Академический Документы
Профессиональный Документы
Культура Документы
MEKELLE UNIVERSITY
Ethiopian Institute of Technology Mekelle
Civil Engineering Department
Declaration
During my internship work in the Mekelle – Dengolat – Samre – Finarawa asphalt road project I
have gained a good experience, observation and achievements. In this case, I would like to
declare as this internship report is my own work.
Acknowledgement
First and fore most I would like to thank for my almighty GOD for his keeping throughout my
life and my family who support me to reach at this level.
I would like to give my greatest acknowledgment for Mekelle University and Defense
Construction Enterprise as they give me an opportunity to participate in the internship program
and improving practical knowledge in the road construction respectively.
I would also like a great appreciation for my advisor Sesen Tekleyohans for her good approach
and advice and also supervisor Atakilty, who guide us in a good manner to participate and follow
the construction process.
Finally, I want to acknowledge for site engineer Yohanse, material engineer Masresha and all of
the remaining employees Forman, lab technician, office worker and labour who show me ways
of conducting to the activities and their willing to answer my question during the four stay of my
internship program.
Abstract
Generally discus about this internship report is to write what I have observed any specific tasks
performed and gained practical knowledge from the road construction processes during my
internship period at Defense Construction Enterprise.
In the first part of my internship report, I have stated a lot of information about the back grounds
of my internship hosting companies related to the history and objective of the companies, its
main products and services, the overall organization and work flow, missions and visions with
the help of internet service and communicating to the professional mans.
On the next section it discus about the overall experience and knowledge I have gained from the
internship. It stars by describing what look like the flow work of the site. It also tells about
the work tasks that are observed and executed at the site and the challenge that I had
faced during the construction process and their remedial measures.
In the third part of my report briefly explains about the overall benefits I gained from my
internship. It includes with improving my theoretical knowledge, practical skills, problem
solving capabilities, team playing skills, leadership skills and work ethics.
Finally, I put my conclusion and recommendation for my company based on what I have
observed in the construction activities.
Table of Content
DECLARATION ......................................................................................................................................... I
ACKNOWLEDGEMENT .......................................................................................................................... II
REFERANCE ........................................................................................................................................... 45
List of Figure
Figure 1 products of Defense construction Enterprises ............................................................ 4
Figure 2 the number of employees in DCE ................................................................................. 5
Figure 3 observed activities ........................................................................................................ 11
Figure 4 modified compaction ................................................................................................... 14
Figure 5 penetration for CBR test ............................................................................................. 15
Figure 6 Soaked CBR Vs dry density........................................................................................ 18
Figure 7 Swelling Vs dry density ............................................................................................... 18
Figure 8 Casugrand test ............................................................................................................. 20
Figure 9 Liquide limit Vs number of blow ............................................................................... 21
Figure 10 particle size distribution ............................................................................................ 22
Figure 11 Aggregate Crusher .................................................................................................... 23
Figure 12 Specific gravity of aggregate determination ........................................................... 24
Figure 13 Material used for slump test ..................................................................................... 25
Figure 14material of Cubic test ................................................................................................. 26
Figure 15 procedure of asphalt mix design............................................................................... 27
Figure 16 Equipment used for subbase ..................................................................................... 29
Figure 17 Curb stone placement ................................................................................................ 30
Figure 18 Side drainage structure ............................................................................................. 31
Figure 19 Pipe production .......................................................................................................... 32
Figure 20 Pipe installation.......................................................................................................... 32
Figure 21 cutoff wall ................................................................................................................... 33
Figure 22 providing formwork for bottom slab concrete........................................................ 33
Figure 23 Batching plant ........................................................................................................... 34
Figure 24 Prime Coat Spraying ................................................................................................. 34
Figure 25 Asphalt plant production .......................................................................................... 35
Figure 26 Method of guiding for asphalt paver ....................................................................... 36
Figure 28 my task at surveying .................................................................................................. 38
Figure 27 my task at reinforcement .......................................................................................... 38
List of Table
Table 1 Analysis of Moisture-Density Relations Of Soils ( AASHTO T180)......................... 13
Table 2 compaction determination for CBR test ..................................................................... 16
Table 3 Moisture Determination for CBR ................................................................................ 17
Table 4 CBR Penetration Determination ................................................................................. 17
Table 5 Swell Determination ...................................................................................................... 17
Table 6 Plastic Limit Determination ......................................................................................... 19
Table 7 Liquid Limit Determination ......................................................................................... 20
Table 9 sieve size analysis ........................................................................................................... 22
CHAPTER ONE
1 Back ground of Defense Construction Enterprise
1.1 Introduction
My internship program that I had been involved in the company was called Mekelle-Dongolat-
Samre-Finarawa asphalt road project which is located in region Tigray. This project covers
around 94 kilo meter highway length which is contracted with an amount of 1.6 billion birr to be
finished within three years from its commencement period of Nov/2006 E.C up to the
completion period of Nov/2009 E.C.
