustment
as a sorting operation, graphical
of settings.
representation operation, calculation
operation,....
fig. 24: several functions, here grouped according to the direction of transmissions between
operator and network, are required for remote control.

Cahier Technique Merlin Gerin n° 155 / p. 22


Automatic energy supply MV telecontrol Electrical networks, whatever their
management layout, adapt completely to this
This management, which aims to
architectures
development. Thus, inspite of the
improve the quality of service via the The advent of digital technologies has diversity of operational methods, it is
continuity of supply on the network, had a considerable impact on the logical that we see development of
has its main application in the solutions employed in MV telecontrol. prioritizing MV control functions. With
permutation of various electrical energy In particular, the ability to use compact this aim, a MV control system defines:
supplies. This application is based on and reasonably priced digital protection ■ functions to be performed,
automatic control. and control units enables, with ■ their prioritized level,
The double shunt type topology, as centralized operation control, the use ■ their geographical location.
operated by the EDF on some of its today of local intelligent systems. This It can be studied in terms of four levels
networks, is an example of this. development offers the following (see fig. 25):
advantages: ■ level 0: MV devices and sensors,
■ it reduces the disadvantages of
■ level 1: protection and control of an
intelligent systems concentrated in one MV cubicle,
single point. Indeed, a fault at this point ■ level 2: local control of a substation
would be catastrophic for the whole or installation,
electrical network operation. ■ level 3: remote control of a MV
■ it offers the advantage of a better
network.
maintainability and an increased (see EDF application in appendix 3).
operational flexibility.

trol of
e-con
remot al network
ic
electr

ation
install
local
l
contro

ntrol
nd co
tion a
protec cubicle
of MV

sors
s and sen
evice
MV d

fig. 25: the various priority levels of MV control-command functions

Cahier Technique Merlin Gerin n° 155 / p. 23


Together this constitutes a MV control As for data transmission, it is of series Transmission protocols
architecture, whose operation relies on type. This means that pieces of binary Protocol is the language used for
numerous exchanges of information (0/1) coded information are sent one information exchange between the
between the various priority levels. This after the other using the same various protection and control units
information is essentially: equipment. Above all the advantages of within an architecture. It defines the
■ remote data transmission, this type of transmission are simple structure of the exchanged messages,
■ telemetering, cabling and good immunity to external both in terms of requests for
■ remote control. disturbances. information and for response
The exchange of such information can Transmission methods messages. These protocols can be
be continuous or as events occur Information transmission requires the unique to one equipment manufacturer
(network incident, switching use of one or several pieces of (or to several manufacturers) or
commands,...); it requires high- equipment. standardized, conforming to various
performance communications standards. As far as public distribution
In the case of control of electrical is concerned, within the concept of
networks. networks, the method used is: architecture that has been presented
■ paired wires, coaxial cable,
above, which is becoming generalized,
communications networks (specialized telephone links or national distributors are trying to standardize
telephone networks) protocols between levels 2 and 3.
All of these exchanges are grouped ■ radio waves (radio links),
together within the remote data However, internal switchgear
■ power cable (power line carrier).
transmission function, as defined by the transmission protocols remain the
following parameters: Optic fibre is still in the experimental choice of the manufacturer.
■ the organization, stage since, inspite of its great Communicating in the chosen protocol
■ the transmission equipment involved, advantage of being insensitive to for an architecture is a condition which
■ the communication protocol. electrical disturbances, its installation a piece of equipment must satisfy if it is
cost remains a considerable hurdle to to be integrated within that architecture.
All these parameters are such as to be overcome. As for power line carrier
ensure that any message transmitted is
systems, to date they have only been
correctly received (free of errors). used for network load management, for
Remote data transmission example sending of signals to change
organization the applied price-rate by the EDF and
The simplest solution is to sending of load shedding commands in
communicate between two the United States. However, they are in
transmitters-receivers. However, with the experimental stage for other
links between only two points, the limit applications, for example remote
of this system’s application possibilities electricity-meter reading or
is very quickly reached. When several reconfiguration of a network following a
units are involved in telecontrol, a fault.
single point-to-point link becomes In fact, at the moment, no one type of
insufficient, and this is where the idea method is predominantly used; the
of multi-point comes in. In this case, choice depending on various criteria:
two organization types are possible: ■ amount of information to be
■ master-master transmitted,
All the units within this organization can ■ frequency of exchange (number and
take the initiative to communicate. periodicity),
■ master-slave ■ speed required for exchanges,
The control unit with the highest priority ■ type of information,
level in the architecture is generally the ■ transmission distance,
master. It is responsible for the ■ geographical constraints (e.g.
management of all transmissions, to mountain region),
which end it interrogates all slave units ■ cost of exchanged information.
in turn on a continuous basis or In practice, an electrical energy
following an incident. The slave units distributor will always use various
respond to the interrogation and methods:
execute orders given by the master ■ specialized lines (paired wires) for
unit. control of important installations (HV/
In terms of control for electrical MV substation, MV/MV substation),
networks, the most frequently used and ■ radio-electrical or telephone links for
the safest organization is that of control of secondary installations
master-slave type. (remote controlled MV/LV substation
and MV pole-mounted switch).

