PROGRAM & LESSON PLANS FOR SEMESTER 2 – 2017 – please note that there are 4 weeks for each of the 3 Units

WK TUES LECTURE TOPIC TOPIC DETAILS UNIT COMPUTERS SELF ACTIVITY - Homework UNIT
DAY
st
1 1 Intro to your Landing Site Book Chapter 1 S.S. Quiz 1 & 2
Aug & the whole 3 Units. A Day in the Life… TASK 1 – Basic Timber Quote
YOUR UNITS? What Steps & Sequencing, Variations, PC & PS TASK 2 – Variation Claim Form (developed from Basic
What is Site Supervision? adjustments, Quote), and the Administrative Steps involved
Claims & Payments Working Roles PPT
The Built Environment PPT
Progress Claims, Practical Completion
th
2 8 On-Site Communication Book Chapter 2 S.S. Quiz 3 & 4
Aug Workplace Verbal & Written Communication TASK 3 – Site Inspection Daily Diary
Recording Information & Gantt Charts PPTs TASK 4 – JSA (SWMS)

Site Supervision – SS
th
3 15 Managing Quality Control Book Chapter 3 S.S. Quiz 5 & 6
Aug Quality Manuals, Controls, Policies & Proc. TASK 5 – Quality Manual - Headings
Site meetings & Defective work. PPTs TASK 6 – Site Inspection Defects Checklist with A.S.
Tolerances
nd
4 22 Completing Project Book Chapter 4 S.S. Quiz 7 & 8
Aug Administration Req. Inspecting Defects, Defect Reports, Rise & Fall, TASK 7 – Handover Checklist
Final Claims, Compliance
th
5 29 Site Investigation Work & Book Chapter 1 & 2 PBW Do both TASKS together:

Plan Building Work – PBW


Aug Contract Docs Dial before you dig TASK 1 – Desk Study Report
Site Access & Planning TASK 2 – Site Condition Report
th
6 5 Construction Strategies Book Chapter 2 & 3 PBW Start looking at Microsoft Project
Sept Subby Pack & OH&S (Toolbox) PPTs & video TASK 3 – Ordered List of Tasks
Look at PERT & Critical Path, Deliveries
th
7 12 Preparing the Project Microsoft Project only PBW TASK 4 – Microsoft Project Gantt Chart
Sept Schedule & Resource Req.
th
8 19 Preparing Conditions Book Chapter 4 & 5 PBW TASK 5 – 4 X On-Site Activities Templates (includes
Sept Reports Plant & Equip, Labour & Site Docs JSA/SWMS also in Site Supervision)
th
26 September Homework Catch-up Term 3 Results & Re-Submits

/Volumes/DC_Passport/WORK/2017/ABS/CPCCBC4008B Site Super/Week 1/2017_Sem_2_Site_admin_PROGRAM.doc Created on 28/7/17 12:17:00 pm V2 ©TAFE SA 2016


nd th
2 to 13 October END OF TERM LECTURER BREAK – 2 Weeks ENJOY - BUT CATCH UP ON YOUR HOMEWORK!
th
9 17 Putting the Portfolio of Book Chapter 1 & 2 L & M TASK 1 – Bricklaying Quote
Oct work together (Intro to What are Schedules? TASK 2 – Resource Tables
Word, Excel & PDF) Word & Excel how to’s.
PDF conversion & usage / VLOOKUP?
st
Michael Slater SPECIAL “CONSTRUCTION CONTRACTS” SATURDAY – 21 October 9:15 – All Day

Labour & Materials - L&M


WORKSHOP
th
10 24 Producing Schedules Legal Req, Materials, Cost Tracking L & M TASK 3 – Pipe-laying Budget
Oct Contract Conditions Site Daily Diaries (S.S.?) TASK 4 – Daily Diary (also in Site Supervision)
(More Excel) TASK 5 - Timesheet
st
11 31 Preparing Site Files & Book Chapter 3 L & M TASK 6 – Window Schedule
Oct Keeping Records Orders, Budgets, Call Forward Sheets TASK 7 – Door Schedule & Purchase Order
th
12 7 Monitoring & Reporting Book Chapter 4 & 5 L & M TASK 8 – Call Forward Sheet (lead times)
Nov Cost Control, Contractors & Suppliers TASK 9 – Roof Costing
th
13 14 Wrap up of 3 x Units WORKSHOP Only All Finish ALL Tasks and Quizzes All
Nov Work Work
st
14 21 Wrap up of 3 x Units WORKSHOP Only All Finish ALL Tasks and Quizzes All
Nov Work Work
th
15 28 No Class Final Submissions by Start Of Business – Monday No Extensions unless fully documented as per Policies
th
Nov morning 4 December and Procedures
th
16 4 Dec Resulting Week
th
11 Dec Counselling Week
th
18 Dec END OF SEMESTER BREAK
Please Note:
Every effort will be taken to follow the above timetable. However, should alterations be necessary, students will be advised in advance. Please make sure that I have your email
address.
All work to be submitted electronically through “Submission Portals” in TAFE SA Learn (Moodle), unless you have made other arrangements.
All work for these Units is by nature “practical”, so will be marked accordingly, with a Pass Achieved if satisfactory.
Comments given will reflect your input.

David Clothier
 Lecturer
 TAFE SA 
 TAFE SA Tonsley Campus


Phone +61 (08) 82072885
 T +61 (8) 8207 2800 F +61 (8) 8207 2804
Tonsley Campus, Alawoona Avenue, Clovelly Park SA 5042 Street Address 1284 South Road, Clovelly Park SA 5042 (Postal Address PO
david.clothier@tafesa.edu.au www.tafesa.edu.au 
 Box 463, Oaklands Park, SA 5046)
CRICOS Provider No 00092B TAFE South Australia

/Volumes/DC_Passport/WORK/2017/ABS/CPCCBC4008B Site Super/Week 1/2017_Sem_2_Site_admin_PROGRAM.doc Created on 28/7/17 12:17:00 pm V2 ©TAFE SA 2016

Вам также может понравиться