Now a day the company has successfully accomplished different construction works estimated at
hundreds of millions of birr for the federal government, regional government, and the private
sectors of Ethiopia. Currently the company is undertaking a number of construction activities in
different parts of the country.
Moreover, it is making its utmost efforts in implementing its role for the vast progresses of
construction of infrastructure underway in the national which as a result enable the national plan
of development and transformation meet its objectives
1.2.1 Objective of the company
The main objective of the company is;
To participate in any construction activity mainly to satisfy the National Defense.
Participate in the socio economic development of our country without any discrimination.
To realize the aforementioned goal to increase the skills, abilities and competencies of its
human resources and establish well organized construction business
To ensure the productivity and profitability without any corruption.
To provide an opportunity of work for the citizen of the country.
Create environment friendly working condition by reducing and gradually eliminating
activities and wastes having adverse effect on the environment and thus contribute its
share in the global effort towards combating environmental degradation;
1.2.2 Vision of the company
Becoming the leading and most sought after company in our continent in the development of
mega and challenging defense infrastructure and related construction works with accepted
construction standards. And also to be the premier choice for all construction works in Ethiopia
and competitive actor undertaking all types of construction work internationally.
In addition to the product and service of the company, Defense construction Enterprises has a
number of employees at the head quarter and projects.
The following graph shows number of employees currently the company regular staff, temporary
workers and permanent employees with their educational level and gender at the head quarter of
the company’s and various projects.
Manage
General
Audit
Planning and
Infrastructure Sector
Programing
Service
Road,
Irrigation
and Dam
Project
CHAPTER TWO
2 Overall Internship Technical Experience
2.1 Introduction
Internship is one method of making opportunity for university students to have a valuable work
experience and get to know with the real world activities.
Prior to my internship period, primarily I took an internship letter from my university and it is
approved by Defense Construction Enterprise to participate in their activities. Then I tried to
know how the activities of company were going on and the name of professional man I need to
be conducted. During my internship work, I conducted with the laboratory activities for about
two month and then I did in the site and office works. In this part, it discusses detail about the
basic things I gained technical experience from the laboratory, site and office works.
During my internship period, I have observed how the contractor, DCE, and consultant, RDDC,
work jointly for the asphalt road project. They perform all work in coordinate mean that the
contractor construct and perform the required activity based on the prepared drawing and the
consultant supervises the work in each step to ensure the best construction according to the
specification. If the activity performed is not satisfied to the required specification, the consultant
orders the contractor to do it again or set a time for the consistency of the constructed structure.
The general work flow of the road project is carried out with the coordinate of the four heads;
Construction Engineer Head, Equipment and Administration Head , Finance & Administration
Head and Office Engineer Head. The procedural work of these heads are stated by the
application of chart, at the over view of this page.
Material Engineer
Chief Surveyor
Data Coordinator Laboratory Technician
Daily lab our
Office Engineer Head Quantity Survey
Equipment administration Head
Site Engineer
haser haser
Quantity Survey
haser
Preparing meetings, with different section heads for reviewing schedules, evaluate
performances, to better understanding of problems and solutions
Carries out detailed planning and scheduling of the project site fore their execution.
Managing the project team, risk and conflicts.
Prepares progress reports and submits it to supervisor
Establish the different crews and supervise their performance.
Controls and checks construction works for compliance with design specification and
desired quality of material and workman ship.
Approve the schedule and budget of the project.
Office Engineer;- Provides technical information to others working on a project to ensure that
the work complies with all engineering standards, codes, specifications, and design instruction.
The work is performed with the following tasks;-
Prepare and submit necessary document for construction project.
Prepare structural and architectural drawing for construction project.
Analyze the data’s to prepare payments and take offs.
Receive and checks for measurement data submitted from the site.