Cahier Technique Merlin Gerin n° 155 / p. 24


6. conclusion

The noticeable feature of current layouts do not facilitate rational


installations, remains their country- analysis.
dependant diversity: Distributors are well aware of this
■ diversity in electrical layouts and their obstacle. Thus, their new long-term
protection system, objectives involve moving towards
■ diversity in basic technical choices, simplification and rationalization of
■ diversity in operating methods. network layouts, which requires long-
However, two major long term term and costly investment. Without
developments are envisaged by all waiting for this future stage, they are
distributors: development towards a MV continually trying solutions that are
system and development towards adapted to their current MV network
automatic control of MV networks. layouts.
In the same way, manufacturers use
Development towards a MV system the most recent technologies to benefit
As has been seen in the above pages a distributors.
MV electrical distribution network, is
formed by the overlapping of two Of course Man must always remain
networks: master of such Systems. And whilst
■ the energy network, whose objective
data processing, born from computing,
is to carry energy to user units. It is already offers distributors better
defined by the single line layout, and is knowledge and understanding of their
made up of electrotechnical equipment, electrical networks, future years will
transformers, cables,... bring innovative solutions which will
■ the information network, whose
contribute to achieving the main
objective is to process data to obtain objective: satisfying the requirements of
maximum safety and overall availability electrical energy consumers with an
within this energy network. Defined by optimum quality of service.
protection and control systems, this
network is made up of protection and
control units, which are interlinked via a
high-performance communications
network and are distributed:
■ on the MV equipment level,
■ on the substation or installation level,
■ on the electrical network level itself.
Thus, from electrical network design to
operation, "Medium Voltage Man"
becomes "System Man".
Development towards automatic
control of MV networks
Following the agricultural and industrial
revolutions, that of communications has
irreversibly created new needs and new
solutions. The next stage will be the
use of expert systems to automatically
analyse and operate networks. This
development is already undergoing
trials by certain distributors, for
example TEPCO in Japan.
However, an obstacle to future
development is the state of existing
networks. Indeed, the latter were not
designed with a view to automatic
operation: their complex, inconsistant

Cahier Technique Merlin Gerin n° 155 / p. 25


appendix 1: some MV product standards

The diversity of equipment mentioned ■ with respect to Ring Main Unit ■ with respect to electromagnetic
in this "Cahier Technique" makes it IEC 129,265,298, and 420, compatibility:
impossible to give all of their respective UTE C 64-130, C 64-131, ■ in terms of susceptibility to
standards. and C 64-400, disturbances,
As an example here are a few VDE 0670, IEC 801 - chapters 1 to 4,
standards: BS 5227, NF C 46-020 to 023,
■ with respect to protection devices ■ in terms of disturbance emission
■ with respect to MV switchgear
IEC 68, EN55 022,
IEC 56 and 694, NF C 91-022.
IEC 470 for contactors IEC 225,
UTE C 64-100 and C 64-101, IEC 655,
VDE 0670, NF C 20-455,
BS 5311, NF C 63-850.
ANSI C37-06 for circuit breakers.