Make a report to the project engineer and provide it to surveyor, Forman or any other
participate in the construction site.
Receive and confirms project site reports related to variance and amendment.
Site Engineer;- Manages, coordinate and supervise the man power and construction activities on
the site with the following detail activities;-
Prepare equipment, material and any other required tools, and checks their availability.
Participate in the planning and scheduling of the construction method of works.
Check the excavation and earthworks according to specification and drawings.
Properly follows the given times schedule in order to avoid any delaying on the project
completion time.
Interpret the work order, technical drawing and specifications to the subordinate.
Ensure that the construction process is in the standard condition or not, and performance
of the equipment and their quality.
Surveyor;- related with the studying of the topographical feature of the road project.
Administrator;- The main activity of the Administrator is solving conflicts between employees,
administrating the working environment and communication with the local government.
Financial:- Carry out salary of the employees and finance the purchasing of materials.
Time Keeper - Control the time of the workers from start to the finishing.
registers ordinary time amount ,overtime works and report summary of a working times
Cashier;- give a payment to all cashier.
Equipment Administration- Manage the activities of all rentals and owned equipment and
provides maintenance service for machines and equipment’s by using data collectors and data
coordinators and time keepers.
Operators:- Operate, fix and maintain different machineries on the site like, vibrator and mixer.
Material Engineer;- Work in the laboratory that make investigation for the quality of material to
be used for construction purpose.
Lab Technicians;- are working under the Materia Engineer. The main responsibility of Lab
Technician is, testing of the material to be used in the road project and check them as they satisfy
to the requirement after construction.
Laboratory work is just an investigation of the strength of material we use in the road way such
as; soil, aggregate, asphalt and cement through the different mechanism of tests.
Objective The main objective is determination of then maximum dry density of the soil under
the optimum moisture content of the soil.
Apparatus; mold with removal collar and base, oven, balance, hammer, can and tirrimer.
Procedure for modified compaction test
Around one quintal of soil came from the site to lab and dry it through air.
Then the soil the air dried is quartered which represent the whole soil sample and sieved
with 20mm sieve size
Add the required amount of water to soil sample
Weigh empty mold
Compact the soil in the mold 56 times per each 5 layer.
Remove the collar and trim off the soil above the top of the mold
Weigh the mold and the sample
Remove the soil from the mold and take representative sample for moisture content
determination
Add water to increase the water content by about 2%and repeat again step 5.
Continue until the mass of the mold decreases from the previous weight of mold.
Finally draw the moisture content to the dry density to find the maximum dry density of
the soil.
1.97
(gm/cc)
1.95
DRY DENSITY
1.93
1.91
1.89
8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00
MOISTURE CONTENT %
First about one quintal of soil came from the site to lab and spread over a plain area to be
dry.
Then the soil the air dried is quartered which represent the whole soil sample and sieved
with 20mm sieve size which retained from 15-30% weighed up to 18 kg for three trials
each 6 kg. If retained soil through 20mm is less than 15% we take soil replacement using
4.75 mm sieve and if it is greater than 30% retained the soil is removed.
Then the soil was mixed with water gained from OMC of the compaction and its natural
moisture content
Place the spacer in the mold, with base plate and collar attached.
After that each trial were compacted with 10, 30 and 65 below per 5 layers
Remove the collar .level the surface with straight edge and the performed base plate,
invert the mold, and replace it on the base plate.
Take a weight before soaking.
Then take initial reading for swelling and soak them in water for about 4 days
Take also final swelling reading after four days and weight
Place it in compression machine and seat the penetration piston on the surface.
Apply a load on the piston, and then record the total load at the specified penetration
depth.
Take a pit of sample to a can to get dry density of the sample at each compaction
Finally determine the CBR value at 2.54mm and 5.08mm penetration depth, its dry
density and swelling value.
Analysis for CBR test (AASHTO-193)
Sample date: 11/8/2017 Representative station: 39+300 - 39+500 Intended for: Classification
Soak date: 11/13/2017 Material Source: Roadway Excavated Material Tested by : Awote G.
Test Date : 11/17/2017 Type of Material: Brown Silty or Clayey gravel Cheked by: Masresha G.
Table 2 compaction determination for CBR test
16.0
1.790 1.840 1.890 1.940
1.00% Dry
swell
0.80%
0.85% density
0.60% 1.80 1.04%
0.00%
1.79 1.84 1.89 1.94
Dry Density at 95% of MDD=1.87
Dry density
Apparatus used are; balance, sieve, distilled water, spatula, dish, cans, flat plate and oven.
Procedure; About 30 g of the soil which is sieved through 0.425mm was taken and rolled with
hand in a large glass plate until 3mm diameter of soil threads was obtained. The portions of the
rolled soils were collected and determined its water content
Container No O Y
Procedure; The dried brown silty and clay soil was first
sieved through 0.425mm sieve and taken about 180 g of soil
for both liquid and plastic limit test. Then a portion of the
paste was taken to the cup and drawn the grooving tool
through the sample along the symmetrical axis of the cup.
After that the crank was turned until 13mm distance of the
gap was closed. Additional trials ware repeated to produce
successive number of bellows which helps to determine an
Figure 8 Casugrand test
accurate water content value in the 25 number of bellows.
Test No. 1 2 3
No. of blows 30 23 16
Container No. D1 D2 D3
MOISTURE CONTENT %
34 LIQUID LIMIT CHART
33
LL=30.8%
32
31
30
29
1 NO. OF BLOWS 100
Conclusion; According to AASHTO T 90 the maximum value of LL and PI is 60% and 30%
respectively. So, the soil is safe by which its consistency.
Procedure;
70.0
65.0
60.0
55.0
50.0
45.0
40.0
35.0
30.0
25.0
0.05 0.5 5 50
Conclusion; The soil will be classified using Group Index and AASHTO method under the
following results.
For GI=0 the soil has good drainage behavior. And based on AASHTO classification the soil is
grouped under A-2-4 which is Silty or Clayey Gravel and Sand.
Dish
Soaked aggregate
Temperature Gauge
Absorbent cloth
Procedure; To obtain the specific gravity and water absorption of the aggregate; primarily, we
mix the sample of aggregate thoroughly and rejected the material which pass through 4.75mm
sieve. Then the aggregates were washed to remove the dust particle and soaked for about one day
in water filled dish. Next the aggregates were rolled on the absorbent clothes until all visible
films of water are removed and its weight was taken. And also the weight of air dried aggregate
was taken when it was immersed in distilled water and oven dried in the oven dry. Finally, its
specific gravity and water absorption was determined based on the weight of aggregate found in
the air dried surface, in the water and in the oven dry weight.
B. Filler materials
Filler materials are fine particle which are used to fill for voids created in the coarser aggregate
when we use as base coarse or other construction. So, one of the quality of the filler material is,
estimated using its specific gravity.
Procedure; the specific gravity of filler material was obtained by which equal volume of water
and filler materials were weighed through a bottle. The air filled to the void of filler material was
extracted properly using vacuum pump, while the volume of filler material is equal to the volume
of water.
Procedure; during the test, first we have mixed the ingredients of the concrete; water, cement,
sand, coarse and fine aggregate according to their proportion. As soon as the discharge of the
concrete commences, we took a sample from the mixed concrete and filled to the one third of the
volume of the cone. Then filled concrete was compacted through the rod 25 times. We continued
the same process with an equal amount of mixed concrete till it overflows through the top up of
the cone. After that we leveled off the surface with a steel rod using a rolling action. Then the
cone was lifted up carefully without moving the sample. Finally, the decreased height of the
sample was measured by inverting the cone upside down, the ruler applied at the top of it. The
reduced height of the sample should be within the set range which is from 25-100mm.
Hammer
Mold
Procedure; the samples are taken when the mixing concrete is carried out or a trucks delivering
concretes from the batch to the structures. Then, the concrete is filled for three trials with 20x20
cubic molds in three layers. Each layer was compacted 25 times through tam pic load and also
the side of the mold was tamped through plastic hammer, to extract the air void. After that, the
mold is removed from the cubic concrete and soaked in water three of them for 7 days and then
remained for 28 days. The specimens are loaded to failure in a compression testing machine and
the maximum load sustained by the specimen is recorded.