appendix 2: various selectivity techniques

general the various techniques Logical selectivity


When a fault occurs on an electrical To give this selectivity in a MV This selectivity is obtained by means of
network, it may be detected protection system five main techniques a "logical stand-by" command emitted
simultaneously by several protection can be used: amperometric, by the first protection device situated
devices situated in different areas. chronometric, differential, distance just upstream of the fault which should
related and logical. break the circuit, transmitted to other
The selectivity of the protection system
protection devices situated further
gives priority of operation to the closest Amperometric selectivity upstream. It enables the number of
device situated upstream of the fault. This is obtained by adjusting trip selectivity steps to be increased without
Thus, interruption of supply is limited to threshold current values. increasing the upstream trip time.
as small a part of the network as
Chronometric selectivity Pilot wires are required between
possible..
This is obtained by adjusting trip protection units. This technique,
However, a protection system also threshold timing values. developed by Merlin Gerin, is detailed
allows for contingencies. Thus, when in "Cahier Technique" n° 2.
the system is designed, provision is Differential selectivity
made for the incorrect functioning of a This is obtained by dividing the network
protection device, in which case a into independant zones, with detection
different device, situated upstream of for each of the zones of any difference
the latter, should function to limit the in the sum of currents entering the zone
effects of the fault. and the sum of currents leaving the
zone. This technique requires wiring
Each of these protection devices
between protection devices situated at
installed in series on the network
the various extremities of the monitored
represents a selectivity step.
zone.
In a MV network, the number of
selectivity steps between HV/MV and Distance related selectivity
MV/LV transformers is generally limited This is obtained by dividing the network
to between 3 and 5 depending on the into zones, with the protection devices
country. Indeed, above this safety can locating in which zone the fault has
no longer be guaranteed since the occured by calculating downstream
reaction time and the fault currents impedances.
become very dangerous.

Cahier Technique Merlin Gerin n° 155 / p. 26


appendix 3: EDF architecture and Merlin Gerin equipment

,,,,,, , , 





,

,


,


,,,,,,, , ,
,,,,,,,,, ,
,,, , , , ,

,


 
3
,





,

,



Grouping and PRR : grouping and reference point
reference point
,

,






,

,
, control interfaces :
internal internal external
,




2
,



,

TCL11MS


,

substation
computer
Isis 2000 :
mimic
diagram

,



status logger

Vigi PA
1 protection and
,



control-command unit

,




,


,



0 SM6 panelboard : RM6 panelboard :


,



miniature switch Ring Main Unit


cubicle switchgear



,
F24G draw-out overhead and/ or underground network
HV/ MV source substation panelboard MV/ LV remote-controlled substations

,



M2S :
remote-controlled
overhead switch

level 3: network remote control


Communications networks:
level 2: local control of an installation
remote transmission via specialised telephone lines
level 1: protection and control-command of a MV cubicle remote transmissions by radio and/ or telephone networks
level 0: MV devices and sensors internal switchgear network (currently line to line)

Cahier Technique Merlin Gerin n° 155 / p. 27


appendix 4: references

Merlin Gerin "Cahiers Techniques"


■ Network protection using the Logical
Selectivity System
"Cahier Technique" n°2 (F. Sautriau)
■ EMC: Electromagnetic Compatibility
"Cahier Technique" n°149 (F. Vaillant)
Various publications
Numerous documents cover certain
themes touched on in this "Cahier
Technique". However, whilst less of
them cover all of the themes, we have
considered it of more use to indicate to
the reader organizations that distribute
technical reports written for various
congresses:
■ "journées d’etude technique S.E.E."
Société des Electriciens et des
Electroniciens (= Society of Electricians
and Electronics Specialists)
■ quality and cost saving for electrical
supply,
■ Medium Voltage rural networks:
developments and future prospects.
Address:
Société des Electriciens et des
Electroniciens
48, Rue de la Procession
75724 PARIS Cedex 15
■ C.I.R.E.D.
Congrès International des Réseaux
Electriques de Distribution
(= International Congress on Electrical
Distribution Networks).
Address:
Institution of Electrical Engineers,
Savoy Place,
London WC2R OBL
United Kingdom.
■ UNIPEDE
Union Internationale des Producteurs et
Distributeurs d’Electricité.
(= International Union of Electricity
Producers and Distributors).
Address:
39 avenue Friedland
75008 PARIS

Real. ERI - Lyon - photo. : IPV


Cahier Technique Merlin Gerin n° 155 / p. 28 IPV - 03-92 - 3500 - Imprimeur : Léostic

Вам также может понравиться