Procedure; Prior to the commencement of mix design of asphalt, the quality test of aggregate
i.e. LAA, flakiness, ACV, TFV, soundness, absorption, specific gravity, coating asphalt, sand
equivalent and fracture face had been carried out. Next the aggregates were blended according
to the specification. Then, the graded aggregate and bitumen were heated for about 160c and
140 respectively, except the filler material. After that, both the aggregate and bitumen were
blended by taking five different content of bitumen. After that, the mixed asphalt was
compacted 75 times in the compactor machine which forms a 5 cm thickness of asphalt
concrete called briquette. Then, the stability, deformation, VMA, VFA and air void of each
briquette should be studied. Finally, we need to select the percent of bitumen content need for
the mixture by which, the briquette satisfies the tolerance.
Aggregate
mixtures Machine compactor
=75 times
+ +
Take to
Compression
Machine
In case of our construction, the road is two ways, and the one way has 10.5 m width. So, during
the construction of an earth work for capping, subgrade and base course , the thickness of the
compaction layer is marked at each 20m interval difference and 3.5 m offset by using blue top.
The blue top helps to know the exact section of the layer during the grading.
Total station used to determine the position such as center line of the road and footing pad
position of man hole.
Procedural work; an excavated soil was came to the site from the quarry site by the application
of damp truck and damped to the road way. The sub base material was spread on the approved
sub grade by Grader without segregation. During spreading of oversize materials should be broke
down and removed from the layer to the adjacent side the road.
During spreading time, the Shower track and Grader should work together. The Grader should
follow the top of the blue top to give compacted thickness 17.5cm. Then, the speeded soil was
compacted by the roller to obtain the required dry density for compaction of the existing sub
base.
Equipment used;
Grader: -. These are used for shaping the sub base Grader
to get the blue top
Shower Drum
truck Roller
Preparation process; the executing process has no that much difference with the sub base coarse.
First the material was spread on the approved sub base layer by mechanical means grader
without segregation. Then the material was loosely spread to give a compacted thickness of
10cm. The material was compacted by the use of rollers progressing gradually from the outside
towards the center of the layer. Compaction was continued until the entire thickness of each layer
is thoroughly and uniformly compacted until the required density reached.
Equipment; used for base coarse preparation are similar with the sub base equipment which are
loader, dump truck, grader, water truck and roller.
A. Curb stone
The curb stone are constructed from concrete which are placed along the side of the shoulder and
center line of the road way. It designed to prevent vehicles from leaving the roadway. The size of
the curb stone is as stated in the figure.
Dimension of the
curb stone
Figure 17 Curb stone placement
Prior to placing of the curb stone, the exact position of the curb stone is determine by the
surveyor. Then, each of the curb stones are connected to each other using cement mortar with a
ratio of 1:2.the curb stone is inserted about 3mm over the finished sub base road.
B. Mane hole
Manhole is a hole by which a man can enter in to the pipe
or other drainage structure to clean up it Since the flood
that pass through the pipe consist of different particles
such as silt, crushed stones and other waste material.
C. Pipe
Production of pipe; Pipe is designed as per hydrological study of the location and it is casted at
casting site then transported from there to a place where it is wanted to installed. The production
site of the pipe is near to Kalamino and three types of pipe are produced. These are 36 inch,42 inch
and 48 inch diameter. The reinforcement used is 8 and it is a double reinforcement in the 42 &
48 inch. During the casting of the pipe, the bars are fixed alone with the a circular shape then
inserted to the circular steel form work. Finally it is casted with a concrete. The concrete used is,
with a ratio of 1:2:3 or for 50 kg cement, 2 bag sand, 2 bag size 02 aggregate and 1 bag size 01
aggregate.
installed with the help of Crane and connected Figure 20 Pipe installation
to each other with the help of mortar 1:2. Then
selected material is added to the side of excavated place and then compacted 15 cm per layer
using Hand Roller. Thereafter, compacted test is taken by lab technicians at site and the test is
called sand cone test. If the test value is greater or equal to the standard value the compaction is
ok then the alignment is done but if the test value is less than the standard value then the soil
taken compacted and the test is taken again and we continue till top of the sub base.
D. Box culvert
Kewami
Steel
formwork
Work process;- First the surveyor sets the center line of the box culvert. Then, it is excavated to
the require depth through the Excavator. After that, the bed level of the culvert is measured its
level then compacted to a thickness of 20cm. After that a lean concrete is paved to a thickness of
5 cm with a ratio 1:3:5. Then reinforcement is placed at the bottom slab and vertical shear wall
based on the designed principle. Next, by fixing bottom form work, the bottom slab is casted
with a ratio 1:2:3 concrete which has 30MPa compressive strength. During casting of the
Production site: Asphalt was mixed by means of automatic Asphalt Concrete Batching Hot
Mixing Plant which is called Marni plant located in Maykeyh. The machine is operated with the
application of computer.
Some parts of the machines are;
Cold bin
Mixing tower
Hot elevator
Drier
Cold bin - are four types that are cold G1,G2,G3 and G4.its main purpose is to contain the
different size of aggregate and pass it to the drier. But in our case one of them is not more served.
Drier - is a circular type which gives a heat to the aggregate from 150c-170c and mix the
aggregate with an optimum circulation.
Hot elevator - is a vertical member which sends the dried aggregate to the mixing tower.
Mixing tower - mixes the aggregate 170 with bitumen 150 at the top and sends it to the bottom
and received it by the asphalt elevator.
Asphalt elevator – translates the asphalt concrete to the asphalt container which is located at a
higher elevation.
Asphalt container - this part of the machine can keep the asphalt too long time without changing
its temperature. It has a gate in its bottom part and drops the asphalt to the dump truck.
Work process – Before commencement of the asphalt concrete placing in the permanent work,
trial section was prepared to check the asphalt concrete acceptance. Prior to paving the asphalt
concrete, the primed base course is cleaned up through the Compressor. Then a straight string is
extended at the base course which keeps the direction of the Paver. The paver receives the
asphalt concrete with 160 from the Dump Truck through its head and paves it to an initial depth
of 6.8 cm using its tail. There is a dipstick and sensor which control the depth of paved asphalt
direction of the paver respectively. When the asphalt concrete reaches 110c-130c Drum rollers
and pneumatic tire roller in combination were used for compaction of asphalt concrete. The
Drum roller compacts with 3 trips, whereas the Pneumatic roller compact with 40 trips. Finally,
the lab technician takes a core of asphalt at each station randomly, to check its thickness, air void
and stability is within the tolerance.
Asphalt
Concrete
During my internship period I have conducted to the office work by which, estimation of cost of
the machinery such as Girder, Roller, Shower Truck, Excavator, Dozer and Loader depend on
the time for what they do at a day. And also I have seen how to evaluate efficiencies of the
machinery. A daily report of the work process is used for evaluation purpose and at each
successive two week they make a report payment of rental machinery.
When I did CBR testing, first I have taken the quartered soil sample and sieved with 20mm
sieve size weighed up to 18 kg for three trials each 6 kg. Then the soil was mixed with water
gained from OMC of the compaction and its natural moisture content. After that each trial were
compacted with 10, 30 and 65 below per 5 layers. When the soil compacted it should be in a
systematic ways that is dropping the hammer by keeping its weight. Then I have soaked them in
water for about 96 hours. After 96 hour I abled to read the penetration load and swelling
percentages of the soaked soil.
During my first internship period I have got a lack of speaking with the professional man,
because of not introducing well with them.
Lack of transportation service to move from my compass to the site, because it is far to
move without helplines of transportation service
Not having an experienced engineer who can easily make the students understand the
work of the laboratory procedures and tests. It was expected from the interns to observe
what was occurring and easily adapt to the procedures
To adapt the weather condition of the site of the project. Because the site is very cold and
high dust over the road.
At the laboratory there weren’t any kinds of reference books that were used for guiding
the lab technicians or interns to do the test.
Not having continuous tasks to do in laboratory which make only cost expense.
Not having enough number of skilled or learnt manual labors that could have shown us
how construction works are going on.
Not having enough space to work at the office
CHPTER THREE
3 Overall Benefit Gained From Internship
During my internship program, I have gained a lot from our stay for a period of four months
around a real work environment. This is due to the fact that what I have been given in the school
gives a real sense with all the challenges and excitements. Apart from the professional skill, I
have built up good cooperative attitude with other partners. I was able to know the gap between
student life and profession life. This internship program provided me a plat form to introduce
myself in professional field. In addition to improving my theoretical and practical skills, I have
been benefited how to conduct with the behavior of workers and their managing system.
In the laboratory work I have been practiced how to apply the different types of tests. For
instance, compaction method of a soil for CBR, procedural work of asphalt mixes design
and other different tests.
I have capable how to tie and fix reinforcement bars by reading drawing.
I have practiced how to evaluate the cost and efficiencies of the different machineries in
the office work.
I have been increased how to read a leveling instrument to determine an elevation of
different area.
During my internship period I have conducted to different teams that can improve and facilitate
in solving a problems and acquiring knew knowledge. I have involved as a team with a student to
solve one problem collaboratively in order to achieve a goal. Therefore, the team playing with
this students were interesting, to discuss the weakness and strength of individuals. Team work is
the process of working with a group of people. Each member is capable and willing to contribute
their information’s, skills and experience. Teams playing with in the workers were very nice and
have an interesting condition to join them. Because, having a team can improve and facilitate the
work process of the road project.
Leadership is making a group of people to do something. So, the leader must responsible to
invite each and every issue properly. During my internship I have been able to see different
engineer in their work and lead the site worker. Some of the skills that I have got from the
managing systems are;
Work ethic is a process of working cooperatively among the different workers and employs
without making any conflict. And it has a vital role to improve the productivity and continuity of
the project. Ethical work conduct enables me in order to posses’ appropriate behaviors in the
work and so I develop proper relationships with co-workers and it helps me to create good
working environment. Some of the ethical works that I have got from my internship are;
CHAPTER FOUR
4 Conclusion and Recommendation
4.1 Conclusion
From the past stay of my internship, I have understood that, as this internship program has a vital
role for students. Because through this program students can build their capacities and can
interpret the theoretical knowledge in to practical skill by which participating in diversified and
realistic practical activities. And also it has a vital role in the method of conducting to the
different work tasks and getting to know with the of the company.
Defense Construction Enterprise is a level one constructor which is upgraded from the previous
years by participating with the different construction infrastructures such as asphalt road,
building construction and dam structures and most of the time the rural asphalts are constructed
by the Defense Construction Enterprise. This shows us that as our country is facing to the
diversified and fast growing infrastructures.
During the previous, I have seen a lot of things which is important for my life. It gave me the
highlight of my future as a civil engineer. It allowed me create valuable connection and gain a
priceless experience. It gave me the chance to revise what I have learned for the past four years
directly or indirectly. It is important in improving my own theoretical, practical, industrial
problem solving, team playing, leadership skills and entrepreneurships. Generally is important
for the future life improvements that are essential to act as an employee. Hence I have gained a
very useful knowledge related to the theoretical concepts of road and practical activities that are
mostly done on the project. I have estimated that it will also be a stepping stone to the next part
of my life.
There had been also some challenges while performing our tasks which we had to take
different measures to overcome them. To conclude on the overall internship program, I am so
lucky as I get this program before my graduation.
4.2 Recommendation
Having good participation and spending time at road construction site, it makes us to become a
professional man and decisive for a problem facing. I was developing a good understanding on
solving different kinds of engineering problems that require engineering solution. It was great to
see the application of theoretical knowledge that I get in class. It really provides a great
opportunity for an out of classroom learning experience that is relevant to our educational
program. So, I am interesting to recommended the following problems what I have facing during
my internship program.
During the tests of materials in the laboratory work, mostly the lab technician and
consultant are not working jointly. As a result, the lab technician makes a mistake during
carrying out of the test. For example, I have observed an error counting of penetration
test for CBR value. So, I recommend that, the consultant to supervise them during
carrying out of the lab test.
When I was at a site, I have seen a cross drainage which pass across the road way and
leads to a center line of another road way. If the construction process is continued along
the roadway, it would be difficult to install on it and not allowed to perform on the
roadway. The main source of the problem is from designation at the office. So, I
recommend that, the office engineer should come to the site and check it the designed
plan to the environment condition.
I have seen a consultant to destruct an erected formwork due to not proper erecting
according to the specified design. Since, the form work is not worked properly; it needs a
skilled man who can read drawing properly.
As I have observed a roadway in town section near to Enda Gabriel, its cross width is
narrowed due to the existence of building at the side of the alignment road. If the building
is removed from its position it would be high cost expense for compensation as a result
they left it as it is. So, I recommend that, it is good to leave the house in its position for a
moment. Because the number of vehicle still can pass without any difficulty. But, for the
future it can be decided depending on the number of vehicle passed though it.
Referance
Highway II lecture hand out
Manual lab report
ERA (2013), Pavement Design Manual, Volume 1
Defense Construction enterprise, Mekelle-Dengolat-Samre-Fineriwa asphalt road project
contract document with Ethiopia Road Authority.
Traffic and Highway Engineering, third edition